Federal-Aid
Policy Guide
July 6, 2005, Transmittal
34
NS
23 CFR 646B
Attachment
3
Non-Regulatory
Supplement
Attachment
OPI:
HSA-10
USE
OF FIXED AMOUNT (LUMP SUM) PAYMENTS TO RAILROADS (PARAGRAPH 6, NS
23 CFR 646B)
Occasionally
on Federal-aid highway projects the States consider proposals
that involve the use of fixed amount (lump sum) payments to
railroads either as reimbursement for needed adjustments to
accommodate construction of the highway project or as
compensation for facilities taken.
The
FHWA regulations have long treated railroad facilities impacted
by highway construction as essential public services that must be
maintained if the need for the services continues to exist. Where
services must be maintained, the FHWA may reimburse the State
based upon necessary costs to restore the essential services in
the most economical method. This is usually done by paying for
construction of a replacement facility. Where the railroad and
the highway agencies agree that existing facilities do not need
to be replaced, the FHWA should pay for the railroad facilities
as a right-of-way acquisition matter. The FHWA policy and use of
fixed amount (lump sum) payments are discussed below.
Case
I - Operational Capabilities are to be Functionally Restored
The
FHWA's regulations covering reimbursement for railroad work on
Federal-aid highway projects are contained in 23 CFR 140, Subpart
I. The basic concept incorporated into these regulations is that
FHWA is willing to reimburse actual costs incurred to
functionally restore a railroad’s existing operating
facilities which existed prior to undertaking a highway project.
It is intended that a railroad's financial and productive
situation be maintained as if the adjustment needed for the
highway project had not occurred. This does not mean that a
replica facility is required, rather that the railroad is to be
made whole by restoring the existing functions of the impacted
facilities.
Typically,
a railroad uses its own forces or lets a contract to accomplish
the needed adjustments to its facilities. Records of actual costs
incurred then form the basis for FHWA reimbursement to the State.
For work performed by a railroad with its own forces, FHWA
regulations allow a fixed amount final payment based on an
estimate of costs prior to construction. This is commonly known
as the lump sum payment method. For railroad work, FHWA's lump
sum payment regulation is 23 CFR 646.216(d)(3).
The
lump sum payment method should only be used where the end
product, in this case the railroad adjustment, can be clearly and
concisely defined. The cost estimate in support of the lump sum
agreement should be accurate, comprehensive, verifiable, and in
sufficient detail to give a clear picture of work involved and
the cost of the individual items. A principal benefit of using
the lump sum payment method is that it should reduce
administrative and record keeping costs associated with
documenting payment for completed work. However, these savings
may be offset by inaccuracies in the cost estimating process. In
recognition of this, the regulation establishes a $100,000
ceiling for use of the lump sum payment method, although for
routine railroad crossing safety improvements (i.e., active
warning devices, crossing surface, etc.) there is no ceiling.
The
railroad regulation contains a mechanism for approving lump sum
amounts where this is found to be in the public interest.
Approval of proposals to exceed the $100,000 ceiling should be a
relatively rare occurrence. Two situations where this may be
justified are as follows:
-
Where the estimated cost of the eligible adjustment work slightly
exceeds, for example, by no more than a few thousand dollars, the
$100,000 ceiling. In this case the ceiling is not being treated
as an inviolable barrier and some flexibility is allowed.
-
Where the cost of the railroad work eligible for Federal-aid
participation represents only a small portion of the overall cost
for all the railroad work that is being performed in conjunction
with the construction of the highway project. For example, a
railroad may be undertaking a major upgrading of its facilities
in an area where a highway project occurs, and the portion of the
work eligible for Federal-aid participation may be relatively
small in comparison, for example $75,000 out of an $800,000
effort. In this case, it may make sense for the highway agency to
agree to a fixed payment to represent its share of the overall
work being accomplished, thus simplifying administration of the
project.
In
either of the above situations, the lump sum payment method
should only be used where the work can be clearly defined and the
costs accurately estimated. Also, whenever a lump sum payment is
used, the highway agency should still verify that the eligible
work has been satisfactorily completed in accordance with the
approved agreement, plans, and specifications before
reimbursement can be approved.
Processing
of a State's proposal for a lump sum payment for railroad work in
excess of $100,000 other than for crossing safety projects
requires approval by the Division Administrator.
Case
II - Operational Capabilities Need not be Functionally Restored
Where
the railroad determines that its existing facilities do not need
to be replaced to maintain its operational capabilities, then
payment for the railroad facilities needed to accommodate
construction of the highway project should be handled as a
right-of-way acquisition matter. The fixed amount (lump sum)
payment for the real property interest of the railroad to be
acquired would be based on the fair market value of its existing
facilities developed in accordance with approved State
right-of-way appraisal and acquisition procedures.
Any
administrative settlement over and above the fair market value
should be supported in accordance with 49 CFR 24.102(i). Various
means, such as appraisals, recent court awards, estimated trial
costs, or valuation problems are recognized as providing support
for a settlement value.
Case
III - Payment for Nonoperational Facilities
Instances
can arise where a highway project may require the acquisition of
a portion of a railroad’s property or facilities that are
not directly a part of the company's physical plant providing the
service (e.g., an office that houses the company’s
marketing and billing operations). In these cases, the fixed
payment to the railroad should always be based on applicable
right-of-way procedures.
|