pdfNOTICE: This report is required by 49 CFR Part 192.1009. Failure to report may result in a civil penalty not to exceed $100,000 for OMB No. 2137-0522
each violation for each day the violation continues up to a maximum of $1,000,000 as provided in 49 USC 60122.
Expiration Date 01/31/2014
U.S. Department of Transportation
Pipeline and Hazardous Materials
Safety Administration
MECHANICAL FITTING FAILURE REPORT FORM
FOR CALENDAR YEAR 20___
FOR DISTRIBUTION OPERATORS
INITIAL REPORT
SUPPLEMENTAL REPORT
A federal agency may not conduct or sponsor, and a person is not required to respond to, nor shall a person be subject to a penalty for failure to comply with a collection of information
subject to the requirements of the Paperwork Reduction Act unless that collection of information displays a current valid OMB Control Number. The OMB Control Number for this
information collection is 2137-0522. Public reporting for this collection of information is estimated to be approximately 1 hours per submission, including the time for reviewing instructions,
gathering the data needed, and completing and reviewing the collection of information. All responses to this collection of information are mandatory. Send comments regarding this
burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to: Information Collection Clearance Officer, PHMSA, Office of Pipeline
Safety (PHP-30) 1200 New Jersey Avenue, SE, Washington, D.C. 20590.
PART A - OPERATOR INFORMATION
DOT USE ONLY
1. NAME OF OPERATOR
3. HEADQUARTERS NAME & ADDRESS
2. OPERATOR'S 5 DIGIT IDENTIFICATION NUMBER
/
/
/
/
/
/
Number and Street
City and County
State and Zip Code
PART B - PREPARER AND AUTHORIZED SIGNATURE
(Type or print) Preparer’s Name and Title
Area Code and Telephone Number
Preparer’s email address
Area Code and Facsimile Number
Preparer's address:
Number and Street
City and County
State and Zip Code
Date Submitted
Authorized Alternative Reporting Submissions Only:
Name and Title of Person Signing
Area Code and Telephone Number
Authorized Signature
Form PHMSA F 7100.1-2 Mechanical Fitting Failures (xy/201311/2011)
Reproduction of this form is permitted.
Page 1 of 2
PART C – MECHANICAL FITTING FAILURE DATA – (If the data about the “Manufacturer”, “Part or Model Number”, or” Lot Number” cannot be
located with reasonable effort or if the data is unknown, enter “Unavailable”; do not leave data fields blank.)
1)
State in Which Fitting Failed: _____________________
2)
Date of Failure:___________________
3)
Specify the Mechanical Fitting Involved: Stab
4)
Specify the Type of Mechanical Fitting: Service or Main Tee Tapping Tee Transition Fitting Coupling Riser
Adapter Valve Sleeve End Cap Other _____________________
5)
Leak Location:
6)
7)
8)
9)
10)
11)
12)
Aboveground
Inside
Main-to-Main
or
or
or
Nut Follower
Belowground;
Outside;
Main-to-Service
Bolted
or
Other Compression Type Fitting______________
Service-to-Service
Meter Set
or
Year Installed: ___________
Year Manufactured: ___________
If Neither Year Installed or Year Manufactured is Known, Provide Decade Installed: ___________
Manufacturer: _____________________________
Part or Model Number:______________________
Lot Number:_______________________________
Other Attributes:____________________________
13) Fitting Material:
Steel Plastic Combination Plastic and Steel
Brass Unknown Other_____________
14) Specify the Two Materials Being Joined:
a) First Pipe
Nominal Size: 1/4”
Unit: IPS
1/2” 3/4”
or
CTS
1”
or
1-1/4” 1-1/2”
NPS
1-3/4”
2”
3”
4”
6”
8” or larger
Material: Steel Cast/Wrought Iron Ductile Iron Copper Plastic
Unknown
Other______________
If Plastic Specify: Polyethylene (PE) Polyvinyl Chloride (PVC) Cross-linked Polyethylene (PEX)
Polybutylene (PB) Polypropylene (PP) Acrylonitrile Butadiene Styrene (ABS) Polyamide (PA)
Cellulose Acetate Butyrate (CAB) Other Specify: __________________________________
b) Second Pipe
Nominal Size: 1/4”
Unit: IPS
1/2” 3/4”
or
CTS
1”
or
1-1/4” 1-1/2”
NPS
1-3/4”
2”
3”
4”
6”
8” or larger
Material: Steel Cast/Wrought Iron Ductile Iron Copper Plastic
Unknown
Other______________
If Plastic Specify: Polyethylene (PE) Polyvinyl Chloride (PVC) Cross-linked Polyethylene (PEX)
Polybutylene (PB) Polypropylene (PP) Acrylonitrile Butadiene Styrene (ABS) Polyamide (PA)
Cellulose Acetate Butyrate (CAB) Other Specify: __________________________________
15) Apparent Cause of Leak:
Corrosion
Natural Forces
Was there thermal expansion/contraction? Yes or No
Excavation Damage
Time excavation damage occurred? At time of leak discovery or Previous to leak discovery
Other Outside Force Damage
Material or Welds/Fusions
Was the leak due to Construction/Installation Defect or Material Defect or Design Defect
Equipment
Incorrect Operation
Other
Explain:_______________________________________
16) How did the leak occur?
Leaked Through Seal
or
Leaked Through Body
or
Pulled Out
17) Operator’s Internal Mechanical Fitting Failure Tracking Number (optional): _______________________________
Record Identification Number <>
Form PHMSA F 7100.1-2 Mechanical Fitting Failures (xy/201311/2011)
Reproduction of this form is permitted.
Page 2 of 2
Instructions (rev xy/2013) for Form PHMSA F 7100.1-2 (rev xy/201311/11)
MECHANICAL FITTING FAILURE REPORT FORM FOR CALENDAR YEAR 20__ FORGAS DISTRIBUTION
OPERATORS SYSTEM
Operators are required to begin collecting mechanical fitting failure information, excluding those
that result only in non-hazardous leaks, beginning January 1, 2011. Submit Mechanical Fitting
Failure Report Form(s) for calendar year 2011 and laterbeyond.
Reporting requirements for this form are contained in Title 49 of the Code of Federal Regulations
§ 192.1009, What must an operator report when mechanical fittings fail? and § 191.12 Distribution
Systems: Mechanical Fitting Failure Reports. Each operator of a gas distribution pipeline, except for
the operators of master meter systems or small liquefied petroleum gas (LPG) operators (see
definitions below), must submit a report for each mechanical fitting failure excluding those that result
only in non-hazardous leaks on a separate Department of Transportation Form PHMSA F 7100.1-2 for
the preceding calendar year no later than March 15th. Operators are permitted to submit mechanical
fitting failure report forms throughout the year.
If a mechanical fitting failure resulted in a reportable incident, both the mechanical fitting failure report
(Form PHMSA F 7100.1-2) and gas distribution incident report (Form PHMSA F 7100-1) are required
to be submitted.
Form PHMSA F 7100.1-2 and these instructions can be found
on http://phmsa.dot.gov/pipeline/library/forms. The applicable documents are listed in the section titled
Accident/Incident/Annual Reporting Forms.
ONLINE SUBMISSION IS REQUIRED UNLESS AN ALTERNATIVE REPORTING
METHOD IS GRANTED BY PHMSA.
If electronic reporting imposes an undue burden and hardship, an operator may submit a written
request for an alternative reporting method to the Information Resources Manager, Office of Pipeline
Safety, Pipeline and Hazardous Materials Safety Administration, PHP-20, 1200 New Jersey Avenue,
SE Washington DC 20590. The request must describe the undue burden and hardship. PHMSA will
review the request and may authorize, in writing, an alternative reporting method. An authorization
will state the period for which it is valid, which may be indefinite. An operator must contact PHMSA
at 202-366-8075, or electronically to [email protected] or make arrangements for
submitting a report that is due after a request for alternative reporting is submitted but before an
authorization or denial is received.Operators should request and receive authorization from PHMSA
prior to the use of alternative reporting methods.
Online Submissions:
Online Reporting Submission Registration Requirements:
Reports must be submitted online through the PHMSA Portal at
https://portal.phmsa.dot.gov/portal, unless an alternate method is approved (see Alternate Reporting
Methods below). You will not be able to submit reports until you have met all of the Portal
registration requirements –
see http://opsweb.phmsa.dot.gov/portal_message/PHMSA_Portal_Registration.pdf
Page 1 of 10
Instructions (rev xy/2013) for Form PHMSA F 7100.1-2 (rev xy/201311/11)
MECHANICAL FITTING FAILURE REPORT FORM FOR CALENDAR YEAR 20__ FORGAS DISTRIBUTION
OPERATORS SYSTEM
Completing these registration requirements could take several weeks. Plan ahead and register well
in advance of the report due date.
The following two requirements must be fulfilled prior to submitting data online:
1. You must have an Office of Pipeline Safety (OPS) provided Operator ID and Personal
Identification Number (PIN)/password. If you do not have one, please complete and submit the
form located on the OPS Online Data Entry and Operator Registration System New Operator
Registration web site at http://opsweb.phmsa.dot.gov/cfdocs/opsapps/pipes/new_operator.cfm to
obtain one.
1. You must have a Username and Password obtained by registering through the PHMSA Portal. If
you have an OPS Operator ID and PIN/password, you may obtain a Username and Password
through the PHMSA Portal.
Each Operator, without an Operator ID, should plan accordingly and allow for several weeks prior to
the due date of the report to obtain their Operator ID.
Online Submission Instructions:
1. Navigate to PHMSA’s, Office of Pipeline Safety web site, Pipeline Safety Community, located
at http://www.phmsa.dot.gov/pipeline.
2. Click the “Online Data Entry” hyperlink listed in the first column. This takes you to the OPS
Online Data Entry and Operator Registration System.
1. Click on theGo to the PHMSA Portal at https://portal.phmsa.dot.gov/portal
2. Enter PHMSA Portal Username and Password; press enter
3. Select OPID: press “continue” button.
3.4.Under “Create Reports” locate the subheading “Mechanical Fitting Failure” Report Form”
hyperlink under the Gas Distribution Systems subtitle. This takes you to the PHMSA Portal login
screen.””
4. Enter your “Username” and “Password and click on “Login”.
5. New reports can be entered individually or uploaded as a batch.Create or modify record:
a. To create an individual report, select “Online form” and proceed with entering your data.To
create a new fitting failure record, click “Submit a Failure”. Enter the “Calendar Year” for
which the report is being filed
OR
b. To upload a batch of reports, select “Batch Upload”. The batch upload option allows
operators to submit multiple failures at once using a comma separated file (CSV) that is
extracted from their own system or an Excel Spreadsheet (saved as a CSV). The file and
data structure must comply with PHMSA’s requirements, which are in the Data Dictionary
and Instructions. PHMSA also provides an Excel Template that operators can opt to use.
All failures submitted via the batch upload process will receive a confirmation of the
number of reports successfully uploaded, PHMSA report number for each failure, and a
batch record number. A PDF copy is obtainable under “Submitted Reports, Mechanical
Fitting Failure”.
To modify an existing submitted fitting failure report, go to “Submitted Reports, Mechanical Fitting
Page 2 of 10
Instructions (rev xy/2013) for Form PHMSA F 7100.1-2 (rev xy/201311/11)
MECHANICAL FITTING FAILURE REPORT FORM FOR CALENDAR YEAR 20__ FORGAS DISTRIBUTION
OPERATORS SYSTEM
Failure” sub-heading. Locate the report; locate the by using the PHMSA Report #, Operator provided
MFF unique ID, failure date, etc., select the record using the “Search” function.and click “Create
Supplemental”. This will allow you to modifychanges to data in Part C to be made. Once the record
is located, click “Create Supplemental” and make the necessary changes. .
6. Follow the detailed instructions below to complete Parts A, B, and C.
7.6.Click “SaveSubmit” when finished.
8.7.A copy of the report can be printed or downloaded in either MS Excel or PDF format. under the
“Submitted Reports” heading.
9.8.For distribution pipelines subject to the jurisdiction of a State agency pursuant to certification
under 49 U.S.C. § 60105, send a copy of the report to the State agency no later than March 15th.
Alternative Reporting MethodsSubmissions:
***Authorization from PHMSA is needed to submit the form using an alternative reporting method***
Operators for whom electronic reporting imposes an undue burden and hardship may submit a written
request for an alternate reporting method. Operators must follow the requirements in §191.7(d) to
request an alternate reporting method and must comply with any conditions imposed as part of
PHMSA’s approval of an alternate reporting method.
Form PHMSA F 7100.1-2 and instructions are available for download on the Office of Pipeline Safety
web site, Pipeline Safety Community, located at http://www.phmsa.dot.gov/pipeline. Click on the
“Library” hyperlink and then the “Forms” hyperlink under the Mini-Menu subtitle. If you have
questions about this report or these instructions, please call (202) 366-8075.
Please type or print all entries when submitting forms by mail or fax.
Alternative Reporting Submission Instructions:
1. Check new or modified report:
a. If this is the first time this mechanical fitting failure is being reported, check Initial
Report.
OR
b. If an initial report has already been filed but that report needs to be modified check
Supplemental Report. Only submit Part C for fittings which the information is being
modified.
2. Enter the Calendar Year for which the report is being filed.
3. Follow the detailed instructions below to complete Part A, B, and C. Complete a separate Part C
for each fitting failure.
4. Submit the report via one of the following methods:
a. Mail to:
DOT/PHMSA Office of Pipeline Safety
Information Resources Manager,
1200 New Jersey Ave., SE
East Building, 2nd Floor, (PHP-20)
Room Number E22-321
Washington, DC 20590
Page 3 of 10
Instructions (rev xy/2013) for Form PHMSA F 7100.1-2 (rev xy/201311/11)
MECHANICAL FITTING FAILURE REPORT FORM FOR CALENDAR YEAR 20__ FORGAS DISTRIBUTION
OPERATORS SYSTEM
OR
b. Fax to: Information Resources Manager at (202) 366-4566.
5.1.For distribution pipelines subject to the jurisdiction of a State agency pursuant to certification
under 49 U.S.C. § 60105, submit a copy of the report to the State agency no later than March 15th.
DEFINITIONS
The following definitions are from §§ 192.3 and 192.1001:
1. “Distribution line” means a pipeline other than a gathering or transmission line.
2. “Operator” means a person who engages in the transportation of gas.
3. “Small LPG Operator” means an operator of a liquefied petroleum gas (LPG) distribution pipeline
that serves fewer than 100 customers from a single source.
4. “Master Meter System” means a pipeline system for distributing gas within, but not limited to, a
definable area, such as a mobile home park, housing project, or apartment complex, where the
operator purchases metered gas from an outside source for resale through a gas distribution
pipeline system. The gas distribution pipeline system supplies the ultimate consumer who either
purchases the gas directly through a meter or by other means, such as by rents.
5. “Mechanical fitting” means a mechanical device used to connect sections of pipe. The term
“Mechanical fitting” applies only to:
a. Stab Type fittings;
b. Nut Follower Type fittings;
c. Bolted Type fittings; or
d. Other Compression Type fittings.
6. “Hazardous Leak” means a leak that represents an existing or probable hazard to persons or
property and requires immediate repair or continuous action until the conditions are no longer
hazardous.
Page 4 of 10
Instructions (rev xy/2013) for Form PHMSA F 7100.1-2 (rev xy/201311/11)
MECHANICAL FITTING FAILURE REPORT FORM FOR CALENDAR YEAR 20__ FORGAS DISTRIBUTION
OPERATORS SYSTEM
INSTRUCTIONS
PART A – OPERATOR INFORMATION
Online Submissions:
Items 1-3 are auto-populated. If this information is incorrect, please contact PHMSA’s Information
Resources Manager at (202) 366-8075.
Alternative Reporting Submissions:
ITEM 1: Provide the name of the operator.
ITEM 2: Provide operators’ ID number. The Pipeline and Hazardous Materials Safety Administration
assigns the operator’s five-digit identification number. Contact PHMSA at (202) 366-8075 if you need
assistance with determining your operator’s five-digit identification number.
ITEM 3: Provide the Headquarters’ name and address.
PART B - PREPARER AND AUTHORIZED SIGNATURE
PREPARER is the name of the person most knowledgeable about the report or the person to be
contacted for more information. Please include the direct phone number, email address, fax number,
and address (e-mail address and/or fax are desired but not required). It should be noted that PHMSA
will use your e-mail address to issue correspondence that is normally sent via mass mailings.
“Correspondence” includes notifications such as the annual reminder letter for Annual Report filings.
When submitting online your username and password take the place of the Authorized Signature.
Date Submitted: Enter the date the information was submitted.
Alternative Reporting Submissions Only:
AUTHORIZED SIGNATURE - The authorized signature may be the preparer, an officer, or other
person whom the operator has designated to review and sign reports. Please include the direct phone
number and email address (e-mail address desired, but not required) and sign the form. It should be
noted that PHMSA will use your e-mail address to issue correspondence that is normally sent via mass
mailings. “Correspondence” includes notifications such as the annual reminder letter for Annual
Report filings.
Page 5 of 10
Instructions (rev xy/2013) for Form PHMSA F 7100.1-2 (rev xy/201311/11)
MECHANICAL FITTING FAILURE REPORT FORM FOR CALENDAR YEAR 20__ FORGAS DISTRIBUTION
OPERATORS SYSTEM
PART C – MECHANICAL FITTING FAILURE DATA
Make an entry in each block for which data are available. Some companies may have very old pipe for
which installation records do not exist. Estimate data if necessary. Avoid entering “Unknown” if
possible.
OperatorsFor reporting purposes operators must report data for each failure of a mechanical fitting that
resultedfailures which result in a hazardous leak during the calendar year that are associated with
mechanical fittings. Report all types and all sizes of mechanical fitting failures which resulted in a
hazardous leak regardless of the material composition of the fitting. The reporting requirements apply
to failures in the bodies of mechanical fittings, failures in the joints between the fitting and the pipe,
indications of leakage from the seals associated with the fitting, and when partial or complete
separation of the pipe pulls out of fitting. Operators are to report mechanical fitting failures that
resulted from any cause. away from the fitting. However, PHMSA does not intend to collectseek
information aboutrelated to failures of cast iron bell &and spigot joints unless the leak resulted from a
failure of a mechanical fitting used to repair or reinforce a joint. Operators are to report mechanical
fitting failures that resulted from any cause.
State in Which Fitting Failed - Enter the state where the mechanical fitting being reported failed.
Date of Failure – Enter the date which the mechanical fitting failure was identified. (mm/dd/yyyy)
Specify the Mechanical Fitting Involved–
Stab Type Mechanical Fitting - Internally there are specially designed components
including an elastomer seal, such as an “O” ring, and a gripping device to affect
pressure sealing and pull-out resistance capabilities. Self-contained stiffeners are
included in this type of fitting. With this style fitting the operator would have to prepare
the pipe ends, mark the stab depth on the pipe, and “stab” the pipe in to the depth
prescribed for the fitting being used.
Nut Follower Type Mechanical Fitting – The components are generally a body; a
threaded compression nut or a follower; an elastomer seal ring; a stiffener or an
integrated stiffener for plastic pipe; and, with some, a gripping ring. Normally the
design concept of this type of fitting typically includes an elastomer seal in the
assembly. The seal, when compressed by tightening of a threaded compression nut grips
the outside of the pipe, affecting a pressure-tight seal and, in some designs, providing
pull-out resistance. TheFor plastic pipe, the inside of the pipe wall should be supported
by the stiffener under the seal ring and under the gripping ring (if incorporated in the
design), to prevent collapse of the pipe. A lack of this support could result in a loss of
the seal affected by the seal ring or the gripping of the pipe for pull-out resistance. This
fitting style is normally used in pipelines 2-inches in diameter and smaller. There are
two categories of this type of joining device manufactured. One type is provides a seal
only, and the other provides a seal plus pipe restraint against pull-out.
Page 6 of 10
Instructions (rev xy/2013) for Form PHMSA F 7100.1-2 (rev xy/201311/11)
MECHANICAL FITTING FAILURE REPORT FORM FOR CALENDAR YEAR 20__ FORGAS DISTRIBUTION
OPERATORS SYSTEM
Bolted Type Mechanical Fitting – The bolt type mechanical fitting has the samesimilar
components as the nut follower except instead of a threaded compression nut or
follower, there is a bolt arrangement. This fitting style is most often used in pipelines 2inches in diameter and larger.
Other Compression Type Fitting – Use “Other” only if the fitting does not fit one of the
above categories and is a compression type fitting.
Specify the Type of Mechanical Fitting: Select the type of fitting which failed. Select “Other” if the
fitting is not listed. For this data collection consider elbows, “Ys”, 3-way tees, and reducer tees as
couplings. Consider the riser to be part of the serviceService or Main Tee should be selected when the
fitting provides for the diversion of the gas stream into a branch pipeline without the use of further
“tapping” either through a built-in mechanism or external equipment. Tapping Tee should be selected
when the fitting is externally attached to the pipeline and a cutter or tapping machine is used. Select
“Other” if the fitting type is not listed and provide a description.
Leak Location – Select the location of the failed mechanical fitting in the pipeline system. Select either
“Aboveground” or “Belowground”. Select either “Inside” or “Outside”. Select one from the following
“Main-to-Main”, “Main-to-Service”, “Service-to-Service”, or “Meter Set”. Consider the riser to be part
of the service.
Year Installed – Provide the year the fitting was installed. If the year installed can be reasonably
estimated, please provide that date. Otherwise, see instructions below regarding Decade Installed.
Select “Unknown” if the year of installation is not known. or cannot be reasonably estimated.
Year Manufactured – Provide the year the fitting was manufactured. If the year manufactured can be
reasonably estimated, please provide that date. Otherwise, see instructions below regarding decade of
installation. Select “Unknown” if the year manufactured is not known or cannot be reasonably
estimated.
If Neither Year Installed or Year Manufactured is Known, Provide Decade Installed – Use this field
only if both the year the fitting was installed and the year it was manufacturer are unknown but the
decade that it was installed is known (e.g., 1960-1969, 1970-1979, etc.). If all three fields are
unknown, enter “Unknown” in this field. Leave blank if either the Year Installed or the Year
Manufactured is known.
If the data about the “Manufacturer”, “Part or Model Number”, or” Lot Number” cannot be
located with reasonable effort or if the data is unknown, enter “Unavailableunknown”; do not
leave these data fields blank.
Manufacturer – This is the name of the company that produced the fitting. The manufacturer name
would typically be on a sticker attached to a fitting or product or it may be stamped into the fitting.
Operators should take care in identifying the manufacturer. Some types of fittings are commonly
referred to as “Dresser fittings” (for example) even though the particular fitting may have been
manufactured by a different company. Operators should report here the company that actually
manufactured the involved fitting when known. To improve data quality, we have created a drop down
Page 7 of 10
Instructions (rev xy/2013) for Form PHMSA F 7100.1-2 (rev xy/201311/11)
MECHANICAL FITTING FAILURE REPORT FORM FOR CALENDAR YEAR 20__ FORGAS DISTRIBUTION
OPERATORS SYSTEM
list with the most common manufacturers that were reported in 2011. This is not an exhaustive list. If
you do not see the name of the manufacturer in the drop down, please select “Other”, and enter the
name of the manufacturer in the text box that is provided. If you do not know the manufacturer, please
select “unknown” from the drop down.
Part or Model Number – Enter the part/model number used by the manufacturer to designate the failed
fitting. If the Part or Model, Number is not known, then enter “unknown”.
Lot Number – Enter the manufacturing lot. If the Lot Number is not known, then enter “unknown”.
Other Attributes – Enter other distinguishing features which may assist in identifying the fitting. If you
do not have other attributes to enter, leave this blank.
Fitting Material – Enter the material that forms the body of the fitting.
Specify the Two Materials Being Joined - For each pipe connected to the fitting, enter the nominal size
and material. If the material is plastic, specify the type of plastic.
Apparent Cause of Leak– Enter the apparent cause of the leak using the definitions below:
Leak causes are classified as:
CORROSION: leak resulting from a holematerial loss in the pipe or other component that was
caused by galvanic, bacterial, chemical, stray current, or other corrosive action.
NATURAL FORCES: leak resulting from earth movements, earthquakes, landslides,
subsidence, lightning, heavy rains/floods, washouts, flotation, mudslide, scouring, temperature,
frost heave, frozen components, high winds, or similar natural causes.
When Natural Forces is the leak cause, indicate if thermal expansion/contraction contributed to
the fitting failure. Thermal Expansion/contraction means the fitting failed due to a change in
volumedimensions in response to a change in temperature.
EXCAVATION DAMAGE: leak resulting from damage caused by earth moving or other
equipment, tools, or vehicles. Include leaks from damage by operator's personnel or contractor
or people not associated with the operator.
When Excavation Damage is the leak cause, indicate if the excavation damage occurred at the
time the leak was discovered or if the damage occurred previous to when the leak was
discovered.
OTHER OUTSIDE FORCE DAMAGE: Include leaks caused by fire or explosion and deliberate
or willful acts, such as vandalism.
MATERIAL OR WELDS/FUSIONS: leak resulting from failure of original sound material from
force applied during construction that caused a dent, gouge, excessive stressmanufacture,
fabrication, material, design, or other defect that eventually resulted in a leak. This includes
Page 8 of 10
Instructions (rev xy/2013) for Form PHMSA F 7100.1-2 (rev xy/201311/11)
MECHANICAL FITTING FAILURE REPORT FORM FOR CALENDAR YEAR 20__ FORGAS DISTRIBUTION
OPERATORS SYSTEM
leaks due to faulty fusions and damage sustained in transportation to the construction or
fabrication site. Also include leak resulting from a defect in the pipe material, component, or
the longitudinal weld or seam due to faulty manufacturing procedures. Leaks from material
deterioration, other than corrosion, after exceeding the reasonable service life, are reported
under Other.
When Material and Welds/Fusions is the leak cause, indicate if the leak was caused by a
construction/installation defect, material defect, or design defect.
Construction or Installation Defect means a component was installed incorrectly. It
could be due to poor workmanship, the procedure was not followed, or there were poor
construction/installation procedures.
Material Defect means an inherent flaw in the material or weld that occurred in the
manufacture or at a point prior to construction, fabrication or installation.
Design Defect means an aspect inherent in a component to which a subsequent failure
has been attributed that is not associated with errors in installation, i.e., is not a
construction defect.. This could include, for example, errors in engineering design or an
application error.
EQUIPMENT: leak resulting from malfunction of control/relief equipment including valves,
regulators, or other instrumentation; stripped threads or broken pipe couplings on nipples,
valves, or mechanical couplings; or seal failures on gaskets, O-rings, seal/pump packing, or
similar leaks. Leaks resulting from construction or installation errors or failure to follow
procedures should be reported in the “Incorrect Operation” category.
INCORRECT OPERATIONS: leaks resulting from inadequate procedures or safety practices, or
failure to follow correct procedures, or other operator error. This category includes
cConstruction or installation defects resulting in a component being installed incorrectly. It
could be due to poor workmanship, the procedure was not followed, or there were poor
construction/installation procedures.
OTHER: leak resulting from any other cause, such as exceeding the service life, not attributable
to the above causes. Specify in more detail the cause if select other.
How did the leak occur? – Enter whether the gas was escaping between the fitting and the pipe (leaked
through seal), from the body of the fitting (leaked through body)), or if the pipe had pulled out of the
fitting.
Operator’s Internal Mechanical Fitting Failure Tracking Number (optional) -)*- If applicable, enter
the operator’s unique tracking number assigned to identify this specific mechanical fitting failure. This
field is intended to help operators easily track which mechanical fitting failures have been submitted to
Page 9 of 10
Instructions (rev xy/2013) for Form PHMSA F 7100.1-2 (rev xy/201311/11)
MECHANICAL FITTING FAILURE REPORT FORM FOR CALENDAR YEAR 20__ FORGAS DISTRIBUTION
OPERATORS SYSTEM
PHMSA. *Note: If you are submitting mechanical fitting failure reports via the batch upload
process, this field is required.
Page 10 of 10
File Type | application/pdf |
Subject | GAS DISTRIBUTION SYSTEM |
Author | David E. Bull |
File Modified | 2013-11-26 |
File Created | 2013-11-26 |