Reliability Standards-PRC-004-3

Reliability Standards-PRC-004-3.pdf

FERC-725G1 (Order in RD14-14) Mandatory Reliability Standards for the Bulk-Power System: Reliability Standard PRC-004-3

Reliability Standards-PRC-004-3

OMB: 1902-0284

Document [pdf]
Download: pdf | pdf
Standard PRC-004-3 — Protection System Misoperation Identification and
Correction
A. Introduction
1.

Title:

Protection System Misoperation Identification and Correction

2.

Number:

PRC-004-3

3.

Purpose: Identify and correct the causes of Misoperations of Protection Systems for
Bulk Electric System (BES) Elements.

4.

Applicability:
4.1.

Functional Entities:
4.1.1 Transmission Owner
4.1.2 Generator Owner
4.1.3 Distribution Provider

4.2.

Facilities:
4.2.1 Protection Systems for BES Elements, with the following exclusions:
4.2.1.1

Non-protective functions that are embedded within a Protection
System.

4.2.1.2

Protective functions intended to operate as a control function
during switching.1

4.2.1.3

Special Protection Systems (SPS).

4.2.1.4

Remedial Action Schemes (RAS).

4.2.2 Underfrequency load shedding (UFLS) that is intended to trip one or more
BES Elements.
5.

Background:
A key factor for BES reliability is the correct performance of Protection Systems. The
monitoring of Protection System events for BES Elements, as well as identifying and
correcting the causes of Misoperations, will improve Protection System performance.
This Reliability Standard PRC-004-3 – Protection System Misoperation Identification
and Correction is a revision of PRC-004-2.1a – Analysis and Mitigation of
Transmission and Generation Protection System Misoperations. The Reliability
Standard PRC-003-1 – Regional Procedure for Analysis of Misoperations of
Transmission and Generation Protection Systems requires Regional Entities to establish
procedures for analysis of Misoperations. In the FERC Order No. 693, the Commission
identified PRC-003-0 as a “fill-in-the-blank” standard. The Order stated that because
the regional procedures had not been submitted, the Commission proposed not to
approve or remand PRC-003-0. Because PRC-003-0 (now PRC-003-1) is not
enforceable, there is not a mandatory requirement for Regional Entity procedures to
support the Requirements of PRC-004-2.1a. This is a potential reliability gap;

1

For additional information and examples, see the “Non-Protective Functions” and “Control Functions” sections in
the Application Guidelines.

Page 1 of 39

Standard PRC-004-3 — Protection System Misoperation Identification and
Correction
consequently, PRC-004-3 combines the reliability intent of the two legacy standards
PRC-003-1 and PRC-004-2.1a.
This project includes revising the existing definition of Misoperation, which reads:
Misoperation


Any failure of a Protection System element to operate within the specified
time when a fault or abnormal condition occurs within a zone of protection.



Any operation for a fault not within a zone of protection (other than operation
as backup protection for a fault in an adjacent zone that is not cleared within a
specified time for the protection for that zone).



Any unintentional Protection System operation when no fault or other
abnormal condition has occurred unrelated to on-site maintenance and testing
activity.

In general, this definition needed more specificity and clarity. The terms “specified
time” and “abnormal condition” are ambiguous. In the third bullet, more clarification is
needed as to whether an unintentional Protection System operation for an atypical, yet
explainable, condition is a Misoperation.
The SAR for this project also included clarifying reporting requirements. Misoperation
data, as currently collected and reported, is not optimal to establish consistent metrics
for measuring Protection System performance. As such, the data reporting obligation
for this standard is being removed and is being developed under the NERC Rules of
Procedure, Section 1600 – Request for Data or Information (“data request”). As a result
of the data request, NERC will analyze the data to: develop meaningful metrics;
identify trends in Protection System performance that negatively impact reliability;
identify remediation techniques; and publicize lessons learned for the industry. The
removal of the data collection obligation from the standard does not result in a
reduction of reliability. The standard and data request have been developed in a manner
such that evidence used for compliance with the standard and data request are intended
to be independent of each other.
The proposed Requirements of the revised Reliability Standard PRC-004-3 meet the
following objectives:


Review all Protection System operations on the BES to identify those that are
Misoperations of Protection Systems for Facilities that are part of the BES.



Analyze Misoperations of Protection Systems for Facilities that are part of the
BES to identify the cause(s).



Develop and implement Corrective Action Plans to address the cause(s) of
Misoperations of Protection Systems for Facilities that are part of the BES.

Misoperations associated with Special Protection Schemes (SPS) and Remedial Action
Schemes (RAS) are not addressed in this standard due to their inherent complexities.
NERC plans to handle SPS and RAS in the second phase of this project.

Page 2 of 39

Standard PRC-004-3 — Protection System Misoperation Identification and
Correction
The Western Electric Coordinating Council (WECC) Regional Reliability Standard
PRC-004-WECC-1 – Protection System and Remedial Action Scheme Misoperation
relates to the reporting of Misoperations of Protection Systems and RAS for a limited
set of WECC Paths. The WECC region plans to conduct work to harmonize the
regional standard with this continent-wide proposed standard and the second phase of
this project concerning SPS and RAS.
Undervoltage load shedding (UVLS) has not been included in this standard’s
applicability because Misoperations of UVLS relays are currently addressed by
Reliability Standard PRC-022-1 – Under-Voltage Load Shedding Program
Performance, Requirement R1.5. Underfrequency load shedding (UFLS) was added to
PRC-004-3 to close a gap in reliability as Misoperations of UFLS relays are not
covered by a Reliability Standard currently.
6.

Effective Dates:
The standard shall become effective on the first day of the first calendar quarter that is
twelve (12) months after the date that the standard is approved by an applicable
governmental authority or as otherwise provided for in a jurisdiction where approval by
an applicable governmental authority is required for a standard to go into effect. Where
approval by an applicable governmental authority is not required, the standard shall
become effective on the first day of the first calendar quarter that is twelve (12) months
after the date the standard is adopted by the NERC Board of Trustees or as otherwise
provided for in that jurisdiction.

 

Page 3 of 39

Standard PRC-004-3 — Protection System Misoperation Identification and
Correction
B. Requirements and Measures
R1. Each Transmission Owner, Generator Owner, and Distribution Provider that owns a
BES interrupting device that operated under the circumstances in Parts 1.1 through 1.3
shall, within 120 calendar days of the BES interrupting device operation, identify
whether its Protection System component(s) caused a Misoperation: [Violation Risk
Factor: Medium][Time Horizon: Operations Assessment, Operations Planning]
1.1

The BES interrupting device operation was caused by a Protection System or by
manual intervention in response to a Protection System failure to operate; and

1.2

The BES interrupting device owner owns all or part of the Composite Protection
System; and

1.3

The BES interrupting device owner identified that its Protection System
component(s) caused the BES interrupting device(s) operation or was caused by
manual intervention in response to its Protection System failure to operate.

M1. Each Transmission Owner, Generator Owner, and Distribution Provider shall have
dated evidence that demonstrates it identified the Misoperation of its Protection System
component(s), if any, that meet the circumstances in Requirement R1, Parts 1.1, 1.2,
and 1.3 within the allotted time period. Acceptable evidence for Requirement R1,
including Parts 1.1, 1.2, and 1.3 may include, but is not limited to the following dated
documentation (electronic or hardcopy format): reports, databases, spreadsheets,
emails, facsimiles, lists, logs, records, declarations, analyses of sequence of events,
relay targets, Disturbance Monitoring Equipment (DME) records, test results, or
transmittals.
R2. Each Transmission Owner, Generator Owner, and Distribution Provider that owns a
BES interrupting device that operated shall, within 120 calendar days of the BES
interrupting device operation, provide notification as described in Parts 2.1 and 2.2.
[Violation Risk Factor: Medium][Time Horizon: Operations Assessment, Operations
Planning]
2.1

For a BES interrupting device operation by a Composite Protection System or by
manual intervention in response to a Protection System failure to operate,
notification of the operation shall be provided to the other owner(s) that share
Misoperation identification responsibility for the Composite Protection System
under the following circumstances:
2.1.1

The BES interrupting device owner shares the Composite Protection
System ownership with any other owner; and

2.1.2

The BES interrupting device owner has determined that a Misoperation
occurred or cannot rule out a Misoperation; and

2.1.3

The BES interrupting device owner has determined that its Protection
System component(s) did not cause the BES interrupting device(s)
operation or cannot determine whether its Protection System components
caused the BES interrupting device(s) operation.

Page 4 of 39

Standard PRC-004-3 — Protection System Misoperation Identification and
Correction
2.2

For a BES interrupting device operation by a Protection System component
intended to operate as backup protection for a condition on another entity’s BES
Element, notification of the operation shall be provided to the other Protection
System owner(s) for which that backup protection was provided.

M2. Each Transmission Owner, Generator Owner, and Distribution Provider shall have
dated evidence that demonstrates notification to the other owner(s), within the allotted
time period for either Requirement R2, Part 2.1, including subparts 2.1.1, 2.1.2, and
2.1.3 and Requirement R2, Part 2.2. Acceptable evidence for Requirement R2,
including Parts 2.1 and 2.2 may include, but is not limited to the following dated
documentation (electronic or hardcopy format): emails, facsimiles, or transmittals.
R3. Each Transmission Owner, Generator Owner, and Distribution Provider that receives
notification, pursuant to Requirement R2 shall, within the later of 60 calendar days of
notification or 120 calendar days of the BES interrupting device(s) operation, identify
whether its Protection System component(s) caused a Misoperation. [Violation Risk
Factor: Medium][Time Horizon: Operations Assessment, Operations Planning]
M3. Each Transmission Owner, Generator Owner, and Distribution Provider shall have
dated evidence that demonstrates it identified whether its Protection System
component(s) caused a Misoperation within the allotted time period. Acceptable
evidence for Requirement R3 may include, but is not limited to the following dated
documentation (electronic or hardcopy format): reports, databases, spreadsheets,
emails, facsimiles, lists, logs, records, declarations, analyses of sequence of events,
relay targets, Disturbance Monitoring Equipment (DME) records, test results, or
transmittals.
R4. Each Transmission Owner, Generator Owner, and Distribution Provider that has not
determined the cause(s) of a Misoperation, for a Misoperation identified in accordance
with Requirement R1 or R3, shall perform investigative action(s) to determine the
cause(s) of the Misoperation at least once every two full calendar quarters after the
Misoperation was first identified, until one of the following completes the
investigation: [Violation Risk Factor: Medium] [Time Horizon: Operations
Assessment, Operations Planning]


The identification of the cause(s) of the Misoperation; or



A declaration that no cause was identified.

M4. Each Transmission Owner, Generator Owner, and Distribution Provider shall have
dated evidence that demonstrates it performed at least one investigative action
according to Requirement R4 every two full calendar quarters until a cause is identified
or a declaration is made. Acceptable evidence for Requirement R4 may include, but is
not limited to the following dated documentation (electronic or hardcopy format):
reports, databases, spreadsheets, emails, facsimiles, lists, logs, records, declarations,
analyses of sequence of events, relay targets, Disturbance Monitoring Equipment
(DME) records, test results, or transmittals.

Page 5 of 39

Standard PRC-004-3 — Protection System Misoperation Identification and
Correction
R5. Each Transmission Owner, Generator Owner, and Distribution Provider that owns the
Protection System component(s) that caused the Misoperation shall, within 60 calendar
days of first identifying a cause of the Misoperation: [Violation Risk Factor: Medium]
[Time Horizon: Operations Planning, Long-Term Planning]


Develop a Corrective Action Plan (CAP) for the identified Protection System
component(s), and an evaluation of the CAP’s applicability to the entity’s other
Protection Systems including other locations; or



Explain in a declaration why corrective actions are beyond the entity’s control
or would not improve BES reliability, and that no further corrective actions will
be taken.

M5. Each Transmission Owner, Generator Owner, and Distribution Provider shall have
dated evidence that demonstrates it developed a CAP and an evaluation of the CAP’s
applicability to other Protection Systems and locations, or a declaration in accordance
with Requirement R5. Acceptable evidence for Requirement R5 may include, but is not
limited to the following dated documentation (electronic or hardcopy format): CAP and
evaluation, or declaration.
R6. Each Transmission Owner, Generator Owner, and Distribution Provider shall
implement each CAP developed in Requirement R5, and update each CAP if actions or
timetables change, until completed. [Violation Risk Factor: Medium][Time Horizon:
Operations Planning, Long-Term Planning]
M6. Each Transmission Owner, Generator Owner, and Distribution Provider shall have
dated evidence that demonstrates it implemented each CAP, including updating actions
or timetables. Acceptable evidence for Requirement R6 may include, but is not limited
to the following dated documentation (electronic or hardcopy format): records that
document the implementation of each CAP and the completion of actions for each CAP
including revision history of each CAP. Evidence may also include work management
program records, work orders, and maintenance records.

Page 6 of 39

Standard PRC-004-3 — Protection System Misoperation Identification and
Correction
C. Compliance
1.

Compliance Monitoring Process
1.1. Compliance Enforcement Authority
As defined in the NERC Rules of Procedure, “Compliance Enforcement
Authority” (CEA) means NERC or the Regional Entity in their respective roles of
monitoring and enforcing compliance with the NERC Reliability Standards.
1.2. Evidence Retention
The following evidence retention periods identify the period of time an entity is
required to retain specific evidence to demonstrate compliance. For instances
where the evidence retention period specified below is shorter than the time since
the last audit, the CEA may ask an entity to provide other evidence to show that it
was compliant for the full time period since the last audit.
The Transmission Owner, Generator Owner, and Distribution Provider shall keep
data or evidence to show compliance as identified below unless directed by its
CEA to retain specific evidence for a longer period of time as part of an
investigation.
The Transmission Owner, Generator Owner, and Distribution Provider shall
retain evidence of Requirements R1, R2, R3, and R4, Measures M1, M2, M3,
and M4 for a minimum of 12 calendar months following the completion of
each Requirement.
The Transmission Owner, Generator Owner, and Distribution Provider shall
retain evidence of Requirement R5, Measure M5, including any supporting
analysis per Requirements R1, R2, R3, and R4, for a minimum of 12
calendar months following completion of each CAP, completion of each
evaluation, and completion of each declaration.
The Transmission Owner, Generator Owner, and Distribution Provider shall
retain evidence of Requirement R6, Measure M6 for a minimum of 12
calendar months following completion of each CAP.
If a Transmission Owner, Generator Owner, or Distribution Provider is found
non-compliant, it shall keep information related to the non-compliance until
mitigation is complete and approved, or for the time specified above, whichever is
longer.
The CEA shall keep the last audit records and all requested and submitted
subsequent audit records.

Page 7 of 39

Standard PRC-004-3 — Protection System Misoperation Identification and
Correction
1.3. Compliance Monitoring and Assessment Processes
Compliance Audit
Self-Certification
Spot Checking
Compliance Investigation
Self-Reporting
Complaint
1.4. Additional Compliance Information
None.

Page 8 of 39

Standard PRC-004-3 — Protection System Misoperation Identification and Correction
D. Table of Compliance Elements
R#

R1

Time
Horizon
Operations
Assessment,
Operations
Planning

VRF

Medium

Violation Severity Levels
Lower VSL

Moderate VSL

High VSL

Severe VSL

The responsible entity
identified whether its
Protection System
component(s) caused a
Misoperation in
accordance with
Requirement R1, but
in more than 120
calendar days and less
than or equal to 150
calendar days of the
BES interrupting
device operation.

The responsible entity
identified whether its
Protection System
component(s) caused a
Misoperation in
accordance with
Requirement R1, but
in more than 150
calendar days and less
than or equal to 165
calendar days of the
BES interrupting
device operation.

The responsible entity
identified whether its
Protection System
component(s) caused a
Misoperation in
accordance with
Requirement R1, but
in more than 165
calendar days and less
than or equal to 180
calendar days of the
BES interrupting
device operation.

The responsible entity
identified whether its
Protection System
component(s) caused a
Misoperation in
accordance with
Requirement R1, but
in more than 180
calendar days of the
BES interrupting
device operation.
OR
The responsible entity
failed to identify
whether its Protection
System component(s)
caused a Misoperation
in accordance with
Requirement R1.

Page 9 of 39

Standard PRC-004-3 — Protection System Misoperation Identification and Correction

R#

R2

Time
Horizon
Operations
Assessment,
Operations
Planning

VRF

Medium

Violation Severity Levels
Lower VSL

Moderate VSL

High VSL

Severe VSL

The responsible entity
notified the other
owner(s) of the
Protection System
component(s) in
accordance with
Requirement R2, but
in more than 120
calendar days and less
than or equal to 150
calendar days of the
BES interrupting
device operation.

The responsible entity
notified the other
owner(s) of the
Protection System
component(s) in
accordance with
Requirement R2, but
in more than 150
calendar days and less
than or equal to 165
calendar days of the
BES interrupting
device operation.

The responsible entity
notified the other
owner(s) of the
Protection System
component(s) in
accordance with
Requirement R2, but
in more than 165
calendar days and less
than or equal to 180
calendar days of the
BES interrupting
device operation.

The responsible entity
notified the other
owner(s) of the
Protection System
component(s) in
accordance with
Requirement R2, but
in more than 180
calendar days of the
BES interrupting
device operation.
OR
The responsible entity
failed to notify one or
more of the other
owner(s) of the
Protection System
component(s) in
accordance with
Requirement R2.

Page 10 of 39

Standard PRC-004-3 — Protection System Misoperation Identification and Correction

R#

R3

Time
Horizon
Operations
Assessment,
Operations
Planning

VRF

Medium

Violation Severity Levels
Lower VSL

Moderate VSL

High VSL

Severe VSL

The responsible entity
identified whether or
not its Protection
System component(s)
caused a Misoperation
in accordance with
Requirement R3, but
was less than or equal
to 30 calendar days
late.

The responsible entity
identified whether or
not its Protection
System component(s)
caused a Misoperation
in accordance with
Requirement R3, but
was greater than 30
calendar days and less
than or equal to 45
calendar days late.

The responsible entity
identified whether or
not its Protection
System component(s)
caused a Misoperation
in accordance with
Requirement R3, but
was greater than 45
calendar days and less
than or equal to 60
calendar days late.

The responsible entity
identified whether or
not its Protection
System component(s)
caused a Misoperation
in accordance with
Requirement R3, but
was greater than 60
calendar days late.
OR
The responsible entity
failed to identify
whether or not a
Misoperation of its
Protection System
component(s) occurred
in accordance with
Requirement R3.

Page 11 of 39

Standard PRC-004-3 — Protection System Misoperation Identification and Correction

R#

R4

Time
Horizon
Operations
Assessment,
Operations
Planning

VRF

Medium

Violation Severity Levels
Lower VSL

Moderate VSL

High VSL

Severe VSL

The responsible entity
performed at least one
investigative action in
accordance with
Requirement R4, but
was less than or equal
to one calendar quarter
late.

The responsible entity
performed at least one
investigative action in
accordance with
Requirement R4, but
was greater than one
calendar quarter and
less than or equal to
two calendar quarters
late.

The responsible entity
performed at least one
investigative action in
accordance with
Requirement R4, but
was greater than two
calendar quarters and
less than or equal to
three calendar quarters
late.

The responsible entity
performed at least one
investigative action in
accordance with
Requirement R4, but
was more than three
calendar quarters late.
OR
The responsible entity
failed to perform
investigative action(s)
in accordance with
Requirement R4.

Page 12 of 39

Standard PRC-004-3 — Protection System Misoperation Identification and Correction

R#

R5

Time
Horizon
Operations
Planning,
Long-Term
Planning

VRF

Medium

Violation Severity Levels
Lower VSL

Moderate VSL

High VSL

Severe VSL

The responsible entity
developed a CAP, or
explained in a
declaration in
accordance with
Requirement R5, but
in more than 60
calendar days and less
than or equal to 70
calendar days of first
identifying a cause of
the Misoperation.

The responsible entity
developed a CAP, or
explained in a
declaration in
accordance with
Requirement R5, but
in more than 70
calendar days and less
than or equal to 80
calendar days of first
identifying a cause of
the Misoperation.

The responsible entity
developed a CAP, or
explained in a
declaration in
accordance with
Requirement R5, but
in more than 80
calendar days and less
than or equal to 90
calendar days of first
identifying a cause of
the Misoperation.

The responsible entity
developed a CAP, or
explained in a
declaration in
accordance with
Requirement R5, but
in more than 90
calendar days of first
identifying a cause of
the Misoperation.

OR

OR

OR

(See next page)

(See next page)

(See next page)

OR
The responsible entity
failed to develop a
CAP or explain in a
declaration in
accordance with
Requirement R5.
OR
(See next page)

Page 13 of 39

Standard PRC-004-3 — Protection System Misoperation Identification and Correction

R#

R5

Time
Horizon

VRF

(Continued)

Violation Severity Levels
Lower VSL

Moderate VSL

High VSL

Severe VSL

The responsible entity
developed an
evaluation in
accordance with
Requirement R5, but
in more than 60
calendar days and less
than or equal to 70
calendar days of first
identifying a cause of
the Misoperation.

The responsible entity
developed an
evaluation in
accordance with
Requirement R5, but
in more than 70
calendar days and less
than or equal to 80
calendar days of first
identifying a cause of
the Misoperation.

The responsible entity
developed an
evaluation in
accordance with
Requirement R5, but
in more than 80
calendar days and less
than or equal to 90
calendar days of first
identifying a cause of
the Misoperation.

The responsible entity
developed an
evaluation in
accordance with
Requirement R5, but
in more than 90
calendar days of first
identifying a cause of
the Misoperation.
OR
The responsible entity
failed to develop an
evaluation in
accordance with
Requirement R5.

R6

Operations
Planning,
Long-Term
Planning

Medium

The responsible entity
implemented, but
failed to update a
CAP, when actions or
timetables changed, in
accordance with
Requirement R6.

N/A

N/A

The responsible entity
failed to implement a
CAP in accordance
with Requirement R6.

Page 14 of 39

Standard PRC-004-3 — Protection System Misoperation Identification and
Correction
E. Regional Variances
None.
F. Interpretations
None.
G. Associated Documents
NERC System Protection and Controls Subcommittee of the NERC Planning Committee,
Assessment of Standards: PRC-003-1 – Regional Procedure for Analysis of Misoperations of
Transmission and Generation Protection Systems, PRC-004-1 – Analysis and Mitigation of
Transmission and Generation Protection Misoperations, PRC-016-1 – Special Protection
System Misoperations, May 22, 2009.2

Version History
Version

Date

Action

Change
Tracking

0

April 1, 2005

Effective Date

New

1

December 1, 2005

1. Changed incorrect use of certain
hyphens (-) to “en dash” (–) and “em
dash (—).”
2. Added “periods” to items where
appropriate.
Changed “Timeframe” to “Time Frame”
in item D, 1.2.

01/20/06

Modified to address Order No. 693
Directives contained in paragraph 1469.

Revised

2
2

August 5, 2010

Adopted by NERC Board of Trustees

1a

February 17, 2011

Added Appendix 1 - Interpretation
regarding applicability of standard to
protection of radially connected
transformers

Project 2009-17
interpretation

2

http://www.nerc.com/comm/PC/System%20Protection%20and%20Control%20Subcommittee%20SPCS%20DL/PR
C-003-004-016%20Report.pdf

Page 15 of 39

Standard PRC-004-3 — Protection System Misoperation Identification and
Correction
1a

February 17, 2011

Adopted by the Board of Trustees

1a

September 26, 2011

FERC Order issued approving the
interpretation of R1 and R3 (FERC’s
Order is effective as of September 26,
2011)

2a

September 26, 2011

Appended FERC-approved
interpretation of R1 and R3 to version 2

2.1a

Errata change: Edited R2 to add “…and
generator interconnection Facility…”

2.1a

February 9, 2012

Errata change adopted by the Board of
Trustees

2.1a

September 19, 2013

FERC Order issued approving PRC004-2.1a (approval becomes effective
November 25, 2013).

3

August 14, 2014

Adopted by Board of Trustees

3

May 13, 2015

FERC letter order issued approving
PRC-004-3

Revision under
Project 2010-07

Revision under
Project 2010-05.1

Page 16 of 39

PRC-004-3 – Application Guidelines
Guidelines and Technical Basis
Introduction
This standard addresses the reliability issues identified in the letter3 from Gerry Cauley, NERC
President and CEO, dated January 7, 2011.
“Nearly all major system failures, excluding perhaps those caused by severe
weather, have misoperations of relays or automatic controls as a factor
contributing to the propagation of the failure. …Relays can misoperate, either
operate when not needed or fail to operate when needed, for a number of reasons.
First, the device could experience an internal failure – but this is rare. Most
commonly, relays fail to operate correctly due to incorrect settings, improper
coordination (of timing and set points) with other devices, ineffective
maintenance and testing, or failure of communications channels or power
supplies. Preventable errors can be introduced by field personnel and their
supervisors or more programmatically by the organization.”
The standard also addresses the findings in the 2011 Risk Assessment of Reliability
Performance4; July 2011.
“…a number of multiple outage events were initiated by protection system
Misoperations. These events, which go beyond their design expectations and
operating procedures, represent a tangible threat to reliability. A deeper review of
the root causes of dependent and common mode events, which include three or
more automatic outages, is a high priority for NERC and the industry.”
The State of Reliability 20145 report continued to identify Protection System Misoperations as a
significant contributor to automatic transmission outage severity. The report recommended
completion of the development of PRC-004-3 as part of the solution to address Protection
System Misoperations.
Definitions
The Misoperation definition is based on the IEEE/PSRC Working Group I3 “Transmission
Protective Relay System Performance Measuring Methodology6.” Misoperations of a Protection
System include failure to operate, slowness in operating, or operating when not required either
during a Fault or non-Fault condition.

3

http://www.nerc.com/pa/Stand/Project%20201005%20Protection%20System%20Misoperations%20DL/201102091
30708-Cauley%20letter.pdf
4
“2011 Risk Assessment of Reliability Performance.” NERC. http://www.nerc.com/files/2011_RARPR_FINAL
.pdf. July 2011. Pg. 3.
5
“State of Reliability 2014.” NERC. May 2014. Pg. 18 of 106. http://www.nerc.com/pa/RAPA/PA/
Performance%20Analysis%20DL/2014_SOR_Final.pdf.
6
“Transmission Protective Relay System Performance Measuring Methodology.” Working Group I3 of Power
System Relaying Committee of IEEE Power Engineering Society. 1999. 

Page 17 of 39

PRC-004-3 – Application Guidelines
For reference, a “Protection System” is defined in the Glossary of Terms Used in NERC
Reliability Standards (“NERC Glossary”) as:


Protective relays which respond to electrical quantities,



Communications systems necessary for correct operation of protective functions,



Voltage and current sensing devices providing inputs to protective relays,



Station dc supply associated with protective functions (including station batteries, battery
chargers, and non-battery-based dc supply), and



Control circuitry associated with protective functions through the trip coil(s) of the circuit
breakers or other interrupting devices.

A BES interrupting device is a BES Element, typically a circuit breaker or circuit switcher that
has the capability to interrupt fault current. Although BES interrupting device mechanisms are
not part of a Protection System, the standard uses the operation of a BES interrupting device by a
Protection System to initiate the review for Misoperation.
The following two definitions are being proposed for inclusion in the NERC Glossary:
Composite Protection System – The total complement of Protection System(s) that function
collectively to protect an Element. Backup protection provided by a different Element’s
Protection System(s) is excluded.
The Composite Protection System definition is based on the principle that an Element’s multiple
layers of protection are intended to function collectively. This definition has been introduced in
this standard and incorporated into the proposed definition of Misoperation to clarify that the
overall performance of an Element’s total complement of protection should be considered while
evaluating an operation.
Composite Protection System – Line Example
The Composite Protection System of the Alpha-Beta line (Circuit #123) is comprised of current
differential, permissive overreaching transfer trip (POTT), step distance (classic zone 1, zone 2,
and zone 3), instantaneous-overcurrent, time-overcurrent, out-of-step, and overvoltage
protection. The protection is housed at the Alpha and Beta substations, and includes the
associated relays, communications systems, voltage and current sensing devices, DC supplies,
and control circuitry.
Composite Protection System – Transformer Example
The Composite Protection System of the Alpha transformer (#2) is comprised of internal
differential, overall differential, instantaneous-overcurrent, and time-overcurrent protection. The
protection is housed at the Alpha substation, and includes the associated relays, voltage and
current sensing devices, DC supplies, and control circuitry.

Page 18 of 39

PRC-004-3 – Application Guidelines

Composite Protection System – Generator Example
The Composite Protection System of the Beta generator (#3) is comprised of generator
differential, overall differential, overcurrent, stator ground, reverse power, volts per hertz, lossof-field, and undervoltage protection. The protection is housed at the Beta generating plant and at
the Beta substation, and includes the associated relays, voltage and current sensing devices, DC
supplies, and control circuitry.
Composite Protection System – Breaker Failure Example
Breaker failure protection provides backup protection for the breaker, and therefore is part of the
breaker’s Composite Protection System. Considering breaker failure protection to be part of
another Element’s Composite Protection System could lead to an incorrect conclusion that a
breaker failure operation automatically satisfies the “Slow Trip” criteria of the Misoperation
definition.


An example of a correct operation of the breaker’s Composite Protection System is when
the breaker failure relaying tripped because the line relaying operated, but the breaker
failed to clear the Fault. The breaker failure relaying operated because of a failed trip
coil. The failed trip coil caused a Misoperation of the line’s Composite Protection
System.



An example of a correct operation of the breaker’s Composite Protection System is when
the breaker failure relaying tripped because the line relaying operated, but the breaker
failed to clear the Fault. Only the breaker failure relaying operated because of a failed
breaker mechanism. This was not a Misoperation because the breaker mechanism is not
part of the breaker’s Composite Protection System.



An example of an “Unnecessary Trip – During Fault” is when the breaker failure relaying
tripped at the same time as the line relaying during a Fault. The Misoperation was due to
the breaker failure timer being set to zero.

Misoperation – The failure a Composite Protection System to operate as intended for
protection purposes. Any of the following is a Misoperation:
1. Failure to Trip – During Fault – A failure of a Composite Protection System to operate
for a Fault condition for which it is designed. The failure of a Protection System
component is not a Misoperation as long as the performance of the Composite Protection
System is correct.
2. Failure to Trip – Other Than Fault – A failure of a Composite Protection System to
operate for a non-Fault condition for which it is designed, such as a power swing,
undervoltage, overexcitation, or loss of excitation. The failure of a Protection System
component is not a Misoperation as long as the performance of the Composite Protection
System is correct.

Page 19 of 39

PRC-004-3 – Application Guidelines
3. Slow Trip – During Fault – A Composite Protection System operation that is slower
than required for a Fault condition if the duration of its operating time resulted in the
operation of at least one other Element’s Composite Protection System.
4. Slow Trip – Other Than Fault – A Composite Protection System operation that is slower
than required for a non-Fault condition, such as a power swing, undervoltage,
overexcitation, or loss of excitation, if the duration of its operating time resulted in the
operation of at least one other Element’s Composite Protection System.
5. Unnecessary Trip – During Fault – An unnecessary Composite Protection System
operation for a Fault condition on another Element.
6. Unnecessary Trip – Other Than Fault – An unnecessary Composite Protection System
operation for a non-Fault condition. A Composite Protection System operation that is
caused by personnel during on-site maintenance, testing, inspection, construction, or
commissioning activities is not a Misoperation.
The Misoperation definition is based on the principle that an Element’s total complement of
protection is intended to operate dependably and securely.




Failure to automatically reclose after a Fault condition is not included as a Misoperation
because reclosing equipment is not included within the definition of Protection System.
A breaker failure operation does not, in itself, constitute a Misoperation.
A remote backup operation resulting from a “Failure to Trip” or a “Slow Trip” does not,
in itself, constitute a Misoperation.

This proposed definition of Misoperation provides additional clarity over the current version. A
Misoperation is the failure of a Composite Protection System to operate as intended for
protection purposes. The definition includes six categories which provide further differentiation
of what constitutes a Misoperation. These categories are discussed in greater detail in the
following sections.
Failure to Trip – During Fault
This category of Misoperation typically results in the Fault condition being cleared by remote
backup Protection System operation.
Example 1a: A failure of a transformer's Composite Protection System to operate for a
transformer Fault is a Misoperation.
Example 1b: A failure of a "primary" transformer relay (or any other component) to
operate for a transformer Fault is not a “Failure to Trip – During Fault” Misoperation as
long as another component of the transformer's Composite Protection System operated.
Example 1c: A lack of target information does not by itself constitute a Misoperation.
When a high-speed pilot system does not target because a high-speed zone element trips
first, it would not in and of itself be a Misoperation.
Example 1d: A failure of an overall differential relay to operate is not a “Failure to Trip
– During Fault” Misoperation as long as another component such as a generator
differential relay operated.

Page 20 of 39

PRC-004-3 – Application Guidelines
Example 1e: The Composite Protection System for a bus does not operate during a bus
Fault which results in the operation of all local transformer Protection Systems connected
to that bus and all remote line Protection Systems connected to that bus isolating the
faulted bus from the grid. The operation of the local transformer Protection Systems and
the operation of all remote line Protection Systems correctly provided backup protection.
There is one “Failure to Trip – During Fault” Misoperation of the bus Composite
Protection System.
In analyzing the Protection System for Misoperation, the entity must also consider whether the
“Slow Trip – During Fault” category applies to the operation.
Failure to Trip – Other Than Fault
This category of Misoperation may have resulted in operator intervention. The “Failure to Trip –
Other Than Fault” conditions cited in the definition are examples only, and do not constitute an
all-inclusive list.
Example 2a: A failure of a generator's Composite Protection System to operate for an
unintentional loss of field condition is a Misoperation.
Example 2b: A failure of an overexcitation relay (or any other component) is not a
"Failure to Trip – Other Than Fault" Misoperation as long as the generator's Composite
Protection System operated as intended isolating the generator from the BES.
In analyzing the Protection System for Misoperation, the entity must also consider whether the
“Slow Trip – Other Than Fault” category applies to the operation.
Slow Trip – During Fault
This category of Misoperation typically results in remote backup Protection System operation
before the Fault is cleared.
Example 3a: A Composite Protection System that is slower than required for a Fault
condition is a Misoperation if the duration of its operating time resulted in the operation
of at least one other Element’s Composite Protection System. The current differential
element of a multiple function relay failed to operate for a line Fault. The same relay's
time-overcurrent element operated after a time delay. However, an adjacent line also
operated from a time-overcurrent element. The faulted line's time-overcurrent element
was found to be set to trip too slowly.
Example 3b: A failure of a breaker's Composite Protection System to operate as quickly
as intended to meet the expected critical Fault clearing time for a line Fault in
conjunction with a breaker failure (i.e., stuck breaker) is a Misoperation if it resulted in
an unintended operation of at least one other Element’s Composite Protection System. If
a generating unit’s Composite Protection System operates due to instability caused by the
slow trip of the breaker's Composite Protection System, it is not an “Unnecessary Trip –
During Fault” Misoperation of the generating unit’s Composite Protection System. This
event would be a “Slow Trip – During Fault” Misoperation of the breaker's Composite
Protection System.

Page 21 of 39

PRC-004-3 – Application Guidelines
Example 3c: A line connected to a generation interconnection station is protected with
two independent high-speed pilot systems. The Composite Protection System for this line
also includes step distance and time-overcurrent schemes in addition to the two pilot
systems. During a Fault on this line, the two pilot systems fail to operate and the timeovercurrent scheme operates clearing the Fault with no generating units or other Elements
tripping (i.e., no over-trips). This event is not a Misoperation.
The phrase “slower than required” means the duration of its operating time resulted in the
operation of at least one other Element’s Composite Protection System. It would be impractical
to provide a precise tolerance in the definition that would be applicable to every type of
Protection System. Rather, the owner(s) reviewing each Protection System operation should
understand whether the speed and outcome of its Protection System operation met their
objective. The intent is not to require documentation of exact Protection System operation times,
but to assure consideration of relay coordination and system stability by the owner(s) reviewing
each Protection System operation.
The phrase “resulted in the operation of any other Composite Protection System” refers to the
need to ensure that relaying operates in the proper or planned sequence (i.e., the primary relaying
for a faulted Element operates before the remote backup relaying for the faulted Element).
In analyzing the Protection System for Misoperation, the entity must also consider the
“Unnecessary Trip – During Fault” category to determine if an “unnecessary trip” applies to the
Protection System operation of an Element other than the faulted Element.
If a coordination error was at the local terminal (i.e., set too slow), then it was a "Slow Trip,"
category of Misoperation at the local terminal.
Slow Trip – Other Than Fault
The phrase “slower than required” means the duration of its operating time resulted in the
operation of at least one other Element’s Composite Protection System. It would be impractical
to provide a precise tolerance in the definition that would be applicable to every type of
Protection System. Rather, the owner(s) reviewing each Protection System operation should
understand whether the speed and outcome of its Protection System operation met their
objective. The intent is not to require documentation of exact Protection System operation times,
but to assure consideration of relay coordination and system stability by the owner(s) reviewing
each Protection System operation.
Example 4: A phase to phase fault occurred on the terminals of a generator. The
generator's Composite Protection System and a transmission line's Composite Protection
System both operated in response to the fault. It was found during subsequent
investigation that the generator protection contained an inappropriate time delay. This
caused the transmission line's correctly set overreaching zone of protection to operate.
This was a Misoperation of the generator’s Composite Protection System, but not of the
transmission line’s Composite Protection System.
The “Slow Trip – Other Than Fault” conditions cited in the definition are examples only, and do
not constitute an all-inclusive list.

Page 22 of 39

PRC-004-3 – Application Guidelines
Unnecessary Trip – During Fault
An operation of a properly coordinated remote Protection System is not in and of itself a
Misoperation if the Fault has persisted for a sufficient time to allow the correct operation of the
Composite Protection System of the faulted Element to clear the Fault. A BES interrupting
device failure, a “failure to trip” Misoperation, or a “slow trip” Misoperation may result in a
proper remote Protection System operation.
Example 5: An operation of a transformer's Composite Protection System which trips
(i.e., over-trips) for a properly cleared line Fault is a Misoperation. The Fault is cleared
properly by the faulted equipment's Composite Protection System (i.e., line relaying)
without the need for an external Protection System operation resulting in an unnecessary
trip of the transformer protection; therefore, the transformer Protection System operation
is a Misoperation.
Example 5b: An operation of a line's Composite Protection System which trips (i.e.,
over-trips) for a properly cleared Fault on a different line is a Misoperation. The Fault is
cleared properly by the faulted line's Composite Protection System (i.e., line relaying);
however, elsewhere in the system, a carrier blocking signal is not transmitted (e.g., carrier
ON/OFF switch found in OFF position) resulting in the operation of a remote Protection
System, single-end trip of a non-faulted line. The operation of the Protection System for
the non-faulted line is an unnecessary trip during a Fault. Therefore, the non-faulted line
Protection System operation is an “Unnecessary Trip – During Fault” Misoperation.
Example 5c: If a coordination error was at the remote terminal (i.e., set too fast), then it
was an "Unnecessary Trip – During Fault" category of Misoperation at the remote
terminal.
Unnecessary Trip – Other Than Fault
Unnecessary trips for non-Fault conditions include but are not limited to: power swings,
overexcitation, loss of excitation, frequency excursions, and normal operations.
Example 6a: An operation of a line's Composite Protection System due to a relay failure
during normal operation is a Misoperation.
Example 6b: Tripping a generator by the operation of the loss of field protection during
an off-nominal frequency condition while the field is intact is a Misoperation assuming
the Composite Protection System was not intended to operate under this condition.
Example 6c: An impedance line relay trip for a power swing that entered the relay’s
characteristic is a Misoperation if the power swing was stable and the relay operated
because power swing blocking was enabled and should have prevented the trip, but did
not.
Example 6d: Tripping a generator operating at normal load by the operation of a reverse
power protection relay due to a relay failure is a Misoperation.
Additionally, an operation that occurs during a non-Fault condition but was initiated directly by
on-site (i.e., real-time) maintenance, testing, inspection, construction, or commissioning is not a
Misoperation.

Page 23 of 39

PRC-004-3 – Application Guidelines
Example 6e: A BES interrupting device operation that occurs at the remote end of a line
during a non-Fault condition because a direct transfer trip was initiated by system
maintenance and testing activities at the local end of the line is not a Misoperation
because of the maintenance exclusion in category 6 of the definition of “Misoperation.”
The “on-site” activities at one location that initiates a trip to another location are included in this
exemption. This includes operation of a Protection System when energizing equipment to
facilitate measurements, such as verification of current circuits as a part of performing
commissioning; however, once the maintenance, testing, inspection, construction, or
commissioning activity associated with the Protection System is complete, the "on-site"
Misoperation exclusion no longer applies, regardless of the presence of on-site personnel.
Special Cases
Protection System operations for these cases would not be a Misoperation.
Example 7a: A generator Protection System operation prior to closing the unit breaker(s)
is not a Misoperation provided no in-service Elements are tripped.
This type of operation is not a Misoperation because the generating unit is not synchronized and
is isolated from the BES. Protection System operations that occur when the protected Element is
out of service and that do not trip any in-service Elements are not Misoperations.
In some cases where zones of protection overlap, the owner(s) of Elements may decide to allow
a Protection System to operate faster in order to gain better overall Protection System
performance for an Element.
Example 7b: The high-side of a transformer connected to a line may be within the zone
of protection of the supplying line’s relaying. In this case, the line relaying is planned to
protect the area of the high-side of the transformer and into its primary winding. In order
to provide faster protection for the line, the line relaying may be designed and set to
operate without direct coordination (or coordination is waived) with local protection for
Faults on the high-side of the connected transformer. Therefore, the operation of the line
relaying for a high-side transformer Fault operated as intended and would not be a
Misoperation.
Below are examples of conditions that would be a Misoperation.
Example7c: A 230 kV shunt capacitor bank was released for operational service. The
capacitor bank trips due to a settings error in the capacitor bank differential relay upon
energization.
Example 7d: A 230/115 kV BES transformer bank trips out when being re-energized due
to an incorrect operation of the transformer differential relay for inrush after being
released for operational service. Only the high-side breaker opens since the low-side
breaker had not yet been closed.

Page 24 of 39

PRC-004-3 – Application Guidelines
Non-Protective Functions
BES interrupting device operations which are initiated by non-protective functions, such as those
associated with generator controls, excitation controls, or turbine/boiler controls, static
voltampere-reactive compensators (SVC), flexible ac transmission systems (FACTS), highvoltage dc (HVdc) transmission systems, circuit breaker mechanisms, or other facility control
systems are not operations of a Protection System. The standard is not applicable to nonprotective functions such as automation (e.g., data collection) or control functions that are
embedded within a Protection System.
Control Functions
The entity must make a determination as to whether the standard is applicable to each operation
of its Protection System in accordance with the provided exclusions in the standard’s
Applicability, see Section 4.2.1. The subject matter experts (SME) developing this standard
recognize that entities use Protection Systems as part of a routine practice to control BES
Elements. This standard is not applicable to operation of protective functions within a Protection
System when intended for controlling a BES Element as a part of an entity’s process or planned
switching sequence. The following are examples of conditions to which this standard is not
applicable:
Example 8a: The reverse power protective function that operates to remove a generating
unit from service using the entity’s normal or routine process.
Example 8b: The reverse power relay enables a permissive trip and the generator
operator trips the unit.
The standard is not applicable to operation of the protective relay because its operation is
intended as a control function as part of a controlled shutdown sequence for the generator.
However, the standard remains applicable to operation of the reverse power relay when it
operates for conditions not associated with the controlled shutdown sequence, such as a motoring
condition caused by a trip of the prime mover.
The following is another example of a condition to which this standard is not applicable:
Example 8c: Operation of a capacitor bank interrupting device for voltage control using
functions embedded within a microprocessor based relay that is part of a Protection
System.
The above are examples only, and do not constitute an all-inclusive list to which the standard is
not applicable.
Extenuating Circumstances
In the event of a natural disaster or other extenuating circumstances, the December 20, 2012
Sanction Guidelines of the North American Electric Reliability Corporation, Section 2.8,
Extenuating Circumstances, reads: “In unique extenuating circumstances causing or contributing
to the violation, such as significant natural disasters, NERC or the Regional Entity may
significantly reduce or eliminate Penalties.” The Regional Entities to whom NERC has delegated

Page 25 of 39

PRC-004-3 – Application Guidelines
authority will consider extenuating circumstances when considering any sanctions in relation to
the timelines outlined in this standard.
The volume of Protection System operations tend to be sporadic. If a high rate of Protection
System operations is not sustained, utilities will have an opportunity to catch up within the 120
day period.
Requirement Time Periods
The time periods within all the Requirements are distinct and separate. The applicable entity in
Requirement R1 has 120 calendar days to identify whether a BES interrupting device operation
is a Misoperation. Once the applicable entity has identified a Misoperation, it has completed its
performance under Requirement R1. Identified Misoperations without an identified cause
become subject to Requirement R4 and any subsequent Requirements as necessary. Identified
Misoperations with an identified cause become subject to Requirement R5 and any subsequent
Requirements as necessary.
In Requirement R2, the applicable entity has 120 calendar days, based on the date of the BES
interrupting device operation, to provide notification to the other Protection System owners that
meet the circumstances in Parts 2.1 and 2.2. For the case of an applicable entity that was notified
(R3), it has the later of 120 calendar days from the date of the BES interrupting device operation
or 60 calendar days of notification to identify whether its Protection System components caused
a Misoperation.
Once a Misoperation is identified in either Requirement R1 or R3, and the applicable entity did
not identify the cause(s) of the Misoperation, the time period for performing at least one
investigative action every two full calendar quarters begins. The time period(s) in Requirement
R4 resets upon each period. When the applicable entity’s investigative actions identify the cause
of the identified Misoperation or the applicable entity declares that no cause was found, the
applicable entity has completed its performance in Requirement R4.
The time period in Requirement R5 begins when the Misoperation cause is first identified. The
applicable entity is allotted 60 calendar days to perform one of the two activities listed in
Requirement R5 (e.g., CAP or declaration) to complete its performance under Requirement R5.
Requirement R6 time period is determined by the actions and the associated timetable to
complete those actions identified in the CAP. The time periods contained in the CAP may
change from time to time and the applicable entity is required to update the timetable when it
changes.
Time periods provided in the Requirements are intended to provide a reasonable amount of time
to perform each Requirement. Performing activities in the least amount of time facilitates prompt
identification of Misoperations, notification to other Protection System owners, identification of
the cause(s), correction of the cause(s), and that important information is retained that may be
lost due to time.

Page 26 of 39

PRC-004-3 – Application Guidelines
Requirement R1
This Requirement initiates a review of each BES interrupting device operation to identify
whether or not a Misoperation may have occurred. Since the BES interrupting device owner
typically monitors and tracks device operations, the owner is the logical starting point for
identifying Misoperations of Protection Systems for BES Elements. A review is required when
(1) a BES interrupting device operates that is caused by a Protection System or by manual
intervention in response to a Protection System failure to operate, (2) regardless of whether the
owner owns all or part of the Protection System component(s), and (3) the owner identified its
Protection System component(s) as causing the BES interrupting device operation or was caused
by manual intervention in response to its Protection System failure to operate.
Since most Misoperations result in the operation of one or more BES interrupting devices, these
operations initiate a review to identify any Misoperation. If an Element is manually isolated in
response to a failure to operate, the manual isolation of the Element triggers a review for
Misoperation.
Example R1a: The failure of a loss of field relay on a generating unit where an operator
takes action to isolate the unit.
Manual intervention may indicate a Misoperation has occurred, thus requiring the initiation of an
investigation by the BES interrupting device owner.
For the case where a BES interrupting device did not operate and remote clearing occurs due to
the failure of a Composite Protection System to operate, the BES interrupting device owner
would still review the operation under Requirement R1. However, if the BES interrupting device
owner determines that its Protection System component operated as backup protection for a
condition on another entity’s BES Element, the owner would provide notification of the
operation to the other Protection System owner(s) under Requirement R2, Part 2.2.
Protection Systems are made of many components. These components may be owned by
different entities. For example, a Generator Owner may own a current transformer that sends
information to a Transmission Owner’s differential relay. All of these components and many
more are part of a Protection System. It is expected that all of the owners will communicate with
each other, sharing information freely, so that Protection System operations can be analyzed,
Misoperations identified, and corrective actions taken.
Each entity is expected to use judgment to identify those Protection System operations that meet
the definition of Misoperation regardless of the level of ownership. A combination of available
information from resources such as counters, relay targets, Supervisory Control and Data
Acquisition (SCADA) systems, or Disturbance Monitoring Equipment (DME) would typically
be used to determine whether or not a Misoperation occurred. The intent of the standard is to
classify an operation as a Misoperation if the available information leads to that conclusion. In
many cases, it will not be necessary to leverage all available data to determine whether or not a
Misoperation occurred. The standard also allows an entity to classify an operation as a
Misoperation if entity is not sure. The entity may decide to identify the operation as a
Misoperation to satisfy Requirement R1 and continue its investigation for a cause of the
Misoperation under Requirement R4. If the continued investigative actions are inconclusive, the
entity may declare no cause found and end its investigation. The entity is allotted 120 calendar

Page 27 of 39

PRC-004-3 – Application Guidelines
days from the date of its BES interrupting device operation to identify whether its Protection
System component(s) caused a Misoperation.
The Protection System operation may be documented in a variety of ways such as in a report,
database, spreadsheet, or list. The documentation may be organized in a variety of ways such as
by BES interrupting device, protected Element, or Composite Protection System.
Repeated operations which occur during the same automatic reclosing sequence do not need a
separate identification under Requirement R1. Repeated Misoperations which occur during the
same 24-hour period do not need a separate identification under Requirement R1. This is
consistent with the NERC Misoperations Report7 which states:
“In order to avoid skewing the data with these repeated events, the NERC SPCS should
clarify, in the next annual update of the misoperation template, that all misoperations due
to the same equipment and cause within a 24 hour period be recorded as one
misoperation.”
The following is an example of a condition that is not a Misoperation.
Example R1b: A high impedance Fault occurs within a transformer. The sudden
pressure relaying detects and operates for the Fault, but the differential relaying did not
operate due to the low Fault current levels. This is not a Misoperation because the
Composite Protection System was not required to operate because the Fault was cleared
by the sudden pressure relay.
Requirement R2
Requirement R2 ensures notification of those who have a role in identifying Misoperations, but
were not accounted for within Requirement R1. In the case of multi-entity ownership, the entity
that owns the BES interrupting device that operated is expected to use judgment to identify those
Protection System operations that meet the definition of Misoperation under Requirement R1;
however, if the entity that owns a BES interrupting device determines that its Protection System
component(s) did not cause the BES interrupting device(s) operation or cannot determine
whether its Protection System components caused the BES interrupting device(s) operation, it
must notify the other Protection System owner(s) that share Misoperation identification
responsibility when the criteria in Requirement R2 is met.
This Requirement does not preclude the Protection System owners from initially communicating
and working together to determine whether a Misoperation occurred and, if so, the cause. The
BES interrupting device owner is only required to officially notify the other owners when it: (1)
shares the Composite Protection System ownership with other entity(ies), (2) determines that a
Misoperation occurred or cannot rule out a Misoperation, and (3) determines its Protection
System component(s) did not cause a Misoperation or is unsure. Officially notifying the other
owners without performing a preliminary review may unnecessarily burden the other owners
with compliance obligations under Requirement R3, redirect valuable resources, and add little

7

“Misoperations Report.” Reporting Multiple Occurrences. NERC Protection System Misoperations Task Force.
http://www.nerc.com/docs/pc/psmtf/PSMTF_Report.pdf. April 1, 2013. pg. 37 of 40.

Page 28 of 39

PRC-004-3 – Application Guidelines
benefit to reliability. The BES interrupting device owner should officially notify other owners
when appropriate within the established time period.
The following is an example of a notification to another Protection System owner:
Example R2a: Circuit breakers A and B at the Charlie station tripped from directional
comparison blocking (DCB) relaying on 03/03/2014 at 15:43 UTC during an external
Fault. As discussed last week, the fault records indicate that a problem with your
equipment (failure to transmit) caused the operation.
Example R2b: A generator unit tripped out immediately upon synchronizing to the grid
due to a Misoperation of its overcurrent protection. The Transmission Owner owns the
230 kV generator breaker that operated. The Transmission Owner, as the owner of the
BES interrupting device after determining that its Protection System components did not
cause the Misoperation, notified the Generator Owner of the operation. The Generator
Owner investigated and determined that its Protection System components caused the
Misoperation. In this example, the Generator Owner’s Protection System components did
cause the Misoperation. As the owner of the Protection System components that caused
the Misoperation, the Generator Owner is responsible for creating and implementing the
CAP.
A Composite Protection System owned by different functional entities within the same registered
entity does not necessarily satisfy the notification criteria in Part 2.1.1 of Requirement R2. For
example, if the same personnel within a registered entity perform the Misoperation identification
for both the Generator Owner and Transmission Owner functions, then the Misoperation
identification would be completely covered in Requirement R1, and therefore notification would
not be required. However, if the Misoperation identification is handled by different groups, then
notification would be required because the Misoperation identification would not necessarily be
covered in Requirement R1.
Example R2c: Line A Composite Protection System (owned by entity 1) failed to
operate for an internal Fault. As a result, the zone 3 portion of Line B’s Composite
Protection System (owned by entity 2) and zone 3 portion of Line C’s Composite
Protection System (owned by entity 3) operated to clear the Fault. Entity 2 and 3 notified
entity 1 of the remote zone 3 operation.
For the case where a BES interrupting device operates to provide backup protection for a nonBES Element, the entity reviewing the operation is not required to notify the other owners of
Protection Systems for non-BES Elements. No notification is required because this Reliability
Standard is not applicable to Protection Systems for non-BES Elements.
Requirement R3
For Requirement R3 (i.e., notification received), the entity that also owns a portion of the
Composite Protection System is expected to use judgment to identify whether the Protection
System operation is a Misoperation. A combination of available information from resources such
as counters, relay targets, SCADA, DME, and information from the other owner(s) would
typically be used to determine whether or not a Misoperation occurred. The intent of the standard
is to classify an operation as a Misoperation if the available information leads to that conclusion.

Page 29 of 39

PRC-004-3 – Application Guidelines
In many cases, it will not be necessary to leverage all available data to determine whether or not
a Misoperation occurred. The standard also allows an entity to classify an operation as a
Misoperation if an entity is not sure. The entity may decide to identify the operation as a
Misoperation to satisfy Requirement R1 and continue its investigation for a cause of the
Misoperation under Requirement R4. If the continued investigative actions are inconclusive, the
entity may declare no cause found and end its investigation.
The entity that is notified by the BES interrupting device owner is allotted the later of 60
calendar days from receipt of notification or 120 calendar days from the BES interrupting device
operation date to determine if its portion of the Composite Protection System caused the
Protection System operation. It is expected that in most cases of a jointly owned Protection
System, the entity making notification would have been in communication with the other
owner(s) early in the process. This means that the shorter 60 calendar days only comes into play
if the notification occurs in the second half of the 120 calendar days allotted to the BES
interrupting device owner in Requirement R1.
The Protection System review may be organized in a variety of ways such as in a report,
database, spreadsheet, or list. The documentation may be organized in a variety of ways such as
by BES interrupting device, protected Element, or Composite Protection System. The BES
interrupting device owner’s notification received may be documented in a variety of ways such
as an email or a facsimile.
Requirement R4
The entity in Requirement R4 (i.e., cause identification), whether it is the entity that owns the
BES interrupting device or an entity that was notified, is expected to use due diligence in taking
investigative action(s) to determine the cause(s) of an identified Misoperation for its portion of
the Composite Protection System. The SMEs developing this standard recognize there will be
cases where the cause(s) of a Misoperation will not be revealed during the allotted time periods
in Requirements R1 or R3; therefore, Requirement R4 provides the entity a mechanism to
continue its investigative work to determine the cause(s) of the Misoperation when the cause is
not known.
A combination of available information from resources such as counters, relay targets, SCADA,
DME, test results, and studies would typically be used to determine the cause of the
Misoperation. At least one investigative action must be performed every two full calendar
quarters until the investigation is completed.

Page 30 of 39

PRC-004-3 – Application Guidelines
The following is an example of investigative actions taken to determine the cause of an identified
Misoperation:
Example R4a: A Misoperation was identified on 03/18/2014. A line outage to test the
Protection System was scheduled on 03/24/2014 for 12/15/2014 as the first investigative
action (i.e., beyond the next two full calendar quarters) due to summer peak conditions.
The protection engineer contacted the manufacturer on 04/10/2014 (i.e., within two full
calendar quarters) to obtain any known issues. The engineer reviewed manufacturer’s
documents on 05/27/2014. The outage schedule was confirmed on 08/29/2014 and was
taken on 12/15/2014. Testing was completed on 12/16/2014 (i.e., in the second two full
quarters) revealing the microprocessor relay as the cause of the Misoperation. A CAP is
being developed to replace the relay.
Periodic action minimizes compliance burdens and focuses the entity’s effort on determining the
cause(s) of the Misoperation while providing measurable evidence. The SMEs recognize that
certain planned investigative actions may require months or years to schedule and complete;
therefore, the entity is only required to perform at least one investigative action every two full
calendar quarters. If an investigative action is performed in the first quarter of a calendar year,
the next investigative action would need to be performed by the end of the third calendar quarter.
If an investigative action is performed in the last quarter of a calendar year, the next investigative
action would need to be performed by the end of the second calendar quarter of the following
calendar year. Investigative actions may include a variety of actions, such as reviewing DME
records, performing or reviewing studies, completing relay calibration or testing, requesting
manufacturer review, requesting an outage, or confirming a schedule.
The entity’s investigation is complete when it identifies the cause of the Misoperation or makes a
declaration that no cause was determined. The declaration is intended to be used if the entity
determines that investigative actions have been exhausted or have not provided direction for
identifying the Misoperation cause. Historically, approximately 12% of Misoperations are
unknown or unexplainable.8
Although the entity only has to document its specific investigative actions taken to determine the
cause(s) of an identified Misoperation, the entity should consider the benefits of formally
organizing (e.g., in a report or database) its actions and findings. Well documented investigative
actions and findings may be helpful in future investigations of a similar event or circumstances.
A thorough report or database may contain a detailed description of the event, information
gathered, investigative actions, findings, possible causes, identified causes, and conclusions.
Multiple owners of a Composite Protection System might consider working together to produce
a common report for their mutual benefit.

8

NERC System Protection and Control Subcommittee. Misoperations Report. April 1, 2013: http://www.nerc.com/
docs/pc/psmtf/PSMTF_Report.pdf. Figure 15: NERC Wide Misoperations by Cause Code. pg. 22 of 40.

Page 31 of 39

PRC-004-3 – Application Guidelines
The following are examples of a declaration where no cause was determined:
Example R4b: A Misoperation was identified on 04/11/2014. All relays at station A and
B functioned properly during testing on 08/26/2014 as the first investigative action. The
carrier system functioned properly during testing on 08/27/2014. The carrier coupling
equipment functioned properly during testing on 08/28/2014. A settings review
completed on 09/03/2014 indicated the relay settings were proper. Since the equipment
involved in the operation functioned properly during testing, the settings were reviewed
and found to be correct, and the equipment at station A and station B is already
monitored. The investigation is being closed because no cause was found.
Example R4c: A Misoperation was identified on 03/22/2014. The protection scheme was
replaced before the cause was identified. The power line carrier or PLC based protection
was replaced with fiber-optic based protection with an in-service date of 04/16/2014. The
new system will be monitored for recurrence of the Misoperation.
Requirement R5
Resolving the causes of Protection System Misoperations benefits BES reliability by preventing
recurrence. The Corrective Action Plan (CAP) is an established tool for resolving operational
problems. The NERC Glossary defines a Corrective Action Plan as, "A list of actions and an
associated timetable for implementation to remedy a specific problem." Since a CAP addresses
specific problems, the determination of what went wrong needs to be completed before
developing a CAP. When the Misoperation cause is identified in Requirement R1, R3 or R4,
Requirement R5 requires Protection System owner(s) to develop a CAP, or explain why
corrective actions are beyond the entity’s control or would not improve BES reliability. The
entity must develop the CAP or make a declaration why additional actions are beyond the
entity’s control or would not improve BES reliability and that no further corrective actions will
be taken within 60 calendar days of first determining a cause.
The SMEs developing this standard recognize there may be multiple causes for a Misoperation.
In these circumstances, the CAP would include a remedy for the identified causes. The CAP may
be revised if additional causes are found; therefore, the entity has the option to create a single or
multiple CAP(s) to correct multiple causes of a Misoperation. The 60 calendar day period for
developing a CAP (or declaration) is established on the basis of industry experience which
includes operational coordination timeframes, time to consider alternative solutions, coordination
of resources, and development of a schedule.
The development of a CAP is intended to document the specific corrective actions needed to be
taken to prevent Misoperation recurrence, the timetable for executing such actions, and an
evaluation of the CAP's applicability to the entity’s other Protection Systems including other
locations. The evaluation of these other Protection Systems aims to reduce the risk and
likelihood of similar Misoperations in other Protection Systems. The Protection System owner is
responsible for determining the extent of its evaluation concerning other Protection Systems and
locations. The evaluation may result in the owner including actions to address Protection
Systems at other locations or the reasoning for not taking any action. The CAP and an evaluation
of other Protection Systems including other locations must be developed to complete
Requirement R5.

Page 32 of 39

PRC-004-3 – Application Guidelines
The following is an example of a CAP for a relay Misoperation that was applying a standing trip
due to a failed capacitor within the relay and the evaluation of the cause at similar locations
which determined capacitor replacement was not necessary.
For completion of each CAP in Examples R5a through R5d, please see Examples R6a through
R6d.
Example R5a: Actions: Remove the relay from service. Replace capacitor in the relay.
Test the relay. Return to service or replace by 07/01/2014.
Applicability to other Protection Systems: This type of impedance relay has not been
experiencing problems and is systematically being replaced with microprocessor relays as
Protection Systems are modernized. Therefore, it was assessed that a program for
wholesale preemptive replacement of capacitors in this type of impedance relay does not
need to be established for the system.
The following is an example of a CAP for a relay Misoperation that was applying a standing trip
due to a failed capacitor within the relay and the evaluation of the cause at similar locations
which determined the capacitors need preemptive correction action.
Example R5b: Actions: Remove the relay from service. Replace capacitor in the relay.
Test the relay. Return to service or replace by 07/01/2014.
Applicability to other Protection Systems: This type of impedance relay is suspected to
have previously tripped at other locations because of the same type of capacitor issue.
Based on the evaluation, a program should be established by 12/01/2014 for wholesale
preemptive replacement of capacitors in this type of impedance relay.
The following is an example of a CAP for a relay Misoperation that was applying a standing trip
due to a failed capacitor within the relay and the evaluation of the cause at similar locations
which determined the capacitors need preemptive correction action.
Example R5c: Actions: Remove the relay from service. Replace capacitor in the relay.
Test the relay. Return to service or replace by 07/01/2014.
Applicability to other Protection Systems: This type of impedance relay is suspected to
have previously tripped at other locations because of the same type of capacitor issue.
Based on the evaluation, the preemptive replacement of capacitors in this type of
impedance relay should be pursued for the identified stations A through I by 04/30/2015.
A plan is being developed to replace the impedance relay capacitors at stations A, B, and
C by 09/01/2014. A second plan is being developed to replace the impedance relay
capacitors at stations D, E, and F by 11/01/2014. The last plan will replace the impedance
relay capacitors at stations G, H, and I by 02/01/2015.

Page 33 of 39

PRC-004-3 – Application Guidelines
The following is an example of a CAP for a relay Misoperation that was due to a version 2
firmware problem and the evaluation of the cause at similar locations which determined the
firmware needs preemptive correction action.
Example R5d: Actions: Provide the manufacturer fault records. Install new firmware
pending manufacturer results by 10/01/2014.
Applicability to other Protection Systems: Based on the evaluation of other locations and
a risk assessment, the newer firmware version 3 should be installed at all installations that
are identified to be version 2. Twelve relays were identified across the system. Proposed
completion date is 12/31/2014.
The following are examples of a declaration made where corrective actions are beyond the
entity’s control or would not improve BES reliability and that no further corrective actions will
be taken.
Example R5e: The cause of the Misoperation was due to a non-registered entity
communications provider problem.
Example R5f: The cause of the Misoperation was due to a transmission transformer
tapped industrial customer who initiated a direct transfer trip to a registered entity’s
transmission breaker.
In situations where a Misoperation cause emanates from a non-registered outside entity, there
may be limited influence an entity can exert on an outside entity and is considered outside of an
entity’s control.
The following are examples of declarations made why corrective actions would not improve
BES reliability.
Example R5g: The investigation showed that the Misoperation occurred due to transients
associated with energizing transformer ABC at Station Y. Studies show that desensitizing the relay to the recorded transients may cause the relay to fail to operate as
intended during power system oscillations.
Example R5h: As a result of an operation that left a portion of the power system in an
electrical island condition, circuit XYZ within that island tripped, resulting in loss of load
within the island. Subsequent investigation showed an overfrequency condition persisted
after the formation of that island and the XYZ line protective relay operated. Since this
relay was operating outside of its designed frequency range and would not be subject to
this condition when line XYZ is operated normally connected to the BES, no corrective
action will be taken because BES reliability would not be improved.

Page 34 of 39

PRC-004-3 – Application Guidelines
Example R5i: During a major ice storm, four of six circuits were lost at Station A.
Subsequent to the loss of these circuits, a skywire (i.e., shield wire) broke near station A
on line AB (between Station A and B) resulting in a phase-phase Fault. The protection
scheme utilized for both protection groups is a permissive overreaching transfer trip
(POTT). The Line AB protection at Station B tripped timed for this event (i.e., Slow Trip
– During Fault) even though this line had been identified as requiring high speed
clearing. A weak infeed condition was created at Station A due to the loss of 4
transmission circuits resulting in the absence of a permissive signal on Line AB from
Station A during this Fault. No corrective action will be taken for this Misoperation as
even under N-1 conditions, there is normally enough infeed at Station A to send a proper
permissive signal to station B. Any changes to the protection scheme to account for this
would not improve BES reliability.
A declaration why corrective actions are beyond the entity’s control or would not improve BES
reliability should include the Misoperation cause and the justification for taking no corrective
action. Furthermore, a declaration that no further corrective actions will be taken is expected to
be used sparingly.
Requirement R6
To achieve the stated purpose of this standard, which is to identify and correct the causes of
Misoperations of Protection Systems for BES Elements, the responsible entity is required to
implement a CAP that addresses the specific problem (i.e., cause(s) of the Misoperation) through
completion. Protection System owners are required in the implementation of a CAP to update it
when actions or timetable change, until completed. Accomplishing this objective is intended to
reduce the occurrence of future Misoperations of a similar nature, thereby improving reliability
and minimizing risk to the BES.
The following is an example of a completed CAP for a relay Misoperation that was applying a
standing trip (See also, Example R5a).
Example R6a: Actions: The impedance relay was removed from service on 06/02/2014
because it was applying a standing trip. A failed capacitor was found within the
impedance relay and replaced. The impedance relay functioned properly during testing
after the capacitor was replaced. The impedance relay was returned to service on
06/05/2014.
CAP completed on 06/25/2014.

Page 35 of 39

PRC-004-3 – Application Guidelines
The following is an example of a completed CAP for a relay Misoperation that was applying a
standing trip that resulted in the correction and the establishment of a program for further
replacements (See also, Example R5b).
Example R6b: Actions: The impedance relay was removed from service on 06/02/2014
because it was applying a standing trip. A failed capacitor was found within the
impedance relay and replaced. The impedance relay functioned properly during testing
after the capacitor was replaced. The impedance relay was returned to service on
06/05/2014.
A program for wholesale preemptive replacement of capacitors in this type of impedance
relay was established on 10/28/2014.
CAP completed on 10/28/2014.
The following is an example of a completed CAP of corrective actions with a timetable that
required updating for a failed relay and preemptive actions for similar installations (See also,
Example R5c).
Example R6c: Actions: The impedance relay was removed from service on 06/02/2014
because it was applying a standing trip. A failed capacitor was found within the
impedance relay and replaced. The impedance relay functioned properly during testing
after the capacitor was replaced. The impedance relay was returned to service on
06/05/2014.
The impedance relay capacitor replacement was completed at stations A, B, and C on
08/16/2014. The impedance relay capacitor replacement was completed at stations D, E,
and F on 10/24/2014. The impedance relay capacitor replacement for stations G, H, and I
were postponed due to resource rescheduling from a scheduled 02/01/15 completion to
04/01/2015 completion. Capacitor replacement was completed on 03/09/2015 at stations
G, H, and I. All stations identified in the evaluation have been completed.
CAP completed on 03/09/2015.
The following is an example of a completed CAP for corrective actions with updated actions for
a firmware problem and preemptive actions for similar installations. (See also, Example R5d).
Example R6d: Actions: fault records were provided to the manufacturer on 06/04/2014.
The manufacturer responded that the Misoperation was caused by a bug in version 2
firmware, and recommended installing version 3 firmware. Version 3 firmware was
installed on 08/12/2014.
Nine of the twelve relays were updated to version 3 firmware on 09/23/2014. The
manufacturer provided a subsequent update which was determined to be beneficial for the
remaining relays. The remaining three of twelve relays identified as having the version 2
firmware were updated to version 3.01 firmware on 11/10/2014.
CAP completed on 11/10/2014.
The CAP is complete when all of the actions identified within the CAP have been completed.

Page 36 of 39

PRC-004-3 – Application Guidelines
Process Flow Chart: Below is a graphical representation demonstrating the relationships
between Requirements:

Entry Point(s)

(Notified Entities)

(2.1) The owner of a BES interrupting device 
that operated, within 120 calendar days of 
the BES interrupting device operation

BES interrupting device owner

The owner of a BES interrupting device that operated, within 120 
calendar days of the BES interrupting device operation
Operation was caused 
by a Protection System 
or by manual 
intervention in 
response to a 
Protection System 
failure to operate

BES interrupting 
device owner 
owns all or part 
of the Protection 
System 
component(s)

BES interrupting device owner must
also consider this as a parallel path if a
Composite Protection System has multiple owners

BES interrupting device 
owner identified that its 
Protection System 
component(s) caused the 
BES interrupting device(s) 
operation or by manual 
intervention

BES 
interrupting 
device owner 
shares the 
Composite 
Protection 
System 
ownership 
with other 
entity(ies)

BES 
BES interrupting 
interrupting 
device owner 
device owner 
determined 
determined 
that its 
that a 
Protection 
Misoperation 
System 
occurred or 
component(s) 
cannot rule 
did not cause 
out a 
the operation 
Misoperation
or is unsure

When
all are
TRUE

R2

Shall identify whether BES interrupting device owner’s Protection 
System component(s) caused a Misoperation

The entity that receives notification, within the later of 
either 60 calendar days of notification or 120 calendar 
days of the BES interrupting device(s) operation, shall 
identify whether its Protection System component(s) 
caused a Misoperation. 

R3
Is a
Misop?

NO

YES
(2.2)

Shall notify the other 
owner(s) of the Protection 
System of the BES 
interrupting device 
operation

When
all are
TRUE

R1

Remote
Backup
Protection
Operated?

NO

The entity that owns the Protection System component that caused 
the Misoperation, within 60 calendar days of first identifying a cause
YES

Stop

Cause
Known?

Corrective
actions are beyond the 
entity’s control or would 
not improve BES
reliability?

YES

NO

R5

An entity that has not determined the cause(s) of a Misoperation 
shall perform at least one investigative action to determine the 
cause(s) of the Misoperation, at least once every two full calendar 
quarters after the Misoperation was first identified, until one of the 
following completes the investigation: 

R4
NO

Cause
Found?

YES

NO
Develop a CAP and
an evaluation

Stop

Implement each Corrective 
Action Plan (CAP), and update 
each CAP if actions or 
timetables change, until 
completed.

Stop
Write a 
declaration 
that no cause 
was identified

YES

Cause
identified

R6

Document why 
corrective actions are 
beyond the entity’s 
control or would not 
improve BES reliability, 
and that no further 
corrective actions will 
be taken

Stop
YES
CAP
complete?

NO

Page 37 of 39

PRC-004-3 – Application Guidelines
Rationale

During development of this standard, text boxes were embedded within the standard to explain
the rationale for various parts of the standard. Upon BOT approval, the text from the rationale
text boxes were moved to this section.
Rationale for Applicability: 
Protection Systems that protect BES Elements are integral to the operation and reliability of the
BES. Some functions of relays are not used as protection but as control functions or for
automation; therefore, any operation of the control function portion or the automation portion of
relays is excluded from this standard. See the Application Guidelines for detailed examples of
non-protective functions. Special Protection Systems (SPS) and Remedial Action Schemes
(RAS) are excluded in this standard because they are planned to be handled in the second phase
of this project.
Rationale for R1:  
This Requirement ensures that entities review those Protection System operations meeting the
circumstances in all three Parts (1.1, 1.2, and 1.3) and identify any that are Misoperations. The
BES interrupting device owner is assigned the responsibility to initiate the review because the
owner is in the best position to be aware of the operation. Manual intervention is included as a
condition that initiates a review. Occasionally, Protection System failures do not yield other
Protection System operations and manual intervention is required to isolate the problematic
equipment. The 120 calendar day period accounts for the sporadic volumes of Protection System
operations, and provides the opportunity to identify any Misoperations which were initially
missed.
Rationale for R2:  
Part 2.1 ensures that the BES interrupting device owner notifies the other owners of the
Composite Protection System. The phrase “owner(s) that share Misoperation identification
responsibility” allows entities to notify the specific other owners that will actually review the
operation to determine if a Misoperation occurred. Part 2.2 ensures that the Protection System
owner(s) for which backup protection was provided receives notification, within the same 120
calendar day period as R1. This ensures other entities are notified to review their Protection
System components. The expectation is that entities will communicate accordingly and when it is
clear that Part 2.1, 2.2, or both are met, the entity would make the notification. It is not intended
for entities to automatically and unnecessarily notify other entities before adequate detail is
known.
Rationale for R3:  
When an entity receives notification of a Protection System operation by the BES interrupting
device owner, the other Protection System owner is allotted at least 60 calendar days to identify
whether it was a Misoperation. A shorter time period is allotted on the basis that the BES
interrupting device owner has already performed preliminary work, collaborated with the other
owners, and that other owners generally have fewer associated Protection System components.
 
 

Page 38 of 39

PRC-004-3 – Application Guidelines
Rationale for R4:  
If a Misoperation cause is not identified within the time period established by Requirements R1
or R3 (i.e., 120 calendar days), the Protection System component owner must demonstrate
investigative actions toward identifying the cause(s). Performing at least one action every two
full calendar quarters from first identifying the Misoperation encourages periodic focus on
finding the cause of the Misoperation.
Rationale for R5:  
A formal CAP is a proven tool for resolving and reducing the possibility of reoccurrence of
operational problems. A time period of 60 calendar days is based on industry experience and
operational coordination time needed for considering such things as alternative solutions,
coordination of resources, or development of a schedule. When the cause of a Misoperation is
identified, a CAP will generally be developed. An evaluation of the CAP’s applicability to the
entity’s other Protection Systems including other locations helps identify similar problems, the
potential for Misoperation occurrences in other Protection Systems, common mode failure,
design problems, etc.
In rare cases, altering the Protection System to avoid a Misoperation recurrence may lower the
reliability or performance of the BES. In those cases, a statement documenting the reasons for
taking no corrective actions is essential for future reference and for justifying the absence of a
CAP.
Rationale for R6:  
Each CAP must accomplish all identified objectives to be complete. During the course of
implementing a CAP, updates may be necessary for a variety of reasons such as new
information, scheduling conflicts, or resource issues. Documenting changes or completion of
CAP activities provides measurable progress and confirmation of completion.

Page 39 of 39


File Typeapplication/octet-stream
File TitleNERC
File Modified0000-00-00
File Created0000-00-00

© 2024 OMB.report | Privacy Policy