2072ss05

2072ss05.docx

NESHAP for Lime Manufacturing (40 CFR Part 63, subpart AAAAA) (Renewal)

OMB: 2060-0544

Document [docx]
Download: docx | pdf

SUPPORTING STATEMENT

ENVIRONMENTAL PROTECTION AGENCY

NESHAP for Lime Manufacturing (40 CFR Part 63, Subpart AAAAA) (Renewal)


1. Identification of the Information Collection


1(a) Title of the Information Collection


NESHAP for Lime Manufacturing (40 CFR Part 63, Subpart AAAAA) (Renewal), EPA ICR Number 2072.05, OMB Control Number 2060-0544


1(b) Short Characterization/Abstract


The National Emission Standards for Hazardous Air Pollutants (NESHAP) for Lime Manufacturing were: 1) proposed on December 20, 2002, (67 FR 78046); 2) promulgated on January 5, 2004 (69 FR 394); and 3) last-amended on April 20, 2006. These regulations apply to both existing facilities and new lime manufacturing plants (LMP) that either emits or has the potential to emit any single hazardous air pollutant (HAP) at a rate of 9.07 megagrams (10 tons) or more per year or any combination of HAP at a rate of 22.68 megagrams (25 tons) or more per year from all emission sources at the plant site. This subpart applies to each existing and new lime kilns and their associated coolers, and processed stone handling (PSH) operation systems located at a LMP that is a major source. A new lime kiln is a lime kiln, and its associated lime cooler for which construction or reconstruction began after December 20, 2002, and a new PSH operations system is the equipment for which construction or reconstruction began after December 20, 2002. This information is being collected to assure compliance with 40 CFR part 63, subpart AAAAA.


In general, all NESHAP standards require initial notification reports, performance tests, and periodic reports by the owners/operators of the affected facilities. They are also required to maintain records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of an affected facility, or any period during which the monitoring system is inoperative. These notifications, reports, and records are essential in determining compliance, and are required of all affected facilities subject to NESHAP.


Any owner/operator subject to the provisions of this part shall maintain a file of these measurements, and retain the file for at least five years following the date of such measurements, maintenance reports, and records. All reports are sent to the delegated state or local authority. In the event that there is no such delegated authority, the reports are sent directly to the U. S. Environmental Protection Agency (EPA) regional office.


Based on our consultations with industry representatives, there is an average of three affected facilities at each plant site and that each plant site has only one respondent (i.e., the owner/operator of the plant site).


Over the next three years, an average of 65 respondents per year will be subject to these standards, and one additional respondent per year will become subject to these same standards.

The Office of Management and Budget (OMB) approved the currently-active Information Collection Request (ICR) without any “Terms of Clearance.”


The “Affected Public” are existing and new lime kilns, associated coolers, and PSH operations systems located at a LMP that is a major source. The “burden” to the Affected Public may be found below in Table 1: Annual Respondent Burden and Cost – NESHAP for Lime Manufacturing (40 CFR Part 63, Subpart AAAAA) (Renewal). The ”burden” to the Federal Government is attributed entirely to work performed by either Federal employees or government contractors and may be found below in Table 2: Average Annual EPA Burden and Cost – NESHAP for Lime Manufacturing (40 CFR Part 63, Subpart AAAAA) (Renewal).


2. Need for and Use of the Collection


2(a) Need/Authority for the Collection


The EPA is charged under Section 112 of the Clean Air Act, as amended, to establish standards of performance for each category or subcategory of major sources and area sources of hazardous air pollutants. These standards are applicable to new or existing sources of hazardous air pollutants and shall require the maximum degree of emission reduction. In addition, section 114(a) states that the Administrator may require any owner/operator subject to any requirement of this Act to:


(A) Establish and maintain such records; (B) make such reports; (C) install, use, and maintain such monitoring equipment, and use such audit procedures, or methods; (D) sample such emissions (in accordance with such procedures or methods, at such locations, at such intervals, during such periods, and in such manner as the Administrator shall prescribe); (E) keep records on control equipment parameters, production variables or other indirect data when direct monitoring of emissions is impractical; (F) submit compliance certifications in accordance with Section 114(a)(3); and (G) provide such other information as the Administrator may reasonably require.


In the Administrator's judgment, HAP emissions from lime manufacturing cause or contribute to air pollution that may reasonably be anticipated to either endanger public health and/or welfare. Therefore, the NESHAP were promulgated for this source category at 40 CFR part 63, subpart AAAAA.


2(b) Practical Utility/Users of the Data


The recordkeeping and reporting requirements in the standard ensure compliance with the applicable regulations which were promulgated in accordance with the Clean Air Act. The collected information is also used for targeting inspections and as evidence in legal proceedings.

Performance tests are required in order to determine an affected facility’s initial capability to comply with the emission standard. Continuous emission monitors are used to ensure compliance with the standards at all times. During the performance test a record of the operating parameters under which compliance was achieved may be recorded and used to determine compliance in place of a continuous emission monitor.


The notifications required in the standard are used to inform the Agency or delegated authority when a source becomes subject to the requirements of the regulations. The reviewing authority may then inspect the source to check if the pollution control devices are properly installed and operated and leaks are being detected and repaired and the standard is being met. The performance test may also be observed.


The required semiannual reports are used to determine periods of excess emissions, identify problems at the facility, verify operation/maintenance procedures and for compliance determinations.


3. Non-duplication, Consultations, and Other Collection Criteria


The requested recordkeeping and reporting are required under 40 CFR part 63, subpart AAAAA.


3(a) Non-duplication


If the subject standards have not been delegated, the information is sent directly to the appropriate EPA regional office. Otherwise, the information is sent directly to the delegated state or local agency. If a state or local agency has adopted its own similar standards to implement the Federal standards, a copy of the report submitted to the state or local agency can be sent to the Administrator in lieu of the report required by the Federal standards. Therefore, duplication does not exist.


3(b) Public Notice Required Prior to ICR Submission to OMB


An announcement of a public comment period for the renewal of this ICR was published in the Federal Register (78 FR 33409) on June 4, 2013. No comments were received on the burden published in the Federal Register.


3(c) Consultations


Consultations with industry representatives (i.e., respondents) were conducted to determine if there is any way for EPA to reduce the recordkeeping and reporting burden or improve the language in the standard to make it easier to comply. In developing this ICR, we contacted: 1) the National Lime Association, at [email protected]; and 2) Carmeuse Lime & Stone, at (412) 995-5500. We received comments from Carmeuse Lime & Stone on October 24, 2013. These comments indicated that the current cost of a repeat Method 5 performance test is between $7,000 and $8,500; therefore, the capital costs associated with performance testing in this ICR has been updated to reflect the comments received.


It is our policy to respond after a thorough review of comments received since the last ICR renewal, as well as those submitted in response to the first Federal Register notice.


3(d) Effects of Less Frequent Collection


Less frequent information collection would decrease the margin of assurance that facilities are continuing to meet the standards. Requirements for information gathering and recordkeeping are useful techniques to ensure that good operation and maintenance practices are applied and emission limitations are met. If the information required by these standards was collected less frequently, the proper operation and maintenance of control equipment and the possibility of detecting violations would be less likely.


3(e) General Guidelines


These reporting or recordkeeping requirements do not violate any of the regulations promulgated by OMB under 5 CFR part 1320, section 1320.5.


These standards require the respondents to maintain all records, including reports and notifications for at least five years. This is consistent with the General Provisions as applied to the standards. EPA believes that the five-year records retention requirement is consistent the Part 70 permit program and the five-year statute of limitations on which the permit program is based. The retention of records for five years allows EPA to establish the compliance history of a source, any pattern of non-compliance and to determine the appropriate level of enforcement action. EPA has found that the most flagrant violators have violations extending beyond five years. In addition, EPA would be prevented from pursuing the violators due to the destruction or nonexistence of essential records.


3(f) Confidentiality


Any information submitted to the Agency for which a claim of confidentiality is made will be safeguarded according to the Agency policies set forth in Title 40, chapter 1, part 2, subpart B - Confidentiality of Business Information (CBI) (see 40 CFR 2; 41 FR 36902, September 1, 1976; amended by 43 FR 40000, September 8, 1978; 43 FR 42251, September 20, 1978; 44 FR 17674, March 23, 1979).


3(g) Sensitive Questions


The reporting or recordkeeping requirements in the standard do not include sensitive questions.





4. The Respondents and the Information Requested


4(a) Respondents/SIC Codes


The respondents to the recordkeeping and reporting requirements are lime manufacturing facilities. The United States Standard Industrial Classification (SIC) code for the respondents affected by the standard is SIC 3274, which corresponds to the North American Industry Classification System (NAICS) code 327410 for the Lime Manufacturing.


4(b) Information Requested


(i) Data Items


In this ICR, all the data that is recorded or reported is required by the NESHAP for Lime Manufacturing (40 CFR Part 63, Subpart AAAAA).


A source must make the following reports:



Notifications

Applicability

63.9(b), 63.7130(a)

Anticipated startup

63.9(b)(4), 63.7130(a)

Commencement of construction

63.9(b)(4), 63.7130(a)

Actual startup

63.9(b)(4), 63.7130(a)

Intention to construct/reconstruct

63.9(b)(4)-(5), 63.7130(a)

Compliance dates/extension

63.9(c), 63.7130(a)

Performance test/opacity observations

63.9(e), 63.7130(a)

Compliance status

63.9(g), 63.7130(a)



Reports

Operation, maintenance, and monitoring plan

63.7100(d)

Startup, shutdown, and malfunction plan

63.6(e)(3), 63.10(d)(5), 63.7100(e)

Semiannual compliance report

63.10(d)(2), 63.7131(b)

Emergency SSM reports, including where procedures were not followed

63.6(e)(3), 63.10(d)(5), 63.7131(b)


A source must keep the following records:


Recordkeeping

Notifications and reports

63.10(b)(2)(xiv),

63.7132(a)(1)

Startup, shutdown, and malfunction plan/events

63.6(e)(3)(iii)-(v), 63.7132(a)(2)

Performance tests and opacity observations

63.10(b)(2)(viii), 63.7132(a)(3)

Records required to demonstrate continuous compliance

63.10(b)(2)(vii), 63.7132(c)

Visual observations

63.6(h)(6), 63.7132(b)

Records are required to be retained for five years

63.10(b)(1)


Electronic Reporting


Some of the respondents are using monitoring equipment that automatically records parameter data. Although personnel at the affected facility must still evaluate the data, internal automation has significantly reduced the burden associated with monitoring and recordkeeping at a plant site.


Also, regulatory agencies in cooperation with the respondents continue to create reporting systems to transmit data electronically. However, electronic reporting systems are still not widely used. At this time, it is estimated that approximately 10 percent of the respondents use electronic reporting.


(ii) Respondent Activities



Respondent Activities


Read instructions.


Install, calibrate, maintain, and operate CMS for opacity, or for pressure drop and liquid supply pressure for control device.


Perform initial performance test, Reference Method 9 test, and repeat performance tests if necessary.


Write the notifications and reports listed above.


Enter information required to be recorded above.


Submit the required reports developing, acquiring, installing, and utilizing technology and systems for the purpose of collecting, validating, and verifying information.


Develop, acquire, install, and utilize technology and systems for the purpose of processing and maintaining information.


Develop, acquire, install, and utilize technology and systems for the purpose of disclosing and providing information.


Train personnel to be able to respond to a collection of information.


Transmit, or otherwise disclose the information.


Currently sources are using monitoring and reporting equipment that provide parameter data in an automated way (e.g., continuous parameter monitoring system). Although personnel at the source still need to evaluate the data, this type of monitoring equipment has significantly reduced the burden associated with monitoring and recordkeeping.


5. The Information Collected: Agency Activities, Collection Methodology, and Information Management


5(a) Agency Activities


EPA conducts the following activities in connection with the acquisition, analysis, storage, and distribution of the required information.



Agency Activities


Observe initial performance tests and repeat performance tests if necessary.


Review notifications and reports, including performance test reports, and excess emissions reports, required to be submitted by industry.


Audit facility records.


Input, analyze, and maintain data in the Online Tracking Information System (OTIS).


5(b) Collection Methodology and Management


Following notification of startup, the reviewing authority could inspect the source to determine whether the pollution control devices are properly installed and operated. Performance test reports are used by the Agency to discern a source’s initial capability to comply with the emission standard. Data and records maintained by the respondents are tabulated and published for use in compliance and enforcement programs. The semiannual reports are used for problem identification, as a check on source operation and maintenance, and for compliance determinations.

Information contained in the reports is entered into OTIS which is operated and maintained by EPA's Office of Compliance. OTIS is EPA’s database for the collection, maintenance, and retrieval of compliance data for approximately 125,000 industrial and government-owned facilities. EPA uses the OTIS for tracking air pollution compliance and enforcement by local and state regulatory agencies, EPA regional offices and EPA headquarters. The EPA and its delegated Authorities can edit, store, retrieve and analyze the data.


The records required by this regulation must be retained by the owner/operator for five years.


5(c) Small Entity Flexibility


The impact on small entities (i.e., small businesses) was taken into consideration during the development of the regulation. In the final rulemaking notice, EPA prepared a regulatory flexibility analysis (FRFA) which examined the impact of the final rule on small entities (See 69 FR 411, January 5, 2004). The EPA identified 19 of these 45 companies owning potentially-affected facilities as small businesses. Eight of these 45 companies manufacture beet sugar (which will not be subject to the final NESHAP), three of which are small firms. Further, an additional 3 of the 19 small companies will not be subject to the final NESHAP because they do not manufacture lime in a kiln (e.g., they are only depot or hydration facilities), and/ or we do not expect them to be major sources. Therefore, it is expected that 13 of the 34 companies subject to the final NESHAP will be small businesses, representing 38 percent of the affected companies. This percentage was applied to the total number of lime manufacturing plants affected by this regulation. For this three-year ICR period, which includes calendar years 2014, 2015, and 2016, it is estimated that there will be an average of 65 lime manufacturing plants. EPA estimates that 25 of these 65 plants (38 percent) are owned by small entities.


Due to technical considerations involving the process operations and the types of control equipment employed, the recordkeeping and reporting requirements are the same for both small and large entities. The Agency considers these to be the minimum requirements needed to ensure compliance and, therefore, cannot reduce them further for small entities. To the extent that larger businesses can use economies of scale to reduce their burden, the overall burden will be reduced.


5(d) Collection Schedule


The specific frequency for each information collection activity within this request is shown below in Table 1: Annual Respondent Burden and Cost – NESHAP for Lime Manufacturing (40 CFR Part 63, Subpart AAAAA) (Renewal).


6. Estimating the Burden and Cost of the Collection


Table 1 documents the computation of individual burdens for the recordkeeping and reporting requirements applicable to the industry for the subpart included in this ICR. The individual burdens are expressed under standardized headings believed to be consistent with the concept of “burden” under the Paperwork Reduction Act. Wherever appropriate, specific tasks and major assumptions have been identified. Responses to this information collection are mandatory.


The Agency may not conduct or sponsor, and a person is not required to respond to, a collection of information, unless it displays a currently valid OMB Control Number.


6(a) Estimating Respondent Burden


The average annual burden to industry over the next three years from these recordkeeping and reporting requirements is estimated to be 15,424 hours (Total Labor Hours from Table 1 below). These hours are based on Agency studies and background documents from the development of the regulation, Agency knowledge and experience with the NESHAP program, the previously-approved ICR, and any comments received.


6(b) Estimating Respondent Costs


(i) Estimating Labor Costs

This ICR uses the following labor rates:


Managerial $123.04 ($58.59+ 110%)

Technical $101.22 ($48.20 + 110%)

Clerical $51.18 ($24.37 + 110%)


These rates are from the United States Department of Labor, Bureau of Labor Statistics, March 2013, “Table 2. Civilian Workers, by occupational and industry group.” The rates are from column 1, “Total compensation.” The rates have been increased by 110 percent to account for the benefit packages available to those employed by private industry.


(ii) Estimating Capital/Startup and Operation and Maintenance Costs


The type of industry costs associated with the information collection activities in the subject standards are both labor costs, which are addressed elsewhere in this ICR, and the costs associated with continuous monitoring. The capital/startup costs are one-time costs when a facility becomes subject to the regulations. Each new respondent must conduct two initial Method 5 performance tests, for the new kiln and for new material handling. The annual operation and maintenance costs are the ongoing costs to hire third-party contractors to conduct repeat Method 5 testing, the annualized cost of the bag leak detector, and other costs such as photocopying and postage. It is assumed that for each kiln control device, a bag leak detector will be installed.




(iii) Capital/Startup vs. Operation and Maintenance (O&M) Costs



Capital/Startup vs. Operation and Maintenance (O&M) Costs


(A)

Continuous Monitoring Device


(B)

Capital/Startup Cost for One Respondent


(C)

Number of New Respondents


(D)

Total Capital/Startup Cost,

(B X C)


(E)

Annual O&M Costs for One Respondent


(F)

Number of Respondents with O&M


(G)

Total O&M,

(E X F)


Bag leak detector a


$0


1


$0


$1,434


65


$93,210


Performance Test for New Kilns b


$10,000


1


$10,000


$7,750


12.8


$99,200


Performance Test for New Material Handling c


$10,000


1


$10,000


$7,750


12.8


$99,200


Total






$20,000






$291,610

a The cost of a bag leak detection monitor is $10,000. The bag leak detector has a life span of 10 years. The capital cost associated with the bag leak detector was annualized assuming a seven percent interest rate and 10-year life (i.e., capital recovery factor [CRF] of 0.1434). To calculate annualized costs, the CRF was multiplied by the capital cost of the detector, or $1,434 per respondent. Each of the 65 respondents is expected to have at least one kiln with a bag leak detection monitor installed. We assume that the bag leak detector is replaced every 10 years and includes this as an O&M cost.


b. Each new respondent is assumed to conduct an initial Method 5 performance test. It is assumed that there will be a total of three new kilns in production over the three year period of the ICR, which will average out to one unit per year. The cost for an initial Method 5 test is $10,000 per new unit. It is also assumed that each existing plant would conduct a Method 5 performance test every 5 years. The cost of a repeat Method 5 test is approximately $7,750. We assume 12.8 respondents will need to conduct repeat performance test per year (64 / 5 = 12.8).


c Each new respondent is assumed to have a material handling operation that would conduct an initial Method 5 performance test. It is assumed that there will be a total of three new kilns in production over the three year period of the ICR, which will average out to one unit per year. The cost of the initial test is $10,000 per new unit. It is assumed that each existing plant has a material handling operation that would conduct a Method 5 performance test every 5 years. The cost of a repeat Method 5 test is approximately $7,750. We assume 12.8 existing respondents per year will conduct repeat test.


The total capital/startup costs for this ICR are $20,000. This is the total of column D in the above table.


The total operation and maintenance (O&M) costs for this ICR are $291,610. This is the total of column G.


The average annual cost for capital/startup and operation and maintenance costs to industry over the next three years of the ICR is estimated to be $311,610. These are the recordkeeping costs.


6(c) Estimating Agency Burden and Cost


The only costs to the Agency are those costs associated with analysis of the reported information. EPA's overall compliance and enforcement program includes activities such as the examination of records maintained by the respondents, periodic inspection of sources of emissions, and the publication and distribution of collected information.


The average annual Agency cost during the three years of the ICR is estimated to be $59,349.


This cost is based on the average hourly labor rate as follows:


Managerial $62.27 (GS-13, Step 5, $38.92 + 60%)

Technical $46.21 (GS-12, Step 1, $28.88 + 60%)

Clerical $25.01 (GS-6, Step 3, $15.63 + 60%)


These rates are from the Office of Personnel Management (OPM), 2013 General Schedule, which excludes locality, rates of pay. The rates have been increased by 60 percent to account for the benefit packages available to government employees. Details upon which this estimate is based appear below in Table 2: Average Annual EPA Burden and Cost – NESHAP for Lime Manufacturing (40 CFR Part 63, Subpart AAAAA) (Renewal).


6(d) Estimating the Respondent Universe and Total Burden and Costs


Based on our research for this ICR, on average over the next three years, approximately 64 existing respondents will be subject to these standards. It is estimated that one additional respondent per year will become subject. The overall average number of respondents, as shown in the table below, is 65 per year.


The number of respondents is calculated using the following table that addresses the three years covered by this ICR.



Number of Respondents



Year


(A)

Number of New Respondents 1


(B)

Number of Existing Respondents


(C)

Number of Existing Respondents

that keep records but do not submit reports


(D)

Number of Existing Respondents That Are Also New Respondents


(E)

Number of Respondents

(E=A+B+C-D)


1


1


63


0


0


64


2


1


64


0


0


65


3


1


65


0


0


66


Average


1


64


0


0


65

1 New respondent include sources with constructed, reconstructed and modified affected facilities. In this standard existing respondents submit initial notifications.

Column D is subtracted to avoid double-counting respondents. As shown above, the average Number of Respondents over the three-year period of this ICR is 65.


The total number of annual responses per year is calculated using the following table:


Total Annual Responses

(A)

Information Collection Activity

(B)

Number of Respondents

(C)

Number of Responses

(D)

Number of Existing Respondents That Keep Records But Do Not Submit Reports

(E)

Total Annual Responses

E=(BxC)+D

Notification of applicability

1

1

0

1

Notification of construction/ reconstruction

1

1

0

1

Notification of anticipated startup

1

1

0

1

Notification of actual startup

1

1

0

1

Notification of special compliance requirements

N/A




Compliance extension request

1

1

0

1

Notification of performance tests

13.8

1

0

13.8

Notification of opacity/VE observations

65

1

0

65

Operation, maintenance, and monitoring plans

1

1

0

1

Startup, shutdown, and malfunction (SSM) plans

1

1

0

1

Site-specific test plan

1

1

0

1

Notification of compliance status

1

1

0

1

Waiver application

N/A




Semiannual compliance reports

65

2

0

130

Emergency SSM reports

3.25

1

0

3.25




Total

221.05


The number of Total Annual Responses is 221 (rounded).


The total annual labor costs are $1,508,728 (rounded). Details regarding these estimates may be found below in Table 1: Annual Respondent Burden and Cost – NESHAP for Lime Manufacturing (40 CFR Part 63, Subpart AAAAA) (Renewal).


6(e) Bottom Line Burden Hours and Cost Tables


The detailed bottom line burden hours and cost calculations for the respondents and the Agency are shown in Tables 1 and 2 below, respectively, and summarized below.


(i) Respondent Tally


The total annual labor hours are 15,424 hours at a cost of $1,508,728. Details regarding these estimates may be found below in Table 1: Annual Respondent Burden and Cost – NESHAP for Lime Manufacturing (40 CFR Part 63, Subpart AAAAA) (Renewal).


Furthermore, the annual public reporting and recordkeeping burden for this collection of information is estimated to average 70 hours (rounded) per response.


The total annual capital/startup and O&M costs to the regulated entity are $311,610. The cost calculations are detailed in Section 6(b)(iii), Capital/Startup vs. Operation and Maintenance (O&M) Costs.


(ii) The Agency Tally


The average annual Agency burden and cost over next three years is estimated to be 1,317 labor hours at a cost of $59,349. See below Table 2: Average Annual EPA Burden and Cost – NESHAP for Lime Manufacturing (40 CFR Part 63, Subpart AAAAA) (Renewal).


6(f) Reasons for Change in Burden


There is an adjustment increase in the respondent and Agency burden from the most recently-approved ICR due to an increase in the number of new or modified sources. This ICR assumes an industry growth rate of one respondent per year, which results in an average increase of three respondents since the last ICR renewal period. The burden increase also occurred due to a correction on burden calculation. In the previous ICR, the hours required for acquisition, installation, and utilization of technology and systems; reading instructions, and required activities were omitted.


There is also an increase in capital and O&M costs. The previous ICR used annualized costs which underestimated the initial costs associated with a performance test. This ICR uses the actual costs associated with a Method 5 performance test.


6(g) Burden Statement


The annual public reporting and recordkeeping burden for this collection of information is estimated to average 70 hours per response. “Burden” means the total time, effort, or financial resources expended by persons to generate, maintain, retain, or disclose or provide information either to or for a Federal agency. This includes the time needed to review instructions; develop, acquire, install, and utilize technology and systems for the purposes of collecting, validating, and verifying information, processing and maintaining information, and disclosing and providing information; adjust the existing ways to comply with any previously applicable instructions and requirements; train personnel to be able to respond to a collection of information; search data sources; complete and review the collection of information; and transmit or otherwise disclose the information.


An agency may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a valid OMB Control Number. The OMB Control Numbers for EPA regulations are listed at 40 CFR part 9 and 48 CFR chapter 15.

To comment on the Agency's need for this information, the accuracy of the provided burden estimates, and any suggested methods for minimizing respondent burden, including the use of automated collection techniques, EPA has established a public docket for this ICR under Docket ID Number EPA-HQ-OECA-2013-0342. An electronic version of the public docket is available at http://www.regulations.gov/ which may be used to obtain a copy of the draft collection of information, submit or view public comments, access the index listing of the contents of the docket, and to access those documents in the public docket that are available electronically. When in the system, select “search,” then key in the docket ID number identified in this document. The documents are also available for public viewing at the Enforcement and Compliance Docket and Information Center in the EPA Docket Center (EPA/DC), WJC West, Room 3334, 1301 Constitution Ave., NW, Washington, DC. The EPA Docket Center Public Reading Room is open from 8:30 a.m. to 4:30 p.m., Monday through Friday, excluding legal holidays. The telephone number for the Reading Room is (202) 566-1744, and the telephone number for the docket center is (202) 566-1752. Also, you can send comments to the Office of Information and Regulatory Affairs, Office of Management and Budget, 725 17th Street, NW, Washington, DC 20503, Attention: Desk Officer for EPA. Please include the EPA Docket ID Number EPA-HQ-OECA-2013-0342 and OMB Control Number 2060-0544 in any correspondence.


Part B of the Supporting Statement


This part is not applicable because no statistical methods were used in collecting this information.

Table 1: Annual Respondent Burden and Cost –NESHAP for Lime Manufacturing (40 CFR Part 63, Subpart AAAAA) (Renewal)


 

Burden Item

(A) Persons hours per occurrence

(B)

Number of occurrences per

respondent

per Year

(C)

Person

hours per respondent per year (C=A x B)

(D) Number of respondents per

Year a

(E) Technical

person

hours per year (E=C x D)

(F) Management person

hours per

year (E x 0.05)

(G) Clerical person hours per year (E x 0.1)

(H)

Total

Costs per Year



1.

Applications

N/A










2.

Surveys and studies

N/A










3.

Acquisition, installation, and utilization of technology and systems b

40

1

40

1

40

2

4

$4,499.60



4.

Reporting requirements

 

 

 

 

 

 

 

 



 

A.

Read Instructions b

2

1

2

1

2

0.1

0.2

$224.98



 

B.

Required Activities

 

 

 

 

 

 

 

 



 

 

 

Repeat performance tests c

40

1

40

12.8

512

25.6

51.2

$57,594.88



 

 

 

Visible emission (VE) report for material handling d

8

1

8

65

520

26

52

$58,494.80



 

 

 

Annual inspection of capture, collection, and transport system e

8

1

8

65

520

26

52

$58,494.80



 

 

 

Inspection and maintenance of affected sources, control devices, and monitoring systems according to operation, maintenance, and monitoring plan f

4

1

4

65

260

13

26

$29,247.40




C.

Create Information

See 4B


 

 

 

 

 

 

 

 


D.

Gather Existing Information

See 4B


 

 

 

 

 

 

 

 

 

E.

Write Report

 

 

 

 

 

 

 

 



 

 

 

Notification of applicability b

2

1

2

1

2

0.1

0.2

$224.98



 

 

 

Notification of construction/reconstruction b

2

1

2

1

2

0.1

0.2

$224.98



 

 

 

Notification of anticipated startup b

2

1

2

1

2

0.1

0.2

$224.98



 

 

 

Notification of actual startup b

2

1

2

1

2

0.1

0.2

$224.98



 

 

 

Notification of special compliance requirements

N/A










 

 

 

Compliance extension request b

2

1

2

1

2

0.1

0.2

$224.98



 

 

 

Notification of performance test

2

1

2

13.8

27.6

1.38

2.76

$3,104.72



 

 

 

Notification of opacity/VE observations

2

1

2

65

130

6.5

13

$14,623.70



 

 

 

Operation, maintenance, and monitoring plan b

40

1

40

1

40

2

4

$4,499.60



 

 

 

Startup, shutdown, and malfunction plan b

40

1

40

1

40

2

4

$4,499.60



 

 

 

Site-Specific test plan b

40

1

40

1

40

2

4

$4,499.60



 

 

 

Notification of compliance status b

8

1

8

1

8

0.4

0.8

$899.92



 

 

 

Waiver application

N/A










 

 

 

Semiannual compliance reports g

8

2

16

65

1,040

52

104

$116,989.60



 

 

 

Emergency startup, shutdown, and malfunction reports h, i

8

1

8

3.25

26

1.3

2.6

$2,924.74



 

Subtotal for Reporting Requirements

 

 

 

 

3,697.74

$361,723.84



5.

Recordkeeping requirements

 

 

 

 

 

 

 

 



 

A.

Read Instructions

See 4A 

 

 

 

 

 

 

 



 

B.

Plan Activities

3

1

3

1

3

0.15

0.3

$337.47



 

C.

Implement Activities j

12

1

12

1

12

0.6

1.2

$1,349.88



 

D.

Develop Record System

3

1

3

1

3

0.15

0.3

$337.47



 

E.

Time to Enter Information

 

 

 

 

 

 

 

 



 

 

 

Record of all information required by standards k

3

52

156

65

10,140

507

1,014

$1,140,648.60



 

F.

Train personnel l

3

1

3

1

3

0.15

0.3

$337.47



 

G.

Time to adjust existing was to comply with previously applicable requirements m

3

1

3

1

3

0.15

0.3

$337.47



 

H.

Time to transmit or disclose information n

0.25

2

0.50

65

33

1.625

3.25

$3,655.93



 

I.

Time for Audits

N/A











Subtotal for Recordkeeping Requirements





11,726.47

$1,147,004.29



 

TOTAL LABOR BURDEN AND COST (rounded)

 

 

 

 

15,424

$1,508,728




Assumptions:

a Assumed that the average number of respondent that will be subject to the rule will be 64 existing respondents. There will be one additional new source per year that will become subject to the rule over the three-year period of this ICR.

b This is a one-time only activity.

c To demonstrate continuous compliance, plants must conduct performance tests every 5 years. The number of respondents to repeat performance test is 12.8 performance tests per year (64 existing respondents/5years). The cost to conduct a repeat Method 5 performance test is $5,000.

d Assumed that each respondent will take 8 hours to complete the annual visible emission (VE) tests for material handling.

e Assumed that each respondent will take 8 hours to complete the annual inspection of the capture, collection, and transport system.

f Assumed that each respondent will take 4 hours to complete the inspection and maintenance of affected sources, control devices, and monitoring systems according to operation, maintenance, and monitoring plan.

g Assumed that it will take 8 hours each and two times per year to complete semiannual compliance reports.

h Assumed that it will take 8 hours once a year to write the emergency startup, shutdown, or malfunction reports.

i Assumed that 5 percent of respondents will have to complete the emergency startup, shutdown, or malfunction reports.

j Assumed that it will take 12 hours to record activities implemented.

k Assumed that all respondents will take 3 hours each to enter records of all the required information 52 times a year.

l Assumed that it will take 3 hours to train each personnel.

m Assumed that it will take 3 hours for each respondent to adjust existing ways to comply with previously applicable requirements.

n Assumed that respondents are required to transmit/disclose information twice per year.

Table 2: Average Annual EPA Burden and Cost – NESHAP for Lime Manufacturing (40 CFR Part 63, Subpart AAAAA) (Renewal)

Burden Item

(A) EPA person hours per occurrence

(B) Number of Occurrences per plant per year

(C) EPA Hours per respondent per year (C=A x B)

(D) Plants per Year a

(E) Technical hours per hear (E=C x D)

(F) Management hours per hear

(E x 0.05)

(G) Clerical hours per hear ( E x 0.1)

(H)

Total

Costs per year

Initial performance tests

40

1

40

1

40

2

4

$2,072.98

Retesting preparation for repeat performance tests b

2

1

2

12.8

25.6

1.28

2.56

$1,326.71

Repeat performance tests b, c

40

1

40

12.8

512

25.6

51.2

$26,534.14

Report Review

 

 

 

 

 

 

 

 

 

 

Notification of applicability

1

1

1

1

1

0.05

0.1

$51.82

 

 

Notification of construction/ reconstruction

1

1

1

1

1

0.05

0.1

$51.82

 

 

Notification of anticipated startup

1

1

1

1

1

0.05

0.1

$51.82

 

 

Notification of actual startup

1

1

1

1

1

0.05

0.1

$51.82

 

 

Notification of special compliance requirements

N/A








 

 

Notification of initial performance tests

1

1

1

1

1

0.05

0.1

$51.82

 

 

Notification of compliance status

4

1

4

1

4

0.2

0.4

$207.30

 

 

Review of repeat performance test report b, d

2

1

2

12.8

25.6

1.28

2.56

$1,326.71

 

 

Review of semiannual compliance report

4

2

8

65

520

26

52

$26,948.74

 

 

Review of waiver application

N/A








 

 

Review of emergency startup, shutdown, and malfunction report e

4

1

4

3.25

13

0.65

1.3

$673.72

TOTAL LABOR BURDEN AND COST (rounded)

 

 

 

 

1,317

$59,349


Assumptions:

a Assumed that the average number of respondents that will be subject to the rule will be 64 existing respondents. There will be one additional new source per year that will become subject to the rule over the three-year period of this ICR for an average of 65 existing and new respondents per year.

b To demonstrate continuous compliance, plants must conduct repeat performance tests every 5 years. The number of respondents to repeat performance test is 12.8 test/year (64 existing respondents/5years = 12.8 performance tests per year) starting in the second year of this ICR.

c Assumed that it will take 40 hours for respondents to repeat performance tests.

d Assumed that it will take 2 hours for respondents to review repeat performance test report.

e Assumed five percent of sources will need to submit emergency startup, shutdown, and malfunction reports.

File Typeapplication/vnd.openxmlformats-officedocument.wordprocessingml.document
File TitleICR Package Instructions
Authorrmarshal
File Modified0000-00-00
File Created2021-01-28

© 2024 OMB.report | Privacy Policy