NESHAP for Wood Furniture Manufacturing Operations (40 CFR part 63, subpart JJ) (Renewal)

ICR 201412-2060-003

OMB: 2060-0324

Federal Form Document

Forms and Documents
Document
Name
Status
Supporting Statement A
2014-12-16
IC Document Collections
ICR Details
2060-0324 201412-2060-003
Historical Active 201110-2060-003
EPA/OAR 1716.09
NESHAP for Wood Furniture Manufacturing Operations (40 CFR part 63, subpart JJ) (Renewal)
Extension without change of a currently approved collection   No
Regular
Approved without change 11/18/2015
Retrieve Notice of Action (NOA) 01/21/2015
In accordance with 5 CFR 1320, the information collection is approved for three years.
  Inventory as of this Action Requested Previously Approved
11/30/2018 36 Months From Approved 11/30/2015
1,434 0 1,459
66,235 0 49,190
24,600 0 18,000

The potential respondents are owners or operators of any existing or new affected source with wood furniture manufacturing operations. There are an estimated 406 existing major sources and 450 existing incidental/area sources subject to the Wood Furniture Manufacturing NESHAP. The affected source is any wood furniture manufacturing facility that is engaged, either in part or in whole, in the manufacture of wood furniture or wood furniture components and that is located at a plant site that is a major source as defined in 40 CFR Part 63.2, excluding sources that meet the criteria established in §63.800(a), (b), and (c) of the Wood Furniture

US Code: 42 USC 7401 et.seq. Name of Law: Clean Air Act
  
None

Not associated with rulemaking

  79 FR 30117 05/27/2014
80 FR 2928 01/21/2015
No

1
IC Title Form No. Form Name
NESHAP for Wood Furniture Manufacturing Operations (40 CFR Part 63, subpart JJ) (Renewal)

  Total Approved Previously Approved Change Due to New Statute Change Due to Agency Discretion Change Due to Adjustment in Estimate Change Due to Potential Violation of the PRA
Annual Number of Responses 1,434 1,459 0 0 -25 0
Annual Time Burden (Hours) 66,235 49,190 0 0 17,045 0
Annual Cost Burden (Dollars) 24,600 18,000 0 0 6,600 0
No
No
There is an increase of 17,045 hours in the total estimated respondent burden as currently identified in the OMB Inventory of Approved Burdens. The active (previous) ICR added the burden from the existing final rule (ICR No. 1716.06) and the rule amendment (ICR No. 1716.08), but did not update the number of affected major sources subject to the existing rule to reflect the most recent information received at the time by the Agency. In this ICR, we have addressed this inconsistency by updating the burden calculations to reflect the appropriate number of major sources. This correction resulted in the observed increase in respondent burden. There is an increase in the O&M cost as compared to the active (previous) ICR. This increase also is the result of updating calculations to reflect the appropriate number of major sources.

$366,275
No
No
No
No
No
Uncollected
Patrick Yellin 202 564-2970 [email protected]

  No

On behalf of this Federal agency, I certify that the collection of information encompassed by this request complies with 5 CFR 1320.9 and the related provisions of 5 CFR 1320.8(b)(3).
The following is a summary of the topics, regarding the proposed collection of information, that the certification covers:
 
 
 
 
 
 
 
    (i) Why the information is being collected;
    (ii) Use of information;
    (iii) Burden estimate;
    (iv) Nature of response (voluntary, required for a benefit, or mandatory);
    (v) Nature and extent of confidentiality; and
    (vi) Need to display currently valid OMB control number;
 
 
 
If you are unable to certify compliance with any of these provisions, identify the item by leaving the box unchecked and explain the reason in the Supporting Statement.
01/21/2015