FARA section 52.236-15

FAR section 52-236-15.pdf

Schedules for Construction Contracts - FAR Section Affected: 52.236-15

FARA section 52.236-15

OMB: 9000-0058

Document [pdf]
Download: pdf | pdf
SUBPART 52.2—TEXT OF PROVISIONS AND CLAUSES
Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.
(End of clause)

52.236-17
fixed-price construction contract providing for unit pricing of
items and for payment based on quantity surveys is
contemplated:
QUANTITY SURVEYS (APR 1984)

52.236-15 Schedules for Construction Contracts.
As prescribed in 36.515, insert the following clause:
SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984)
(a) The Contractor shall, within five days after the work
commences on the contract or another period of time determined by the Contracting Officer, prepare and submit to the
Contracting Officer for approval three copies of a practicable
schedule showing the order in which the Contractor proposes
to perform the work, and the dates on which the Contractor
contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and
equipment). The schedule shall be in the form of a progress
chart of suitable scale to indicate appropriately the percentage
of work scheduled for completion by any given date during
the period. If the Contractor fails to submit a schedule within
the time prescribed, the Contracting Officer may withhold
approval of progress payments until the Contractor submits
the required schedule.
(b) The Contractor shall enter the actual progress on the
chart as directed by the Contracting Officer, and upon doing
so shall immediately deliver three copies of the annotated
schedule to the Contracting Officer. If, in the opinion of the
Contracting Officer, the Contractor falls behind the approved
schedule, the Contractor shall take steps necessary to improve
its progress, including those that may be required by the Contracting Officer, without additional cost to the Government. In
this circumstance, the Contracting Officer may require the
Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant,
and to submit for approval any supplementary schedule or
schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will
be regained.
(c) Failure of the Contractor to comply with the requirements of the Contracting Officer under this clause shall be
grounds for a determination by the Contracting Officer that
the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the
contract. Upon making this determination, the Contracting
Officer may terminate the Contractor’s right to proceed with
the work, or any separable part of it, in accordance with the
default terms of this contract.
(End of clause)
52.236-16 Quantity Surveys.
As prescribed in 36.516, the contracting officer may insert
the following clause in solicitations and contracts when a

(a) Quantity surveys shall be conducted, and the data
derived from these surveys shall be used in computing the
quantities of work performed and the actual construction completed and in place.
(b) The Government shall conduct the original and final
surveys and make the computations based on them. The Contractor shall conduct the surveys for any periods for which
progress payments are requested and shall make the computations based on these surveys. All surveys conducted by the
Contractor shall be conducted under the direction of a representative of the Contracting Officer, unless the Contracting
Officer waives this requirement in a specific instance.
(c) Promptly upon completing a survey, the Contractor
shall furnish the originals of all field notes and all other
records relating to the survey or to the layout of the work to
the Contracting Officer, who shall use them as necessary to
determine the amount of progress payments. The Contractor
shall retain copies of all such material furnished to the Contracting Officer.
(End of clause)
Alternate I (Apr 1984). If it is determined at a level above
that of the Contracting Officer that it is impracticable for Government personnel to perform the original and final surveys,
and the Government wishes the Contractor to perform these
surveys, substitute the following paragraph (b) for
paragraph (b) of the basic clause:
(b) The Contractor shall conduct the original and final surveys and surveys for any periods for which progress payments
are requested. All these surveys shall be conducted under the
direction of a representative of the Contracting Officer, unless
the Contracting Officer waives this requirement in a specific
instance. The Government shall make such computations as are
necessary to determine the quantities of work performed or
finally in place. The Contractor shall make the computations
based on the surveys for any periods for which progress payments are requested.

52.236-17 Layout of Work.
As prescribed in 36.517, insert the following clause in
solicitations and contracts when a fixed-price construction
contract is contemplated and use of this clause is appropriate
due to a need for accurate work layout and for siting verification during work performance:
LAYOUT OF WORK (APR 1984)
The Contractor shall lay out its work from Government
established base lines and bench marks indicated on the drawings, and shall be responsible for all measurements in connec52.2-243


File Typeapplication/pdf
File TitleFAR.book
AuthorDorisStallard
File Modified2010-01-13
File Created2010-01-13

© 2024 OMB.report | Privacy Policy