NESHAP for Polyether Polyol Production (40CFR part 63, Supbart PPP - Renewal)

Table 1 & 2

OMB: 2060-0415

Document [ppt]
Download: ppt | pdf

Overview

Industry
Agency


Sheet 1: Industry

Table 1 - Nationwide Industry Burden for Major Sources



A B C D E F G H
Burden Item Person hours Annual occurrences Annual person hours Total number Technical hours Management hours Clerical hours Total Annual

per occurrence per respondent per respondent of respondents per year per year per year Cost



(A X B)
(C X D) (E x 0.05) (E x 0.10)

1. Applications N/A







2. Surveys and Studies N/A







3. Reporting requirements








a. Read rule and instructions 1 1 1 1 1 0.1 0.1 $92
b. Required Activities








i. Initial Performance Test - Process Vents 480 1 480 1 480 24.0 48.0 $44,057
ii. Initial Performance Test - Wastewater 160 1 160 1 160 8.0 16.0 $14,686
c. Write Reports








i. Notification of Applicability 2 1 2 1 2 0.1 0.2 $184
ii. Notification of Construction/Reconstruction 2 1 2 1 2 0.1 0.2 $184
iii. Notification of Actual Startup 2 1 2 1 2 0.1 0.2 $184
iv. Initial notification 14 1 14 1 14 0.7 1.4 $1,285
v. Performance test notification 2 1 2 1 2 0.1 0.2 $184
vi. Compliance status notification 2 1 2 1 2 0.1 0.2 $184
vii. Performance test reports 80 1 80 1 80 4.0 8.0 $7,343
viii. Startup/shutdown/malfunction reports 2 1 2 1 2 0.1 0.2 $184
ix. Semi-annual summary report 20 2 40 82 3,280 164 328 $301,056
x. Notification of Physical/operational change 2 1 2 8 16 0.8 1.6 $1,469
Total Number of Responses


180




2. Recordkeeping requirements








a. Read rule and instructions Included in 3.a. above







b. Develop Record System 40 1 40 1 40 2 4 $3,671
c. Time to train personnel 40 1 40 1 40 2 4 $3,671
d. Continuously Monitored parameter Included in 3.c. above







e. LDAR Program 88 1 88 82 7,216 361 722 $662,324
f. SS&M Plan 2 1 2 1 2 0.1 0.2 $184
Total



11,341 567 1,134 $1,040,942















Total Burden Hours 13,042












Sheet 2: Agency

Table 2. Annual Burden and Cost for the Federal Government to Implement
NESHAP for Polyether Polyols Facilities

A B C D E F
Burden item Technical Technical Management Clerical Total cost

hours per Occurrences hours per year hours per year hours per year per year

occurrence per year (C = A x B) (C x 0.05) (C x 0.1)



@ $41.57 @ $56.02 @ $22.50







Review notification of construction/reconstruction 2 1 2 0.1 0.2 $93
Review notification of physical/operational changes 2 8 16 0.8 1.6 $746
Review notification of actual startup 2 1 2 0.1 0.2 $93
Review initial notification reports 8 1 8 0.4 0.8 $373
Review notifications of compliance status 10 1 10 0.5 1 $466
Review semiannual summary reports 2 160 320 16 32 $14,919
Review notifications of performance tests 4 1 4 0.2 0.4 $186
Review test results 10 1 10 0.5 1 $466
Review startup/shutdown/malf. report 2 18 36 1.8 3.6 $1,678
Total

408 20.4 40.8 $19,020




Total Hours 469.20