Regulatory Analysis for Final Rule" 10 CFR Part 73

Regulatory - Analysis ML120050180.pdf

10 CFR 73, Physical Protection of Plants and Materials

Regulatory Analysis for Final Rule" 10 CFR Part 73

OMB: 3150-0002

Document [pdf]
Download: pdf | pdf
Regulatory Analysis for Final Rule: 10 CFR 73.37,
Physical Protection of Irradiated Reactor Fuel in Transit

U.S. Nuclear Regulatory Commission
February 2012

Table of Contents
EXECUTIVE SUMMARY .......................................................................................................................................... ii
ACRONYMS AND ABBREVIATIONS .................................................................................................................... iv
1. INTRODUCTION .................................................................................................................................................. 1
1.1 Statement of the Problem and Objective of the Rulemaking .................................................................. 1
1.2 Background .................................................................................................................................................... 2
1.3 Commission Orders ...................................................................................................................................... 2
2. IDENTIFICATION OF ALTERNATIVE APPROACHES .................................................................................. 3
2.1 Alternative 1: No-Action .............................................................................................................................. 3
2.2 Alternative 2: Rulemaking to Enhance the Physical Protection of SNF in Transit ............................. 3
3. ANALYSIS OF VALUES AND IMPACTS .......................................................................................................... 3
3.1 Identification of Affected Attributes ............................................................................................................ 4
3.2 Analytic Methodology.................................................................................................................................... 6
3.3 Main Analysis (Post Orders) ........................................................................................................................ 6
3.3.1 Baseline for the Main Analysis ......................................................................................................... 6
3.3.2 Main Analysis Assumptions .............................................................................................................. 7
3.4 Pre-order Analysis (Orders and Lessons Learned) ................................................................................. 7
3.4.1 Pre-order Analysis Assumptions ...................................................................................................... 7
4. RESULTS ............................................................................................................................................................... 8
4.1 Benefits and Cost for Main Analysis ........................................................................................................... 9
4.2 Backfit Analysis ............................................................................................................................................ 11
5. DECISION RATIONALE AND IMPLEMENTATION ...................................................................................... 11
6. REFERENCES .................................................................................................................................................... 12
Appendix .................................................................................................................................................................... 13

i

EXECUTIVE SUMMARY
The U.S. Nuclear Regulatory Commission (NRC or the Commission) is amending its security
regulations for the transport of irradiated reactor fuel.1 This rulemaking establishes generically
applicable security requirements similar to the requirements currently imposed by NRC Order
EA-02-109, “Issuance of Order for Interim Safeguards and Security Compensatory Measures for
the Transportation of Spent Nuclear Fuel Greater than 100 Grams,” (67 FR 63167; October 10,
2002). This Order was issued to NRC power reactor licensees, non-power reactor licensees,
independent spent fuel storage installation (ISFSI) licensees, and special nuclear material
licensees, who shipped, received, or planned to ship or receive spent nuclear fuel (SNF) under
the provisions of Title 10 of the Code of Federal Regulations (10 CFR) Part 71. Subsequently,
the Commission issued similar orders to licensees shipping SNF during the period October
2003 through December 8, 2010. These orders are collectively referred to as the “Orders for
SNF in Transit” or “the Orders.” This rulemaking also establishes performance standards and
objectives for the protection of SNF shipments from theft, diversion, or radiological sabotage.
Additionally, this rulemaking also addresses, in part, a 1999 petition for rulemaking from the
State of Nevada (PRM-73-10) that requests NRC to strengthen the regulations governing the
security of SNF shipments against malevolent acts. This rule will apply to NRC licensees who
transport, or deliver to a carrier for transport SNF.
The purpose of this regulatory analysis is to measure the incremental costs of the rule. The
baseline for the analysis is the No-Action Alternative, or how things would be without the rule.
In the absence of the rule, the Commission’s Orders would remain in place. The assumption in
the regulatory analysis is that in the absence of the rule, the Commission will continue to issue
Orders for SNF in Transit to licensees who were not covered under previously issued Orders.
The costs evaluated in the regulatory analysis are only those costs that would be incurred under
the rule, not under the Commission Orders for SNF in Transit or the existing § 73.37
regulations. In addition, another analysis called the “pre-order analysis” is included in this
regulatory analysis for informational purposes only. Under these assumptions, the analysis
presented in this document examines the benefits and costs of the new security requirements.
The analysis found:
•

Total Cost to Industry. The total annual cost of implementing the rule for each NRC
licensee who transports, or delivers to a carrier for transport, SNF (industry) is $71,000,
and total one-time costs are $5,000. The total present value of the costs to industry is
$0.5 million (using a 7 percent discount rate) and $0.6 million (using a 3 percent discount
rate) over a 10-year analysis period. These costs reflect additional security
requirements that were developed as a result of lessons learned from implementation of
the Orders. These costs are discussed in Section 3.

•

Value of Benefits Not Reflected Above. With the exception of some of the direct
monetary savings to industry, the cost figures shown above do not reflect the value of
the benefits of the final rule. These benefits are evaluated qualitatively in Section 4.1.
Based on the qualitative analysis, the NRC determined that the costs of the rule are
justified in view of the qualitative benefits.

1

For purposes of this rulemaking, the terms “irradiated reactor fuel” and “spent nuclear fuel” (SNF) are
used interchangeably.
ii

•

Costs to NRC. There are no annual costs for the NRC associated with the
implementation of the rule. The NRC has a one-time cost associated with updating the
associated guidance, NUREG-0561, Physical Protection of Irradiated Reactor Fuel in
Transit, to be consistent with the final rule, which is $5,000.

•

Decision Rationale. The analysis did not quantify the benefits of this rulemaking.
Rather, it, qualitatively examines the benefits of the rule. It was concluded that the rule
would provide security-related benefits. These security-related benefits are associated
with safeguards and security considerations stemming from the decreased risk of a
security-related event, such as an act of sabotage. Thus, decreasing the risk of a
security-related event protects the common defense and security, protects the health of
the public and occupational workers, and decreases the risk of damage to offsite
properties.

The sum total of the requirements in the final rule will provide additional assurance of NRC
licensees’ ability to protect SNF security requirements in transit from theft, diversion, or
radiological sabotage. The final rule provides a substantial increase in the protection of the
common defense and security and the public health and safety from SNF in Transit.
Specifically, the final rule will require armed escorts throughout the rail and road route, minimum
of 2 weapons for private armed escorts, private armed escorts’ deadly force training, and
additional NRC notifications. The rule will also include implementation of certain technological
advances in the areas of communications and global positional tracking, which are necessary
during a safeguards contingency event. In addition, the rule’s requirements for training and
procedures for the transportation security program and background investigations for all
personnel associated with the shipment will increase the effectiveness of NRC licensees'
security programs. Finally, public confidence in the NRC and its licensees would increase
because the rule will establish performance standards and objectives for the physical protection
of SNF in Transit from theft, diversion, or radiological sabotage that are generally applicable to
all NRC licensees authorized to transport, or delivers to a carrier for transport SNF.
In conclusion, the NRC staff believes that these qualitative benefits represent a substantial
increase in public health safety and the protection of the common defense and security. As
such, the costs of the final rulemaking are justified based upon the qualitative benefits.

iii

ACRONYMS AND ABBREVIATIONS
CFR
FR
LLEA
NRC
NUREG
NUREG/BR
OMB
SECY
SGI
SNF

Code of Federal Regulations
Federal Register
Local Law Enforcement Agency
Nuclear Regulatory Commission
Nuclear Regulatory Commission technical report designation
NUREG brochure
Office of Management and Budget
A paper addressing policy, rulemaking, or adjudicatory matters submitted to the
Commission for consideration in a document style and format established
specifically for the purpose.
Safeguards Information
Spent Nuclear Fuel

iv

1. INTRODUCTION
This document presents a regulatory analysis of the security requirements for the physical
protection of irradiated reactor fuel.2 The U.S. Nuclear Regulatory Commission (NRC or the
Commission) is revising Title 10 to the Code of Federal Regulations (10 CFR) Part 73 to
establish generically applicable security requirements similar to those issued after the events of
September 11, 2001. This rulemaking will also establish performance standards and objectives
for the protection of spent nuclear fuel (SNF) shipments from theft, diversion, or radiological
sabotage. Additionally, this rulemaking also addresses, in part, a 1999 petition for rulemaking
from the State of Nevada (PRM-73-10) that requests NRC to strengthen the regulations
governing the security of SNF shipments against malevolent acts. This rule will apply to NRC
licensees who transport, or deliver to a carrier to transport SNF.
The purpose of this regulatory analysis is to measure the incremental costs of the rule.
Section 1.1 of this document states the problem and the reasons for the rulemaking.
Section 1.2 provides background information. Section 1.3 discusses the regulatory objectives
of the rule.
1.1

Statement of the Problem and Objective of the Rulemaking

After the attacks of September 11, 2001, the NRC reevaluated its security requirements for SNF
in Transit. From this effort, additional security measures were identified. In the area of security
for SNF in transit, the Commission imposed additional security requirements through NRC
Order EA-02-109, “Issuance of Order for Interim Safeguards and Security Compensatory
Measures for the Transportation of Spent Nuclear Fuel Greater than 100 Grams,” (67 FR
63167; October 10, 2002). This Order was issued to NRC power reactor licensees, non-power
reactor licensees, independent spent fuel storage installation (ISFSI) licensees, and special
nuclear material licensees, who shipped, received, or planned to ship or receive SNF under the
provisions of 10 CFR Part 71. Subsequently, the Commission issued similar orders to licensees
shipping SNF during the period October 2003 through December 8, 2010. These orders are
collectively referred to as the “Orders for SNF in Transit” or “the Orders.” The current
rulemaking incorporates the security requirements in the Orders as well as lessons learned from
implementation of the Orders. It also addresses, in part, the 1999 petition for rulemaking
submitted by the State of Nevada (PRM-73-10).
Orders, unlike rules, do not apply prospectively to applicants for new licenses. The NRC would
have to periodically issue new orders to cover new and amended licenses. In order to make the
security requirements generally applicable to present and future licensees who transport, or
deliver to a carrier for transport SNF, the security-related requirements need to be incorporated
into NRC regulations. In addition, notice and comment rulemaking allows for public participation
and is an open and transparent process.
The NRC objectives for this rulemaking are to: 1) establish generically applicable security
requirements similar to those previously imposed by Commission Orders issued after
September 11, 2001; 2) establish the performance standards and objectives for the protection of
2

For purposes of this rulemaking, the terms “irradiated reactor fuel” and “spent nuclear fuel” (SNF) are
used interchangeably.

1

SNF shipments from theft, diversion, or radiological sabotage; 3) ensure that the performance
standards and objectives for SNF shipments apply to all licensees authorized to transport, or
deliver to a carrier for transport SNF; and 4) address, in part, the requests for NRC rulemaking
raised in PRM-73-10.
1.2

Background

The SNF comes from commercial nuclear power reactors and non-power reactors. After the
fresh fuel has been used in a reactor, highly radioactive SNF assemblies remain. The
assemblies must be removed from the reactor for storage to make room for new assemblies
and to allow the fuel to cool. Currently, most SNF assemblies are stored in pools of water,
aboveground vaults, or concrete casks. The SNF may be shipped to temporary storage sites
when space at reactor sites is limited. It is also shipped for research studies. The NRC
regulates SNF shipments to protect both public health and safety and common defense and
security.
On June 15, 1979, the NRC published in the Federal Register (44 FR 34466) an interim final
rule that established requirements for the physical protection of irradiated reactor fuel in transit.
The interim final rule added a new Section 73.37 to 10 CFR Part 73 entitled, “Physical
Protection of Irradiated Reactor Fuel in Transit.” The interim rule and related guidance,
NUREG-0561, “Physical Protection of Shipments of Irradiated Reactor Fuel,” were issued in
effective form without the benefit of public comment. At the time of publication, public
comments were solicited on the interim regulation and the guidance document. After
considering public comments, amendments to the interim final rule and the guidance document
were issued on June 3, 1980 (45 FR 37399). This rulemaking also requires that the physical
protection system: 1) provide for the early detection and assessment of attempts to gain
unauthorized access to or control over SNF shipments; 2) provide notification to the appropriate
response forces of any sabotage events; and 3) impede attempts at radiological sabotage of
SNF shipments in heavily populated areas or attempts to illicitly move such shipments into
heavily populated areas.
1.3

Commission Orders

In response to the September 11, 2001, terrorist attacks, the NRC determined that additional
security measures were needed to enhance the protection of SNF shipments from theft,
diversion, or radiological sabotage. The Commission imposed these additional security
requirements through Orders for SNF in Transit. The Orders were issued to NRC power reactor
licensees, non-power reactor licensees, ISFSI licensees, and special nuclear material licensees,
who shipped, received, or planned to ship or receive SNF under the provisions of 10 CFR
Part 71.
The specifics of the Orders for SNF in Transit are protected as safeguards information (SGI); as
such, their details cannot be discussed in this document. In general, the security requirements
in the Orders resulted in enhancements in the following areas: 1) preplanning and coordination
with local law enforcement agency (LLEA) and State law enforcement agencies;
2) communications among movement control personnel; 3) development of normal operating
and contingency procedures; 4) a minimum number of weapons for escorts; and 5) background
investigations for individuals associated with SNF shipments.
2

2.

IDENTIFICATION OF ALTERNATIVE APPROACHES

The NRC considered two alternatives to meet the regulatory goals identified in the previous
section. The alternatives are described below.
2.1

Alternative 1: No-Action

Alternative 1 is the No-Action Alternative. The No-Action Alternative is how the regulatory
environment for SNF in transit would look absent the rule. Under the No-Action Alternative, the
NRC would not move forward with the rule. The existing regulations in § 73.37, the Orders for
SNF in Transit would remain in place, and the Commission would continue to issue Orders for
SNF in Transit to licensees who were not covered under previously issued Orders. The
No-Action alternative serves as the baseline against which the Rule Alternative (described
below) is measured.
This alternative does not reflect the additional security requirements developed as a result of
lessons learned from implementation of the Orders, and from the implementation of the Orders.
Thus, this alternative would not incorporate the additional requirements needed to establish
performance standards and objectives for the protection of SNF shipments from theft, diversion,
or radiological sabotage.
In addition, this alternative would place an administrative burden on the NRC. Unlike the
requirements of a rule which apply to all applicable licensees, the Orders for SNF in Transit
apply only to the licensees that are specifically subject to the Orders. It would not apply to new
licensees, unless the Orders are sent to them as well. The NRC would be required to issue
Orders to each new licensee seeking to transport SNF, which makes this alternative less
efficient and effective than developing regulations.
2.2

Alternative 2: Rulemaking to Enhance the Physical Protection of SNF in Transit

Under Alternative 2, the NRC would enhance the requirements for the physical protection of
SNF in Transit through rulemaking. The rulemaking would include revisions to §§ 73.37 and
73.72 and the creation of a new § 73.38, as described in the rule.
Alternative 2 is more efficient and effective than the continued issuance of Orders for SNF in
Transit. The NRC has estimated the qualitative benefits and costs of this alternative, as
described in Sections 3 and 4 of this regulatory analysis. The preferred approach is
Alternative 2 (Rulemaking) for the reasons discussed in Section 5.
3.

Evaluation of Benefits and Costs

This section examines the benefits and costs expected from this rulemaking, and are presented
in four subsections. Section 3.1 identifies the attributes that are expected to be affected by the
rulemaking. Section 3.2 describes how the benefits and costs have been analyzed for the main
analysis. Section 3.3 describes how the benefits and costs have been analyzed for costs of the
rule compared to the costs associated with the No-Action Alternative.

3

Throughout this analysis, various labor rates are used. These rates are used consistently for all
of the analyses and their derivations are described below.
Licensee labor rates were obtained from National Wage Data available on the Bureau of Labor
Statistics web site (www.bls.gov). Depending on the industry and the occupation (e.g.,
manufacturing, health and safety, etc.), the NRC selected an appropriate mean hourly labor
rate. The rate is then increased using a multiplier of 1.5 to account for benefits (insurance
premiums, pension, and legally required benefits). Because exact hourly rates would be difficult
to obtain and may not be recent, the NRC used nationwide mean hourly rates. For all licensee
labor rates, $73.20/hour is used, which is from Bureau of Labor Statistics Employer Costs for
Employee Compensation data set, “Nuclear Engineers,”3 however, some of the actions
evaluated may be conducted by lower paid employees, such as clerical staff.
The NRC’s labor rates are determined using the calculation methodology described in
Abstract 5.2, “NRC Labor Rates in the Generic Cost Catalog,” of NUREG/CR-4627, "Generic
Cost Estimates." This methodology considers only variable costs that are directly related to the
implementation, operation, and maintenance of the requirement. Currently, this hourly labor
rate for the NRC is $119.
The estimation of costs for rulemaking is based on professional staff full-time equivalent (FTE).
Based on actual data from the NRC’s time and labor system, the number of hours in 1 year that
directly relate to implementation of assigned duties is 1,451; this excludes hours on such things
as leave, training, and completing administrative tasks. Therefore, an NRC professional staff
FTE hour rate is based on 1,451 hours. As described in the Office of Management and Budget
(OMB) Circular A-76, “Performance of Commercial Activities,” the number of productive hours in
one year is 1,776. As this actual value is likely to vary from State to State and no specific data
are available, the FTE costs for the States are based on the number of hours estimated in OMB
Circular A-76.
3.1

Identification of Affected Attributes

This section identifies the factors within the public and private sectors that the NRC expects the
final rule to affect, using the list of potential attributes in Chapter 5 of NUREG/BR-0184,
“Regulatory Analysis Technical Evaluation Handbook,” issued January 1997, and in Chapter 4
of NUREG/BR-0058, “Regulatory Analysis Guidelines of the U.S. Nuclear Regulatory
Commission,” Revision 4, issued September 2004. The basis for selecting those attributes is
presented below.
Affected attributes include the following:

3

U.S. Department of Labor, Bureau of Labor Statistics. Occupational Employment Statistics,
Occupational Employment and Wages, May 2010 17-2161 Nuclear Engineers. Mean hourly wage is
$48.80 x 1.5 = $73.20/hour.

4

•

Environmental Considerations – The rule will result in a decrease in the potential risk of
environmental contamination that could result from theft, diversion, or radiological
sabotage of SNF shipments.

•

Improvements in Knowledge – The rule will result in an increase in the information
available to the NRC on SNF shipments.

•

Industry Implementation – The rule will require licensees to revise their Transportation
Physical Security Plans, Safeguards Contingency Plans, and Training and Qualification
Plans, and conduct background investigations of personnel associated with SNF
shipments.

•

Industry Operation – The rule will require licensees to modify their operations due to
additional security activities beyond those currently required.

•

NRC Implementation –The rule will require the NRC to update existing guidance,
NUREG-0561, “Physical Protection of Shipments of Irradiated Reactor Fuel."

•

NRC Operation – The rule will require the NRC Operations Center to receive additional
notifications.

•

Occupational Health (Accident) – The rule will reduce the risk that occupational health
would be affected by radiological releases resulting from radiological sabotage.

•

Offsite Property – The rule will reduce the risk that offsite properties would be affected
by radiological releases resulting from radiological sabotage.

•

Other Government – The rule will require additional State and LLEA interaction with
licensees and the NRC.

•

Public Health (Accident) – The rule will reduce the risk that public health would be
affected by radiological releases resulting from radiological sabotage.

•

Regulatory Efficiency – The rule will enhance regulatory efficiency by incorporating
security requirements similar to those previously imposed by Commission Orders for
SNF in Transit and additional security requirements in regulations resulting form the
lessons learned from implementing the Orders.

•

Safeguards and Security Considerations – The rule will establish the performance
standards and objectives for the physical protection of SNF in Transit that will provide
high assurance that the transport of SNF is not inimical to the common defense and
security and does not constitute an unreasonable risk to the public health and safety.

The rule is not expected to affect the following attributes: antitrust considerations, general
public, occupational health (routine), public health (routine), improvements in knowledge, and
on-site property.

5

3.2

Analytic Methodology

This section describes the process used to evaluate the incremental values (benefits) and
impacts (costs) associated with the rule relative to the No-Action Alternative. The benefits
include desirable changes in affected attributes, e.g., monetary savings and improved safety
and security. The analysis relies upon a qualitative evaluation of the benefits associated with
improved safety and security of spent nuclear fuel transport.
The costs include undesirable changes in affected attributes, e.g., increased monetary costs
and radiation exposure levels. The NRC evaluated industry implementation and operating costs
and the NRC implementation and operating costs quantitatively. Quantitative analysis requires
a baseline characterization. This analysis includes: 1) the average number of shipments
affected; 2) the nature of current activities; 3) the types of new or modified systems and
procedures that would be implemented, or would no longer be implemented; and 4) the number
of hours and costs entailed in conforming to written procedures.
Licensees may, however, respond differently to the orders. Their responses are dependent on
site-specific characteristics, such as: 1) site physical attributes; 2) current contingency, security,
training, and qualification plan contents; and 3) organizational and management structure.
Costs are also dependent upon the number of anticipated shipments and the number of States
each shipment would pass through; these considerations would require additional efforts in
terms of planning and coordination. Because individual licensee physical protection system
information in large part is considered SGI under § 73.21, this analysis only examines licensees
in the aggregate by making general assumptions.
The NRC collected input assumptions using data and information from NRC workgroups and
staff experience and NRC databases. In accordance with OMB guidance and NUREG/BR-0058,
Rev. 4, the results of the analysis are calculated using both 3 percent and 7 percent real
discount rates.
3.3

Main Analysis (Post Orders)

The Main Analysis identifies the incremental impacts of Alternative 2 relative to the No-Action
Alternative.
3.3.1

Baseline for the Main Analysis

The baseline for the Main Analysis is the No-Action Alternative. The No-Action Alternative is
how the regulatory environment for SNF in transit would be absent the rulemaking. The
baseline assumes full compliance with existing NRC requirements, including current regulations
and orders. This baseline is consistent with NUREG/BR-0058, “Regulatory Analysis Guidelines
of the U.S. Nuclear Regulatory Commission,” Rev. 4, which states that, “in evaluating a new
requirement..., the staff should assume that all existing NRC requirements have been
implemented.” An additional assumption of the baseline for this analysis is that the Commission
would continue to issue Orders for SNF in Transit to those licensees not covered under previous
orders. The incremental costs represented in the Main Analysis are costs that are in addition to
costs already incurred by licensees in their efforts to comply with the Orders for SNF in Transit.

6

3.3.2

Main Analysis Assumptions

NRC used licensee and State labor rates from National Wage Data available on the Bureau of
Labor Statistics web site (www.bls.gov). The NRC assumes an industry labor cost of $73.20
per hour, and State labor cost of $50 per hour, and an NRC labor cost of $119 per hour. Costs
are expressed in 2011 dollars and are modeled either on an annual recurring cost basis or on a
one-time implementation basis. The analysis calculates costs over a 10-year period, with the
annual costs in each year beyond 2011 discounted back at a 7 percent and 3 percent discount
rate, in accordance with NUREG/BR-0058, “Regulatory Analysis Guidelines of the U.S. Nuclear
Regulatory Commission,” Rev. 4.
The licensee activities in the Main Analysis, which are in addition to compliance with security
orders, are activities that would be required by the rule that are the additional requirements
developed as a result of the lessons learned from implementation of the security Orders. These
include licensee activities to document and preplan coordinating activities, to perform more
thorough background investigations compared to what is required under the orders, to provide
cancellation notices, and to maintain records. The assumptions used to represent these
activities are listed in Appendix 1.
An assumption is made in the Main Analysis that the NRC would update existing guidance
documents, at a one-time cost of $5,000.
3.4

Pre-order Analysis (Orders and Lessons Learned)

To date the Orders have been issued to only a small number of licensees. The pre-order
analysis measures the incremental impacts of the rule assuming that the orders were never
issued. The analysis assumes full licensee compliance with existing NRC regulations, but not
the orders that have been issued. This reflects anticipated behavior in the event that the
regulation is not imposed and the Orders were not in effect. In addition, this analysis considers
the cost of implementing the security requirements as well as the costs of regulatory changes
based on lessons learned.
The Pre-Order Analysis is presented to give the reader an idea of the costs and savings that
have already been incurred or would be incurred absent the rulemaking as a result of the
Orders for SNF in Transit. This analysis is for informational purposes only and should not be
used to determine whether or not to proceed with the rulemaking.
3.4.1

Pre-order Analysis Assumptions

To represent the cost of implementing the Orders for SNF in Transit, the NRC assumes 20 SNF
shipments per year which is based on historical data. This data was obtained from NUREG0725, “Public Information Circular for Shipments of Irradiated Reactor Fuel,” Rev. 15, dated
January 2010, which summarizes data for highway and rail shipments of SNF from 1979-2007.
The 20 shipments would consist of 10 shipments via highway and 10 via railway. No shipments
occur via water. An analysis of existing approved shipping routes showed that the shipments
pass through or cross, on average, five States per shipment. Annually, five of the shipments
would originate in U.S. ports as part of international shipments of SNF (i.e., imports of US-origin
SNF). These shipments would then be shipped from port via highway or railway. The NRC
assumes that five shipments would incur difficulties annually, each of which would require
7

revisions to the shipping schedule, and that one shipment would be canceled over a 3-year
period. The 20 shipments would impact 18 licensees per year on average, as 2 licensees are
assumed to ship twice each year. Also, the NRC estimates that one shipment in a 3-year period
would incur an “event” which would require reporting and investigation. The NRC assumes an
industry labor cost of $73.20 per hour, State labor cost of $50 per hour, and an NRC labor cost
of $119 per hour.
Licensees would bear the largest share of this rule’s costs in the Pre-order Analysis. These
costs include establishing a communication program (which includes maintaining two distinct
means of communication), an armed escort training and qualification program, and a telemetric
monitoring system to track various modes of SNF in transit.
NRC assumes that industry uses contractors to ship SNF and that only two security support
companies are used industry-wide to provide private armed escorts for SNF shipments. The
two security support companies would incur a one-time implementation cost to cover
background investigations for armed escorts, for a total of 10 personnel. NRC also assumes
that industry will incur annual background investigation costs as a result of each licensee losing
and gaining one employee per year due to attrition. New armed escorts must undergo
background investigations and the associated costs are considered in this cost analysis.
To implement 10 CFR 73.38, the NRC assumes that eight research and test reactor licensees
as well as two other licensees would have to develop and implement written background
investigation procedures. The NRC estimates that it will take 70 hours per licensee to develop
and implement these procedures, which is a cumulative total of 700 hours for the 10 anticipated
licensees.
The NRC incurs annual costs in the Pre-order Analysis, estimated to be $5,000 per year, due to
handling advance notifications and potential theft investigations.
States also incur annual costs, estimated to be $10,000 per year, for advance notifications and
preplanning and coordinating activities.
The benefits in the Pre-order Analysis are expressed in qualitative terms (i.e., existing
regulations). The security-related benefits are associated with safeguards and security
considerations stemming from the decreased risk of a security-related event, such as an act of
sabotage. Thus, decreasing the risk of a security-related event protects the common defense
and security, protects the health of the public and occupational workers, and decreases the risk
of damage to offsite properties.
4.

RESULTS

This section presents results of benefits and costs that the NRC expects will be derived from the
rule. To the extent that the affected attributes could be analyzed quantitatively, the costs have
been calculated and are presented below. The benefits are expressed only on a qualitative
basis because there are no quantifiable limits associated with the benefits of protection of public
health and safety, and security.

8

4.1

Benefits and Costs for Main Analysis

The benefits of this rule are associated with safeguards and security considerations and the
decreased risk of a security-related event, such as theft, diversion, or radiological sabotage of
SNF and subsequent use for malevolent purposes. By enhancing the physical protection of
SNF in Transit, the risk of security-related events decreases, and the common defense and
security of the nation increases. Other qualitative values that are positively affected by the
decreased risk of a security-related event include public and occupational health due to an
accident or event and the risk of damage to onsite and offsite property. In addition, regulatory
efficiency is enhanced by the rule because orders, unlike rules, do not apply prospectively to
applicants for new licenses. The NRC would have to periodically issue new orders to cover new
and amended licenses, and perhaps reissue orders periodically to existing licensees if
requirements or administrative practices change. In order to make the requirements generically
applicable to all present and future licensees, the security-related requirements need to be
placed in the regulations.
The results of the cost for the Main Analysis are summarized in Table 4-1. The Rulemaking
Alternative costs between $0.5 million and $0.6 million (7 percent and 3 percent discount rate,
respectively). The Rulemaking Alternative would result in an estimated $71,000 of additional
annual costs when compared to the No-Action Alternative. These costs are from implementing
rule provisions derived from insights gained while implementing the orders.
Table 4-1: Net Impact of Alternatives 1 and 2
Regulatory Alternative
1. No-Action
2. Rulemaking

10-year total
3% discount rate ($)
0
$617,352

10-year total
7% discount rate ($)
0
$510,089

Alternative 1: There are no costs associated with the No-Action Alternative. No changes would
be made to the regulations and orders would continue to be issued on a case-by-case basis.
The NRC licensees who are subject to existing Orders for SNF in Transit would continue to
comply with these requirements. Costs have already been incurred by licensees carrying out
the Orders.
Alternative 2: The Rulemaking Alternative would impose a new annual cost to the industry of an
estimated $71,000. The itemized assumptions for this cost are listed in Appendix 1, Table 1
Post Orders. This cost is derived from the additional requirements resulting from lessons
learned from implementing the Orders for SNF in Transit. The benefits of this Alternative are
associated with safeguards and security considerations and the decreased risk of a securityrelated event, such as theft, diversion, or radiological sabotage of SNF and subsequent use for
malevolent purposes. By enhancing the physical protection of SNF in transit, the risk of
security-related events decreases, and the common defense and security of the nation
increases. Other qualitative values that are positively affected by the decreased risk of a
security-related event include public and occupational health due to an accident or event and
the risk of damage to onsite and offsite property. In addition, regulatory efficiency is enhanced
by the rule because orders, unlike rules, do not apply prospectively to applicants for new
licenses. The NRC would have to periodically issue new orders to cover new and amended
9

licenses, and perhaps reissue orders periodically to existing licensees if requirements or
administrative practices change. In order to make the requirements generically applicable to all
present and future licensees, the security-related requirements need to be incorporated into
NRC regulations.
Table 4-2 summarizes the Main Analysis costs by entity. Over a 10-year analysis period, these
costs range between $0.5 and $0.6 million (7 percent and 3 percent discount rate, respectively).
Almost all of the costs are incurred by industry. The NRC incurs a small one-time cost. The
States incur no additional costs. The itemized assumptions for the Main Analysis are listed in
Summary Table 1 in Appendix 1.
Table 4-2: Summary of Costs for Main Analysis by Entity

One-time
Start up
Costs
Industry
NRC
States
Total

$5,050
$5,000
$0
$10,050

Total
Total
Cost with Cost with
Annual Cost
3%
7%
discount discount
rate
rate
$71,194
$612,352 $505,089
$0
$5,000
$5,000
$0
$0
$0
$71,194
$617,352 $510,089

Table 4-3 summarizes the Pre-order Analysis by entity, using a baseline of costs incurred prior
to the issuance of Orders for SNF in Transit. Over a 10-year analysis period, these costs range
between $6.2 and $7.5 million (7 percent and 3 percent discount rate, respectively). Almost all
of the costs are incurred by industry. The NRC and States incur annual costs of $4,760 and
$10,000 per year, respectively. The itemized assumptions for the Pre-order Analysis are listed
in Summary Table 2 in Appendix 1. Security during shipping accounts for the majority of
industry costs, at $580,000 annually. Other costs include non-LLEA armed response,
preplanning and coordination activities, documentation, advance notification and cancellations,
recordkeeping, background checks, and investigations.
Table 4-3: Summary of Costs for Pre-order Analysis by Entity
One-time
Start up
Costs
Industry
NRC
States
Total

$76,050
$5,000
$0
$81,050

Total Cost Total Cost
with 3%
with 7%
Annual Cost
discount
discount
rate
rate
$860,229
$7,413,975 $6,117,936
$4,760
$45,604
$38,432
$10,000
$85,302
$70,236
$874,989
$7,544,881 $6,226,604

10

4.2

Backfit Analysis

The NRC has determined that the Backfit Rule does not apply to this rule, because this
amendment does not add or modify any regulations to impose backfits as defined in 10 CFR
50.109 or 10 CFR 72.62. Part 50.109(a)(1) defines backfitting as the modification of or addition
to systems, structures, components, or design of a facility; or the design approval or
manufacturing license for a facility; or the procedures or organization required to design,
construct or operate a facility. The definition in 10 CFR 72.62 is similar in relevant part to the
definition in Part 50. This rulemaking will impose new requirements to enhance the security of
SNF in transit. It will not make any modification or addition to any systems, structures or
components or the design of a facility, affect the design approval or manufacturing license of a
facility, or affect the procedures or organization required to design, construct or operate a
facility. Therefore, it is the NRC’s determination that a backfit analysis is not required.
5.

DECISION RATIONALE AND IMPLEMENTATION

Two alternatives were evaluated in this Regulatory Analysis. Alternative 1 (No-Action
Alternative) would maintain the regulations as currently written, continue to require licensees to
comply with the Orders for SNF in Transit and require the NRC to issue new Orders as needed.
Alternative 2 (Rulemaking Alternative) would amend NRC regulations to: 1) establish
generically applicable security requirements similar to those previously imposed by Commission
orders issued after September 11, 2001; 2) establish the performance standards and objectives
for the protection of SNF shipments from theft, diversion, or radiological sabotage; 3) ensure
that the performance standards and objectives for SNF shipments apply to all licensees
authorized to transports, or delivers to a carrier for transport SNF; and 4) address, in part, the
State of Nevada petition for rulemaking (PRM-73-10).
Specifically, the new rule would require the following: 1) armed escorts throughout the rail and
road routes; 2) procedures for normal and contingency responses; 3) the training of personnel;
4) continuous and active monitoring of the SNF shipment by a movement control center;
5) shipment preplanning and coordination with States; 6) constant visual surveillance by armed
escorts; 7) two-way redundant communication capabilities; 8) a minimum of two weapons for
armed escorts; 9) additional NRC notifications; 10) private armed escort instructions on the use
of deadly force; and 11) background investigations for individuals granted unescorted access to
SNF shipments.
Alternative 2 would have significant qualitative benefits. The benefits of this Alternative are
associated with safeguards and security considerations and the decreased risk of a securityrelated event, such as theft, diversion, or radiological sabotage of SNF and subsequent use for
malevolent purposes. By enhancing the physical protection of SNF in transit, the risk of
security-related events decreases, and the common defense and security of the nation
increases. Other qualitative values that are positively affected by the decreased risk of a
security-related event include public and occupational health due to an accident or event and
the risk of damage to onsite and offsite property. In addition, regulatory efficiency is enhanced
by the rule because orders, unlike rules, do not apply prospectively to applicants for new
licenses. The NRC would have to periodically issue new orders to cover new and amended
licenses, and perhaps reissue orders periodically to existing licensees if requirements or
11

administrative practices change. In order to make the requirements generically applicable to all
present and future licensees, the security-related requirements need to be placed in the
regulations.
Further, there are relatively low costs associated with the rule because of the baseline
assumption of full compliance with previously issued Orders. The large majority of costs have
already been incurred under the baseline condition. Alternative 2 qualitative benefits represent
a substantial increase in public health safety and the protection of the common defense and
security. As such, the costs of the final rulemaking are justified based upon the qualitative
benefits. Therefore, the Rulemaking Alternative is the preferred approach. The rule is planned
for publication in the Federal Register in spring of 2012.
6.

REFERENCES

NUREG/BR-0058, “Regulatory Analysis Guidelines of the U.S. Nuclear Regulatory
Commission,” Rev. 4.
NUREG-0725, “Public Information Circular for Shipments of Irradiated Reactor Fuel,” Rev. 14.
NUREG-0561, “Physical Protection of Shipments of Irradiated Reactor Fuel,” Rev. 1.
NUREG/BR-0184, “Regulatory Analysis Technical Evaluation Handbook, Final Report,” Office of
Nuclear Regulatory Research, January 1997.

12

Appendix
§ 73.37(b)(1)(vii) - Document the Preplanning and Coordination Activities
The current regulations do not require the coordination of law enforcement escorts, the sharing
of movement control information, or the coordination of safe haven locations. The revisions
would require licensees to preplan and coordinate spent fuel shipment information with the
States through which transport will occur and to document these activities.
Hours of staff time to preplan and coordinate, per shipment
Cost of staff time per hour

40
73.20
$2928

Number of annual shipments

x 20

Total annual cost for preplanning and coordination activities

($58,560)

§ 73.37(b)(2)(v) - Cancellation Notice
Although the current regulations require the NRC and the State to receive advanced
notifications of shipments, there is no provision requiring the notification of a cancellation of a
previously approved advance notification. This is a rare occurrence. It is assumed that one
shipment will be canceled over a 3-year period.
Hours of staff time per call
Cost of manager’s time per hour

1
73.20

Number of cancellations per year

x 0.33

Total annual cost of cancellation notice

($24.16)

§ 73.37(b)(2)(i-iii) - Written Advance Notices
The current regulations do not require the coordination of law enforcement escorts, the sharing
of movement control information, or the coordination of safe haven locations. The revisions
would require licensees to preplan and coordinate spent fuel shipment information with the
States through which transport will occur and to document these activities.
The licensee must coordinate with all States that shipments pass through. For the purposes of
the Regulatory Analysis, we are assuming an average of five states would require advance
notification. Thus, 20 annual shipments would require 100 written advance notices to States
and each of the 20 shipments would require an advance notice to the NRC.
Hours of staff time
Cost of staff time per hour
Number of notifications

0.50
$73.20
120

Total annual cost of advance notifications
13

($4,392)

§ 73.37(b)(3)(v) - Security Procedures
The licensee shall develop, maintain, revise, and implement written transportation physical
protection procedures. These procedures are needed to protect SNF during transport and to
provide an adequate response to various emergencies that may occur during shipment.
Preparation of the security plan and procedures necessary to implement the security program.
Hours of staff time to prepare and update procedures (per license per year)
Cost of staff time per hour
Impacted Licensees
Total annual cost of staff time for procedures

150
$73.20
18
($197,640)

§§ 73.37(b)(1)(vii), (2)(vi), (3)(iv-vi), (4)(iii) and § 73.38(l) - Records
Although there are record requirements in 10 CFR § 73.70, the SNF regulations in § 73.37 do
not have any recordkeeping requirements. As such, the rulemaking would require new
recordkeeping requirements. These records would include a copy of the preplanning and
coordination activities, advance notification, and any revision or cancellation notice. These
records are to be maintained for 3 years in accordance with § 73.70. Records in § 73.38(i) are
to be kept for 5 years.
Number of Shipments
Cost of staff (clerical) time per hour
Hours of staff time to maintain records per shipment
Total Annual Cost for Recordkeeping

20
$73.20
3.275
($4,795)

Implementation cost of additional file cabinets, etc, for all licensees

$1,000

Total Implementation Cost for Recordkeeping (one-time cost)

($1,000)

§ 73.37(c)(d) - Shipping Costs
Industry has averaged 20 shipments of SNF via road and rail (collectively) per year over the last
5 years. For purposes of the regulatory analysis, an assumption of 20 shipments per year is
used. The NRC regulations define the modes of transport to be by “road,” “rail,” and “sea.”
Road and sea modes would incur equal costs; shipping by rail would be lower. Nevertheless,
for this regulatory analysis, zero shipments by sea are assumed.
Industry has indicated that it is more cost effective to hire contractors to conduct SNF
shipments. The below mentioned costs take into consideration all the internal costs that
contractors incur to be compliant with NRC orders and the regulation.

14

Ship by Road
Number of shipments
Average trip transit costs, including rental
Average trip communication costs
Contractor cost
Total annual cost by road

10
$3,000
$2,000
$25,000
($300,000)

Ship by Rail
Number of shipments
Average trip transit costs, including rental
Average trip communication costs
Contractor cost

10
$1,000
$2,000
$25,000

Total annual cost by rail

($280,000)

Total annual cost for shipping

($580,000)

§ 73.37(f)- Event Investigations
Although licensees are required by 10 CFR 73.71 to notify the NRC of any safeguards events
and to submit a report concerning the event, there is no specific requirement for an
investigation. This requirement is being added to address this issue. It is assumed that any
safeguards events would be rare. It is assumed that one would occur every 3 years.
Hours of staff time per investigation
Hours of staff to write report
Cost of staff time per hour

40
40
$73.20

Number of investigations per year (1/3)

x 0.33

Total annual cost of event investigation

($1932)

§ 73.38(d) - Background Investigation
Section 73.38(d) is being added to Part 73 to implement an access authorization program that
requires background investigations of individuals involved with the transportation of SNF.
Number of hours to conduct a background check
6
(this includes labor associated with criminal history records; verification of true
identity; employment history evaluation; verification of education and military
history; credit history evaluation; local criminal history review; and character and
reputation determination).
Cost of manager time per hour
$73.20
____
$439
15

Cost of credit history
Cost of taking fingerprints
Cost for fingerprint submission
Cost of background check
Number of individuals needing background checks (per year)

$20
$10
$36
$505
x 18

Total annual cost of background checks

($9,090)

The implementation cost for two companies providing support assumes 10 background
investigations up front, as a one-time cost.
Total Implementation Cost for Background Investigations

($5,050)

§ 73.38(j) Procedures for Background Investigations
Licensees shall develop, implement, and maintain written procedures for conducting
background investigations for persons who are applying for unescorted access authorization for
spent nuclear fuel in transit. Licensees shall develop, implement, and maintain written
procedures for updating background investigations for persons who are applying for
reinstatement of unescorted access authorization. Licensees shall develop, implement, and
maintain written procedures to ensure that persons who have been denied unescorted access
authorization are not allowed access to spent nuclear fuel in transit or information relative to
spent nuclear material in transit. Licensees shall develop, implement, and maintain written
procedures for the notification of individuals who are denied unescorted access. The
procedures must include provisions for the review of a denial or termination of unescorted
access authorization, if the affected individual requests such a review. The procedure must
contain a provision to ensure that the individual is informed of the grounds for the denial or
termination of unescorted access authorization and allow the individual an opportunity to
provide additional relevant information. The implementation cost is estimated to be a 70-hour
effort at $73.20 per hour labor cost for each of the eight research and test reactors and two
other licensees who would need to prepare these procedures, assuming all other licensees
would have existing procedures.
Total Implementation Cost for Background Investigations Procedures

($70,000)

§ 73.72 - Advance Notification
The current regulations in § 73.72(a)(4) require NRC notification, by phone, 2 days before the
shipment commences. The rule would require two additional notifications of the NRC, one to be
made 2 hours before the shipment commences, and the other to be made when the shipment
reaches its final destination. These additional notifications would allow the NRC to monitor SNF
shipments and to maximize its readiness in case of a safeguards event. The NRC estimates
each phone call to take 18 minutes for a total of 36 minutes of notifications per shipment.
Staff time to phone in advance notification per shipment (hours)
Cost of staff time per hour
Number of shipments per year
Total annual cost of advance notifications
16

0.6
$73.2
20
($878)

Summary Table 1 Post Orders
Licensee

Description
Document the
Preplanning and
Coordination
Activities
Cancellation
Notice
Records
Background
Investigations
Totals

Section

One time
Cost

Total
Annual
Cost

Present
Value 10
year at 3%

Present
Value 10
year at 7%

73.37(b)(1)(vii)

$0

$58,560

$499,529

$411,301

$24

$206

$170

$-

$622

$5,307

$4,370

$ 5,050

$11,988

$107,310

$89,249

$5,050

$71,194

$612,352

$505,089

One time
Cost

Total NRC
Annual
Cost

Present
Value 10
year at 3%

Present
Value 10
year at 7%

$5,000

$5,000

$0

$5,000

$5,000

Total State
Annual
Cost
$0

Present
Value 10
year at 3%
$0

Present
Value 10
year at 7%
$0

73.37(b)(2)(v)
73.38(d)

NRC

Description

Section

Update
Guidance
Totals

$ 5,000
$ 5,000

States
Description
Totals

Section

One time
Cost
$

-

17

Summary Table # 2 Pre Orders
Licensee

Description
Document the
Preplanning and
Coordination Activities
Written advance
notices to NRC/States
Cancellation Notice
Security Procedures
Records
Ship by Highway/Road
Ship by Rail
Background
Investigations
Develop Procedures
Advance Notification
Requirements
Event Investigations
Totals

Section

One time
Cost ($)

Total
Annual
Cost ($0

Present
Value 10
year at 3%
($)

Present
Value 10
year at 7%
($)

73.37(b)(1)

0

58,560

499,529

411,301

73.37(b)(2)(i-ii)

4,392

37,465

30,848

73.37(b)(2)(v)
73.37(b)(3)(v)
73.37(b)(2)(vi),
73.38(i),73.38(g)
73.37 (c)
73.37(d)

24
197,640

206
1,685,909

170
1,388,141

1,000

4,795

41,899

34,675

0
0

300,000
280,000

2,559,061
2,388,457

2,107,074
1,966,603

73.38(d)

5,050

11,988

107,310

89,249

73.38(j))

70,000

0

70,000

70,000

73.72

0

878

7,493

6,170

73.37(f)

0
76,050

1,952
860,229

16,647
7,413,975

13,707
6,117,936

NRC
Description
Written advance
notices to NRC
Update Guidance
Event Investigations
Written advance
notices to States

Section

One
time
Cost ($)

Total
NRC
Annual
Cost ($)

Present
Value 10
year at 3%
($)

Present Value
10 year at 7%
($)

73.37(b)(2)(i-iii)

0

1,190

10,151

8,358

73.37(f)

5,000
0

3,570

5,000
30,453

5,000
25,074

73.37(b)(2)(i-ii)

0

2,500

21,326

17,559

18

States

Description
Document the
Preplanning and
Coordination Activities
Written advance notices
to States

Section

One
time
Cost ($)

Total
State
Annual
Cost ($)

Present
Value 10
year at 3%
($)

Present Value
10 year at 7%
($)

73.37(b)(1)(vii)

0

7,500

63,977

52,677

73.37(b)(2)(i-ii)

0

2,500

21,326

17,559

19


File Typeapplication/pdf
File TitleMicrosoft Word - ML120050180.docx
AuthorORPUser
File Modified2012-08-28
File Created2012-02-07

© 2024 OMB.report | Privacy Policy