Inspection Checklist

for ENERGY STAR Qualified Modular Home – Prescriptive Path

Home Address: _____________________________________________________________________________________________

City: _____________________________________________ State: ______ Zip: _________ Home ID: ______________________

Instructions: Write your initials in each applicable box. If an item does not apply to the home, write “n/a”. Raters should attempt to inspect as many critical items as possible but may delegate a builder’s representative to verify and initial up to six (6) Thermal Bypass items (numbered items on the first page of this checklist). If the builder verifies any item, they must sign the second page of this checklist. Every line must contain at least one set of initials or “n/a”.

Thermal Bypass Item

Inspection Guidelines

Plant QC

Rater

Pass

Pass

Fail

Overall Air Barrier and Thermal Barrier Alignment

General requirements:

  • Insulation shall be installed in full contact with sealed interior and exterior air barrier except for alternate to interior air barrier under walls adjoining exterior walls or unconditioned spaces (see below).

All climate zones:

  1. Overall alignment throughout home

_________

_________

_________

  1. Garage band joist air barrier (at bays adjoining conditioned space)

_________

_________

_________

  1. Attic eave baffles where vents/leakage exist

_________

_________

_________

Only at Climate Zones 4 and higher:

  1. Slab-edge insulation (Up to 25% of the slab edge may be uninsulated in Climate Zones 4 and 5.)

_________

_________

_________

Best practices encouraged, not required:

  1. Air barrier at all band joists (Climate Zones 4 and higher)

_________

_________


  1. Minimize thermal bridging (e.g., OVE framing, SIPs, ICFs)

_________

_________


Walls Adjoining Exterior Walls or Unconditioned Spaces

General requirements:

  • Fully insulated wall aligned with air barrier at both interior and exterior, OR

  • Alternate for Climate Zones 1 thru 3, sealed exterior air barrier aligned with RESNET Grade 1 insulation fully supported

  • Continuous top and bottom plates or sealed blocking

    1. Wall behind shower/tub

_________

_________

_________

    1. Wall behind fireplace

_________

_________

_________

    1. Insulated attic slopes/walls

_________

_________

_________

    1. Attic knee walls

_________

_________

_________

    1. Skylight shaft walls

_________

_________

_________

    1. Wall adjoining porch roof

_________

_________

_________

    1. Staircase walls

_________

_________

_________

    1. Double walls

_________

_________

_________

Floors between Conditioned and Exterior Spaces

General requirements:

  • Air barrier is installed at any exposed insulation edges

  • Insulation is installed to maintain permanent contact w/ sub-floor above

  1. Insulated floor above garage

_________

_________

_________

  1. Cantilevered floor

_________

_________

_________

Shafts

General requirements:

  • Openings to unconditioned space are fully sealed with solid blocking or flashing and any remaining gaps are sealed with caulk or foam (provide fire-rated collars and caulking where required)

      1. Duct shaft

_________

_________

_________

      1. Piping shaft/penetrations

_________

_________

_________

      1. Flue shaft

_________

_________

_________

Attic / Ceiling Interface

General requirements:

  • All attic penetrations and dropped ceilings include a full interior air barrier aligned with insulation with any gaps fully sealed with caulk, foam or tape

  • Movable insulation fits snugly in opening and air barrier is fully gasketed

  1. Attic access panel (fully gasketed and insulated)

_________

_________

_________

  1. Attic drop-down stair (fully gasketed and insulated)

_________

_________

_________

  1. Dropped ceiling/soffit (full air barrier aligned with insulation)

_________

_________

_________

  1. Recessed lighting fixtures (ICAT labeled and sealed to drywall)

_________

_________

_________

  1. Whole-house fan (insulated cover gasketed to the opening)

_________

_________

_________

Common Walls Between Dwellings

General requirements:

  • Gap between drywall shaft wall (common wall) and structural framing between units is sealed at all exterior boundary conditions

  1. Common wall between dwelling units

_________

_________

_________




Home ID: _____________________

BOP Item

Inspection Guidelines

Plant QC

Rater

Pass

Pass

Fail

Cooling Equipment (when provided)

General requirements:

Hot Climates (2004 IRC Climate Zones 1,2,3) Right-Sized1:

  • ENERGY STAR qualified AC (14.5 SEER / 12 EER) OR ENERGY STAR qualified heat pump (14.5 SEER / 12 EER / 8.2 HSPF)

Mixed and cold climates (2004 IRC Climate Zones 4,5,6,7,8) Right-sizedError: Reference source not found:

  • 13 SEER AC OR ENERGY STAR qualified heat pump2 (14.5 SEER / 12 EER / 8.5 HSPF)

_________

_________

_________

Heating Equipment

General requirements:

Hot Climates (2004 IRC Climate Zones 1,2,3):

  • 80 AFUE gas furnace OR 80 AFUE boiler OR 80 AFUE oil furnace OR ENERGY STAR qualified heat pump (14.5 SEER / 12 EER / 8.2 HSPF)

Mixed and Cold Climates (2004 IRC Climate Zones 4,5,6,7,8):

  • ENERGY STAR qualified gas furnace (90 AFUE) OR ENERGY STAR qualified boiler
    (85 AFUE)
    OR ENERGY STAR qualified oil furnace (85 AFUE) OR ENERGY STAR qualified heat pumpError: Reference source not found (14.5 SEER / 12 EER / 8.5 HSPF)

_________

_________

_________

Thermostat

General requirements:

  • ENERGY STAR qualified thermostat (except zones with radiant heat)Error: Reference source not found

_________

_________

_________

Ductwork

General requirements:

  • Leakage ≤ 4 cfm to outdoors per 100 sq. ft. of conditioned floor area

_________

_________

_________

  • Ducts in unconditioned spaces wrapped with R-6 minimum insulation

_________

_________

_________

  • All exterior ducts mechanically secured and supported off the ground

_________

_________

_________

Envelope

General requirements:

  • Infiltration (ACH50): 7 in CZs 1– 2 │ 6 in CZs 3 4 │ 5 in CZs 5 7 │ 4 in CZ 8

_________

_________

_________

  • Insulation levels that meet or exceed the 2004 IRCError: Reference source not found

_________

_________

_________

Windows

General requirements:

  • ENERGY STAR qualified windows or better (additional requirements in CZ 2 and CZ 4)Error: Reference source not found

_________

_________

_________

Water Heater 3

General requirements:

  • Gas (EF): 40 Gal = 0.61 │ 60 Gal = 0.57 │ 80 Gal = 0.53

_________

_________

_________

  • Electric (EF): 40 Gal = 0.93 │ 50 Gal = 0.92 │ 80 Gal = 0.89

_________

_________

_________

  • Oil or Gas water heating system ≥ 0.78 EF is integrated with space heating boiler4

_________

_________

_________

Lighting and Appliances

General requirements:

  • Five (5) or more ENERGY STAR qualified appliances, light fixtures, ceiling fans equipped with lighting fixtures, water heaters and/or ventilation fans are installed, as listed below.Error: Reference source not found

    1. _____________________________ 4. _____________________________

    2. _____________________________ 5. _____________________________

    3. _____________________________

_________

_________

_________

Marriage Line Seal

General requirements:

  • All vertical and horizontal marriage line areas filled with continuous non-porous insulating gaskets creating a permanent air barrier at joints in the ceiling, walls and floor. Gaskets may be one or two-part systems, including proprietary gaskets, foams, insulation wrapped in poly, or insulation covered by butyl or other long-life tape on one side. No visible signs of gaps or tears are permitted.

_________

_________

_________

Floors over Unconditioned Spaces

General requirements:

  • Air barrier between floor and unconditioned crawlspace is continuous and sealed.

_________

_________

_________

Plant QC

Date: _______________________________

Company: ___________________________

Signature: ___________________________

Initials:______________________________

Rater

Date: _______________________________

Company: ___________________________

Signature: ___________________________

Initials:______________________________

Builder

Date: _________________________________

Company: _____________________________

Signature: _____________________________

Initials:________________________________




EPA Form 5900-190

The government estimates the average time needed to fill out this form is 0.50 hours and welcomes suggestions for reducing this effort. Send comments (referencing OMB Control Number) to the Director, Collection Strategies Division, U.S. EPA (2822T), 1200 Pennsylvania Ave., NW, Washington, D.C. 20460.


1 For more information, see “ENERGY STAR Qualified Homes Codes and Standards Information.”

2 Only applicable to homes in Climate Zones 4 and 5. Homes with heat pumps in Climate Zones 6, 7 and 8 cannot be qualified using the Prescriptive Path (BOP), but can earn the label using the ENERGY STAR Performance Path requirements.

3 Efficiency ratings not applicable if ENERGY STAR qualified water heater is installed to comply with Lighting and Appliances requirement.

4 Can use instantaneous water heating system or an indirect storage system with a boiler that has a system efficiency of ≥ 85 AFUE. Homes with tankless coil water heating systems cannot be qualified using the Prescriptive Path (BOP), but can be qualified using the ENERGY STAR Performance Path.

File Typeapplication/msword
File TitleENERGY STAR Qualified Homes Modular Home Inspection Checklist
Authortgeorge
Last Modified Byctsuser
File Modified2009-09-17
File Created2009-09-09

© 2024 OMB.report | Privacy Policy