NESHAP for Aerospace Manufacturing and Rework Facilities (40 CFR Part 63, Subpart GG) (Renewal)

OMB: 2060-0314

Document [doc]
Download: doc | pdf

13


SUPPORTING STATEMENT

ENVIRONMENTAL PROTECTION AGENCY


NESHAP for Aerospace Manufacturing and Rework Facilities (40 CFR Part 63, Subpart GG) (Renewal)


1. Identification of the Information Collection


1(a) Title of the Information Collection


NESHAP for Aerospace Manufacturing and Rework Facilities (40 CFR Part 63, Subpart GG) (Renewal), EPA ICR Number 1687.08, OMB Control Number 2060-0314


1(b) Short Characterization/Abstract


The National Emission Standards for Hazardous Air Pollutants (NESHAP) for Aerospace Manufacturing and Rework Facilities were proposed on June 6, 1994, and promulgated on September 1, 1995. This regulation applies to existing and new Aerospace Manufacturing and Rework facilities where the total hazardous air pollutants (HAP) emitted are greater than or equal to 10 tons per year of any combination of HAP, or where the total HAP emitted are greater than or equal to 25 tons per year of any combination of HAP. New facilities include those that commenced construction or reconstruction after the date of the proposal. Operations covered include: cleaning, primer and top coat application, depainting, chemical milling maskant application, and handling and storage of waste. This information is being collected to ensure compliance with 40 CFR part 63, subpart GG.


In general, all NESHAP standards require initial notifications, performance tests, and compliance status reports. Owners or operators are also required to maintain records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of an affected facility, or any period during which the monitoring system is inoperative. Semiannual reports are also required. These notifications, reports, and records are essential in determining compliance, and are required of all sources subject to NESHAP.


Any owner or operator subject to the provisions of this part shall maintain a file of these measurements, and retain the file for at least five years following the date of such measurements, maintenance reports, and records. All reports are sent to the delegated state or local authority. In the event that there is no such delegated authority, the reports are sent directly to the United States Environmental Protection Agency (EPA) regional office.


Based on our consultations with industry representatives, there is an average of two effected facility at each plant site, and each plant site has only one respondent (i.e., the owner/operator of the plant site).


Over the next three years, an average of 136 facilities per year will be subject to the standard, and it is estimated that no additional sources becoming subject to the standard over the next three years.

All of the aerospace manufacturing and rework facilities in the United States are owned and operated by the aerospace manufacturing and rework industry (the “Affected Public”). None of the facilities in the United States are owned by state, local, tribal or the Federal government. They are all privately, owned for-profit businesses. The burden to the “Affected Public” is listed below in Tables 1a through 1c: Annual Respondent Burden and Cost - NESHAP for Aerospace Manufacturing and Rework Facilities (40 CFR Part 63, Subpart GG) (Renewal); the statistics for these three tables are also combined below in Table 1d: Summary of Annual Respondent Burden and Cost for Tables 1a, 1b,& 1c – NESHAP for Aerospace manufacturing and Rework Facilities (40 CFR Part 63, Subpart GG) (Renewal). The Federal government burden associated with the review of reports submitted by the respondent is shown below in Table 2: Average Annual EPA Burden - NESHAP for Aerospace Manufacturing and Rework Facilities (40 CFR Part 63, Subpart GG) (Renewal).


The Office of Management and Budget (OMB) approved the currently active Information Collection Request (ICR) without any “Terms of Clearance.”


2. Need for and Use of the Collection


2(a) Need/Authority for the Collection


The EPA is charged under section 112 of the Clean Air Act, as amended, to establish standards of performance for each category or subcategory of major sources and area sources of HAP. These standards are applicable to new or existing sources of HAP and shall require the maximum degree of emission reduction. In addition, section 114(a) states that the Administrator may require any owner or operator subject to any requirement of this Act to:


(A) Establish and maintain such records; (B) make such reports; (C) install, use, and maintain such monitoring equipment, and use such audit procedures, or methods; (D) sample such emissions (in accordance with such procedures or methods, at such locations, at such intervals, during such periods, and in such manner as the Administrator shall prescribe); (E) keep records on control equipment parameters, production variables or other indirect data when direct monitoring of emissions is impractical; (F) submit compliance certifications in accordance with Section 114(a)(3); and (G) provide such other information as the Administrator may reasonably require.


In the Administrator's judgment, HAP emissions from aerospace manufacturing and rework facilities cause, or contribute to air pollution that may reasonably be anticipated to endanger public health or welfare. Therefore, the NESHAP standards were promulgated for this source category at 40 CFR part 63, subpart GG.


2(b) Practical Utility/Users of the Data


The recordkeeping and reporting requirements in the standard ensure compliance with the applicable regulations which were promulgated in accordance with the Clean Air Act. In addition, the collected information is used for targeting inspections and as evidence in legal proceedings.


Performance tests are required in order to determine an affected facility’s initial capability to comply with the emission standard. Continuous emission monitors are used to ensure compliance with the standard at all times. During the performance tests, a record of the operating parameters under which compliance was achieved may be recorded and used to determine compliance in place of a continuous emission monitor.


The notifications required in the standard are used to inform the Agency or delegated authority when a source becomes subject to the requirements of the regulations. The reviewing authority may then inspect the source to ensure that the pollution control devices are properly installed and operated, that leaks are being detected and repaired, and that the standards are being met. The performance test may also be observed.


The required semiannual reports are used to determine periods of excess emissions, identify problems at the facility, verify operation/maintenance procedures, and for compliance determinations.


The information generated by the monitoring, recordkeeping and reporting requirements described in this ICR is used by the Agency to ensure that facilities affected by the NESHAP continues to operate the control equipment in compliance with the regulation.


3. Non-duplication, Consultations, and Other Collection Criteria


The requested recordkeeping and reporting are required under 40 CFR part 63, subpart GG.


3(a) Non-duplication


If the subject standards have not been delegated, the information is sent directly to the appropriate EPA regional office. Otherwise, the information is sent directly to the delegated state or local agency. If a state or local agency has adopted their own similar standards to implement the Federal standards, a copy of the report submitted to the state or local agency can be sent to the Administrator in lieu of the report required by the Federal standards. Therefore, no duplication exists.


3(b) Public Notice Required Prior to ICR Submission to OMB

An announcement of a public comment period for the renewal of this ICR was published in the Federal Register (75 FR 30813) on June 2, 2010. No comments were received on the burden published in the Federal Register.


3(c) Consultations


The Agency’s industry experts have been consulted, and the Agency’s internal data sources and projections of industry growth over the next three years have been considered. The primary source of information as reported by industry, in compliance with the recordkeeping and reporting provisions in the standard, is the Online Tracking Information System (OTIS) which is operated and maintained by the EPA Office of Compliance. OTIS is the EPA database for the collection, maintenance, and retrieval of all compliance data. The growth rate for the industry is based on our consultations with the Agency’s internal industry experts.


Industry trade associations and other interested parties were provided an opportunity to comment on the burden associated with the standard as it was being developed. We contacted the Aerospace Manufacturing Technologies (AMT) at (360) 435-1119, and Aerospace Industries Association at (703) 358-1000.


3(d) Effects of Less Frequent Collection


Less frequent information collection would decrease the margin of assurance that facilities are continuing to meet the standards. Requirements for information gathering and recordkeeping are useful techniques to ensure that good operation and maintenance practices are applied and emission limitations are met. If the information required by these standards was collected less frequently, the proper operation and maintenance of control equipment and the possibility of detecting violations would be less likely.


3(e) General Guidelines


None of these reporting or recordkeeping requirements violate any of the regulations established by OMB at 5 CFR part 1320, section 1320.5.


These standards require the respondents to maintain all records, including reports and notifications for at least five years. This is consistent with the General Provisions as applied to the standards. EPA believes that the five-year records retention requirement is consistent with the Part 70 permit program and the five-year statute of limitations on which the permit program is based. The retention of records for five years allows EPA to establish the compliance history of a source, any pattern of non-compliance, and to determine the appropriate level of enforcement action. EPA has found that the most flagrant violators have violations extending beyond the five years. Without the five-year record retention, EPA would be prevented from pursuing the violators due to the destruction or nonexistence of essential records.


3(f) Confidentiality


Any information submitted to the Agency for which a claim of confidentiality is made will be safeguarded according to the Agency policies set forth in title 40, chapter 1, part 2, subpart B - Confidentiality of Business Information (CBI) (see 40 CFR 2; 41 FR 36902, September 1, 1976; amended by 43 FR 40000, September 8, 1978; 43 FR 42251, September 20, 1978; 44 FR 17674, March 23, 1979).


3(g) Sensitive Questions


None of the reporting or recordkeeping requirements contain sensitive questions.


4. The Respondents and the Information Requested


4(a) Respondents/SIC Codes


The respondents to the recordkeeping and reporting requirements are aerospace manufacturing and rework facilities. The North American Industry Classification System (NAICS) codes are listed below for each source category description.


40 CFR part 63, subpart GG

SIC Codes

NAICS Codes

Aircraft and Parts

3720


Aircraft Manufacturing

3721

336411

Aircraft Engine and Engine Parts Manufacturing

3724

336412

Other Aircraft Part and Auxiliary Equipment Manufacturing

3728

336413

Fluid Power Valve and Hose Fitting Manufacturing

3728

332912

Aircraft Manufacturing

3728

336411

Guided Missiles, Space Vehicles, and Parts

3760


Guided Missiles and Space Vehicles Manufacturing

3761

336414

Guided Missile and Space Vehicle Propulsion Unit and Propulsion Unit Parts Manufacturing

3764

336415

Other Guided Missile and Space Vehicle Parts and Auxiliary Equipment Manufacturing

3769

336419

Airports, Flying Fields, and Airport Terminal Services

4581

488119


4(b) Information Requested


None of these reporting or recordkeeping requirements violate any of the regulations established by OMB at 5 CFR part 1320, section 1320.5.


(i) Data Items


In this ICR, all the data recorded or reported is required by the NESHAP for Aerospace Manufacturing and Rework Facilities (40 CFR part 63, subpart GG).


A source must make the following reports:


Notifications

Notification of construction and modification

63.743(a)(2-3), 63.6(e), 63.753(a), 63.5(d), 63.10(d)(5)

Initial notification for existing sources

63.9(b)(2), 63.753(a)(2)

Notification of performance test and results

63.7(b), 63.7(g)(1), 63.9(e), 63.10(d)(2), 63.753(a)

Notification and report of physical and operational changes

63.5(b)(6), 63.743(a)(2), 63.753(a)

Notification and report of production capacity

63.9(b)(2), 63.753(a)

Notification and report of compliance status

63.9(h), 63.753(a)

Report of startup, shutdown, malfunction plan

63.10(a), 63.10(d)(5), 63.743(b), 63.753(a)

Notification and report for waiver applications

63.7(h)(3), 63.753(a)

Semiannual report

63.6(e), 63.10(d)(5), 63.10(e)(3), 63.753(b), 63.753(c)(1), 63.753(d)(1) and (3), 63.753(e)

Annual report

63.753(c)(2), 63.753(d)(2)


A source must keep the following records:


Recordkeeping

Records of daily and monthly inspections

63.6(e)(3), 63.10(b)(2), 63.743(a)(3), 63.752(a)

Emission testing

63.10(b)(2), 63.752(a)

Facility operation and maintenance including startup, shutdown, malfunction, construction and modification

63.5(b), 63.6(e), 63.743(a)(2) and (3), 63.743(b), 63.752

Cleaning solvents, all information records

63.752(b)(1)

Cleaning solvents, approved composition and vapor pressure, solvent usage records

63.752(b)(2)

Cleaning solvents, non-approved composition, approved vapor pressure, solvent usage records

63.752(b)(3)

Cleaning solvents, usage log for exempt processes

63.752(b)(4)

Cleaning solvents, log of spray gun cleaner leaks

63.752(b)(5)

Primers/topcoats/maskants: Records using compliant coatings without averaging

63.752(c)(1-3), 63.752(f)(1)

Primers/topcoats/maskants: Records using averaging

63.752(c)(1), 63.752(c)(4), 63.752(f)(2)

Primers/topcoats/maskants: Records using control devices

63.752(c)(1), 63.752(c)(5-6), 63.752(d), 63.752(f)(3), 63.752(f)(4)

Chemical strippers, records and parts removed

63.752(e)(1), 63.752(e)(4)

Chemical strippers, records using control devices

63.752(e)(2), 63.752(e)(3)

Depainting equipment malfunction log

63.752(e)(5)

Annual exempt chemical stripper usage log and reworked airplane log for spot stripping and decal removal

63.752(e)(6)

Depainting control device maintenance log

63.752(e)(7)

5-years retention of records

63.10(b)(1), 63.752(a)


Electronic Reporting


Some of the respondents are using monitoring equipment that automatically records parameter data. Although personnel at the affected facility must still evaluate the data, internal automation has significantly reduced the burden associated with monitoring and recordkeeping at a plant site.


Also, regulatory agencies, in cooperation with the respondents, continue to create reporting systems to transmit data electronically. However, electronic reporting systems are not widely used. At this time, it is estimated that approximately 10 percent of the respondents are reporting electronically.


(ii) Respondent Activities


Respondent Activities

Read instructions.

Install, calibrate, maintain, and operate CMS for opacity, or for pressure drop and liquid supply pressure for control device.

Perform initial performance test, Reference Methods 1, 1A, 2, 2B, 2C, 2D, 3, 4,18, 24, 25A, 40, 301, or 319 test as applicable, and repeat performance test if necessary.

Write the notifications and reports listed above.

Enter information required to be recorded above.

Submit the required reports developing, acquiring, installing, and utilizing technology and systems for the purpose of collecting, validating, and verifying information.

Develop, acquire, install, and utilize technology and systems for the purpose of processing and maintaining information.

Develop, acquire, install, and utilize technology and systems for the purpose of disclosing and providing information.

Train personnel to be able to respond to a collection of information.

Transmit, or otherwise disclose the information.


Currently, sources are using monitoring equipment that provides parameter data in an automated way (e.g., continuous parameter monitoring system). Although personnel at the source still need to evaluate the data, this type of monitoring equipment has significantly reduced the burden associated with monitoring and recordkeeping.





5. The Information Collected: Agency Activities, Collection Methodology, and Information Management


5(a) Agency Activities


EPA conducts the following activities in connection with the acquisition, analysis, storage, and distribution of the required information.


Agency Activities

Observe initial performance tests and repeat performance tests if necessary.

Review notifications and reports, including performance test reports, excess emissions reports, required to be submitted by industry.

Audit facility records.

Input, analyze, and maintain data in the OTIS.


5(b) Collection Methodology and Management


Following notification of startup, the reviewing authority might inspect the source to determine whether the pollution control devices are properly installed and operational. Performance test reports are used by the Agency to discern a source’s initial capability to comply with the emission standard, and note the operating conditions under which compliance was achieved. Data and records maintained by the respondents are tabulated and published for use in compliance and enforcement programs.


Information contained in the reports is entered into OTIS which is operated and maintained by the EPA Office of Compliance. OTIS is the EPA database for the collection, maintenance, and retrieval of compliance data for approximately 125,000 industrial and government-owned facilities. EPA uses OTIS for tracking air pollution compliance and enforcement by local and state regulatory agencies, EPA regional offices, and EPA headquarters. EPA edits, stores, retrieves and analyzes the data.


The records required by this regulation must be retained by the owner or operator for five years.


5(c) Small Entity Flexibility


The majority of the respondents are large entities (i.e., large businesses). However, the impact on small entities (i.e., small businesses) was taken into consideration during the development of the regulation. Due to technical considerations involving the process operations and the types of control equipment employed, the recordkeeping and reporting requirements are the same for both small and large entities. The Agency considers these to be the minimum requirements needed to ensure compliance and, therefore, cannot reduce them further for small entities. To the extent that larger businesses can use economies of scale to reduce their burden, the overall burden will be reduced.


5(d) Collection Schedule


The specific frequency for each information collection activity within this request is shown in Tables 1a through 1c: Annual Industry Burden for NESHAP for Aerospace Manufacturing and Rework Facilities (40 CFR Part 63, Subpart GG) (Renewal).


6. Estimating the Burden and Cost of the Collection


Table 1 documents the computation of individual burdens for the recordkeeping and reporting requirements applicable to the industry for the subpart included in this ICR. The individual burdens are expressed under standardized headings believed to be consistent with the concept of burden under the Paperwork Reduction Act. Wherever appropriate, specific tasks and major assumptions have been identified. Responses to this information collection are mandatory.


The Agency may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB Control Number.


6(a) Estimating Respondent Burden


The average annual burden to industry over the next three years from these recordkeeping and reporting requirements is estimated to be 141,010 (Total Labor Hours from Table 1). These hours are based on Agency studies and background documents from the development of the regulation, Agency knowledge and experience with the NESHAP program, the previously approved ICR, and any comments received.


6(b) Estimating Respondent Costs


This ICR uses the following labor rates:


Managerial $114.49 ($54.52 + 110%)

Technical $98.20 ($46.76 + 110%)

Clerical $48.53 ($23.11 + 110%)


These rates are from the United States Department of Labor, Bureau of Labor Statistics, September 2009, ”Table 2. Civilian Workers, by Occupational and Industry group.” The rates are from column 1, ”Total Compensation.” The rates have been increased by 110 percent to account for the benefit packages available to those employed by private industry.


(ii) Estimating Capital/Startup and Operation and Maintenance Costs


The type of industry costs associated with the information collection activities in the subject standard are labor costs which are addressed elsewhere in this ICR and the costs associated with continuous monitoring. The capital/startup costs are one-time costs when a facility becomes subject to the regulation. The annual operation and maintenance costs are the ongoing costs to maintain the monitor and other costs such as photocopying and postage.


  1. Capital/Startup vs. Operation and Maintenance (O&M) Cost


Capital/Startup vs. Operation and Maintenance (O&M) Costs

(A)

Continuous Monitoring Device

(B)

Capital/

Startup Cost for One Respondent

(C)

Number of New Respondents

(D)

Total

Capital/

Startup Cost

(B X C)

(E)

Annual O&M Costs for One Respondent

(F)

Number of Respondents with O&M

(G)

Total O&M,

(E X F)

CEM

$14,000

0

$0

$1,000

136

$136,000

Total



$0



$136,000


The total capital/startup costs for this ICR are zero. This is the total of column D in the above table.


The total operation and maintenance (O&M) costs for this ICR are $136,000. This is the total of column G.


The average annual cost for capital/startup and operation and maintenance costs to industry over the next three years of the ICR is estimated to be $136,000.


6(c) Estimating Agency Burden and Cost


The only costs to the Agency are those costs associated with analysis of the reported information. The EPA compliance and enforcement program includes activities such as: the examination of records maintained by the respondents; periodic inspection of sources of emissions; and the publication and distribution of collected information.


The average annual Agency cost during the three years of the ICR is estimated to be $199,110.


This cost is based on the average hourly labor rate as follows:


Managerial $62.27 (GS-13, Step 5, $38.92 + 60%)

Technical $46.21 (GS-12, Step 1, $28.88 + 60%)

Clerical $25.01 (GS-6, Step 3, $15.63 + 60%)


These rates are from the Office of Personnel Management (OPM), 2010 General Schedule, which excludes locality rate of pay. The rates have been increased by 60 percent to account for the benefit packages available to government employees. Details upon which this estimate is based appear below in Table 2: Average Annual EPA Burden - NESHAP for Aerospace Manufacturing and Rework Facilities (40 CFR Part 63, Subpart GG) (Renewal).


6(d) Estimating the Respondent Universe and Total Burden and Costs


Based on our research for this ICR, on average over the next three years, approximately 136 respondents will be subject to the standard. It is estimated that no new respondents per year will become subject to the standard. The overall average number of respondents, as shown in the table below is 136 per year.


The number of respondents is calculated using the following table which addresses the three years covered by this ICR.


Number of Respondents

Year

(A)

Number of New Respondents

(B)

Number of Existing Respondents

(C)

Number of Existing Respondents That Keep Records But Do Not Submit Reports

(D)

Number of Existing Respondents That Are Also New Respondents

(E)

Number of Respondents

(E=A+B+C-D)

1

0

136

0

0

136

2

0

136

0

0

136

3

0

136

0

0

136

Average

0

136

0

0

136


To avoid double-counting respondents, column D is subtracted. As shown above, the average Number of Respondents over the three-year period of this ICR is 136.


The total number of annual responses per year is calculated using the following table:


Total Annual Responses

(A)



Information Collection Activity

(B)

Number of Respondents

(C)

Number of Responses

(D)

Number of Existing Respondents That Keep Records But Do Not Submit Reports

(E)

Total Annual Responses

E=(BxC)+D

Notification of construction/reconstruction

0

1

0

0

Notification of physical and operational changes

7

1

0

7

Notification of actual startup

0

1

0

0

Notification of change in production capacity

0

1

0

0

Compliance status information report

136

1

0

136

Waiver application

14

1

0

14

Startup, shutdown, malfunction plan

136

1

0

136

Startup, shutdown, malfunction report

27

1

0

27

Semiannual report – including report of periods of noncompliance

109

2

0

218

Total Number of Annual Responses



Total

538


The number of Total Annual Responses is 538.


The total annual labor costs are $13,294,729. Details regarding these estimates may be found below in Tables 1a through 1c: Annual Respondent Burden and Cost - NESHAP for Aerospace Manufacturing and Rework Facilities (40 CFR Part 63, Subpart GG) (Renewal).


6(e) Bottom Line Burden Hours Burden Hours and Cost Tables


The detailed bottom line burden hours and cost calculations for the respondents and the Agency are shown in Tables 1 and 2, respectively, and summarized below.


(i) Respondent Tally


The total annual labor hours are 141,010. Details regarding these estimates may be found below in Table 1: Annual Respondent Burden and Cost - NESHAP for Aerospace Manufacturing and Rework Facilities (40 CFR Part 63, Subpart GG) (Renewal).


Furthermore, the annual public reporting and recordkeeping burden for this collection of information is estimated to average 262 hours per response.


The total annual capital/startup and Operation and Maintenance (O&M) costs to the regulated entity are $136,000.


(ii) The Agency Tally


The average annual Agency burden and cost over next three years is estimated to be 4,418 labor hours at a cost of $199,110. See below Table 2: Average Annual EPA Burden and Cost – NESHAP for Aerospace Manufacturing and Rework Facilities (40 CFR Part 63, Subpart GG) (Renewal).


6(f) Reasons for Change in Burden


There is no change in the number of affected facilities as compared to the previous ICR. There is a change in the number of responses which is due to a more accurate accounting.


There is however, a small decrease in the estimated labor burden hours as currently identified in the OMB Inventory of approved Burdens. The decrease is not due to any program changes. The change in the labor burden hours occurred because the previous ICR rounded their calculations, and this renewal did not. There is also an increase in the cost estimates as compared to the previous ICR. The change in the cost estimates was caused by the updated labor rates, which resulted in an increase in the labor costs.

6(g) Burden Statement


The annual public reporting and recordkeeping burden for this collection of information is estimated to average 262 hours per response. Burden means the total time, effort, or financial resources expended by persons to generate, maintain, retain, disclose or provide information to or for a Federal agency. This includes the time needed to review instructions; to develop, acquire, install, and utilize technology and systems for the purposes of collecting, validating, and verifying information, processing and maintaining information, and disclosing and providing information; to adjust the existing ways to comply with any previously applicable instructions and requirements; to train personnel to be able to respond to a collection of information; to search data sources; to complete and review the collection of information; and to transmit or otherwise disclose the information.


An agency may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a valid OMB Control Number. The OMB Control Numbers for EPA’s regulations are listed at 40 CFR part 9 and 48 CFR chapter 15.


To comment on the Agency's need for this information, the accuracy of the provided burden estimates, and any suggested methods for minimizing respondent burden, including the use of automated collection techniques, EPA has established a public docket for this ICR under Docket ID Number EPA-HQ-OECA-2010-0373. An electronic version of the public docket is available at http://www.regulations.gov/ which may be used to obtain a copy of the draft collection of information, submit or view public comments, access the index listing of the content of the docket, and to access those documents in the public docket that are available electronically. When in the system, select “search” than key in the docket ID number identified in this document. The documents are also available for public viewing at the Enforcement and Compliance Docket and Information Center in the EPA Docket Center (EPA/DC), EPA West, Room 3334, 1301 Constitution Avenue, N.W., Washington, DC. The EPA Docket Center Public Reading Room is open from 8:30 a.m. to 4:30 p.m., Monday through Friday, excluding legal holidays. The telephone number for the Reading Room is (202) 566-1744, and the telephone number for the Enforcement and Compliance Docket and Information Center Docket is (202) 566-1752. Also, you can send comments to the Office of Information and Regulatory Affairs, Office of Management and Budget, 725 17th Street, N.W., Washington, DC 20503, Attention: Desk Officer for EPA. Please include the EPA Docket ID Number EPA-HQ-OECA-2010-0373 and OMB Control Number 2060-0314 in any correspondence.


Part B of the Supporting Statement


This part is not applicable because no statistical methods were used in collecting this information.

Table 1a: Annual Respondent Burden and Cost - NESHAP for Aerospace Manufacturing and Rework Facilities (40 CFR Part 63, Subpart GG) (Cleaning Operations) (Renewal)


Burden item

(A)

Person hours per occurrence

(B)

No. of occurrences per respondent per year

(C)

Person hours per respondent per year

(C=AxB)

(D)

Respondents per year a

(E)

Technical person- hours per year

(E=CxD)

(F)

Management person hours per year

(Ex0.05)

(G)

Clerical person hours per year

(Ex0.1)

(H)

Total Cost

Per year b


1. Applications

N/A








2. Surveys and studies

N/A








3. Reporting requirements









A. Read instructions c

1

1

1

136

136

6.8

13.6

$14,793.74

B. Required activities

N/A








C. Create information

See 3E & 4C








D. Gather existing information

See 3E & 4C








E. Write report









Notification of construction/reconstruction

2

1

2

0

0

0

0

$0

Notification of physical and operational changes d

8

1

8

7

56

2.8

5.6

$6,091.54

Notification of actual startup

2

1

2

0

0

0

0

$0

Notification of change in production capacity

2

1

2

0

0

0

0

$0

Compliance status information report e

20

1

20

136

2,720

136

272

$285,314.67

Waiver application f

4

1

4

14

56

2.8

5.6

$6,091.54

Startup, shutdown, malfunction plan g

4

1

4

136

544

27.2

54.4

$59,174.96

Preparation of site-specific test plan

N/A








Notification of initial performance test

N/A








Report of initial test

N/A








Startup, shutdown, malfunction report h

2

1

2

27

54

2.7

5.4

$5,873.98

Semiannual report – including report of periods of

noncompliance i

12

2

24

109

2,616

130.8

261.6

$284,561.94

Subtotal for Reporting Requirements






7,109.3



4. Recordkeeping requirements









A. Read instructions

See 3A








B. Plan activities

4

1

4

136

544

27.2

54.4

$59,174.96

C. Implement activities









Solvent information records

4

2

8

136

1,088

54.4

108.8

118,349.92

Approved composition solvent records

(demonstrating compliance) j

4

1

4

41

164

8.2

16.4

$17,839.51

Non-approved list solvent usage records k

1

12

12

122

1,464

73.2

146.4

$158,250.26

Solvent usage log for exempt processes l

0.5

12

6

95

570

28.5

57

$62,003.17

Log of gun cleaner leaks m

1

6

6

27

162

8.1

16.2

$17,621.96

D. Develop record system n

20

1

20

136

2,720

136

272

$285,314.67

E. Time to enter information









Records of startup, shutdown, and malfunction

2

1

2

27

54

2.7

5.4

$5,873.93

Records of all measurements and information

required by standard









F. Time to train personnel o

4

50

200

136

27,200

1,360

2,720

2,958,748.00

G. Time for audits

20

1

20

136

2,720

136

272

$285,314.67

Subtotal for Recordkeeping Requirements






42,188.9








42,868

2,143.4

4,286.8

$4,630,393.42

TOTAL LABOR BURDEN AND COST (rounded)






49,298.2

49,298 (rounded)


$4,630,393


Assumptions:

a We have assumed that the average number of respondents that will be subject to this rule will be 136. There will be no new additional sources during the next three years of this ICR.

b This ICR uses the following labor rates: $114.49 per hour for Executive, Administrative, and Managerial labor; $98.20 per hour for Technical labor, and $48.53 per hour for Clerical labor. These rates are from the United States Department of Labor, Bureau of Labor Statistics, September, 2009, Table 2. Civilian Workers, by Occupational and Industry group. The rates are from column 1, Total Compensation. The rates have been increased by 110 percent to account for the benefit packages available to those employed by private industry.

c We have assumed that there will be no net growth for the industry over the three-year period of this ICR, only existing sources will read instructions.

d We have assumed that 5 percent of the total existing facilities will write the physical and operational changes report.

e We have assumed that each respondent will write compliance status information report.

f We have assumed that 10 percent of the respondents will request a waiver.

g This is based on the number of facilities with add-on control systems that require the development of inspection and maintenance and startup, shutdown, malfunction plan. We have assumed that all of the facilities will have enclosed gun cleaners.

h We have assumed that 20 percent of facilities with add-on control system will have a malfunction.

i We have assumed that 80 percent of facilities will have excess emissions or will change their process in some way.

j We have assumed that 30 percent of facilities will use the approved list of solvents.

k We have assumed that 90 percent of facilities will use some solvents not on the approved list.

l We have assumed that 70 percent of facilities will use some solvents for exempt processes.

m We have assumed that 20 percent of facilities will have a leak in their enclosed gun cleaner.

n We have assumed that all facilities will need to develop a record keeping system.

o We have assumed that each respondent will take 4 hours 50 times per year to complete task.

Table 1b: Annual Respondent Burden and Cost - NESHAP for Aerospace Manufacturing and Rework Facilities (40 CFR Part 63, Subpart GG) (Coating Operations) (Renewal)


Burden item

(A)

Person hours per occurrence

(B)

No. of occurrences per respondent per year

(C)

Person hours per respondent per year

(C=AxB)

(D)

Respondents per year a

(E)

Technical person- hours per year

(E=CxD)

(F)

Management person hours per year

(Ex0.05)

(G)

Clerical person hours per year

(Ex0.1)

(H)

Total Cost

Per year b


1. Applications

N/A








2. Surveys and studies

N/A








3. Reporting requirements









A. Read instructions c

1

1

1

136

136

6.8

13.6

$14,793.74

B. Required activities









Initial performance tests d

280

1

280

4

1,120

56

112

$121,830.80

Repeat performance test e

280

1

280

1

280

14

28

$30,457.70

C. Create information

See 3E & 4C








D. Gather existing information

See 3E & 4C








E. Write report









Notification of construction/reconstruction

2

1

2

0

0

0

0

$0

Notification of physical and operational changes f

8

1

8

7

56

2.8

5.6

$6,091.54

Notification of actual startup

2

1

2

0

0

0

0

$0

Notification of change in production capacity

2

1

2

0

0

0

0

$0

Compliance status information report

10

1

10

136

1,360

68

136

$147,937.40

Waiver application g

4

1

4

14

56

2.8

5.6

$6,091.54

Startup, shutdown, malfunction plan h

4

1

4

41

164

8.2

16.4

$17,839.51

Preparation of site-specific test plan

See 3B








Notification of initial performance test

2

1

2

4

8

0.4

0.8

$870.22

Report of initial test

See 3B








Startup, shutdown, malfunction report i

4

1

4

27

108

5.4

10.8

$11,747.97

Semiannual report – including report of periods of

noncompliance j

11

2

22

109

2,398

119.9

239.8

$260,848.44

Subtotal for Reporting Requirements






6,538.9



4. Recordkeeping requirements









A. Read instructions

See 3A








B. Plan activities

4

1

4

136

544

27.2

54.4

$59,174.96

C. Implement activities









Compliance coating records

1

12

12

136

1,632

81.6

163.2

$177,524.88

Daily records of weighted average mass k

1

250

250

14

3,500

175

350

$380,721.25

Control device maintenance or rolling material

balance log (organics)

0.5

250

125

4

500

25

50

$54,388.75

Control device maintenance log (inorganics)

0.25

250

63

136

8,568

428.4

856.8

$932,005.62

D. Develop record system l

10

1

10

136

1,360

68

136

$147,937.40

E. Time to enter/maintain information









Records of startup, shutdown, and malfunction

2

1

2

27

54

2.7

5.4

$5,873.98

Records of all measurements and information

required by standard

See 4C








F. Time to train personnel

8

50

400

136

54,400

2,720

5,440

$5,917,496.00

G. Time for audits

20

1

20

136

2,720

136

272

$285,314.67

Subtotal for Recordkeeping Requirements






84,269.7








78,964

3,948.2

7,896.4

$8,578,946.37

TOTAL LABOR BURDEN AND COST (rounded)






90,808.6

90,809 (rounded)


$8,578,946

Assumptions:

a We have assumed that the average number of respondents that will be subject to this rule will be 136. There will be no new additional sources during the next three years of this ICR.

b This ICR uses the following labor rates: $114.49 per hour for Executive, Administrative, and Managerial labor; $98.20 per hour for Technical labor, and $48.53 per hour for Clerical labor. These rates are from the United States Department of Labor, Bureau of Labor Statistics, September, 2009, Table 2. Civilian Workers, by Occupational and Industry group. The rates are from column 1, Total Compensation. The rates have been increased by 110 percent to account for the benefit packages available to those employed by private industry.

c We have assumed that there will be no net growth for the industry over the three-year period of this ICR, only existing sources will read instructions.

d We have assumed that 10 percent of existing facilities will use add-on control equipment for maskant application (40x10%).

e We have assumed that 20 percent of existing facilities with add-on control equipment will repeat performance test (40x20%x10%).

f We have assumed that 5 percent of existing facilities will write the physical and operational changes report.

g We have assumed that 10 percent of facilities will request a waiver.

h We have assumed that 30 percent of facilities will be required to submit operational plans due to deviations from manufacturers’ specifications, and based on the number of facilities with add-on control systems that require the development of inspection, maintenance, startup, shutdown, and malfunction plans.

i We have assumed that 20 percent of facilities with add-on control system (including particulate filters) will have a malfunction.

j We have assumed that 80 percent of facilities will have excess emissions or will change their process in some way.

k The final rule required monthly records. Daily averaging was included in the cost analysis because 90 percent of the industry is located in non-attainment areas and will be required to use daily averaging by the permitting agency.

l We have assumed that all facilities will need to develop a record keeping system.

Table 1c: Annual Respondent Burden and Cost - NESHAP for Aerospace Manufacturing and Rework Facilities (40 CFR Part 63, Subpart GG) (Depainting Operations) (Renewal)


Burden item

(A)

Person hours per occurrence

(B)

No. of occurrences per respondent per year

(C)

Person hours per respondent per year

(C=AxB)

(D)

Respondents per year a

(E)

Technical person- hours per year

(E=CxD)

(F)

Management person hours per year

(Ex0.05)

(G)

Clerical person hours per year

(Ex0.1)

(H)

Total Cost

Per year b


1. Applications

N/A








2. Surveys and studies

N/A








3. Reporting requirements









A. Read instructions c

1

1

1

5

5

0.25

0.5

$543.88

B. Required activities

N/A








Initial performance tests d

280

1

280

0

0

0

0

$0

Repeat performance test e

280

1

280

0

0

0

0

$0

C. Create information

See 3E & 4C








D. Gather existing information

See 3E & 4C








E. Write report









Notification of construction/reconstruction

2

1

2

0

0

0

0

$0

Notification of physical and operational changes f

8

1

8

0

0

0

0

$0

Notification of actual startup

2

1

2

0

0

0

0

$0

Notification of change in production capacity

2

1

2

0

0

0

0

$0

Compliance status information report

10

1

10

5

50

2.5

5

$5,438.87

Waiver application g

4

1

4

0

0

0

0

$0

Startup, shutdown, malfunction plan h

5

1

5

0

0

0

0

$0

Preparation of site-specific test plan

N/A








Notification of initial performance test

2

1

2

0

0

0

0

$0

Report of initial test

See 3B








Startup, shutdown, malfunction report i

4

1

4

0

0

0

0

$0

Semiannual report – including report of periods of

Noncompliance j

12

2

24

4

96

4.8

9.6

$10,442.64

Subtotal for Reporting Requirements






173.65



4. Recordkeeping requirements









A. Read instructions

See 3A








B. Plan activities

4

1

4

5

20

1

2

$2,175.55

C. Implement activities k









Chemical stripper records (demonstrating

compliance)

8

1

8

4

32

1.6

3.2

$3,480.88

Chemical stripper usage log

1

12

12

4

48

2.4

4.8

$5,221.32

Depainting equipment malfunction log

4

3

12

2

24

1.2

2.4

$2,610.66

Exempt stripper usage log and reworked airplane

log spot stripping and decal removal

1

12

12

5

60

3

6

$6,526.65

Record of parts removed for parts depainting

8

2

16

5

80

4

8

$8,702.20

Control device maintenance log

0.5

250

125

2

250

12.5

25

$27,194.37

D. Develop record system l

10

1

10

5

50

2.5

5

$5,438.87

E. Time to enter information









Records of startup, shutdown, and malfunction

2

1

2

0

0

0

0

$0

Records of all measurements and information

required by standard

See 4C








F. Time to train personnel

4

1

4

5

20

1

2

$2,175.55

G. Time for audits

10

1

10

5

50

2.5

5

$5,438.87

Subtotal for Recordkeeping Requirements






729.1








785

39.25

78.5

$85,390.31

TOTAL LABOR BURDEN AND COST (rounded)






902.75

903 (rounded)


$85,390


Assumptions:

a We have assumed that the average number of respondents that will be subject to this rule will be 136. There will be no new additional sources during the next three years of this ICR.

b This ICR uses the following labor rates: $114.49 per hour for Executive, Administrative, and Managerial labor; $98.20 per hour for Technical labor, and $48.53 per hour for Clerical labor. These rates are from the United States Department of Labor, Bureau of Labor Statistics, September, 2009, Table 2. Civilian Workers, by Occupational and Industry group. The rates are from column 1, Total Compensation. The rates have been increased by 110 percent to account for the benefit packages available to those employed by private industry.

c We have assumed that there will be no net growth for the industry over the three-year period of this ICR, only existing sources will read instructions..

d We have assumed that 1 percent of the total existing facilities will use add-on control equipment for HAP containing chemical stripper usage (70% of 5).

e We have assumed that 20 percent of facilities with add-on control equipment will repeat performance test (20% of 1% of 5).

f We have assumed that 5 percent of existing facilities (total facilities include only the 96 rework facilities) will write the physical and operational changes report.

g We have assumed that 10 percent of facilities will request a waiver.

h This is based on the number of facilities with add-on control systems that require the development of inspection and maintenance and startup, shutdown, malfunction plan. We have assumed that 15 percent will use blasting equipment that must have add-on control equipment. Assume that 29 percent of blasting operations will operate particulate control systems according to manufacturer’s specifications and that only 30 percent will be required to submit operational plans due to deviations from manufacturer specification. Also assume that 1 percent of all facilities will use HAP containing chemical strippers with emissions control systems and 70 percent will use non-HAP chemical strippers which do not require add-on

control equipment.

i We have assumed that 20 percent of facilities with add-on control system will have a malfunction.

j We have assumed that 80 percent of facilities will have excess emissions or will change their process in some way.

k We have assumed that 1 percent of facilities will use HAP containing chemical strippers as the primary stripping techniques, 29 percent will use media blasting equipment, 70 percent

will use non-HAP chemical strippers, and 100 percent of facilities will use some HAP stripper for exempt processes.

l We have assumed that all respondents will need to develop a record keeping system.



























Table 1d: Summary of Annual Respondent Burden and Cost for Tables 1a, 1b, & 1c - NESHAP for Aerospace Manufacturing and Rework Facilities (40 CFR Part 63, Subpart GG) (Renewal)



Burden

Burden Hours per Year for

Reporting

Burden Hours per Year for Recordkeeping

Total Burden Hours per

Year

Annual

Costs in

$ (rounded)

1a. Cleaning Operations

7,109.3

42,188.9

49,298.2

$4,630,393

1b. Coating Operations

6,538.9

84,269.7

90,808.6

$8,578,946

1c. Depainting Operations

173.65

729.1

902.75

$85,390

Total Burden and Cost (rounded)

13,822

127,188

141,010

$13,294,729





















Table 2: Average Annual EPA Burden - NESHAP for Aerospace Manufacturing and Rework Facilities (40 CFR Part 63, Subpart GG)

(Renewal)


Activity

(A)

EPA person- hours per occurrence

(B)

No. of occurrences per plant per year

(C)

EPA person- hours per plant per year

(C=AxB)

(D)

Plants per year a

(E)

Technical person- hours per year

(E=CxD)

(F)

Management person-hours per year

(Ex0.05)


(G)

Clerical person-

hours per year

(Ex0.1)

(H)

Cost, $ b

1. Initial performance test

80

1

80

0

0

0

0

$0

2. Repeat performance test









Retesting preparation c

16

1

16

1

16

0.8

1.6

$829.20

Retesting d

80

1

80

0

0

0

0

$0

3. Report review









Notification of construction/reconstruction

2

1

2

0

0

0

0

$0

Notification of physical or operational changes e

2

1

2

14

28

1.4

2.8

$1,451.09

Notification of anticipated startup

2

1

2

0

0

0

0

$0

Notification of actual startup

2

1

2

0

0

0

0

$0

Notification of changes in production capacity

2

1

2

0

0

0

0

$0

Compliance status information report f

6

1

6

279

1,674

83.7

167.4

$86,754.21

Waiver application g

6

1

6

28

168

8.4

16.8

$8,706.52

Review of startup, shutdown, malfunction plan h

6

1

6

177

1,062

53.1

106.2

$55,037.62

Review of site specific test plan

N/A








Notification of initial performance test i

2

1

2

4

8

0.4

0.8

$414.60

4. Report review









Report of initial test

8

1

8

0

0

0

0

$0

Review of startup, shutdown, malfunction reports

4

1

4

55

220

11

22

$11,401.39

Review of semiannual reports j

3

1

3

222

666

33.3

66.6

$34,515.12

Subtotals Labor Burden and Cost





3,842

192.1

384.2

$199,109.75

TOTAL ANNUAL BURDEN AND COST (rounded)





4,418.3

4,418 (rounded)

$199,110


Assumptions:

a We have assumed that the average number of respondents that will be subject to this rule will be 136. There will be no new additional sources during the next three years of this ICR.

b This cost is based on the following labor rates which incorporates a 1.6 benefits multiplication factor to account for government overhead expenses: $62.27 Managerial rate (GS-13, Step 5, $38.92 x 1.6), $46.21 Technical rate (GS-12, Step 1, $28.88 x 1.6), and $25.01 Clerical rate (GS-6, Step 3, $15.63 x 1.6). These rates are from the Office of Personnel Management (OPM) 2010 General Schedule which excludes locality rates of pay.

c We have assumed that it will take each respondent 16 hours to prepare for retesting.

d We have assumed that 20 percent of respondents will fail the initial performance test and will have to be retested.

e We have assumed that it will take each of the respondents two hours once per year to review the compliance status information report..

f We have assumed that it will take each respondent six hours to review the compliance status information report.

g We have assumed that 28 respondents will each take 6 hours to review the waiver application.

h We have assumed that it will take each respondent six hours to review the startup, shutdown, malfunction plan.

i We have assumed that it will take each respondent 2 hours to review the initial performance test.

j We have assumed that it will take each respondent 3 hours to review the semiannual report.