8_11_11Supporting_Statement_FERC-516A_2011_final[1]

8_11_11Supporting_Statement_FERC-516A_2011_final[1].doc

FERC-516A, Standardization of Small Generator Interconnection Agreements and Procedures,

OMB: 1902-0203

Document [doc]
Download: doc | pdf

FERC-516A (OMB Control No. 1902-0203) 14


SUPPORTING STATEMENT FOR

FERC-516A "Standardization of Small Generator Interconnection

Agreements and Procedures”

(Three Year Extension Requested)


The Federal Energy Regulatory Commission (Commission) requests that the Office of Management and Budget (OMB) review and extend its approval of FERC-516A “Standardization of Small Generator Interconnection Agreements and Procedures” (OMB No. 1902-0203) for an additional three years.


A. Justification


1. CIRCUMSTANCES THAT MAKE THE COLLECTION OF INFORMATION NECESSARY


Under sections 205 and 206 of the Federal Power Act (FPA) (Attachment A) the Commission is charged with ensuring just and reasonable electric transmission rates and charges as well as ensuring that jurisdictional providers do not subject any person to any undue prejudice or disadvantage.


The lack of consistent and readily accessible terms and conditions for connecting resources to the grid led to a large number of disputes between jurisdictional transmission providers and small generators1 in the late 1990s and early 2000s. In response, the Commission directed transmission providers to include Commission-approved, standard, pro-forma interconnection procedures and a single uniformly applicable interconnection agreement in their open-access transmission tariffs (OATTs). The requirement to create and file these documents was instituted August 12, 2005, by Commission Order 20062 and is codified in 18 CFR 35.28(f) (Attachment B). Continuation of this collection is necessary because it sets and maintains a standard in OATTs for consistent consideration and processing of interconnection requests by transmission providers.

2. HOW, BY WHOM AND FOR WHAT PURPOSE IS THE INFORMATION TO BE USED AND THE CONSEQUENCES OF NOT COLLECTING THE INFORMATION


The requirement of jurisdictional transmission service providers to include pro forma interconnection procedures and a standard interconnection application within their OATTs made it no longer necessary for small generators and transmission providers to draft these documents on an interconnection-by-interconnection basis. Instead, these standard documents are used by jurisdictional transmission providers and small generators. Because most, if not all aspects of the interconnection are already set out in these documents, the activity occurs more easily and consistently.


If this information were not required to be included in transmission provider OATTs, the jurisdictional providers and small generators would revert to the lengthy process of drafting these documents on an individual interconnection basis. The resulting unduly burden and inefficiency would hamper business and require more FERC resources to process. Disputes between transmission providers and small generators would increase.

3. DESCRIBE ANY CONSIDERATION OF THE USE OF IMPROVED INFORMATION TECHNOLOGY TO REDUCE BURDEN AND TECHNICAL OR LEGAL OBSTACLES TO REDUCING BURDEN


The required interconnection documents have been in OATTs since 2005 when the Commission first put the requirement in place. All transmission providers included their pro forma small generator interconnection information as part of their eTariff baseline filings in 2010. These documents and related procedures are now electronically available via FERC’s eTariff system. Only the burden of maintaining the document within the eTariff OATT and the needed drafting of situation-specific procedures and nonconforming agreements remain for industry implementation and Commission review and action.


4. DESCRIBE EFFORTS TO IDENTIFY DUPLICATION AND SHOW SPECIFICALLY WHY ANY SIMILAR INFORMATION ALREADY AVAILABLE CANNOT BE USED OR MODIFIED FOR USE FOR THE PURPOSE(S) DESCRIBED IN INSTRUCTION NO. 2

The collection is specific to interstate electric transmission tariffs regulated by the Commission. Current staff involvement with the tariffs and regulated entities has not resulted in locating any similar sources of information that could be used or modified in connecting small generators to the grid.


5. METHODS USED TO MINIMIZE THE BURDEN IN THE COLLECTION OF INFORMATION INVOLVING SMALL ENTITIES


This collection was instituted to reduce existing burden on small entities, namely the small generator requiring new transmission interconnection. Prior to beginning this collection, small generators would follow case-by-case interconnection procedures for each interconnection they sought. They would have to draft and submit customized applications to transmission providers.


Small generator and jurisdictional transmission providers have benefitted from the availability of the easy access to standard documents on the Internet through the Commission’s eTariff system. Transmission providers have benefitted because they no longer need to negotiate and process small generator interconnection requests on a case-by-case basis. Typical information needed for interconnection from each small generator seeking interconnection is asked for uniformly.



6. CONSEQUENCE TO FEDERAL PROGRAM IF COLLECTION WERE CONDUCTED LESS FREQUENTLY


After an initial baseline filing is made in eTariff by the jurisdictional transmission provider, the collection only requires the filing of nonconforming agreements and updated procedures on an as-needed basis. It is not possible to make require this filing less frequently because the filings occur only as necessary so the transmission provider’s OATT is up-to-date and accurate.


7. EXPLAIN ANY SPECIAL CIRCUMSTANCES RELATING TO THE INFORMATION COLLECTION


The FERC-516A is a filing that is part of the OATT and as such does not necessitate the display of an OMB control number as it could not be updated as renewals occur.


8. DESCRIBE EFFORTS TO CONSULT OUTSIDE THE AGENCY: SUMMARIZE PUBLIC COMMENTS AND THE AGENCYS RESPONSE TO THESE COMMENTS


In accordance with 5 CFR 1320.8(d), the Commission’s notice to renew its OMB approval of the FERC-516A information collection was published in the Federal Register on May 27, 20113 (Attachment C). The Commission did not receive any comments in response to this notice.


9. EXPLAIN ANY PAYMENT OR GIFTS TO RESPONDENTS


No payments or gifts have been made to respondents.


10. DESCRIBE ANY ASSURANCE OF CONFIDENTIALITY PROVIDED TO RESPONDENTS


The FERC-516A information submitted to the Commission is public and therefore is not considered confidential. Specific requests for confidential treatment to the extent permitted by law will be considered pursuant to 18 CFR 388.112.


11. PROVIDE ADDITIONAL JUSTIFICATION FOR ANY QUESTIONS OF A SENSITIVE NATURE


There are no questions of a sensitive nature.


12. ESTIMATED BURDEN OF THE COLLECTION OF INFORMATION

The estimated information collection burden is based on the Commission’s previous experience with the collection and is as follows:


Number of Respondents

Annually

(1)

Number of Responses Per Respondent

(2)

Average Burden Hours Per Response

(3)

Total Annual Burden Hours

(1)x(2)x(3)

238

(maintenance of documents)

1

1

238 hours

40

(filing of non-conforming agreements)

1

25

1,000 hours

278 Total Respondents



Total



1,238 hours


Currently, the reporting burden for FERC-516A is 1,238 hours. There was a one time start-up cost to comply with Order No. 2006 requirements that was included when the Commission first sought authorization for this information collection in 2005 and was removed in the last submission to OMB under this collection of information (Information Collection Request Reference No: 200806-1902-001). The estimated burden of the continued requirement to maintain the procedures and agreement documents in transmission provider OATTs is included above as is the filing of non-conforming interconnection procedures and agreements that occur on occasion.


13. ESTIMATE OF TOTAL ANNUAL COST OF BURDEN TO RESPONDENTS


Total Number of Cost per Total

Respondent ÷ Hours per x Staff = Annualized

Burden Hours Staff year Employee4 Cost


1,238 ÷ 2,080 x $142,372 = $84,739


The estimated total cost to respondents is $84,739 (rounded) [1,238 hours divided by 2080 hours 5 per year, times $142,3726 equals $84,739]. The average cost per respondent is calculated to be $305 (rounded) [$84,739 divided by 278].


14. ESTIMATED ANNUALIZED COST TO FEDERAL GOVERNMENT


The estimated annualized cost to the Federal government is shown below:


Operation Total Cost


a) Data clearance (FERC FY 2011) $ 1,575

b) Data analysis (1 FTE x $142,372) $142,372


Total cost in one year of operation $143,947


The estimate of the cost to the Federal government is based on salaries for professional and clerical support. It reflects the de minimis effort required to analyze and process about 238 recordkeeping filings and the 40 non-conforming interconnection agreements per year through the eTariff system.


15. REASONS FOR CHANGES IN BURDEN INCLUDING THE NEED FOR ANY INCREASE


There is no change in respondent burden from the Commission’s last OMB submission. The only burden that results from this collection is associated with the electronic maintenance of small generator interconnection agreement documents and the burden related to the preparation of non-conforming small generator interconnection agreement exists. This burden estimate is based on recent Commission experience with the filings.


16. TIME SCHEDULE FOR INFORMATION COLLECTION AND PUBLICATION


This is not an information collection for which results are published.

17. DISPLAY OF EXPIRATION DATE


It is not appropriate to display the expiration date for OMB approval of the information collected. This is a submission to the Commission that is part of the transmission provider’s OATT and maintenance of that submission by the transmission provider.


18. EXCEPTIONS TO THE CERTIFICATION STATEMENT


The information collected for this reporting requirement is not used for statistical purposes. Therefore, the Commission does not employ effective and efficient statistical survey methodology as is required on the certification statement.


B. Collection of Information Employing Statistical Methods


This is not a collection of information employing statistical methods.


ATTACHMENT A


Federal Power Act - Sections 205 and 206

RATE AND CHARGES; SCHEDULES; SUSPENSION OF NEW RATES


SEC. 205(a) all rates and charges made, demanded, or received by any public utility for or in connection with the transmission or sale of electric energy subject to the jurisdiction of the

Commission, and all rules and regulations affecting or pertaining to such rates or charges shall be just and reasonable, and any such rate or charge that is not just and reasonable is hereby declared to be unlawful.


(b) No public utility shall, with respect to any transmission or sale subject to the jurisdiction of the Commission, (1) make or grant any undue preference or advantage to any person or subject any person to any undue prejudice or disadvantage, or (2) maintain any unreasonable difference in rates, charges, service, facilities, or in any other respect, either as between localities or as between classes of service.


(c) Under such rules and regulations as the Commission may prescribe, every public utility shall file with the Commission, within such time and in such form as the Commission may designate, and shall keep open in convenient form and place for public inspection schedules showing all rates and charges for any transmission or sale subject to the jurisdiction of the Commission, and the classification, practices, and regulations affecting such rates and charges, together with all contracts which in any manner affect or relate to such rates, charges, classifications, and services.


(d) Unless the Commission otherwise orders, no change shall be made by any public utility in any such rates, charges, classification, or service, or in any rule, regulation, or contract relating thereto, except after sixty days’ notice to the Commission and to the public. Such notice shall be given by filing with the Commission and keeping open for public inspection new schedules stating plainly the change or changes to be made in the schedule or schedules

then in force and the time when the change or changes will go into effect. The Commission, for good cause shown, may allow changes to take effect without requiring the sixty days’ notice herein provided for by an order specifying the changes so to be made and the time when they shall take effect and the manner in which they shall be filed and published.


(e) Whenever any such new schedule is filed the Commission shall have authority, either upon complaint or upon its own initiative without complaint at once, and, if it so orders, without answer or formal pleading by the public utility, but upon reasonable notice to enter upon a hearing concerning the lawfulness of such rate, charge, classification, or service; and, pending such hearing and the decision thereon the Commission, upon filing with such schedules and delivering to the public utility affected thereby a statement in writing of its reasons for such suspension, may suspend the operation of such schedule and defer the use of such rate, charge, classification, or service, but not for a longer period than five months

beyond the time when it would otherwise go into effect; and after full hearings, either completed before or after the rate, charge, classification, or service goes into effect, the Commission may make such orders with reference thereto as would be proper in a proceeding initiated after it had become effective. If the proceeding has not been concluded and an order made at the expiration of such five months, the proposed change of rate, charge, classification, or service shall go into effect at the end of such period, but in case of a proposed increased rate or charge, the Commission may by order require the interested public utility or public utilities to keep accurate account in detail of all amounts received by reason of such increase, specifying by whom and in whose behalf such amounts are paid, and upon completion of the hearing and decision may by further order require such public utility or public utilities to refund, with interest, to the persons in whose behalf such amounts

were paid, such portion of such increased rates or charges as by its decision shall be found not justified. At any hearing involving a rate or charge sought to be increased, the burden of proof to show that the increased rate or charge is just and reasonable shall be upon the public utility, and the Commission shall give to the hearing and decision of such questions preference over other questions pending before it and decide the same as speedily as possible.

(16 U.S.C. 824d)



FIXING RATES AND CHARGES; DETERMINATION OF COST OF

PRODUCTION OR TRANSPORTATION


SEC. 206. (a) Whenever the Commission, after a hearing had upon its own motion or upon complaint, shall find that any rate, charges, or classification demanded, observed, charged, or collected by any public utility for any transmission or sale subject to the jurisdiction

of the Commission, or that any rule, regulation, practice, or contract affecting such rate, charge, or classification is unjust, unreasonable, unduly discriminatory or preferential, the Commission shall determine the just and reasonable rate, charge, classification, rule, regulation, practice, or contract to be thereafter observed and in force, and shall fix the same by order.


(b) Whenever the Commission institutes a proceeding under this section, the Commission shall establish a refund effective date. In the case of a proceeding instituted on complaint, the refund effective date shall not be earlier than the date 60 days after the filing of such complaint nor later than 5 months after the expiration of such 60-day period. In the case of a proceeding instituted by the Commission on its own motion, the refund effective date shall not be earlier than the date 60 days after the publication by the Commission of notice of its intention to initiate such proceeding nor later than 5 months after the expiration of such 60-day period. Upon institution of a proceeding under this section, the Commission shall give to the decision of such proceeding the same preference as provided under section 205 of this Act and otherwise act as speedily as possible. If no final decision is rendered by the refund effective date or by the conclusion of the 180-day period commencing upon initiation of a proceeding pursuant to this section, whichever is earlier, the Commission shall state the reasons why it has failed to do so and shall state its best estimate as to when it reasonably expects to make such decision. In any proceeding under this section, the burden of proof to show that any rate, charge, classification, rule, regulation, practice, or contract is unjust,

unreasonable, unduly discriminatory, or preferential shall be upon the Commission or the complainant. At the conclusion of any proceeding under this section, the Commission may order the public utility to make refunds of any amounts paid, for the period subsequent

to the refund effective date through a date fifteen months after such refund effective date, in excess of those which would have been paid under the just and reasonable rate, charge, classification, rule, regulation, practice, or contract which the Commission orders to be thereafter observed and in force: Provided, That if the proceeding is not concluded within fifteen months after the refund effective date and if the Commission determines at the conclusion of the proceeding that the proceeding was not resolved within the fifteen-month period primarily because of dilatory behavior by the public utility, the Commission may order refunds of any or all amounts paid for the period subsequent to the refund effective

date and prior to the conclusion of the proceeding. The refunds shall be made, with interest, to those persons who have paid those rates or charges which are the subject of the proceeding.


(c) Notwithstanding subsection (b), in a proceeding commenced under this section involving two or more electric utility companies of a registered holding company, refunds which might otherwise be payable under subsection (b) shall not be ordered to the extent that such refunds would result from any portion of a Commission order that (1) requires a decrease in system production or transmission costs to be paid by one or more of such electric companies; and (2) is based upon a determination that the amount of such decrease should be paid through an increase in the costs to be paid by other electric utility companies of such registered holding company: Provided, That refunds, in whole or in part, may be ordered by the Commission if it determines that the registered holding company would not experience any reduction in revenues which results from an inability of an electric utility company of the holding company to recover such increase in costs for the period between the refund effective date and the effective date of the Commission’s order. For purposes of this subsection, the terms ‘‘electric utility companies’’ and ‘‘registered holding company’’ shall have the same meanings as provided in the Public Utility Holding Company Act of 1935, as

amended.


(d) The Commission upon its own motion, or upon the request of any State commission whenever it can do so without prejudice to the efficient and proper conduct of its affairs, may investigate and determine the cost of the production or transmission of electric energy by means of facilities under the jurisdiction of the Commission in cases where the Commission has no authority to establish a rate governing the sale of such energy.



ATTACHMENT B


Title 18: Conservation of Power and Water Resources


§ 35.28 (f) Standard generator interconnection procedures and agreements


(1) Every public utility that is required to have on file, a non-discriminatory open access transmission tariff under this section must amend such tariff by adding the standard interconnection procedures and agreement contained in Order No. 2003, FERC Stats. & Regs. & 31,146 (Final Rule on Generator Interconnection), as amended by the Commission in Order No. 661, FERC Stats. & Regs. ¶31,186 (Final Rule on Interconnection for Wind Energy), and the standard small generator interconnection procedures and agreement contained in Order No. 2006, FERC Stats. & Regs. ¶31,180 (Final Rule on Small Generator Interconnection), or such other interconnection procedures and agreements as may be approved by the Commission consistent with Order No. 2003, FERC Stats. & Regs. & 31,146 (Final Rule on Generator Interconnection) and Order No. 2006, FERC Stats. & Regs. ¶31,180 (Final Rule on Small Generator Interconnection).

(i) The amendment to implement the Final Rule on Generator Interconnection required by the preceding subsection must be filed no later than January 20, 2004.

(ii) The amendment to implement the Final Rule on Small Generator Interconnection required by the preceding subsection must be filed no later than August 12, 2005.

(iii) The amendment to implement the Final Rule on Interconnection for Wind Energy required by the preceding subsection must be filed no later than December 30, 2005.

(iv)Any public utility that seeks a deviation from the standard interconnection procedures and agreement contained in Order No. 2003, FERC Stats. & Regs. & 31,146 (Final Rule on Generator Interconnection), as amended by the Commission in Order No. 661, FERC Stats. & Regs. ¶31,186 (Final Rule on Interconnection for Wind Energy), or the standard small generator interconnection procedures and agreement contained in Order No. 2006, FERC Stats. & Regs. ¶31,180 (Final Rule on Small Generator Interconnection), must demonstrate that the deviation is consistent with the principles of either Order No. 2003, FERC Stats. & Regs. & 31,146 (Final Rule on Generator Interconnection) or Order No. 2006, FERC Stats. & Regs. ¶31,180 (Final Rule on Small Generator Interconnection).

(2) The non-public utility procedures for tariff reciprocity compliance described in paragraph (e) of this section are applicable to the standard interconnection procedures and agreements.

(3) A public utility subject to the requirements of this paragraph pertaining to the Final Rule on Generator Interconnection may file a request for waiver of all or part of the requirements of this paragraph, for good cause shown. An application for waiver must be filed either:

(i) No later than January 20, 2004, or

(ii) No later than 60 days prior to the time the public utility would otherwise have to comply with the requirements of this paragraph.

(4) A public utility subject to the requirements of this paragraph pertaining to the Final Rule on Small Generator Interconnection may file a request for waiver of all or part of the requirements of this paragraph, for good cause shown. An application for waiver must be filed either:

(i) No later than August 12, 2005, or

(ii) No later than 60 days prior to the time the public utility would otherwise have to comply with the requirements of this paragraph.

[Order 888, 61 FR 21693, May 10, 1996, as amended by Order 2003, 68 FR 49929, Aug. 19, 2003; Order 2006, 70 FR 34240, June 13, 2005; Order 661, 70 FR 75014, Dec. 19, 2005; Order 676, 71 FR 26212, May 4, 2006; Order 890, 72 FR 12492, Mar. 15, 2007]


ATTACHMENT C


UNITED STATES OF AMERICA

FEDERAL ENERGY REGULATORY COMMISSION


[Docket No. IC11-516A-000]


COMMISSION INFORMATION COLLECTION ACTIVITIES (FERC-516A),

PROPOSED COLLECTION; COMMENT REQUEST; EXTENSION

(May 20, 2011)


AGENCY: Federal Energy Regulatory Commission.

ACTION: Notice.

SUMMARY: In compliance with the requirements of section 3506(c) (2) (a) of the Paperwork Reduction Act of 1995 (Pub. L. No. 104-13), the Federal Energy Regulatory Commission (Commission) is soliciting public comment on the specific aspects of the information collection described below.

DATES: Comments in consideration of the collection of information are due [60 days after publication of this Notice in the Federal Register].

ADDRESSES: Commenters must send an original of their comments to: Federal Energy Regulatory Commission, Secretary of the Commission, 888 First Street, NE, Washington, DC 20426. Comments may be filed either on paper or on CD/DVD, and should refer to Docket No. IC11-516A-000. Documents must be prepared in an acceptable filing format and in compliance with Commission submission guidelines at http://www.ferc.gov/help/submission-guide.asp. eFiling and eSubscription are not available for Docket No. IC11-516A-000, due to a system issue.

All comments and FERC issuances may be viewed, printed or downloaded remotely through FERC’s eLibrary at http://www.ferc.gov/docs-filing/elibrary.asp, by searching on Docket No. IC11-516A. For user assistance, contact FERC Online Support by e-mail at [email protected], or by phone at: (866) 208-3676 (toll-free), or (202) 502-8659 for TTY.

FOR FURTHER INFORMATION: Ellen Brown may be reached by e-mail at [email protected], telephone at (202) 502-8663, and fax at (202) 273-0873.

SUPPLEMENTARY INFORMATION: The information collected under the requirements of FERC-516A, "Small Generator Interconnection Agreements” (OMB No. 1902-2003), is used by the Commission to enforce the statutory provisions of sections 205 and 206 of the Federal Power Act (FPA), as amended by Title II, section 211 of the Public Utility Regulatory Policies Act of 1978 (PURPA)(16 U.S.C. 825d). FPA sections 205 and 206 require the Commission to remedy undue discriminatory practices within interstate electric utility operations.

The Commission amended its regulations in 2005 with Order No. 2006 to require public utilities that own, control, or operate facilities used for the transmission of electric energy in interstate commerce to amend their Open Access Transmission Tariffs (OATTs) to include a Commission-approved pro forma interconnection procedures document and a standard interconnection agreement for the interconnection of generating facilities having a capacity of no more than 20 MW (Small Generators).7

Prior to Order No. 2006, the Commission’s policy had been to address interconnection issues on a case-by-case basis. Although a number of transmission providers had filed interconnection procedures as part of their OATTs, many industry participants remained dissatisfied with existing interconnection policies and procedures. With an increasing number of interconnection-related disputes, it became apparent that the case-by-case approach was an inadequate and inefficient means to address interconnection issues. This prompted the Commission to adopt, in Order No. 2006, a single set of procedures for jurisdictional transmission providers and a single uniformly applicable interconnection agreement for transmission providers to use in interconnecting with Small Generators.

With the incorporation of these documents in their OATTs, there is no longer a need for transmitting utilities to file case-by-case interconnection agreements and procedures with the Commission. However, on occasion, circumstances warrant non-conforming agreements or a situation-specific set of procedures. These non-conforming documents must be filed in their entirety with the Commission for review and action.

The information collected is in response to a mandatory requirement. The Commission implements these filing requirements in the Code of Federal Regulations (CFR) under 18 CFR Part 35, § 35.28(f).

Action: The Commission is requesting a three-year extension of the current expiration date, with no changes to the existing collection of data.

Burden Statement: Public reporting burden for this collection is estimated as:

Number of Respondents

Annually

(1)

Number of Responses Per Respondent

(2)

Average Burden Hours Per Response

(3)

Total Annual Burden Hours

(1)x(2)x(3)

238

(maintenance of documents)

1

1

238 hours

40

(filing of conforming agreements)

1

25

1,000 hours

Totals



1,238 hours

The estimated burden of the continued requirement to maintain the procedures and agreement documents in transmission providers’ OATTs is reflected herein as is the filing of non-conforming interconnection procedures and agreements that occur on occasion. The estimated total cost to respondents is $84,739 (rounded). [1,238 hours divided by 2080 hours8 per year, times $142,3729 equals $84,739]. The average cost per respondent is $305 (rounded).

The reporting burden includes the total time, effort, or financial resources expended


to generate, maintain, retain, disclose, or provide the information including: (1) reviewing


instructions; (2) developing, acquiring, installing, and utilizing technology and systems for


the purposes of collecting, validating, verifying, processing, maintaining, disclosing and


providing information; (3) adjusting the existing ways to comply with any previously


applicable instructions and requirements; (4) training personnel to respond to a collection of


information; (5) searching data sources; (6) completing and reviewing the collection of


information; and (7) transmitting, or otherwise disclosing the information.


The estimate of cost for respondents is based upon salaries for professional and


clerical support, as well as direct and indirect overhead costs. Direct costs include all costs


directly attributable to providing this information, such as administrative costs and the cost


for information technology. Indirect or overhead costs are costs incurred by an organization


in support of its mission. These costs apply to activities which benefit the whole


organization rather than any one particular function or activity.


Comments are invited on: (1) whether the proposed collection of information is


necessary for the proper performance of the functions of the Commission, including whether


the information will have practical utility; (2) the accuracy of the agency's estimate


of the burden of the proposed collection of information, including the validity of the


methodology and assumptions used; (3) ways to enhance the quality, utility and clarity of the


information to be collected; and (4) ways to minimize the burden of the collection of


information on those who are to respond, including the use of appropriate automated,


electronic, mechanical, or other technological collection techniques or other forms of


information technology e.g. permitting electronic submission of responses.





Kimberly D. Bose,

Secretary.

1 ? “Small generators” are generating facilities having a capacity of no more than 20 MW.

2 ? Standardization of Small Generation Interconnection Agreements and Procedures, Order No. 2006, 70 FR 34189 (May 12, 2005), FERC Stats. & Regs. ¶31,180 (2005).

3 ? The notice appeared at 76 FR 30927-30928.

44 The “Cost per Staff Employee” estimate is based on the estimated annual allocated cost per Commission employee for fiscal year 2011. The estimated $142,372 “cost” consists of salaries, benefits and overhead.

5 Number of hours an employee works each year.

6 Average annual salary per employee.

7 ? Standardization of Small Generator Interconnection Agreements and Procedures,

Order No. 2006, 70 FR 34189 (May 12, 2005), FERC Stats. & Regs. ¶ 31,180 (2005).

8 Number of hours an employee works each year.


9 Average annual salary, benefits, and overhead per employee.

File Typeapplication/msword
AuthorMpmed12
Last Modified ByEllen Brown
File Modified2011-08-11
File Created2011-08-11

© 2024 OMB.report | Privacy Policy