1587j11

1587j11.docx

State Operating Permit Regulations (40 CFR part 70) (Change Worksheet for Tailoring Rule and SIP Fix Implementation Rule)

1587j11

OMB: 2060-0243

Document [docx]
Download: docx | pdf

State Operating Permit Regulations (40 CFR part 70)

EPA Number 1587.11, OMB Control Number 2060-0243

Change Worksheet Justification



Introduction

The analysis in this document was performed to support changes in the Title V Operating Permit Regulations (40 CFR Part 70) Information Collection Request (ICR), OMB tracking number 2060-0243. This update is assigned EPA tracking number ICR #1587.11. The Part 70 Program ICR was last renewed in September 2007 and expires in April 2012. In the interim, the following changes are underway.

The EPA is proceeding with the implementation of the Flexible Air Permitting Rule, and these changes are addressed in a separate ICR completed in November 2008.1 This rule promotes the use of flexible air permits (FAPs), which is a permit designed to facilitate flexible market-responsive operations at an industrial facility while ensuring equal or greater environmental protection than conventional air permits. Through this action, the Agency anticipates cost savings to subject sources to be approximately $2.4 million annually, while permitting authorities should experience $2.3 million annual cost savings. The Agency is estimated to expend over $205,000 additional cost during the same time frame.

The Prevention of Significant Deterioration and Title V Greenhouse Gas Tailoring Rule (“Tailoring Rule”) was finalized in May 2010. To reflect the impact of including greenhouse gases (GHGs) in title V permitting programs, the corresponding changes were made to the title V burden estimates. These changes are explained in further detail in this change worksheet.







The Tailoring Rule

This final rule “tailors” the requirements of the Clean Air Act (CAA) permitting programs to limit which facilities will be required to obtain title V operating permits. The rule establishes a schedule that will initially focus Part 70 operating permit programs on the largest sources with the most permitting experience, then expanding to cover the largest sources of greenhouse gases GHGs that may not have been previously covered by the CAA for other pollutants.

Under Step 1, occurring from January 2011 through June 2011, only sources required to have title V permits for non-GHG pollutants (i.e., “anyway” title V sources) will be required to address GHGs as part of their title V permitting. During this time, no sources would be subject to title V requirements due solely to GHG emissions.

Building on Step 1, Step 2 is in effect from July 2011 through June 2013. A source may be subject to title V permitting solely on the basis of its GHG emissions, provided the source exceeds the established Tailoring Rule thresholds. GHG emission sources that emit or have the potential to emit at least 100,000 tpy CO2e, and also emit or have the potential to emit 100 tpy of GHGs on a mass basis will be required to obtain a title V permit if they do not already have one.



Changes

Information obtained for this assessment of estimated resource requirements came from the burden analysis for the Tailoring Rule.2 For this rule, the EPA determined the approximate number of affected sources and the different burdens associated with each permitting action involving GHGs. Before the current ICR expires, permitting authorities will undergo six months of Step 1 and 18 months of Step 2.

The most recent title V program ICR estimates that 50 permits are completed every year for new sources.3 For this analysis, it is assumed that all 50 of these typically large industrial-type sources will be capable of potentially emitting GHG and will need to add GHG-related requirements to the permit. The estimated burden per title V permit in the ICR represents an average of multiple pollutants; EPA estimates the addition of GHGs will add an additional 10% of the time currently estimated for a new title V permit. Ten percent is considered to be appropriate amount because for the most part, these sources will simply need to add information concerning inventory, reporting, or monitoring of their GHG emissions, as appropriate, which they can readily do.

Out of the 3,267 permit renewals conducted annually, the EPA estimates that 80% may potentially emit GHGs above the threshold due to combustion activities.4 Therefore, approximately 2,614 sources will need to address GHG in the new version of the permit. For such permit renewals, the EPA assumes that the inclusion of GHGs will require adding an additional 10% to the average time to process and issue. This equates to 99 and 220 additional burden hours for the permitting authorities and sources respectively.

Revisions to title V permits will also be necessary based on the number of modifications calculated for this analysis. Revisions occurring specifically due to GHG may involve significant revisions, minor revisions, or administrative actions to operating permits. EPA estimates that this activity will require 40 hours per permit on average for permitting authorities to complete.5 At any level, it is assumed that the 448 modifications involving combustion that occur annually will need to include any GHG requirements in the revision of their respective title V permits. EPA estimates that permitting authorities will spend, in addition to the current burden to issue a title V permit revision, an additional 10% of the 40 hours needed to complete this process, or four hours per action. Sources will experience a similar increase in burden, adding 4 more hours to the average revision time.

Permitting Authorities

Based on the Tailoring Rule burden analysis, this update distinguishes between two types of sources – industrial and commercial/residential - with differences in associated burdens. The EPA estimates that an industrial permit due solely to GHGs will require the same amount of time to process and issue as a conventional pollutant, or 428 hours, as shown in Table 1. New commercial/residential permits will require only 50% of that time, or 214 hours.

Table 2 identifies the average burden by activity for the permitting authorities. Estimates are greater than the previous ICR primarily due to the increase in affected source numbers. Twenty-seven new commercial/residential sources and 258 residential sources are expected to require a title V permit during this time due to GHG emissions. For an anyway source entering the title V program due to conventional pollutants, a permitting authority will spend an estimated 43 additional hours to account for any applicable requirements associated with GHGs, bringing the average burden to 471 hours per permit.



Sources

The EPA estimates that an industrial permit due solely to GHGs will require the same amount of time to process and issue as a conventional pollutant, or 350 hours, as shown in Table 3. New commercial/residential permits will require only 50% of that time, or 180 hours.

Source burden, shown in Table 4, is expected to increase throughout the remaining two years of this ICR. As noted for permitting authorities, 27 new commercial/residential sources are expected to require a title V permit during this time, as well as approximately 258 industrial sources. For an anyway source in the title V program due to conventional pollutants, an additional 34 hours will be spent including applicable GHG requirements, bringing the average burden to 374 hours per permit. Overall, the annual burden for sources is estimated to be 4.3 million hours.



Agency

The Tailoring Rule and its supporting documents did not focus on Agency burden impacts. However, due to the increase in sources subject to title V more time will be spent processing and revising title V permit applications. Updated burden estimates are represented in Table 5. The total annual effort is almost 41,000 hours at a cost of $1.8 million.



Additional Burden Due to Recent Actions

Tables 6 and 7 highlight the burden impacts occurring as a result of the most recent program actions. The total additional burden for permitting authorities is estimated at 225,824 hours for the two-year period, while sources will experience a combined approximate burden of 262,791 hours.

While the number of responding permitting authorities will remain the same, over the next two years there will be 285 additional sources that will respond due to GHGs.

Incorporating these burden revisions into the currently approved Part 70 program ICR leads to an overall increase of 244,307 hours annually for respondents, bringing the overall burden to almost 5.7 million hours. In addition, the total number of respondents will increase to an estimated17,073 annually.

















Table 1. Average Permitting Authority Burden per GHG Title V Permit

Activity

Burden Hours per Permit - Industrial

Burden Hours per Permit - Commercial/ Residentiala

Permit Application Review

100

33

Draft Permits Preparation

150

50

Comment Period Notification

10

10

Hold Public Hearings

100

90

Interaction with EPA

20

5

Analyze Public Comments

40

20

Permits Issuance

8

6

Total Burden

428

214

aCommercial/residential permits will be simpler, so the permitting authority would take about 1/3 of the time to review the permit application and draft the permit than it would for an industrial source permit. The comment period notification and time for public hearings, however, would be about the same because of the fixed time necessary to provide notice and hold hearings. The amount of time interacting with EPA would be much less due to the relative simplicity of the permits. Analyzing public comments would take half as long as for an industrial permit because although the permits are much simpler, there could be a fair amount of public interest because of the location of the source. Permit issuance would take slightly less time than for an industrial source since most of the costs are fixed.









Table 2. Permitting Authority Burden and Cost (Annual)

Activity

Number of Units

Hours per Unit

Total Hours

Total Cost ($)b

Annual Hours

Annual Cost ($)

Year 1a

Year 2

Program Administration

112 Programs

112 programs

3500

784,000

$36,064,000

392,000

$18,032,000

Permit Preparation and Issuancec

 

New Industrial Permit due to GHG

86

172

428

110,424

$5,079,504

55,212

$2,539,752

 

New Industrial Permit - add GHG component

50

50

471

47,100

$2,166,600

23,550

$1,083,300

 

New Commercial/Residential Permit

9

18

214

5,778

$265,788

2,889

$132,894

General Permits Administration

112 Programs

112 programs

80

17,920

$824,320

8,960

$412,160

Permit Revisions

 

Permit Revisions - Due to GHG

458

915

40

54,920

$2,526,320

27,460

$1,263,160

 

Permit Revisions - add GHG to Current Non-GHG Permits

448

448

4

3,584

$164,864

1,792

$82,432

 

Permit Revisions - Significant

1394

1394

90

250,920

$11,542,320

125,460

$5,771,160

 

Permit Revisions - Minor

6968

6968

30

418,080

$19,231,680

209,040

$9,615,840

 

Permit Revisions - Administrative

6968

6968

5

69,680

$3,205,280

34,840

$1,602,640

Permit Renewals

 

Permit Renewals w/addition of GHG

2614

2614

99

517,572

$23,808,312

258,786

$11,904,156

 

Permit Renewals

653

653

90

117,540

$5,406,840

58,770

$2,703,420

 

Review General Permits

622

622

10

12,440

$572,240

6,220

$286,120

 

Review Monitoring and Compliance Certification Reports

16,603

16,603

15

498,090

$22,912,140

249,045

$11,456,070

 

Annual Enforcement Activity Reporting

112 Programs

112 programs

40

8,960

$412,160

4,480

$206,080

Totals

 

 

 

2,917,008

$134,182,368

1,458,504

$67,091,184

aYear 1 is comprised of Step 1 and six months of Step 2 under the GHG Tailoring Rule; throughout Year 2 Step 2 will be in place.

bSalaries from Title V ICR adjusted to 2007 dollars using 2007 OPM General Schedule Salary Table available at: http://www.opm.gov/oca/07tables/index.asp

cIncorporating GHG information/requirements into new, revised, and renewed permits adds an additional 10% to the current time.

dNew commercial/residential permits require half the time needed for new industrial permits

eThe Title V ICR estimates that 3,267 permits annually undergo renewal and we estimate that 80% of these will involve combustion. Therefore, 2,614 must add GHG requirements; while 653 do not.



Table 3. Average Source Burden per GHG Title V Permit

Activity

Burden Hours per Permit - Industrial

Burden Hours per Permit - Commercial/ Residentiala

Prepare Application

300

150

Draft Permits Interaction

40

20

Public Hearing Participation

10

10

Total Burden

350

180

aCommercial/residential permit applications will be significantly simpler than industrial source title V permit applications. However, due to their inexperience, we estimate commercial/residential sources will take half as long to complete their steps for their permit application as it will for industrial sources to complete their steps. Less interaction, again 50% less time, will be needed with permitting authorities during the permit drafting process. Finally, public hearing participation will likely require the same amount of time because of the fixed time burdens necessary to complete hearings.





Table 4. Source Respondent Burden and Cost (Annual)

Activity

Number of Units

Hours per Unit

Total Hours

Total Cost (s)a

Annual Hours

Annual Cost ($)

Year 1

Year 2

Prepare Application

 

Industrial Permit due to GHG

86

172

300

77,400

$11,455,200

38,700

$5,727,600

 

Industrial Permit - add GHG component to Non-GHG Permit

50

50

330

33,000

$4,884,000

16,500

$2,442,000

 

Commercial/Residential Permit

9

18

150

4,050

$599,400

2,025

$299,700

Draft Permit

 

Industrial

86

172

40

10,320

$402,480

5,160

$201,240

 

Add GHG component to new Non-GHG Permit

50

50

44

4,400

$171,600

2,200

$85,800

 

Commercial/Residential

9

18

20

540

$21,060

270

$10,530

Gap Filling Monitoring Development

54

54

40

4,320

$168,480

2,160

$84,240

Public Hearing Participation

3

4

10

70

$2,730

35

$1,365

Operate Gap Filling Monitoring

8302

8302

200

3,320,800

$129,511,200

1,660,400

$64,755,600

Prepare Monitoring Reports

16,603

16,603

80

2,656,480

$103,602,720

1,328,240

$51,801,360

Permit Revisions

 

Significant Permit Modifications

1394

1394

80

223,040

$8,698,560

111,520

$4,349,280

 

Minor Permit Modifications

6968

6968

40

557,440

$21,740,160

278,720

$10,870,080

 

Administrative Amendments

6968

6968

8

111,488

$4,348,032

55,744

$2,174,016

 

Permit Revisions - due to GHG

 

915

43

39,345

$1,534,455

19,673

$767,228

 

Permit Revisions - add GHG to current non-GHG permits

448

448

4

3,393

$132,321

1,696

$66,161

Permit Renewals

 

General Permit Renewal

622

622

2

2,488

$97,032

1,244

$48,516

 

Permit Renewals w/addition of GHG

2614

2614

220

1,150,160

$44,856,240

575,080

$22,428,120

 

Permit Renewals

653

653

200

261,200

$10,186,800

130,600

$5,093,400

 

Other Activities

3267

3267

20

130,680

$5,096,520

65,340

$2,548,260

Totals

 

 

 

8,590,614

$335,033,940

4,295,307

$167,516,970

aYear 1 is comprised of Step 1 and six months of Step 2 under the GHG Tailoring Rule; throughout Year 2 Step 2 will be in place.

bSalaries from Title V ICR adjusted to 2007 dollars using 2007 OPM General Schedule Salary Table available at: http://www.opm.gov/oca/07tables/index.asp

cIncorporating GHG information/requirements into new, revised, and renewed permits adds an additional 10% to the current time.

dNew commercial/residential permits require half the time needed for new industrial permits

eThe Title V ICR estimates that 3,267 permits annually undergo renewal and we estimate that 80% of these will involve combustion.







Table 5. Agency Burden and Cost for the Two-Year Period

Activity

Number of Units

Hours per Unit

Total Hours

Total Cost (s)

Annual Hours

Annual Cost ($)

Year 1a

Year 2

Review Permits and Revisions

 

New Permitsb

36

60

20

1,920

$86,688

960

$43,344

 

Renewals

163

163

20

6,520

$294,378

3,260

$147,189

 

Permit Revisions due to GHGsc

458

915

8

10,984

$495,928

5,492

$247,964

 

Significant Permit Revisions

1,394

1,394

8

22,304

$1,007,026

11,152

$503,513

 

Minor Permit Revisions

6,968

6,968

1

13,936

$629,210

6,968

$314,605

Consult with Permitting Authority

 

New Permits

36

60

8

768

$34,675

384

$17,338

 

Permit Revisions due to GHGs

115

229

8

2,752

$124,253

1,376

$62,126

 

Significant Permit Revisions

348

348

8

5,568

$251,395

2,784

$125,698

 

Minor Permit Revisions

1,742

1,742

1

3,484

$157,303

1,742

$78,651

Program Oversight

112 Programs

112 Programs

50

11,200

$505,680

5,600

$252,840

Review the Annual Report

112

112

10

2,240

$101,136

1,120

$50,568

Totals




81,676

$3,687,671

40,838

$1,843,836

aYear 1 is comprised of Step 1 and six months of Step 2 under the GHG Tailoring Rule; throughout Year 2 Step 2 will be in place.

bReview and consultation conducted on approximately 25% of permits annually

cPermit revisions due to GHGs [add text for the fact these are separate?] are assumed to require the same amount of review and consultation time as significant or minor permit revisions.













Table 6. Additional Permitting Authority Burden and Cost For the Two-Year Period

Activity

Burden Hour per Permit

Affected Permits

Total Burden (hours)

Total Cost ($2007)b

Year 1a

Year 2

New Permit Preparation and Issuance - Industrial

428

86

172

110,281

5,072,941

Add GHG component to new Non-GHG Permitb

43

50

50

4,300

$197,800

New Permit Preparation and Issuance - Commercial/Residentialc

214

9

18

5,707

$262,507

Permit Revisions - due to GHG

40

458

915

54,900

$2,525,400

Permit Revisions - add GHG to Current Non-GHG Permits

4

448

448

3,584

$164,864

Permit Renewalsd

9

2614

2,614

47,052

$2,164,392

Total Additional Burden

 

 

 

225,824

$10,387,904

aYear 1 is comprised of Step 1 and six months of Step 2 under the GHG Tailoring Rule; throughout Year 2 Step 2 will be in place.

 

bSalaries from Title V ICR adjusted to 2007 dollars using 2007 OPM General Schedule Salary Table available at: http://www.opm.gov/oca/07tables/index.asp

cIncorporating GHG information/requirements into new, revised, and renewed permits adds an additional 10% to the current time.

dNew commercial/residential permits require half the time needed for new industrial permits

eThe Title V ICR estimates that 3,267 permits annually undergo renewal and we estimate that 80% of these will involve combustion.















Table 7. Additional Source Burden and Cost For the Two-Year Period

Activity

Burden Hour per Permit

Rate per Houra

Affected Permits

Total Burden (hours)

Total Cost ($2007)b

Year 1a

Year 2

Prepare Application - Industrial

300

$148

86

172

77,300

$11,440,400

Prepare Application - add GHG component to Non-GHG Permitc

30

$148

50

50

3,000

$444,000

Prepare Application - Commercial/Residentiald

150

$148

9

18

4,000

$592,000

Draft Permit - Industrial

40

$39

86

172

10,307

401,960

Draft Permit - Add GHG component to new Non-GHG Permit

4

$39

50

50

400

$15,600

Draft Permit - Commercial/Residential

20

$39

9

18

533

$20,800

Public Hearing Participatione

10

$39

3

4

68

$2,647

Permit Revisions - due to GHG

43

$39

458

915

59,039

$2,302,521

Permit Revisions - add GHG to current non-GHG permits

4

$39

448

448

3,584

$139,776

Permit Renewalsf

20

$39

2614

2,614

104,560

$4,077,840

Total Additional Burden

 

 

 

 

262,791

$19,437,544

aYear 1 is comprised of Step 1 and six months of Step 2 under the GHG Tailoring Rule; throughout Year 2 Step 2 will be in place.

 

 

bSalaries from Title V ICR adjusted to 2007 dollars using Employment Cost Index, Table 1, Private Industry Workers, Management, professional, and related. Index for December 2007 relative to December 2006. Available at: http://www.bls.gov/web/echistrynaics.pdf

cIncorporating GHG information/requirements into new, revised, and renewed permits adds an additional 10% burden to the current time.

dNew commercial/residential permits require half the time needed for new industrial permits

eAmount of time required for public hearing participation remains the same for all permits, and one in 50 permits requires a hearing.


 

fThe Title V ICR estimates that 3,267 permits annually undergo renewal; assume 80% of these involve combustion and require the addition of GHG components.





1 Information Collection Request For Changes To The Part 70 Operating Permit Regulations, The Part 71 Operating Permit Regulations, and The Parts 51 and 52 Prevention of Significant Deterioration and Non-Attainment New Source Review Regulations for Flexible Air Permits, November 2008.

2 Summary of Methodology and Data Used to Estimate Burden Relief and Evaluate Resource Requirements at Alternative Greenhouse Gas (GHG) Permitting Thresholds. Prepared by EPA Staff; March 2010.

3 Information Collection Request for State Operating Permit Regulations (Renewal), EPA ICR Number 1587.07, OMB Control Number 2060-0243, 2007. A copy of this document is available in the docket for the final Tailoring Rule.

4 The 80% estimate was obtained through a review of existing title V permit source categorization.

5 The Title V ICR indicates the burdens associated with revisions are as follows: 90 hours for a significant revision, 30 hours for a minor revision, and 5 hours for an administrative action. See Table 8 at 23. Which revision will be required for any modification that exceeds the GHG significance level threshold would be determined on a case-by-case basis depending on the change; therefore, EPA averages the three permitting burdens to obtain a value of 40 hours per permit.

3


File Typeapplication/vnd.openxmlformats-officedocument.wordprocessingml.document
Authordoriguzzi
File Modified0000-00-00
File Created2021-02-01

© 2025 OMB.report | Privacy Policy