NESHAP for the Secondary Lead Smelter Industry (40 CFR part 63, subpart X) (Final Rule)

OMB: 2060-0296

Document [docx]
Download: docx | pdf

ICINFORMATION COLLECTION REQUEST

SUPPORTING STATEMENT

NATIONAL EMISSION STANDARDS FOR HAZARDOUS AIR POLLUTANTS FOR SECONDARY LEAD SMELTING (40 CFR PART 63, SUBPART X) (FINAL RULE)

PART A

1. Identification of the Information Collection

(a) Title and Number of the Information Collection.

NESHAP for Secondary Lead Smelting (40 CFR part 63, subpart X), EPA ICR Number 1686.09, OMB Control Number 2060-0296.

(b) Short Characterization.

This ICR is prepared for a U.S. Environmental Protection Agency (EPA) rulemaking developed under authority of section 112 of the Clean Air Act (CAA). The rulemaking amends Title 40, chapter I, part 63, subpart X, National Emission Standards for Hazardous Air Pollutants (NESHAP) for Secondary Lead Smelting, of the Code of Federal Regulations (CFR). The previous NESHAP was proposed on June 23, 1995, and promulgated on June 13, 1997. The revised NESHAP was proposed on May 19, 2011. The potential respondents are owners or operators of any existing or new affected source with secondary lead smelting operations. There are 16 facilities subject to the NESHAP. The NESHAP is applicable to the following processes at a secondary lead smelter: blast, reverberatory, rotary, and electric smelting furnaces; refining kettles; agglomerating furnaces; dryers; process fugitive sources; and fugitive dust sources. The affected sources are those that meet the criteria established in §63.541 of the Secondary Lead Smelting NESHAP.

The amendments reduce the emissions limits for lead. Specifically, sources are required to maintain the concentration of lead compounds in any process vent gas at or below 1.0 milligrams of lead per dry standard cubic meter (mg/dscm) (0.00043 grains of lead per dry standard cubic foot (gr/dscf)), and they also are required to maintain the flow-weighted average concentration of lead compounds in vent gases from a secondary lead facility at or below 0.20 mg/dscm (0.000087 gr/dscf). The amendments also establish emissions limits for total hydrocarbons (THC) and dioxins and furans (D/F) from furnace sources.

The final amendments include an emission limit for THC of 12 parts per million volume (expressed as propane) corrected to 4 percent carbon dioxide (CO2) for new and existing reverberatory furnaces not collocated with a blast furnace and reverberatory furnaces mixed with electric furnaces.

With regard to D/F, we are revising the previous NESHAP to include the following emissions limits for dioxins and furans:

  • For reverberatory furnaces not collocated with blast furnaces, and for reverberatory furnaces where the exhaust gases are mixed with electric furnaces, a limit of 0.20 nanograms per dry standard cubic meter (ng/dscm) at 7 percent oxygen (O2) expressed on a toxic equivalency (TEQ) basis and 0.1 ng/dscm at 7 percent O2 expressed on a TEQ basis for existing and new affected sources, respectively.

  • For blast furnaces, a limit of 170 ng/dscm at 7 percent O2 expressed on a TEQ basis and 10 ng/dscm at 7 percent O2 expressed on a TEQ basis for existing and new sources, respectively.

  • For collocated blast and reverberatory furnaces, a limit of 0.5 ng/dscm at 7 percent O2 expressed on a TEQ basis for both new and existing sources.

To control fugitive lead emissions, we are finalizing amendments that require each facility to totally enclose all sources of fugitive emissions (e.g., storage piles, material handling, battery breaking, dryers, and casting kettles) and operate the total enclosures under negative pressure in addition to requiring facilities to implement comprehensive work practices designed to prevent the formation of fugitive dust. The work practices include pavement cleaning, vehicle washing, cleaning of all affected areas after accidental releases, inspection of the battery storage areas for broken batteries, performance of maintenance activities in a manner that minimizes fugitive lead dust emissions, and transport of lead bearing dust in closed systems. The requirements for full enclosure are new provisions under the final amendments.

The amendments to the rule eliminate the startup, shutdown, and malfunction (SSM) exemption, remove the SSM plan requirement, add provisions to provide an affirmative defense against civil penalties for exceedances of emission standards caused by malfunctions, add a requirement for electronic submittal of performance test data, and correct editorial errors.

Recordkeeping for stack testing will be the same with the exception of records of the additional testing requirements for THC and D/F.

The final amendments for control of fugitive emissions that include work practices and enclosure standards have a compliance date of 2 years from the promulgation date which will allow the facility to construct any enclosures necessary to meet the new and revised requirements. The compliance date for the amendments for the revised stack lead emission limit and new THC and D/F emissions limits is 2 years from the date of promulgation. The compliance date for the revised SSM requirements is the date of promulgation. The final amendments require stack testing for D/F every 6 years.

The information collection requirements associated with the final amendments to the NESHAP are listed in Attachment 2.

2. Need For and Use of the Collection

(a) Need/Authority for the Collection.

Section 112 of the (CAA) requires EPA to establish NESHAP for both major and area sources of hazardous air pollutants (HAP) that are listed for regulation under section 112(c) of the CAA. A major source is a stationary source that emits or has the potential to emit more than 10 tons per year (tpy) of any single HAP or more than 25 tpy of any combination of HAP. An area source is a stationary source that is not a major source (i.e., an area source that does not emit and does not have the potential to emit more than 10 tpy of any single HAP and more than 25 tpy of any combination of HAP). For major sources, these technology-based standards must reflect the maximum degree of emission reductions of HAP achievable (after considering cost, energy requirements, and non-air quality health and environmental impacts) and are commonly referred to as maximum achievable control technology (MACT) standards. Section 112(d)(6) of the CAA requires EPA to review these technology-based standards and to revise them “as necessary (taking into account developments in practices, processes, and control technologies)” no less frequently than every 8 years. In addition, section 112(f) of the CAA requires EPA to determine for source categories subject to certain CAA section 112(d) standards whether the emissions limitations provide an ample margin of safety to protect public health. For MACT standards for HAP “classified as a known, probable, or possible human carcinogen" that "do not reduce lifetime excess cancer risks to the individual most exposed to emissions from a source in the category or subcategory to less than 1-in-1 million,” EPA must promulgate residual risk standards for the source category (or subcategory) as necessary to provide an ample margin of safety to protect public health. In doing so, EPA may adopt standards equal to existing MACT standards, if EPA determines that the existing standards are sufficiently protective. EPA must also adopt more stringent standards, if necessary, to prevent an adverse environmental effect, but must consider cost, energy, safety, and other relevant factors in doing so.

Certain records and reports are necessary for the Administrator to confirm the compliance status of sources subject to NESHAP, identify any new or reconstructed sources subject to the standards, and confirm that the standards are being achieved on a continuous basis. These recordkeeping and reporting requirements are specifically authorized by section 114 of the CAA (42 U.S.C. 7414) and set out in the part 63 NESHAP General Provisions. The recordkeeping and reporting requirements for title V permits are contained in 40 CFR 70.6 and 40 CFR 71.6. Under parts 63 and 70 or 71, the owner or operator must keep each record for 5 years following the date of each occurrence, measurement, maintenance, corrective action, report, or record.

(b) Use/Users of the Data.

The information will be used by the delegated authority (State agency, or Regional Administrator if there is no delegated State agency) to ensure that the standards and other requirements are being achieved. Based on review of the recorded information at the site and the reported information, the delegated permitting authority can identify facilities that may not be in compliance and decide which facilities, records, or processes may need inspection.

3. Nonduplication, Consultations, and Other Collection Criteria

(a) Nonduplication.

A computer search of EPA’s ongoing information collection requests (ICRs) revealed no duplication of information-gathering efforts.

(b) Public Notice Required Prior to ICR Submission to OMB.

The preamble to the final rule will give public notice of this ICR.

(c) Consultations.

The amendments were developed in consultation with the Association of Battery Recyclers (ABR) and various companies (including the Revere Smelting and Refining (RSR) Corporation and Exide Technologies, who own 9 of the 16 facilities and Johnson Controls, Inc., who is in the process of constructing a new secondary lead smelting facility). The non-EPA persons consulted on the information collection activities are identified in Table 1.

TABLE 1. PERSONS CONSULTED ON THE INFORMATION COLLECTION ACTIVITIES

Contact

Organization

Telephone No.

Russell Kemp

Environ Corp.

678-388-1654

Robert Steinwurtzel

Baker and Hostetler

202-861-1708

Steve Arnold

The Doe Run Company

573-626-3495

Mark Cummings

Exide Technologies

678-566-9280

Mike Buckantz

RSR Corp

626-937-3245

Keith McCoy

Johnson Controls, Inc.

202-406-4068

(d) Effects of Less Frequent Collection.

If the relevant information was collected less frequently, the delegated permitting authority (State or EPA) will not be reasonably assured that a facility is in compliance with the standards.

(e) General Guidelines.

None of the guidelines in 5 CFR 1320.6 are being exceeded.

(f) Confidentiality.

All information submitted to the Agency for which a claim of confidentiality is made will be safeguarded according to the Agency policies set forth in Title 40, Chapter 1, Part 2, Subpart B--Confidentiality of Business Information (see 40 CFR 2; 41 FR 36902, September 1, 1976; amended by 43 FR 39999, September 28, 1978; 43 FR 42251, September 28, 1978; 44 FR 17674, March 23, 1979).

(g) Sensitive Questions.

This section is not applicable because this ICR does not involve matters of a sensitive nature.

4. The Respondents and the Information Requested

(a) Respondents/NAICS Codes.

Potential respondents under subpart X are owners or operators of any existing or new facility engaged in secondary lead smelting. Secondary lead smelting facilities are primarily classified under NAICS codes 331492, Secondary Lead Smelting and Refining.

There are 16 facilities that will be subject to the final amendments to the NESHAP. One new secondary lead smelting facility is under construction at this time. No additional facilities are expected during the 3­year period of this ICR.

(b) Information Requested.

(i) Data Items, Including Recordkeeping Requirements. Attachment 2, Information Requirements, summarizes the data items, including recordkeeping and reporting requirements, for the Secondary Lead Smelting source category. The amendments to the NESHAP require that any performance tests performed after December 31, 2011 be submitted electronically to EPA’s Central Data Exchange by using the Electronic Reporting Tool (ERT) for test methods that are compatible with ERT. This new requirement to submit the data to the ERT is in addition to the other existing submission requirements for this data.

(ii) Respondent Activities. The respondent activities that will be required by the final amendments to the Secondary Lead Smelting NESHAP are identified in Tables 1-3 of Attachment 1 and are introduced in section 6(a).

EPA is including an estimate of the burden associated with performing an affirmative defense. EPA is providing this as an illustrative example of the potential additional administrative burden a source may incur to assert in an affirmative defense in response to an action to enforce the standards set forth in the applicable subpart.

This illustrative estimate is not considered a duplicate estimate of cost under the General Duty to Minimize Emissions clause under 63.6(e)(1)(i), which states: “At all times, the owner and operator must operate and maintain any affected source, including associated air pollution control equipment and monitoring equipment, in a manner consistent with safety and good air pollution control practices for minimizing emissions. Determining whether such operation and maintenance procedures are being used will be based on information available to the Administrator which may include, but is not limited to, monitoring results, review of operation and maintenance procedures, review of operation and maintenance records, and inspection of the source.”

To provide the public with an estimate of the relative magnitude of the burden associated with an assertion of the affirmative defense position adopted by a source, EPA provides an administrative adjustment to this ICR that estimates the costs of the notification, recordkeeping and reporting requirements associated with the assertion of the affirmative defense. EPA’s estimate for the required notification, reports and records, including the root cause analysis, associated with a single incident totals approximately $3,141 and is based on the time and effort required of a source to review relevant data, interview plant employees, and document the events surrounding a malfunction that has caused an exceedance of an emission limit. The estimate also includes time to produce and retain the records and reports for submission to EPA. EPA provides this illustrative estimate of this burden because these costs are only incurred if there has been a violation and a source chooses to take advantage of the affirmative defense.

Of the number of excess emission events reported by source operators, only a small number would be expected to result from a malfunction, and only a subset of excess emissions caused by malfunctions would result in the source choosing to assert the affirmative defense. Thus we believe the number of instances in which source operators might be expected to avail themselves of the affirmative defense will be extremely small. For this reason, we estimate no more than 2 or 3 such occurrences for all sources within a given category over the 3-year period covered by this ICR. For the purpose of this estimate, we are adding two instances of affirmative defense. We expect to gather information on such events in the future and will revise this estimate as better information becomes available.

5. The Information Collected–Agency Activities, Collection Methodology, and Information Management

(a) Agency Activities.

The Agency activities associated with the final amendments to the Secondary Lead Smelting NESHAP are provided in Tables 5-7 of Attachment 1 and are introduced in section 6(c).

(b) Collection Methodology and Management.

Data and records maintained by the respondents are tabulated and published for use in compliance and enforcement programs of the delegated permitting authority. EPA is the permitting authority until the State agency is delegated authority to implement the final amendments to the rule. Therefore, information contained in any report submitted to the Regional Administrator will be entered into the Air Facility System (AFS), which is operated and maintained by EPA’s Office of Compliance. AFS is EPA’s database for the collection, maintenance, and retrieval of compliance data for approximately 125,000 industrial and government-owned facilities. EPA uses the AFS for tracking air pollution compliance and enforcement by local and state regulatory agencies, EPA regional offices and EPA headquarters. EPA and its delegated authorities can edit, store, retrieve and analyze the data.

(c) Small Entity Flexibility.

The Small Business Administration defines a small entity engaging in secondary lead smelting operations as a firm having no more than 700 employees. 13 of the 16 facilities subject to the final amendments for the Secondary Lead Smelting source category do not meet the definition of a small entity. Three facilities are owned by small entities. Gopher Resources owns two facilities, and The Battery Recycling Company owns one facility. Based on the definition, however, we estimate that the economic impacts to these entities will not be significant. One Gopher Resources facility is already relatively well controlled and therefore will not need to spend a significant amount of capital on new control devices. The second Gopher Resources facility is currently undergoing an expansion that includes upgrades to their control devices and total enclosures and will therefore also not need to spend a significant amount of capital on new control devices. The third facility owned by The Battery Recycling Company will require some facility upgrades. However, the estimated construction and operating costs for these upgrades have not been determined to be significant based on guidelines developed for the analysis. Therefore, we have determined that these amendments will not impose a significant impact on a substantial number of small entities.

(d) Collection Schedule.

The specific frequency for each information collection activity within this request is shown in Tables 1-3 of Attachment 1 for the Secondary Lead Smelting category.

6. Estimating the Burden and Cost of the Collection

(a) Estimating Respondent Burden.

The annual burden estimates for the final amendments to the Secondary Lead Smelting NESHAP are shown in Tables 1-3 of Attachment 1. These numbers were derived from estimates based on EPA’s experience with other standards. Burden estimates for the one new source are included in the estimate.

(b) Estimating Respondent Costs.

(i) Estimating Labor Costs. Labor rates and associated costs are based on Bureau of Labor Statistics (BLS) data. Technical, management, and clerical average hourly rates for private industry workers associated with Nonferrous Metal Production and Processing were taken from the United States Department of Labor, Bureau of Labor Statistics, Occupational Employment Statistics available at http://bls.gov/oes/current/naics4_331400.htm#43-0000. Wages for technical labor are based on "Environmental Engineer," with a total compensation of $38.10/hour. Wages for management labor are taken from "Engineering Managers," with a total compensation of $50.65/hour. Wages for clerical labor are based on "Secretaries, Except Legal, Medical, and Executive," with a total compensation of $15.98/hour. These rates represent salaries plus fringe benefits and do not include the cost of overhead. An overhead rate of 110 percent is used to account for these costs. The fully-burdened hourly wage rates used to represent respondent labor costs are: technical at $80.01/hour, management at $106.37/hour, and clerical at $33.56/hour.

(ii) Estimating Capital and Operations and Maintenance (O&M) Costs. The capital costs associated with the NESHAP including monitoring system initial costs; one-time costs when a facility becomes subject to the regulation. The annual operation and maintenance costs are the ongoing costs to maintain the monitors and conducting stack testing.

(iii) Capital/Startup vs. Operation and Maintenance (O&M) Costs. The estimated capital and O&M costs for the affected units for the first 3 years after promulgation are provided. The total annualized capital and O&M costs are $1.33 million for an average of $440,280 per year.

(iv) Affirmative Defense, Root Cause Analysis, and Malfunction Costs. EPA’s estimate for an affirmative defense and root cause analysis is based on general experience to calculate the time and effort required of a source to review relevant data, interview plant employees, and reconstruct the events prior to a malfunction in order to determine primary and contributing causes. The level of effort also includes time to produce and retain the report in document form so that the source will have it available should EPA or state enforcement agencies ever request to review it.

(c) Estimating Agency Burden and Cost.

The only costs to the Agency are those costs associated with analysis of the reported information. EPA’s overall compliance and enforcement program includes activities such as the examination of records maintained by the respondents, periodic inspection of sources of emission, and the publication and distribution of collected information.

The average annual Agency cost during the three years of the ICR is estimated to be $51,822.

The Agency labor rates are from the Office of Personnel Management (OPM) 2010 General Schedule, which excludes locality rates of pay. These rates can be obtained from Salary Table 2010-GS available on the OPM website, http://www.opm.gov/oca/10tables/pdf/gs_h.pdf.

Managerial $62.27 (GS-13, Step 5, $38.92+ 60%)

Technical $46.21 (GS-12, Step 1, $28.88+ 60%)

Clerical $25.01 (GS-6, Step 3, $15.63 + 60%)

These rates were increased by 60 percent to include fringe benefits and overhead.

(d) Estimating the Respondent Universe and Total Burden and Costs.

There are 16 facilities that are subject to the revised Secondary Lead Smelting NESHAP. One new source is expected to begin operation in the first year of the 3-year compliance period. Over the 3-year period, it is estimated that these 16 facilities will have 114 responses for an average of 38 per year.

(e) Bottom Line Burden Hours and Cost Tables.

(i) Respondent tally. The bottom line respondent burden hours and costs presented in Tables 1-3 of Attachment 1 are calculated by adding person-hours per year down each column for technical, managerial, and clerical staff, and by adding down the cost column. The average annual burden for the recordkeeping and reporting requirements in the final amendments to subpart X for the 16 facilities that are subject to the Secondary Lead Smelting NESHAP is $788,873. This includes 4,503 annual labor hours.

(ii) The Agency tally. The average annual Federal Government cost is $51,822 for 1,150 hours for the final amendments to subpart X. The bottom line Agency burden hours and costs presented in Tables 5-7 of Attachment 1 are calculated by adding person-hours per year down each column for technical, managerial, and clerical staff, and by adding down the cost column.

(iii) Variations in the annual bottom line. The total respondent costs for years 1, 2, and 3 are $1.17 million, 0.75 million, and $0.45 million, respectively. The corresponding total respondent hours for years 1, 2, and 3 are 5,633; 4,087; and 3,788 respectively.

(f) Reasons for Change in Burden.
This ICR is prepared for a U.S. Environmental Protection Agency (EPA) rulemaking developed under authority of section 112 of the Clean Air Act (CAA). The rulemaking amends Title 40, chapter I, part 63, subpart X, National Emission Standards for Hazardous Air Pollutants (NESHAP) for Secondary Lead Smelting, of the Code of Federal Regulations (CFR).
(g) Burden Statement

The average annual respondent burden for the final amendments to the Secondary Lead Smelting NESHAP is estimated at 119 hours per response.

Burden means the total time, effort, or financial resources expended by persons to generate, maintain, retain, or disclose or provide information to or for a Federal agency. This includes the time needed to review instructions; develop, acquire, install, and utilize technology and systems for the purposes of collecting, validating, and verifying information, processing and maintaining information, and disclosing and providing information; adjust the existing ways to comply with any previously applicable instructions and requirements; train personnel to be able to respond to a collection of information; search data sources; complete and review the collection of information; and transmit or otherwise disclose the information.

An agency may not conduct or sponsor, and a person is not required to respond to a collection of information unless it displays a currently valid Office of Management and Budget (OMB) control number. The OMB control numbers for EPA’s regulations in 40 CFR part 63 are listed in 40 CFR part 9.

To comment on the Agency’s need for this information, the accuracy of the provided burden estimates, and for any suggestions for minimizing respondent burden, including through the use of automated collection techniques, EPA has established a public docket for this ICR under Docket ID No. EPA-HQ-OAR-2011-0344, which is available for online viewing at http://www.regulations.gov, or in person viewing at the Air and Radiation Docket and Information Center in the EPA Docket Center (EPA/DC), EPA West, Room 3334, 1301 Constitution Ave., NW, Washington, DC. The EPA Docket Center Public Reading Room is open from 8:30 a.m. to 4:30 p.m., Monday through Friday, excluding legal holidays. The telephone number for the Reading Room is (202) 566-1744, and the telephone number for the Air Docket is (202) 566-1742. An electronic version of the public docket is available at http://www.regulations.gov. This site can be used to submit or view public comments, access the index listing of the contents of the public docket, and to access those documents in the public docket that are available electronically. When in the system, select “search,” then key in the Docket ID Number identified above. Also, you can send comments to the Office of Information and Regulatory Affairs, Office of Management and Budget, 725 17th Street, NW, Washington, DC 20503, Attention Desk Officer for EPA. Please include the relevant Docket ID Number (EPA-HQ-OAR-2011-0344) and OMB Control Number (2060-0296) in any correspondence.

PART B

This section is not applicable because statistical methods are not used in data collection associated with the final rule.



ATTACHMENT 1

Burden Estimate Tables 1 – 8


Tables 1 – 3: Annual Respondent Burden and Cost of Recordkeeping and Reporting Requirements for the Secondary Lead Smelters NESHAP - Years 1 – 3

Table 4: Summary of Annual Respondent Burden and Cost of Recordkeeping and Reporting Requirements for the Secondary Lead Smelters NESHAP

Tables 5 – 7: Annual Designated Administrator Burden and Cost of Recordkeeping and Reporting Requirements for the Secondary Lead Smelters NESHAP - Years 1 - 3

Table 8: Summary of Annual Designated Administrator Burden and Cost of Recordkeeping and Reporting Requirements for the Secondary Lead Smelters NESHAP



Table 1 - Annual Respondent Burden and Cost of Recordkeeping and Reporting Requirements for the Secondary Lead Smelters NESHAP - Year 1

Burden Item

(A)
Respondent Hours per Occurrence (Technical hours)

(B)
Stack Testing Cost Per Occurrence

(C)
Other Non-Labor Costs Per Occurrence

(D)
Number of Occurrences Per Respondent Per Year

(E)
Technical Hours per Respondent Per Year
(A X D)

(F)
Number of Respondents Per Year

(G) Technical Hours per Year (E X F)

(H)
Clerical Hours per Year
(G X 0.1)

(I)
Management Hours per Year
(G X .05)

(J)
Total Labor Costs Per Year

(K)
Total Non-Labor Costs Per Year [(B+C)xDxF]

(L)
Total Number of Responses per Year
(D X F)

Footnotes

1. Applications

NA

 

 

 

 

 

 

 

 

 

 

 

 

2. Surveys and Studies

NA

 

 

 

 

 

 

 

 

 

 

 

 

3. Reporting Requirements

 

 

 

 

 

 

 

 

 

 

 

 

 

A. Read Rule

20

$0

$0

1

20

16

320

32

16

$28,379

$0

0

 

B. Required Activities

 

 

 

 

 

 

 

 

 

 

 

 

 

1. THC testing

10

$4,700

$0

1

10

34

340

34

17

$30,153

$159,800

0

 

2. Dioxin/Furan testing

10

$19,300

$0

1

10

23

230

23

12

$20,397

$443,900

0

 

3. Lead testing

10

$10,000

$0

1

10

0

0

0

0

$0

$0

0

 

4. Differential pressure monitor

2

$0

$2,300

1

2

46

92

9

5

$8,159

$105,800

0

 

5. Differential pressure monitor (annual O&M)

2

$0

$230

1

2

46

92

9

5

$8,159

$10,580

0

 

6. Inspection and repair enclosure

24

$0

$0

1

24

16

384

38

19

$34,055

$0

0

 

7. Inspect battery storage areas

24

$0

$0

1

24

16

384

38

19

$34,055

$0

0

 

C. Create Information

Inc. in 3B

 

 

 

 

 

 

 

 

 

 

 

 

D. Gather Information

Inc. in 3E

 

 

 

 

 

 

 

 

 

 

 

 

E. Report Preparation

 

 

 

 

 

 

 

 

 

 

 

 

 

1. Annual report

10

$0

$0

1

10

16

160

16

8

$14,189

$0

16

 

2. Differential pressure monitoring report

10

$0

$0

1

10

16

160

16

8

$14,189

$0

16

 

3. Develop SOP for work practices

40

$0

$0

1

40

16

640

64

32

$56,758

$0

16

 

4. Affirmative defense

30

$0

$0

1

30

1

30

3

2

$3,141

$0

1

 

Reporting Subtotal

 

 

 

 

 

 

2802

280

140

$251,634

$720,080

48

 

4. Recordkeeping Requirements

 

 

 

 

 

 

 

 

 

 

 

 

 

A. Read Instructions

Inc. in 3A

 

 

 

 

 

 

 

 

 

 

 

 

B. Implements Activities

NA

 

 

 

 

 

 

 

 

 

 

 

 

C. Develop Record System

NA

 

 

 

 

 

 

 

 

 

 

 

 

D. Record information

 

 

 

 

 

 

 

 

 

 

 

 

 

1. Records of fugitives

1

$0

$0

12

14

16

224

22

11

$19,865

$0

0

 

2. Records of flow weighted average for lead standard

1

$0

$0

1

1

16

16

2

1

$1,419

$0

0

 

3. Records of continuous pressure monitors

1

$0

$0

12

12

16

192

19

10

$17,027

$0

0

 

4. Records of power outages

1

$0

$0

12

12

16

192

19

10

$17,027

$0

0

 

5. Records of facility enclosure inspections

1

$0

$0

12

12

16

192

19

10

$17,027

$0

0

 

6. Records of startup and shutdown

1

$0

$0

12

12

16

192

19

10

$17,027

$0

0

 

7. Records of malfunctions

2

$0

$0

6

12

16

192

19

10

$17,027

$0

0

 

8. Records of actions taken during malfunctions

1

$0

$0

6

6

16

96

10

5

$8,514

$0

0

 

9. Records for BLDS

1

$0

$0

12

12

16

192

19

10

$17,027

$0

0

 

10. Records of furnace inspection

1

$0

$0

12

12

16

192

19

10

$17,027

$0

0

 

11. Records of recovery of plastic battery casing material

1

$0

$0

6

6

16

96

10

5

$8,514

$0

0

 

E. Personnel Training

20

$0

$0

1

20

16

320

32

16

$28,379

$0

0

 

F. Time for Audits

NA

 

 

 

 

 

 

 

 

 

 

 

 

Recordkeeping Subtotal

 

 

 

 

 

 

2096

210

105

$185,880

$0

0

 

TOTAL

 

 

 

 

 

 

4898

490

245

$437,514

$720,080

48

 

 

 

 

 

Summary of Respondent Burden

Total Hours

Labor

Non-Labor

Total

 

 

 

 

 

 

5,633

$437,514

$720,080

$1,157,594

 

 

 

 

 

 

Initial Capital and Startup

 

 

$105,800

 

 

 

 

 

 

 

Annualized Capital/Start-up and O & M

 

 

 

$720,080

 

 

 


Table 2 - Annual Respondent Burden and Cost of Recordkeeping and Reporting Requirements for the Secondary Lead Smelters NESHAP - Year 2

Burden Item

(A)
Respondent Hours per Occurrence (Technical hours)

(B)
Stack Testing Cost Per Occurrence

(C)
Other Non-Labor Costs Per Occurrence

(D)
Number of Occurrences Per Respondent Per Year

(E)
Technical Hours per Respondent Per Year
(A X D)

(F)
Number of Respondents Per Year

(G) Technical Hours per Year (E X F)

(H)
Clerical Hours per Year
(G X 0.1)

(I)
Management Hours per Year
(G X .05)

(J)
Total Labor Costs Per Year

(K)
Total Non-Labor Costs Per Year [(B+C)xDxF]

(L)
Total Number of Responses per Year
(D X F)

Footnotes

1. Applications

NA

 

 

 

 

 

 

 

 

 

 

 

 

2. Surveys and Studies

NA

 

 

 

 

 

 

 

 

 

 

 

 

3. Reporting Requirements

 

 

 

 

 

 

 

 

 

 

 

 

 

A. Read Rule

20

$0

$0

1

20

0

0

0

0

$0

$0

0

 

B. Required Activities

 

 

 

 

 

 

 

 

 

 

 

 

 

1. THC testing

10

$4,700

$0

1

10

34

340

34

17

$30,153

$159,800

0

 

2. Dioxin/Furan testing

10

$19,300

$0

1

10

0

0

0

0

$0

$0

0

 

3. Lead testing

10

$10,000

$0

1

10

26

260

26

13

$23,058

$260,000

0

 

4. Differential pressure monitor

2

$0

$2,300

1

2

0

0

0

0

$0

$0

0

 

5. Differential pressure monitor (annual O&M)

2

$0

$230

1

2

46

92

9

5

$8,159

$10,580

0

 

6. Inspection and repair enclosure

20

$0

$0

1

24

16

384

38

19

$34,055

$0

0

 

7. Inspect battery storage areas

20

$0

$0

1

24

16

384

38

19

$34,055

$0

0

 

C. Create Information

Inc. in 3B

 

 

 

 

 

 

 

 

 

 

 

 

D. Gather Information

Inc. in 3E

 

 

 

 

 

 

 

 

 

 

 

 

E. Report Preparation

 

 

 

 

 

 

 

 

 

 

 

 

 

1. Annual report

10

$0

$0

1

10

16

160

16

8

$14,189

$0

16

 

2. Differential pressure monitoring report

10

$0

$0

1

10

16

160

16

8

$14,189

$0

16

 

3. Develop SOP for work practices

40

$0

$0

1

40

0

0

0

0

$0

$0

0

 

4. Affirmative defense

30

$0

$0

1

30

1

30

3

2

$3,141

$0

1

 

Reporting Subtotal

 

 

 

 

 

 

1810

181

91

$160,999

$430,380

33

 

4. Recordkeeping Requirements

 

 

 

 

 

 

 

 

 

 

 

 

 

A. Read Instructions

Inc. in 3A

 

 

 

 

 

 

 

 

 

 

 

 

B. Implements Activities

NA

 

 

 

 

 

 

 

 

 

 

 

 

C. Develop Record System

NA

 

 

 

 

 

 

 

 

 

 

 

 

D. Record information

 

 

 

 

 

 

 

 

 

 

 

 

 

1. Records of fugitives

1

$0

$0

12

12

16

192

19

10

$17,027

$0

0

 

2. Records of flow weighted average for lead standard

1

$0

$0

1

1

16

16

2

1

$1,419

$0

0

 

3. Records of continuous pressure monitors

1

$0

$0

12

12

16

192

19

10

$17,027

$0

0

 

4. Records of power outages

1

$0

$0

12

12

16

192

19

10

$17,027

$0

0

 

5. Records of facility enclosure inspections

1

$0

$0

12

12

16

192

19

10

$17,027

$0

0

 

6. Records of startup and shutdown

1

$0

$0

12

12

16

192

19

10

$17,027

$0

0

 

7. Records of malfunctions

2

$0

$0

6

12

16

192

19

10

$17,027

$0

0

 

8. Records of actions taken during malfunctions

1

$0

$0

6

6

16

96

10

5

$8,514

$0

0

 

9. Records for BLDS

1

$0

$0

12

12

16

192

19

10

$17,027

$0

0

 

10. Records of furnace inspection

1

$0

$0

12

12

16

192

19

10

$17,027

$0

0

 

11. Records of recovery of plastic battery casing material

1

$0

$0

6

6

16

96

10

5

$8,514

$0

0

 

E. Personnel Training

8

$0

$0

1

8

0

0

0

0

$0

$0

0

 

F. Time for Audits

NA

 

 

 

 

 

 

 

 

 

 

 

 

Recordkeeping Subtotal

 

 

 

 

 

 

1744

174

87

$154,663

$0

0

 

TOTAL

 

 

 

 

 

 

3554

355

178

$315,662

$430,380

33

 

 

 

 

 

 

 

 

 

Total Hours

Labor

Non-Labor

Total

 

 

 

 

 

 

 Summary of Respondent Burden 

 

4,087

$315,662

$430,380

$746,042

 

 

 

 

 

 

Initial Capital and Startup 

 

 

 

$0

 

 

 

 

 

 

 

 Annualized Capital/Start-up and O & M 

 

 

 

$430,380

 

 

 


Table 3 - Annual Respondent Burden and Cost of Recordkeeping and Reporting Requirements for the Secondary Lead Smelters NESHAP - Year 3

Burden Item

(A)
Respondent Hours per Occurrence (Technical hours)

(B)
Stack Testing Cost Per Occurrence

(C)
Other Non-Labor Costs Per Occurrence

(D)
Number of Occurrences Per Respondent Per Year

(E)
Technical Hours per Respondent Per Year
(A X D)

(F)
Number of Respondents Per Year

(G) Technical Hours per Year (E X F)

(H)
Clerical Hours per Year
(G X 0.1)

(I)
Management Hours per Year
(G X .05)

(J)
Total Labor Costs Per Year

(K)
Total Non-Labor Costs Per Year [(B+C)xDxF]

(L)
Total Number of Responses per Year
(D X F)

Footnotes

1. Applications

NA

 

 

 

 

 

 

 

 

 

 

 

 

2. Surveys and Studies

NA

 

 

 

 

 

 

 

 

 

 

 

 

3. Reporting Requirements

 

 

 

 

 

 

 

 

 

 

 

 

 

A. Read Rule

20

$0

$0

1

20

0

0

0

0

$0

$0

0

 

B. Required Activities

 

 

 

 

 

 

 

 

 

 

 

 

 

1. THC testing

10

$4,700

$0

1

10

34

340

34

17

$30,153

$159,800

0

 

2. Dioxin/Furan testing

10

$19,300

$0

1

10

0

0

0

0

$0

$0

0

 

3. Lead testing

10

$10,000

$0

1

10

0

0

0

0

$0

$0

0

 

4. Differential pressure monitor

2

$0

$2,300

1

2

0

0

0

0

$0

$0

0

 

5. Differential pressure monitor (annual O&M)

2

$0

$230

1

2

46

92

9

5

$8,159

$10,580

0

 

6. Inspection and repair enclosure

20

$0

$0

1

24

16

384

38

19

$34,055

$0

0

 

7. Inspect battery storage areas

20

$0

$0

1

24

16

384

38

19

$34,055

$0

0

 

8. HEPA filter monitor

 

 

 

 

 

 

 

 

 

 

 

 

 

Initial capital

2

$0

$32,759

1

2

0

0

0

0

$0

$0

0

 

Annual (O&M)

2

$0

$4,665

1

2

0

0

0

0

$0

$0

0

 

C. Create Information

Inc. in 3B

 

 

 

 

 

 

 

 

 

 

 

 

D. Gather Information

Inc. in 3E

 

 

 

 

 

 

 

 

 

 

 

 

E. Report Preparation

 

 

 

 

 

 

 

 

 

 

 

 

 

1. Annual report

10

$0

$0

1

10

16

160

16

8

$14,189

$0

16

 

2. Differential pressure monitoring report

10

$0

$0

1

10

16

160

16

8

$14,189

$0

16

 

3. Develop SOP for work practices

40

$0

$0

1

40

0

0

0

0

$0

$0

0

 

4. Affirmative defense

30

$0

$0

1

30

1

30

3

2

$3,141

$0

1

 

Reporting Subtotal

 

 

 

 

 

 

1550

155

78

$137,941

$170,380

33

 

4. Recordkeeping Requirements

 

 

 

 

 

 

 

 

 

 

 

 

 

A. Read Instructions

Inc. in 3A

 

 

 

 

 

 

 

 

 

 

 

 

B. Implements Activities

NA

 

 

 

 

 

 

 

 

 

 

 

 

C. Develop Record System

NA

 

 

 

 

 

 

 

 

 

 

 

 

D. Record information

 

 

 

 

 

 

 

 

 

 

 

 

 

1. Records of fugitives

1

$0

$0

12

12

16

192

19

10

$17,027

$0

0

 

2. Records of flow weighted average for lead standard

1

$0

$0

1

1

16

16

2

1

$1,419

$0

0

 

3. Records of continuous pressure monitors

1

$0

$0

12

12

16

192

19

10

$17,027

$0

0

 

4. Records of power outages

1

$0

$0

12

12

16

192

19

10

$17,027

$0

0

 

5. Records of facility enclosure inspections

1

$0

$0

12

12

16

192

19

10

$17,027

$0

0

 

6. Records of startup and shutdown

1

$0

$0

12

12

16

192

19

10

$17,027

$0

0

 

7. Records of malfunctions

2

$0

$0

6

12

16

192

19

10

$17,027

$0

0

 

8. Records of actions taken during malfunctions

1

$0

$0

6

6

16

96

10

5

$8,514

$0

0

 

9. Records for BLDS

1

$0

$0

12

12

16

192

19

10

$17,027

$0

0

 

10. Records of furnace inspection

1

$0

$0

12

12

16

192

19

10

$17,027

$0

0

 

11. Records of recovery of plastic battery casing material

1

$0

$0

6

6

16

96

10

5

$8,514

$0

0

 

E. Personnel Training

8

$0

$0

1

8

0

0

0

0

$0

$0

0

 

F. Time for Audits

NA

 

 

 

 

 

 

 

 

 

 

 

 

Recordkeeping Subtotal

 

 

 

 

 

 

1744

174

87

$154,663

$0

0

 

TOTAL

 

 

 

 

 

 

3294

329

165

$292,604

$170,380

33

 

 

 

 

 

 

 

 

 

Total Hours

Labor

Non-Labor

Total

 

 

 

 

 

 

 Summary of Respondent Burden

3,788

$292,604

$170,380

$462,984

 

 

 

 

 

 

 Initial Capital and Startup 

 

 

$0

 

 

 

 

 

 

 

 Annualized Capital/Start-up and O & M

 

 $170,380

 

 

 




Table 4 - Summary of Annual Respondent Burden and Cost of Recordkeeping and Reporting Requirements for the Secondary Lead Smelters NESHAP

Year

Technical Hours

Clerical Hours

Management Hours

Total Labor Hours

Labor Costs

Non-Labor (Annualized Capital/Startup and O&M) Costs

Total Costs

1

4,898

490

245

5,633

$437,514

$720,080

$1,157,594

2

3,554

355

178

4,087

$315,662

$430,380

$746,042

3

3,294

329

165

3,788

$292,604

$170,380

$462,984

Total

11,746

1,175

587

13,508

$1,045,780

$1,320,840

$2,366,620

Average

3,915

392

196

4,503

$348,593

$440,280

$788,873




Table 5 - Annual Designated Administrator Burden and Cost of Recordkeeping and Reporting Requirements for the Secondary Lead Smelters NESHAP - Year 1





 

(A)

(B)

(C)

(D)

(E)

(F)

Footnotes

Burden Item

Number of Occurrences Per Year

EPA Hours Per Occurrence

Tech Hours Per Year (C=AxB)

Management Hours Per Year (D=Cx0.05)

Clerical Hours Per Year (E=Cx0.1)

EPA Cost Per Year (a,b)

1.

Applications

 

not applicable

2.

Read and Understand Rule Requirements

 

20

40

800

40

80

$41,458

a

3.

Required Activities

 

 

 

A.

Observe stack tests

7

48

336

17

34

$17,412

B

 

B.

Excess emissions -- Enforcement Activities

 

3

24

72

4

7

$3,731

c

 

C.

Create Information

 

not applicable

 

D.

Gather Information

 

not applicable

 

E.

Report Reviews

 

 

 

 

1.

Review work practice SOP

 

16

10

160

8

16

$8,292

 

 

 

2.

Review different presure monitoring report

 

16

3

48

2

5

$2,487

 

 

 

3.

Review annual compliance report

 

16

10

160

8

16

$8,292

D

 

F.

Prepare annual summary report

 

1

64

64

3

6

$3,317

e

 

TOTAL

 

 

 

 

1640

82

164

$84,989

 


FOOTNOTES

a Number of occurences is the number of states where affected sources will exist and each EPA Region (10 states + 10 EPA regions = 20 respondents).

b Assumes EPA personnel attend 20 percent of the stack tests.

c Assume 10 percent of the facilities will exceed emissions.

d Only hours to review new requirements.

e Using four hours per state to write annual summary report.



Table 6 - Annual Designated Administrator Burden and Cost of Recordkeeping and Reporting Requirements for the Secondary Lead Smelters NESHAP - Year 2

 

 

 

 

 

(A)

(B)

(C)

(D)

(E)

(F)

Footnotes

Burden Item

Number of Occurrences Per Year

EPA Hours Per Occurrence

Tech Hours Per Year (C=AxB)

Management Hours Per Year (D=Cx0.05)

Clerical Hours Per Year (E=Cx0.1)

EPA Cost Per Year (a,b)

1.

Applications

 

not applicable

2.

Read and Understand Rule Requirements

 

0

40

0

0

0

$0

a

3.

Required Activities

 

 

 

A.

Observe stack tests

7

48

336

17

34

$17,412

b

 

B.

Excess emissions -- Enforcement Activities

 

3

24

72

4

7

$3,731

c

 

C.

Create Information

 

not applicable

 

D.

Gather Information

 

not applicable

 

E.

Report Reviews

 

 

 

 

1.

Review work practice SOP

 

0

10

0

0

0

$0

 

 

 

2.

Review different presure monitoring report

 

16

3

48

2

5

$2,487

 

 

 

3.

Review annual compliance report

 

16

10

160

8

16

$8,292

d

 

F.

Prepare annual summary report

 

1

64

64

3

6

$3,317

e

 

TOTAL

 

 

 

 

680

34

68

$35,239

 

 

 

 

 

 

 

 

 

 

 

 

 


FOOTNOTES

a Number of occurences is the number of states where affected sources will exist and each EPA Region (10 states + 10 EPA regions = 20 respondents).

b Assumes EPA personnel attend 20 percent of the stack tests.

c Assume 10 percent of the facilities will exceed emissions.

d Only hours to review new requirements.

e Using four hours per state to write annual summary report.


Table 7 - Annual Designated Administrator Burden and Cost of Recordkeeping and Reporting Requirements for the Secondary Lead Smelters NESHAP - Year 3

 

 

 

 

 

(A)

(B)

(C)

(D)

(E)

(F)

Footnotes

Burden Item

Number of Occurrences Per Year

EPA Hours Per Occurrence

Tech Hours Per Year (C=AxB)

Management Hours Per Year (D=Cx0.05)

Clerical Hours Per Year (E=Cx0.1)

EPA Cost Per Year (a,b)

1.

Applications

 

not applicable

2.

Read and Understand Rule Requirements

 

0

40

0

0

0

$0

a

3.

Required Activities

 

 

 

A.

Observe stack tests

7

48

336

17

34

$17,412

b

 

B.

Excess emissions -- Enforcement Activities

 

3

24

72

4

7

$3,731

c

 

C.

Create Information

 

not applicable

 

D.

Gather Information

 

not applicable

 

E.

Report Reviews

 

 

 

 

1.

Review work practice SOP

 

0

10

0

0

0

$0

 

 

 

2.

Review different presure monitoring report

 

16

3

48

2

5

$2,487

 

 

 

3.

Review annual compliance report

 

16

10

160

8

16

$8,292

d

 

F.

Prepare annual summary report

 

1

64

64

3

6

$3,317

e

 

TOTAL

 

 

 

 

680

34

68

$35,239

 


FOOTNOTES

a Number of occurences is the number of states where affected sources will exist and each EPA Region (10 states + 10 EPA regions = 20 respondents).

b Assumes EPA personnel attend 20 percent of the stack tests.

c Assume 10 percent of the facilities will exceed emissions.

d Only hours to review new requirements.

e Using four hours per state to write annual summary report.



Table 8 - Summary of Annual Designated Administrator Burden and Cost of Recordkeeping and Reporting Requirements for the Secondary Lead Smelters NESHAP

Year

Technical Hours

Management Hours

Clerical Hours

Total Hours

Labor Costs

Non-Labor Costs

Total Costs

1

1,640

82

164

1,886

$84,989

$0

$84,989

2

680

34

68

782

$35,239

$0

$35,239

3

680

34

68

782

$35,239

$0

$35,239

Total

3,000

150

300

3,450

$155,467

$0

$155,467

Average

1,000

50

100

1,150

$51,822

$0

$51,822



ATTACHMENT 2. INFORMATION REQUIREMENTS----AMENDMENTS TO SECONDARY LEAD SMELTING NESHAP



Requirement

Citation for existing sources

Citation for new sources

General Provisions citation

Emission limits for vents

§63.543

§63.543


Standards for Fugitive Emissions

§63.545

§63.545


Monitoring

§63.548

§63.548

N/A

Notifications

§63.549

§63.549

63.9

Recordkeeping and reporting requirements

§63.550

§63.550


Reports of malfunctions that result in an exceedances of the standard for the purpose of affirmative defense

§63.552

§63.552


Records

§63.541

§63.541

63.10

Reports

§63.541

§63.541

63.10


5