Download:
pdf |
pdfAppendix K1
Detailed Unit Burden and Cost for Injection and Geologic Sequestration of Carbon Dioxide (Subpart RR)
(Does Not Include Burden Cost for Exemption Requests)
Annual Burden & Cost Per Facility, Subpart RR
ICR Activity
Estimation of Fugitive Emission from
Surface Facilities
Periodic Digital Color Infrared
Orthoimagery (CIR) or Hyperspectral
Imaging to detect changes to
vegetation.
Periodic mobile survey to detect
surface leaks. May be good option
where vegetation is sparse.
Soil zone monitoring (sampling gas
from accumulation chambers)
Vadose zone monitoring wells to
sample gas above water table.
Monitoring wells for samples from
water table.
Cost of Episodic Surveys to Quantify
Leaks
MRV
Monitoring
Reporting and Recodkeeping
Sub Categories/Notes
Total Labor
Cost
($)
Responses/
Respondent
Total
Responses
Total Burden
(hrs)
Planning and initial inventory
1
1
40
$
5,957 $
$
$
5,957
Annual calculations
1
1
24
$
3,574 $
$
$
3,574
Planning and QA
0.5
0.5
0
$
$
$
48,000 $
48,000
Mobilization
0.5
0.5
0
$
$
$
3,000 $
3,000
Airborne Survey
0.5
0.5
0
$
$
$
30,000 $
30,000
Planning and QA
0.5
0.5
0
$
$
$
48,000 $
48,000
Mobilization
0.5
0.5
0
$
$
$
3,000 $
3,000
Airborne Survey
0.5
0.5
0
$
$
$
11,520 $
11,520
Monitoring plan
1
1
40
$
5,957 $
4,321 $
$
10,277
Sampling and Analysis
1
1
0
$
$
$
2,880 $
2,880
Monitoring plan
1
1
40
$
5,957 $
5,761 $
$
11,718
Sampling and Analysis
1
1
0
$
$
$
2,880 $
2,880
Monitoring plan
1
1
40
$
5,957 $
57,607 $
$
63,564
Sampling and Analysis
1
1
0
$
$
$
11,520 $
11,520
0.01
0.01
2
$
189 $
$
$
189
0.01
0.01
2
$
189 $
$
473 $
662
0.01
0.01
3
$
378 $
$
$
378
0.01
0.01
2
$
189 $
$
1,248 $
1,437
0.01
0.01
1
$
414 $
$
840 $
1,254
Evaluate Leakage Pathways
1
1
16
$
1,253 $
$
$
1,253
Delineate Areas of Monitoring
Develop strategy for leak
detection, verification and
1
1
32
$
2,505 $
$
$
2,505
1
1
160
$
12,526 $
$
$
12,526
Establish baseline conditions
1
1
16
$
1,253 $
$
$
1,253
Tailor mass balance equation
1
1
8
$
626 $
$
$
626
Write MRV plan
Discuss MRV plan with EPA
and edits
1
1
400
$
31,316 $
$
$
31,316
1
1
100
$
7,829 $
$
$
7,829
Annual Report
CO2 Flow Meter Data
Collection
1
1
100
$
7,829 $
$
$
7,829
1
1
4
$
332 $
$
$
332
Reporting
1
1
23
$
1,700 $
$
$
1,700
Recordkeeping
1
1
7
$
500 $
$
$
500
Totals
22
22
1,059
$
96,429 $
67,688 $
163,361 $
327,478
Surface leak detected by air,
soil or water table monitoring
or subsurface leak detected by
pressure anomaly etc.
(material balance).
Surface leak detected by MIT
survey or by air, soil or water
table monitoring (well logs).
pressure anomaly in
containment zone (pressure
readings).
soil or water table monitoring
(seismic).
soil or water table monitoring
(tenting).
Capital Cost
($)
O&M Cost
($)
Total Cost
($)
Appendix K1
Detailed Unit Burden and Cost for Injection and Geologic Sequestration of Carbon Dioxide (Subpart UU)
Annual Burden & Cost Per Facility, Subpart UU
ICR Activity
Monitoring
Reporting and
Recodkeeping
Sub
Categories/Notes
Total Labor
Cost
($)
Responses/
Respondent
Total
Responses
Total Burden
(hrs)
Injectate Sampling
and Analysis
4
4
10
$
630 $
$
2,256 $
2,886
Reporting
1
1
24
$
1,700 $
$
$
1,700
Recordkeeping
1
1
7
$
500 $
$
$
500
Totals
6
6
41
$
2,830 $
$
2,256 $
5,086
Capital Cost
($)
O&M Cost
($)
Total Cost
($)
Appendix K-2
Summary of Burden and Cost for Injection and Geologic Sequestration of Carbon Dioxide (Subparts
RR and UU)*
Year 1
Source Category
No. Respondents
Responses/
Respondent
Total
Responses
Total Burden
(hrs)
Total Labor Cost
($)
Capital Cost
($)
Subpart RR
1
Varies
22
1,059
$
96,429
$
Subpart UU
91
Varies
546
3,702
$
257,565
$
Exemption requests (Subpart RR)
1
1
1
16
$
1,097
Total
93
Varies
569
4,777
$
355,090 $
67,688
67,688
O&M Cost
($)
Total Cost
($)
$
163,361
$
327,478
$
205,296
$
462,861
$
1,097
$
791,436
$
368,657
Year 2
Source Category
No. Respondents
Responses/
Respondent
Total
Responses
Total Burden
(hrs)
Total Labor Cost
($)
Capital Cost
($)
O&M Cost
($)
Total Cost
($)
Subpart RR
2
Varies
44
2,118
$
192,858
$
$
326,722
$
654,956
Subpart UU
92
Varies
552
3,743
$
260,395
$
$
207,552
$
467,947
Exemption requests (Subpart RR)
1
1
1
16
$
1,097
$
$
$
1,097
Total
95
0
597
5,877
$
454,350 $
$
1,124,000
No. Respondents
Responses/
Respondent
Total
Responses
Total Burden
(hrs)
Subpart RR
3
Varies
66
3,177
Subpart UU
93
0
558
Exemption requests (Subpart RR)
1
1
1
Total
97
0
625
No. Respondents
Responses/
Respondent
Total
Responses
Total Burden
(hrs)
135,376
135,376
$
534,274
Year 3
Source Category
Total Labor Cost
($)
Capital Cost
($)
$
289,287
$
3,783
$
263,225
16
$
1,097
6,977
$
553,609 $
203,065
O&M Cost
($)
$
490,083
$
$
209,808
$
$
203,065
$
699,891
Total Cost
($)
$
982,435
$
473,033
$
1,097
$
1,456,565
Annual Average 3 year ICR Period
Source Category
Total Labor Cost
($)
Capital Cost
($)
O&M Cost
($)
Total Cost
($)
Subpart RR
2
Varies
44
2,118
$
192,858
$
$
326,722
$
654,956
Subpart UU
92
Varies
552
3,743
$
260,395
$
$
207,552
$
467,947
Exemption requests (Subpart RR)
1
1
1
16
$
1,097
$
$
$
1,097
$
1,124,000
Total
95
0
597
5,877
$
454,350 $
* Does not include the provision of information on parent companies, NAICS codes, and whether emissions are from cogeneration.
135,376
135,376
$
534,274
Appendix K-3
Subpart RR - Summary of Cost and Burden
Non-Federal Respondents
Source Category
No.
Respondents
Subpart RR
Subpart UU
2
87
Total
89
Current Inventory (OMB No. 2060 0649, ICR No. 2372.02, 2372,03)
Total Labor
Responses/
Total
Total Burden
Capital Cost O&M Cost
Cost
Respondent
Responses
(hrs)
($)
($)
($K)
16
32
1,234
$
133 $
88 $
244
6
520
3,560
$
224 $
$
196
22
552
4,794
$
357 $
88 $
Total Cost
($)
$
$
465
420
439 $
884
Revised Inventory
Source Category
Total Labor
Cost
($K)
No.
Respondents
Responses/
Respondent
Total
Responses
Total Burden
(hrs)
Subpart RR
Subpart UU
3
92
Varies
Varies
45
552
2,134
3,743
$
$
194
260
Total
95
0
597
5,877
$
454 $
Source Category
No.
Respondents
Responses/
Respondent
Total
Responses
Subpart RR
Subpart UU
1
5
Varies
Varies
13
32
Total
6
45
Capital Cost
($)
O&M Cost
($)
Total Cost
($)
$
$
$
$
$
$
656
468
534 $
1,124
135
135 $
327
208
Difference
Total Labor
Capital Cost O&M Cost
Total Burden
Cost
($)
($)
(hrs)
($)
900
$
61 $
47 $
83
183
$
36 $
$
12
1,083
$
97 $
47 $
Total Cost
($)
$
$
192
48
95 $
240
Reason for Change in Burden (see Appendix K 3 for more details):
• Shifted the activities associated with Subpart RR two years into the future to reflect the fact that Class VI UIC permits were not issued as quickly
as anticipated in the ICR. For example, the activities estimated for Year 1 of the current ICR (2011) have been shifted to Year 1 of the renewal
ICR (2013, the first year in which Class VI injection is expected to begin).
• Adjusted the labor hours, labor cost, O&M costs, and capital cost per facility for Subpart UU to recognize the completion of the one time
activities that occurred in the first year of data collection (2011).
• Adjusted the number of respondents for Subpart UU to reflect the slightly higher number of facilities anticipated in the out years of the
previous ICR.
File Type | application/pdf |
File Title | K cover |
Author | Patty Hertzler |
File Modified | 2012-09-17 |
File Created | 2012-09-17 |