1. PURPOSE. This circular is a reissuance of guidance on application procedures and project
management responsibilities for FTA’s Research Programs. This revision incorporates
provisions of the Moving Ahead for Progress in the 21st Century Act (MAP-21),
Pub. L. 112-141, July 6, 2012, and includes the most current available guidance as of the
date of publication. These requirements are intended to assist recipients in administering
FTA-funded projects and in meeting Federal assistance responsibilities and reporting
requirements. Recipients have a responsibility to comply with Federal statutory and
regulatory requirements and to be aware of all guidance and pertinent documents to assist
in the management of Federal assistance.
2. CANCELLATION. This circular, when final, will cancel FTA Circular 6100.1D, “Transit
Research and Technology Programs: Application Instructions and Program Management
Guidelines,” dated 5-1-2011.
3. AUTHORITY.
a. Federal Transit Laws, codified at 49 U.S.C. chapter 53.
b. 49 CFR 1.51.
4. WAIVER. FTA reserves the right to waive any provision of this circular to the extent
permitted by Federal law or regulation.
5. FEDERAL REGISTER NOTICE. In conjuction with publication of this circular, FTA
published a notice in the Federal Register on April 10, 2015, addressing comments
received during development of the circular.
6. AMENDMENTS TO THE CIRCULAR. FTA reserves the right to update this circular to
reflect changes in other revised or new guidance and regulatio ns that undergo notice and
comment without further notice and comment on this circular. FTA will post updates on
our website: http://www.fta.dot.gov. The website allows the public to register for
notification when FTA issues Federal Register notices or new guidance. Please visit the
website and click on “Connect with FTA” for more information.
Distribution:
FTA Headquarters Offices (T-W-2)
FTA Regional Offices (T-X-2)
OPI:
Office of Research,
Demonstration and
Innovation
Page 2
FTA C 6100.1E
7. ACCESSIBLE FORMATS. This document is available in accessible formats upon
request. To obtain paper copies of this circular as well as information regarding these
accessible formats, telephone FTA’s Administrative Services Help Desk, at 202-3664865. Individuals with hearing impairments may contact the Federal Relay Service at 800877-8339 for assistance with the call.
_______/S/ Orginial Signed By__________
Therese W. McMillan
Acting Administrator
FTA C 6100.1E
Page i
6100.1E RESEARCH, TECHNICAL ASSISTANCE, AND TRAINING PROGRAM
CIRCULAR
TABLE OF CONTENTS
CHAPTER
PAGE
I.
INTRODUCTION AND BACKGROUND ........................................... I–1
1. The Federal Transit Administration (FTA) ....................................... I–1
2. Authorizing Legislation .................................................................... I–1
3. How to Contact FTA Headquarters ................................................... I–1
4. How to Contact FTA Regional Offices ............................................. I–2
5. Grants.gov ......................................................................................... I–2
6. Definitions ......................................................................................... I–2
II.
PROGRAM OVERVIEW ..................................................................... II–1
1. Statutory Authority .......................................................................... II–1
2. Responsibilities of Project Management ......................................... II–2
3. Civil Rights Requirements ............................................................... II–5
4. Cross-Cutting Requirements ............................................................ II–9
III.
APPLICATION INSTRUCTIONS ...................................................... III–1
1. Overview ......................................................................................... III–1
2. Agreement Life Cycle ...................................................................... III–1
3. Application Process ......................................................................... III–2
4. System Registration Requirements .................................................. III–2
5. Proposal and Preapplication Guidelines .......................................... III–4
6. Formal Application Procedures ...................................................... III–6
7. Peer Review and Independent Evaluation ..................................... III–17
8. Complete Application ................................................................... III–17
9. Master Agreement.......................................................................... III–17
10. Awarding Instrument ..................................................................... III–18
11. Cost Share ..................................................................................... III–18
12. Project Approval ........................................................................... III–21
IV.
PROJECT ADMINISTRATION ..........................................................IV–1
1. Overview ..........................................................................................IV–1
2. Application Process .........................................................................IV–1
3. Project Identification .......................................................................IV–1
4. Reporting Requirements .................................................................IV–1
5. Prior Approvals ...............................................................................IV–8
6. Project Modifications ....................................................................IV–10
7. Equipment .....................................................................................IV–13
8. Intangible Property ........................................................................IV–17
9. Supplies .........................................................................................IV–19
Page ii
FTA C 6100.1E
CHAPTER
PAGE
10. Third Party Procurement ...............................................................IV–19
11. Project Closeout ............................................................................IV–20
12. Suspension ....................................................................................IV–21
13. Termination ...................................................................................IV–22
14. Retention and Access Requirements for Records .........................IV–23
V.
FINANCIAL MANAGEMENT ............................................................. V–1
1. General .............................................................................................. V–1
2. Internal Controls .............................................................................. V–1
3. Local Share ...................................................................................... V–5
4. General Principles for Determining Allowable Costs ..................... V–5
5. Indirect Costs ................................................................................... V–7
6. Program Income ............................................................................... V–9
7. Annual Audit .................................................................................. V–10
8. Payment Procedures ....................................................................... V–12
VI.
FTA OVERSIGHT ................................................................................VI–1
1. General ............................................................................................VI–1
2. Program Specific Reviews ..............................................................VI–1
3. Project Level Reviews ....................................................................VI–2
TABLES, GRAPHS, AND ILLUSTRATIONS
1. University Budget Example ............................................................ III–8
2. Sample Request for Advance or Reimbursement Form
(SF–270) ........................................................................................... C–3
3. Instructions for Completing Request for Advance or
Reimbursement Form (SF–270) ....................................................... C–4
APPENDICES
APPENDIX A.
INSTRUCTIONS FOR COMPLETING FEDERAL
FINANCIAL REPORT (FFR) .................................................... A–1
APPENDIX B.
COST ALLOCATION PLAN .................................................... B–1
APPENDIX C.
REQUEST FOR ADVANCE OR
REIMBURSEMENT .................................................................. C–1
APPENDIX D.
PREPARATION INSTRUCTIONS FOR FTA
FINAL REPORTS ...................................................................... D–1
INDEX
SUBJECT AND LOCATION IN CIRCULAR
FTA C 6100.1E
Page iii
This page intentionally left blank
FTA C 6100.1E
Page I–1
CHAPTER I
INTRODUCTION AND BACKGROUND
1.
THE FEDERAL TRANSIT ADMINISTRATION (FTA). The Federal Transit
Administration (FTA) is one of ten operating administrations within the U.S. Department
of Transportation (U.S. DOT), and is headed by an administrator appointed by the
president of the United States. The FTA functions through a headquarters office in
Washington, DC, ten regional offices, and five metropolitan offices. These offices assist
transit agencies in all fifty states, the District of Columbia, Puerto Rico, the U.S. Virgin
Islands, Guam, the Northern Mariana Islands, American Samoa, and federally recognized
Indian Tribes.
Public transportation means regular, continuing, shared-ride surface transportation services
that are open to the general public or open to a segment of the general public defined by
age, disability, or low income. Public transportation generally includes, but is not limited
to, transportation services provided by buses, heavy rail, light rail, commuter rail, fixed
guideway, bus rapid transit, passenger ferry boats, trolleys, inclined railways, people
movers, vans, streetcars, jitneys, and aerial tramways. Public transportation can be either
fixed-route or demand-response service, but excludes intercity passenger rail provided by
Amtrak, intercity bus service, charter bus service, school bus service, sightseeing service,
courtesy shuttle service for patrons of one or more specific establishments, and
intraterminal or intrafacility shuttle service.
The Federal Government, through FTA, provides financial assistance to develop new
transit systems and improve, maintain, and operate existing systems. FTA oversees
thousands of grants to hundreds of state and local transit providers, primarily through its
ten regional offices. These recipients are responsible for managing their programs in
accordance with Federal requirements, and FTA is responsible for ensuring that recipients
follow Federal statutory and administrative requirements.
2. AUTHORIZING LEGISLATION. Most Federal transit laws are codified at Title 49,
United States Code, chapter 53 (49 U.S.C. chapter 53). Authorizing legislation is
substantive legislation enacted by Congress that establishes or continues the legal operation
of a Federal program or agency. FTA’s most recent authorizing legislation is the Moving
Ahead for Progress in the 21st Century Act (MAP-21), Pub. L. 112-141, signed into law on
July 6, 2012, and effective on October 1, 2012. This circular reflects changes to Federal
transit law as well as changes required by other laws that have become effective since the
circular was last published on May 1, 2011.
3. HOW TO CONTACT FTA HEADQUARTERS. Visit FTA’s website,
http://www.fta.dot.gov, or contact FTA headquarters at the following address and phone
number:
Page I–2
FTA C 6100.1E
Federal Transit Administration
Office of Communication and Congressional Affairs
1200 New Jersey Avenue, SE
East Building
Washington, DC 20590
Phone: 202-366-4043
Fax: 202-366-3472
4. HOW TO CONTACT FTA REGIONAL OFFICES. FTA regional and metropolitan offices
work with local transit officials in developing and processing Federal assistance (grant and
cooperative agreement) applications. Major metropolitan areas have additional support
located in those cities. General program information and policy is set at the FTA
headquarters in Washington, DC. A complete list of FTA regional and metropolitan offices
can be found by visiting FTA’s website, http://www.fta.dot.gov, or by using your internet
search tool if a website should be changed.
5. GRANTS.GOV. FTA posts all competitive grant and cooperative agreement opportunities
on Grants.gov. Grants.gov is the one website for information on all discretionary Federal
assistance opportunities to pursue Federal grants and cooperative agreements. Grants.gov
was established as a governmental resource named the E-Grants Initiative, part of the
president’s 2002 fiscal year management agenda to improve government services to the
public. The concept has its origins in the Federal Financial Assistance Management
Improvement Act of 1999, also known as Public Law 106-107. Grants.gov assists the
Federal financial assistance community with delivery, management, coordination, and
accountability of Federal grants and cooperative agreements. Today, Grants.gov is a central
storehouse for information on over 1,000 Federal assistance programs and provides access
to approximately $500 billion in annual awards. More information about Grants.gov is
available at http://www.grants.gov.
6. DEFINITIONS. All definitions in 49 U.S.C. 5302 apply to this circular as well as the
following definitions:
a.
Accrual Basis of Accounting. The accounting method in which income is recognized
when earned instead of when received and expenses are recognized when incurred
instead of when paid.
b.
Acquisition Cost of Project Property. The purchase price of property. This is the net
invoice unit price, including the cost of modifications, attachments, accessories, or
auxiliary apparatus necessary to make the equipment usable for the intended purpose.
Other charges such as the cost of inspection, installation, transportation, taxes, duty, or
protective in-transit insurance should be treated, in accordance with the recipient’s
regular accounting practices, as separate line items. The cost of items separately
FTA C 6100.1E
Page I–3
installed and removable from rolling stock, such as fare boxes and radios, is treated as a
separate acquisition and not as part of the cost of the vehicle.
c.
Activity Line Item (ALI). The description and dollar amount contained in the budget
for an approved project activity associated within a particular scope approved as part of
a cooperative agreement, grant agreement, or other agreement. ALIs under each scope
are informational and are used as tools for FTA and the recipient to manage the
agreement.
d.
Administering Office. The headquarters, regional, or metropolitan office responsible
for the award and administration of an FTA or FTA-assisted project covered by this
circular.
e.
Administrative Amendment. A minor change in a cooperative agreement, grant
agreement, or other agreement normally initiated by FTA to modify or clarify certain
terms, conditions, or provisions of a project.
f.
Agreement. Includes a cooperative agreement, grant agreement, or other agreement.
g.
Applicant. In this circular, the term “applicant” is used to identify an entity that is
seeking, but has not yet been awarded, specific Federal assistance directly from FTA.
h.
Budget Revision. Any change within the scope of the project that has an impact on the
budget allocations of the original project. A budget revision may be a transfer of
Federal assistance within a project scope or between existing activity line items (ALIs)
within an approved project. It could also include the addition or deletion of an ALI.
i.
Cash Basis of Accounting. Cash basis of accounting is the method in which revenue is
recorded when received, rather than when earned, and expenses are recorded when
paid, rather than incurred. FTA does not permit the Federal financial report (FFR) to be
prepared in the cash method of accounting.
j.
Catalog of Federal Domestic Assistance (CFDA). The Catalog of Federal Domestic
Assistance is a governmentwide compendium of Federal programs, projects, services,
and activities that provide assistance or benefits to the American public. It contains
financial and nonfinancial assistance programs administered by departments and
agencies of the Federal Government. As the basic reference source of Federal
programs, the primary purpose of CFDA is to assist users in identifying programs that
meet specific objectives of the potential applicant and to obtain general information on
Federal assistance programs. In addition, the intent of CFDA is to improve coordination
and communication between the Federal Government and state and local governments.
The CFDA number assigned to each program is used to report and track audit findings
related to federally assisted projects.
Page I–4
FTA C 6100.1E
k.
Common Rules. The current common rule is U.S. DOT regulations, “Uniform
Administrative Requirements, Cost Principles, and Audit Requirements for Federal
Awards,” 2 CFR part 1201 which incorporates by reference U.S. OMB “Uniform
Administrative Requirements, Cost Principles, and Audit Requirements for Federal
Awards,” 2 CFR part 200, applies to Awards and Amendments made on or after
December 26, 2014, to any Award. The previous common rules, U.S. DOT’s Uniform
Administrative Requirements, former 49 CFR parts 18 or 19, and Federal Cost
Principles, former 2 CFR part 220, 225, or 230, apply to Awards and Amendments to
any Award made before December 26, 2014.
l.
Cooperative Agreement. An award of Federal assistance in the form of money, or
property in lieu of money, to a recipient in which the Federal Government anticipates a
substantial role, as set forth in 31 U.S.C. 6305. At a minimum, FTA’s role includes the
right to participate in decisions to redirect and reprioritize project activities, goals, and
deliverables. For this circular, the term “Federal assistance” is inclusive of cooperative
agreements and grant agreements unless specified otherwise.
m.
Cost of Project Property. The purchase price of project property. This is the net invoice
unit price, including the cost of modifications, attachments, accessories, or auxiliary
apparatus necessary to make the property usable for the intended purpose. Other
charges such as the cost of inspection, installation, transportation, taxes, duty, or intransit insurance should be treated in accordance with the recipient’s regular accounting
practices, in the same line items or separate line items. The cost of items separately
installed and removable from rolling stock, such as fare boxes and radios, is treated as a
separate acquisition and not as part of the cost of the vehicle if not included in the
procurement of rolling stock.
n.
Depreciation. Method used to calculate the reduction in value of an item of personal or
real property over time. Depreciation is the term most often used to indicate that
personal property has declined in service potential. For the purpose of this circular, it is
also a method of determining fair market value when disposing of an asset prior to the
end of its useful life.
o.
Discretionary Funding. Federal assistance distributed at the discretion of the agency as
distinct from formula funding.
p.
Delphi eInvoicing System. eInvoicing is a Department of Transportation (DOT)Webbased application system that processes payment requests from FTA cooperative
agreement recipients.
q.
Electronic Clearing House Operation (ECHO) System. ECHO is an FTA Web-based
application system that processes payment requests from FTA grant recipients.
FTA C 6100.1E
Page I–5
r.
Electronic Award and Management System. A system that applicants, recipients, and
FTA use to manage Federal assistance applications, including the review, approval, and
management of all grants. Applicants use this system to submit financial status reports
and milestone progress reports and to submit requests for modifications to their grant or
Cooperative Agreement modification requests; this term includes FTA’s Transportation
Electronic Award and Management System (TEAM) and its successor.
s.
Equipment. An article of nonexpendable, tangible personal property having a useful life
of more than one year and an acquisition cost that equals or exceeds the lesser of the
capitalization level established by the governmental unit for financial statement
purposes, or $5,000. Equipment includes rolling stock and all other such property used
in the provision of public transit service.
t.
Equipment Inventory. A physical inventory of personal property (other than real
property) taken with the results reconciled with the recipient’s personal property
records.
u.
Excess Property. Property that the recipient determines is no longer required for its
public transportation needs or fulfillment of its responsibilities that has not met its
useful life under an FTA-assisted project.
v.
Fair Market Value. The most probable price equipment or real property would bring in
a competitive and open market.
w.
Federal Assistance. Refers to the transfer of money, property, services, or anything of
value by the Federal Government, the principal purpose of which is to accomplish a
public purpose of support or stimulation authorized by Federal law. Federal assistance
includes Federal financial assistance or other benefits for a governmental or
nongovernmental entity other than a department or agency of the Federal Government.
For FTA’s research programs, Federal assistance is most frequently awarded through
cooperative agreements, and less often through grant agreements, other agreements,
other transactions, or subagreements. A financial assistance instrument may also fund
more than one project or a portion of a project.
x.
Grant. An award of Federal assistance in the form of money, or property in lieu of
money, to an eligible recipient in which the Federal Government does not anticipates a
substantial role, as set forth in 31 U.S.C. 6304. Used interchangeably with Grant
Agreement.
y.
Grantee. Grantee means a recipient to which FTA awards a Grant directly to support a
specific project in which FTA does not take an active role or retain substantial control,
as set forth in 31 U.S.C. 6302 and 6304. In this circular FTA uses the term “grantee”
interchangeably with “grant recipient,” and “direct recipient.”
z.
Grant Period. See “Period of Performance.”
Page I–6
FTA C 6100.1E
aa.
Grant Scope. See “Scope of the Project.”
bb.
Incidental Use of Project Property and Equipment. The authorized use of real property
and equipment acquired with FTA assistance for purposes of transit service but which
also has limited nontransit use due to transit operating circumstances. Such use must be
compatible with the approved purposes of the project and not interfere with intended
public transportation uses of project assets.
cc.
Key Person. The recipient’s principal investigator or project manager of a research
project and anyone identified in the project award as key personnel. Changes in key
persons specified in the application, cooperative agreement, grant agreement, or other
agreement must receive prior approval.
dd.
Master Agreement. The official FTA document containing FTA and other cross-cutting
Federal requirements applicable to the FTA recipient and its project(s). The Master
Agreement is incorporated by reference and made part of each FTA cooperative
agreement, grant agreement, or other agreement, and amendment thereto.
ee.
National Environmental Policy Act (NEPA). The National Environmental Policy Act
(NEPA), signed into law on January 1, 1970, 42 U.S.C. 4321–4370d, declares a
national policy to safeguard the environment and created the Council on Environmental
Quality in the Executive Office of the President. To implement the national
environmental policy, NEPA requires that environmental factors such as noise, air,
vibration, groundwater, habitat, wildlife, and historic resources be considered when
Federal agencies make decisions and that a detailed statement of environmental impacts
be prepared for all major Federal actions significantly affecting the quality of the
human environment.
ff.
Net Present Value. The discounted monetized value of expected net benefits (i.e.,
benefits minus costs). It is calculated by assigning monetary values to benefits and
costs, discounting future benefits and costs using an appropriate discount rate to obtain
a present value, and subtracting the sum total of discounted costs from the sum total of
discounted benefits.
gg.
Net Proceeds from the Sale of Project Equipment and Real Property. The amount
realized from the sale of property no longer needed for transit purposes minus the
expense of any actual and reasonable selling and any other necessary expenses
associated with repairs to make saleable.
hh.
Period of Performance. The period established in the award document during which
Federal sponsorship begins and ends.
FTA C 6100.1E
Page I–7
ii.
Principal Investigator. The principal investigator or project manager is the individual
representing the recipient responsible for controlling the technical direction and quality
of the project and ensuring that the project is carried out in compliance with all
pertinent laws, regulations, policies, and award terms.
jj.
Prior Approval. Means prior written or electronic approval from an authorized FTA
official. Prior approval can take the form of FTA’s acceptance of the proposal and/or
proposal budget and subsequent incorporation into the award, or written or electronic
approval of a separate request submitted by the recipient.
kk.
Program Income. Gross income received by the recipient or subrecipient directly
produced by a project supported activity or earned only as a result of the federally
assisted project during the project period (the time between the effective date of the
Federal assistance award and the ending date of the project supported by that award
reflected in the final financial report).
ll.
Project Amendment. The modification of a project that includes a change in scope
and/or change in amount of Federal assistance.
mm. Project. For the purposes of the FTA program, public transportation research activities
with a specific goal financed under one or more Federal assistance agreements, such as
a cooperative agreement, grant agreement, or other agreement. An agreement may also
finance more than one project or a portion of a project.
nn.
Project Manager. See Principal Investigator.
oo.
Project Property. Includes rolling stock and other equipment, real property, and
supplies.
pp.
Project Scope. See “Scope of the Project.”
qq.
Public Transportation. The term “public transportation” means regular, continuing
shared-ride surface transportation services that are open to the general public or open to
a segment of the general public defined by age, disability, or low income; and does not
include: intercity passenger rail transportation provided by the entity described in
49 U.S.C. chapter 243 (AMTRAK or a successor to such entity), intercity bus service,
charter bus service, school bus service, sightseeing service, courtesy shuttle service for
patrons of one or more specific establishments, or intraterminal or intrafacility shuttle
services.
rr.
Real Property. Land, including affixed land improvements, structures, and
appurtenances. Real property does not include movable machinery and equipment.
Page I–8
FTA C 6100.1E
ss.
Recipient. Recipient means an entity that receives funds from FTA to carry-out an
activity under a federal program. For purpose of this circular, a recipient can be a
recipient of federal assistance through a cooperative agreement, grant recipient,
grantee, or a direct recipient. The term recipient does not include subrecipient.
tt.
Remaining Federal Interest for Dispositions before the End of Useful Life. The amount
calculated by multiplying the current fair market value or proceeds from a sale by
FTA’s Federal interest in the property. Fair market value is the greater of the
unamortized value of the remaining service life based on straight line depreciation of
the original purchase price of the property or the Federal share of the sales proceeds.
uu.
Research and Development. Research and development includes all research activities,
both basic and applied, and all development activities that are supported at universities,
colleges, other nonprofit institutions, for-profit, and governmental entities. “Research”
is defined as a systematic study directed toward fuller scientific knowledge or
understanding of the subject studied. “Development” is the systematic use of
knowledge and understanding gained from research directed toward the production of
useful materials, devices, systems or methods, including design and development of
prototypes and processes. The term research also includes activities involving the
training of individuals in research techniques where such activities utilize the same
facilities as other research and development activities and where such activities are not
included in the instruction function.
vv.
Sales Proceeds. Sales proceeds are the net proceeds resulting from the disposition of
excess real property or equipment that was purchased in whole or in part with Federal
assistance provided by FTA.
ww. Scope of the Project. The broad purpose of a specific project supported by the
cooperative agreement, grant Agreement, or other agreement. There may be multiple
scopes identifying each of the different activities within a cooperative agreement, grant
agreement, or other agreement and each scope may contain a number of activities or
tasks that represent the estimate of actions needed to complete the project. FTA
reserves the right to consider other information in determining the “scope of the
project” when that term is used for legal purposes. See the Master Agreement, supra.
xx.
Straight Line Depreciation. In the absence of fair market value or when FTA
determines that the use of the fair market value is inappropriate, the straight line
depreciation method is used to determine the remaining useful life of property. This
method is considered as a function of time instead of a function of usage. This method
is widely used in practice because of its simplicity. It basically assumes that the asset’s
economic usefulness is the same each year.
yy.
Subrecipient. An entity that receives FTA assistance through a pass-through agreement
with a direct recipient or designated recipient, whereby the original recipient remains
FTA C 6100.1E
Page I–9
responsible for compliance with all terms, conditions, and requirements associated with
the cooperative agreement, grant agreement, or other agreement.
zz.
Supplies. All tangible personal property other than equipment with a unit value of less
than $5,000.
aaa. Unliquidated Obligations. A recipient’s funding commitments that have been incurred,
but for which outlays have not yet been recorded because goods and services have not
been received. Unliquidated obligations should be accounted for on Lines I and J of the
Federal financial report (FFR).
FTA C 6100.1E
Page II–1
CHAPTER II
PROGRAM OVERVIEW
1.
STATUTORY AUTHORITY. The Federal Transit Administration’s (FTA) Research,
Development, Demonstration, Deployment, Cooperative Research, Technical Assistance,
Standards Development, and Human Resources and Training programs are generally
authorized at 49 U.S.C. 5312, 5313, 5314, and 5322, although other research programs
with national implications have been and can be authorized under other Federal laws. The
code assigned to the FTA research program in the Catalog of Federal Domestic Assistance
(CFDA) is 20.514.
Section 5312 has been amended extensively to group various research and development
activities into separate categories.
In broad terms, Section 5312(a) authorizes the Secretary of Transportation to make grants
and enter into contracts, cooperative agreements, and other agreements for research,
development, demonstration, and deployment projects and evaluation of research and
technology of national significance to public transportation, and that the Secretary
determines will improve public transportation.
Section 5312(b) focuses on public transportation research projects with the goal of
developing and deploying new and innovative ideas, practices, and approaches.
Section 5312(c) authorizes public transportation innovation and development projects
seeking to improve public transportation systems nationwide by providing more efficient
and effective delivery of public transportation services, including through technology and
technological capacity improvements.
Section 5312(d)(1) – (4) establishes a program to promote the early deployment and
demonstration of innovation in public transportation that has broad applicability.
Section 5312(d)(1)(5) establishes a program within FTA’s research program to support low
or no emission vehicle deployment.
Depending on the statutory section under which a project is undertaken, Section 5312
authorizes the Secretary to make grants to and enter into contracts, cooperative agreements,
and other agreements with departments, agencies, and instrumentalities of the government,
including Federal laboratories; state and local governmental entities; providers of public
transportation; private or nonprofit organizations; institutions of higher education; and
technical and community colleges.
Section 5313 authorizes the Secretary to make grants to, and cooperative agreements with,
the National Academy of Sciences to carry out a public transportation cooperative research
program.
Page II–2
FTA C 6100.1E
Section 5314(a) authorizes the Secretary to assist in the development of voluntary and
consensus-based standards and best practices by the public transportation industry.
Support for compliance with Americans with Disabilities act of 1990 (ADA) (42 U.S.C.
12101 et seq.) is codified in Section 5314(b), which authorizes the Secretary to make grants
and enter into contracts, cooperative agreements, and other agreements to provide public
transportation-related technical assistance to comply with the ADA; comply with human
services transportation coordination requirements and enhance the coordination of related
Federal resources; meet the transportation needs of elderly individuals; assist market-based
development around transit stations; address transportation equity for low-income and
minority individuals; and any other technical assistance activity that the Secretary
determines is necessary to advance the interests of public transportatio n.
Section 5322(a) authorizes the Secretary to undertake, or make grants and contracts for,
programs that address human resource needs as they apply to public transportation
activities including employment training, outreach to minority and female candidates,
research on public transportation personnel and training needs, and training and assistance
for minority business opportunities.
Section 5322(b) directs the Secretary to establish an innovative public transportation
workforce development program to assist the development of innovative activities in these
areas.
In addition, Section 5322(d) directs the Secretary to establish a national transit institute and
award grants to a public four-year degree-granting institution of higher education to
develop and conduct training and educational programs for Federal, state, and local
transportation employees, United States citizens, and foreign nationals engaged or to be
engaged in government aid public transportation work.
2. RESPONSIBILITIES OF PROJECT MANAGEMENT. Recipients are responsible for the
day-to-day management of their federally assisted projects and of project-supported
activities. FTA monitors federally assisted projects and project-supported activities to
confirm that recipients establish and follow procedures that comply with Federal
requirements. Chapter III of this circular describes application procedures under the FTA
research program. Chapter IV of this circular describes the mechanics and requirements for
project administration. Chapter V describes the requirements for financial management.
a. Recipient’s Role. Recipients must monitor federally supported projects and activities to
ensure compliance with Federal requirements. This includes the administration and
management of the project in compliance with the Federal law; Federal regulations;
their cooperative agreement, grant agreement, or other agreement; and in accordance
with applicable FTA circulars. The recipient is also responsible for Federal assistance
that “passes through” to a subrecipient. In general, submission of the recipient’s annual
certifications and assurances stands in lieu of detailed FTA oversight before approval of
a federally assisted project; however, the results of ongoing or routine FTA oversight
activities also will be considered as applicable. Annual independent organization-wide
FTA C 6100.1E
Page II–3
audits (A-133 audits), audits of recipients, and other recurring and specialized reviews
give FTA an opportunity to verify the recipient’s annual certifications and assurances.
The recipient’s responsibilities include, but are not limited to, actions that:
(1) Demonstrate legal, financial, and technical capacity to carry out the project,
including safety and security aspects of the project.
(2) Provide administrative and management support of project implementation.
(3) Provide, directly or by contract, adequate technical inspection and supervision by
qualified professionals of all work in progress.
(4) Ensure conformity with cooperative agreements, grant agreements, or other
agreements, applicable laws, regulations, codes, ordinances, and safety standards.
(5) Maintain the project work schedule agreed to by FTA and the recipient, and
monitor project activities to assure that schedules are met and other performance
goals are achieved.
(6) Keep expenditures within the latest approved project budget.
(7) Ensure compliance with FTA requirements by subrecipients, agencies, consultants,
contractors, and subcontractors working under approved subagreements, thirdparty contracts, or interagency agreements.
(8) Request and withdraw Federal assistance for eligible activities only in amounts
and when needed to make payments for project costs that are due and payable
within three business days and retain receipts to substantiate withdrawals.
(9) Account for project property and maintain property inventory records that contain
all the elements required.
(10) Demonstrate and retain satisfactory continuing control over the use of project
property.
(11) Demonstrate procedures for asset management and adequate maintenance of
equipment and facilities.
(12) Ensure that an annual independent organization-wide audit is conducted in
accordance with the Office of Management and Budget (OMB) Circular A–133,
“Audits of States, Local Governments, and Non-Profit Organizations.”
(13) Prepare cost allocation plans (CAPs) or indirect cost proposals and submit and
obtain approval if applicable before incurring costs.
(14) Prepare and submit FTA required reports (see Chapter IV, Section 4, “Reporting
Requirements,” of this circular).
Page II–4
FTA C 6100.1E
(15) Update and retain FTA required reports and records for availability during audits
or oversight reviews.
(16) Ensure that effective control and accountability is maintained for all projects and
subrecipient projects, cash, real and personal property, and other assets. Recipients
and subrecipients must ensure that resources are properly used and safeguarded,
and that they are used solely for authorized purposes.
(17) Obtain all necessary prior approvals and/or waivers before incurring costs or
taking the requested action.
b. Headquarters’ Role. FTA headquarters in Washington, DC, serves a broad, programlevel role in the administration of the programs. FTA headquarters:
(1) Provides overall policy and is primarily responsible for policy and program
guidance for all FTA programs, and ensures that programs are consistent with the
law.
(2) Ensures consistent administration of programs by the administering office.
(3) Develops and implements financial management procedures.
(4) Initiates and manages program support activities, such as training, courses,
regional consistency, and oversight reviews.
(5) Conducts national program reviews and evaluations.
(6) Carries out responsibility for national compliance with program requirements.
(7) Develops national standard operating practices.
c. Administering Office Role. FTA headquarters, regional, and metropolitan offices are
responsible for the day-to-day administration or oversight of projects and programs.
Depending on the office administering the project, responsibilities include, but are not
limited to, actions that:
(1) Review and approve Federal assistance applications, project amendments, and
budget revisions, as necessary.
(2) Obligate and deobligate Federal assistance.
(3) Work with recipients to implement and manage the programs and projects and
ensure recipient compliance.
(4) Provide technical assistance.
FTA C 6100.1E
Page II–5
(5) Review milestone progress reports (MPRs) including quarterly narrative reports
and Federal financial reports (FFRs) as well as monitor and close grants.
(6) Conduct reviews as necessary.
(7) In the case of cooperative agreements, provide substantial involvement in project
activities or at a minimum the right to redirect project activities.
3. CIVIL RIGHTS REQUIREMENTS. The recipient agrees to comply with all applicable
civil rights laws and implementing regulations including, but not limited to, the following:
a. Nondiscrimination in Federal Public Transportation Programs. The recipient agrees to
comply, and assures the compliance of each third-party contractor at any tier and each
subrecipient at any tier under the project, with the provisions of 49 U.S.C. 5332. These
provisions prohibit discrimination on the basis of race, color, religion, national origin,
sex, disability, or age, and prohibit discrimination in employment or business
opportunity.
b. Nondiscrimination on the Basis of Disability. The recipient agrees to comply, and assures
the compliance of each third-party contractor and each subrecipient at any tier of the
project, with the applicable laws and regulations, discussed below, for nondiscrimination
on the basis of disability.
(1) Section 504 of the Rehabilitation Act of 1973, as amended (29 U.S.C. 794), prohibits
discrimination on the basis of disability by recipients of Federal financial assistance.
(2) The ADA, as amended (42 U.S.C. 12101 et seq.), prohibits discrimination against
qualified individuals with disabilities in all programs, activities, and services of
public entities, as well as imposes specific requirements on public and private
providers of public transportation.
(3) U.S. DOT regulations implementing Section 504 and the ADA include 49 CFR
parts 27, 37, 38, and 39. Among other provisions, the regulations specify accessibility
requirements for the design and construction of new transportation facilities and
vehicles; require that vehicles acquired (with limited exceptions) be accessible to and
usable by individuals with disabilities, including individuals using wheelchairs;
require public entities (including private entities “standing in the shoes” of a public
entity as a subrecipient or under a contract or other arrangement) providing fixedroute service to provide complementary paratransit service to individuals with
disabilities who cannot use the fixed-route service; and include service requirements
intended to ensure that individuals with disabilities are afforded equal opportunity to
use transportation systems.
(4) Providers of fixed-route service must generally utilize accessible vehicles. Private
entities may utilize nonaccessible vehicles if they can provide equivalent service in
terms of schedules and headways, in addition to the equivalent service requirements
described above for demand responsive service. Public entities must also provide
Page II–6
FTA C 6100.1E
complementary paratransit service to fixed-route service as defined in 49 CFR
37.121.
(5) Providers of demand responsive service must utilize accessible vehicles, as defined at
49 CFR 37.7, or meet the applicable equivalent service standard. For private and
public entities, the service must be equivalent in regards to schedules, response times,
geographic areas of service, hours and days of service, availability of informatio n,
reservations capability, constraints on capacity or service availability, and restrictions
based on trip purpose.
(6) In addition, Recipients of any FTA assistance should be aware that they also have
responsibilities under Titles I, II, III, IV, and V of the ADA in the areas of
employment, public services, public accommodations, telecommunications, and other
provisions, many of which are subject to regulations issued by other Federal agencies.
c. Nondiscrimination—Title VI. The recipient agrees to comply, and assures the compliance
of each third-party contractor at any tier and each subrecipient at any tier of the project,
with all of the following requirements under Title VI of the Civil Rights Act of 1964:
(1) Title VI of the Civil Rights Act of 1964, as amended (42 U.S.C. 2000d et seq.),
provides that no person in the United States must, on the grounds of race, color, or
national origin, be excluded from participation in, be denied the benefits of, or be
subjected to discrimination under any program or activity receiving Federal financial
assistance;
(2) U.S. DOT regulations, “Nondiscrimination in Federally-Assisted Programs of the
Department of Transportation—Effectuation of Title VI of the Civil Rights Act of
1964,” 49 CFR part 21;
(3) FTA Circular 4702.1B “Title VI Requirements and Guidelines for Federal Transit
Administration Recipients”. This document provides FTA recipients and
subrecipients with guidance and instructions necessary to carry out U.S. DOT Title
VI regulations (49 CFR part 21), U.S. DOT’s Order 5610.2 on Environmental Justice
(62 FR 18377, Apr. 15, 1997), and U.S. DOT Policy Guidance Concerning
Recipient’s Responsibilities to Limited English Proficient (LEP) Persons (70 FR
74087, Dec. 14, 2005);
(4) U.S. DOT Policy Guidance Concerning Recipients’ Responsibilities to Limited
English Proficient (LEP) Persons (December 14, 2005). This Executive Order 13166
guidance clarifies the responsibilities of recipients of Federal financial assistance
from U.S. DOT and assists them in fulfilling their responsibilities to LEP persons,
pursuant to Title VI of the Civil Rights Act of 1964 and Executive Order 13166.
(5) FTA Circular 4703.1 “Environmental Justice Policy Guidance for Federal Transit
Administration Recipients.” This document provides FTA recipients and
subrecipients with guidance and instructions necessary to carry out U.S. DOT Order
FTA C 6100.1E
Page II–7
5610.2 to Address Environmental Justice in Minority Populations and Low-Income
Populations, and Executive Order 12898 on Environmental Justice that describes the
process that the office of the Secretary of Transportation and each operating
administration will use to incorporate environmental justice principles into existing
programs, policies, and activities.
(6) U.S. DOT Order to Address Environmental Justice in Minority Populations and LowIncome Populations. U.S. DOT Order 5610.2 describes the process that the office of
the Secretary of Transportation and each operating administration will use to
incorporate environmental justice principles (as embodied in Executive Order 12898
on environmental justice) into existing programs, policies, and activities.
d. Equal Employment Opportunity. The recipient agrees to comply, and assures the
compliance of each third-party contractor and each subrecipient at any tier of the project,
with all equal employment opportunity (EEO) requirements of Title VII of the Civil
Rights Act of 1964, as amended, (42 U.S.C. 2000e), and with 49 U.S.C. 5332 and any
implementing regulations U.S. DOT may issue.
e. Nondiscrimination on the Basis of Sex. The recipient agrees to comply with all applicable
requirements of Title IX of the Education Amendments of 1972, as amended (20 U.S.C.
1681 et seq.), with U.S. DOT implementing regulations, “Nondiscrimination on the Basis
of Sex in Education Programs or Activities Receiving Federal Financial Assistance,”
49 CFR part 25.
f.
Nondiscrimination on the Basis of Age. The recipient agrees to comply with all
applicable requirements of the Age Discrimination Act of 1975, as amended (42 U.S.C.
6101 et seq.), and Department of Health and Human Services (DHHS) is implementing
regulations, “Nondiscrimination on the Basis of Age in Programs or Activities Receiving
Federal Financial Assistance,” (45 CFR part 90), which prohibit discrimination against
individuals on the basis of age. In addition, the recipient agrees to comply with all
applicable requirements of the Age Discrimination in Employment Act (ADEA),
29 U.S.C. 621 through 634, and Equal Employment Opportunity Commission (EEOC)
implementing regulations, “Age Discrimination in Employment Act” (29 CFR part
1625), which prohibit employment discrimination against individuals on the basis of age.
g. Nondiscrimination on the Basis of Disability. The recipient agrees to comply, and assures
the compliance of each third-party contractor and each subrecipient at any tier of the
project, with the applicable laws and regulations, discussed below, for nondiscrimination
on the basis of disability.
(1) Section 504 of the Rehabilitation Act of 1973 (Section 504), as amended (29 U.S.C.
794), prohibits discrimination on the basis of disability by recipients of Federal
assistance.
(2) The Americans with Disabilities Act of 1990 (ADA), as amended (42 U.S.C. 12101
et seq.), prohibits discrimination against qualified individuals with disabilities in all
Page II–8
FTA C 6100.1E
programs, activities, and services of public entities as well as imposes specific
requirements on public and private providers of transportation.
(3) U.S. DOT regulations implementing Section 504 and the ADA include 49 CFR
parts 27, 37, 38, and 39. Among other provisions, the regulations specify accessibility
requirements for the design and construction of new transportation facilities and
vehicles; require that vehicles acquired (with limited exceptions) be accessible to and
usable by individuals with disabilities, including individuals using wheelchairs;
require public entities (including private entities “standing in the shoes” of a public
entity as a subrecipient or under a contract or other arrangement) providing fixedroute service to provide complementary paratransit service to individuals with
disabilities who cannot use the fixed-route service; and include service requirements
intended to ensure that individuals with disabilities are afforded equal opportunity to
use transportation systems.
(4) In addition, recipients of any FTA assistance should be aware that they also have
responsibilities under Titles I, II, III, IV, and V of the ADA in the areas of
employment, public services, public accommodations, telecommunications, and other
provisions, many of which are subject to regulations issued by other Federal agencies.
h. Disadvantaged Business Enterprise (DBE). To the extent required by Federal law,
regulation, or directive, the recipient agrees to take the following measures to facilitate
participation by DBEs:
(1) The recipient agrees and assures that it will comply with MAP-21 Section 1101(b)
23 U.S.C. 101, which directs the Secretary of Transportation to expend not less than
10 percent of authorized Federal funds with DBEs. This 10 percent national goal is
aspirational and is used by the U.S. DOT to help monitor and evaluate DBE
participation in U.S. DOT-assisted contracting opportunities.
(2) The recipient agrees and assures that it will comply with U.S. DOT regulation,
“Participation by Disadvantaged Business Enterprises in Department of
Transportation Financial Assistance Programs,” 49 CFR part 26. Among other
provisions, this regulation requires certain recipients of U.S. DOT Federal assistance,
namely state and local transportation agencies, to establish goals for the participation
of disadvantaged entrepreneurs and certify the eligib ility of DBE firms to participate
in their U.S. DOT-assisted contracts.
(3) The recipient agrees and assures that it must not discriminate on the basis of race,
color, sex, or national origin, in the award and performance of any third-party
contract, or subagreement supported with Federal assistance derived from U.S. DOT,
or in the administration of its DBE program, and will comply with the requirements
of 49 CFR part 26. The recipient agrees to take all necessary and reasonable steps set
forth in 49 CFR part 26 to ensure nondiscrimination in the award and administration
of all third party contracts and subagreements supported with Federal assistance
derived from U.S. DOT. As required by 49 CFR part 26 and approved by U.S. DOT,
FTA C 6100.1E
Page II–9
the recipient’s DBE program is incorporated by reference and made part of the
cooperative agreement, grant agreement, or other agreement. The recipient agrees that
implementation of this DBE program is a legal obligation, and that failure to carry out
its terms must be treated as a violation of the cooperative agreement, grant agreement,
or other agreement. Upon notification by U.S. DOT to the recipient of a failure to
implement its approved DBE program, U.S. DOT may impose sanctions as provided
for under 49 CFR part 26 and may, in appropriate cases, refer the matter for
enforcement under 18 U.S.C. 1001, and/or the Program Fraud Civil Remedies Act,
(31 U.S.C. 3801 et seq.).
For further guidance, refer to the Federal laws, regulations, and executive orders cited
in this chapter. FTA’s regional civil rights officers or headquarters civil rights staff
will also provide current guidance upon request.
4. CROSS-CUTTING REQUIREMENTS. The recipient understands and agrees that it must
comply with all applicable Federal laws, regulations, and directives, except to the extent
that FTA determines otherwise in writing. Refer to FTA’s Master Agreement for a list of
applicable laws, regulations, and directives. FTA updates the Master Agreement annually.
FTA C 6100.1E
Page III–1
CHAPTER III
APPLICATION INSTRUCTIONS
1. OVERVIEW. This chapter discusses the requirements and provides guidance for applying
for Federal Transit Administration (FTA) assistance to fund cooperative agreements, grant
agreements, or other agreements (Agreements). Project management requirements are
described in Chapter IV. Financial management requirements are described in Chapter V.
2. AGREEMENT LIFE CYCLE. The life cycle for a Federal assistance awarded under this
circular is:
a. The applicant creates its application for Federal assistance,
b. FTA assigns a project number,
c. The applicant submits its application,
d.
FTA obtains the necessary concurrences and approvals,
e. FTA reserves Federal assistance for the agreement,
f.
The Federal assistance is awarded through a cooperative agreement, grant agreement,
or other agreement,;
g. The recipient executes the agreement,
h. The recipient and FTA implement, manage, and oversee projects and activities
supported by the agreement,
i.
The period of performance is completed,
j.
The recipient delivers the final report, independent evaluation, and other products due
FTA as described in the agreement,
k. The recipient disposes of any excess equipment and property acquired with Federal
assistance, with FTA approval if needed,
l.
The final Federal financial report, budget revision, and actual milestones accomplished
are recorded in FTA’s electronic award and management system and approved by FTA,
and
m. FTA closes the Project.
Page III–2
FTA C 6100.1E
3. APPLICATION PROCESS. FTA provides a streamlined electronic interface between
applicants and FTA that allows complete electronic application submission, review,
approval, and management of all federally assisted projects. Among other things, FTA’s
electronic award and management system permits applicants to apply for Federal assistance
for their projects and project activities, inquire about the status of their applications or
projects after FTA awards funding for them, file the required financial status and milestone
progress reports, and submit annual certifications and assurances.
FTA’s enabling legislation requires certain awards to be made through a competitive bid
process or a competitive program. FTA submits competitive opportunities for Federal
assistance for publication on Grants.gov and/or Federal Register under CFDA number
20.514. Each posting provides information on the types of projects solicited, as well as
instructions. If the project is selected for further consideration, FTA may require a preapplication proposal and a formal application in FTA’s current electronic award and
management system. FTA will advise applicants if their proposed project is not being
considered for funding.
FTA staff notifies recipients by phone and/or email of project approval. Applicants also can
check the status of their applications in FTA’s current electronic award and management
system to determine when Federal assistance has been awarded. The cooperative
agreement, grant agreement, or other agreement includes the “FTA Award” which, among
other things, specifies FTA’s financial commitment and incorporates a Master Agreement
setting forth standard terms and conditions for the FTA-assisted project. The approved
project budget is incorporated by reference, and made part of the agreement. Conditions of
award that apply to a specific project may be included in the award, sometimes as
amendments to the current Master Agreement. Conditions of award, if any, are displayed in
the electronic agreement. Conditions of award may also be included in documents
authorizing preaward authority for a project, if applicable. In certain cases, preaward
authority may be available for incurring project-related costs prior to approval of an
application.
Once FTA awards Federal assistance through a cooperative agreement, grant agreement, or
other agreement, the recipient executes the agreement in FTA’s current electronic award
and management system. The recipient’s electronic execution of the agreement signifies
that the project is active and post-award project requirements apply.
4. SYSTEM REGISTRATION REQUIREMENTS. The use of FTA’s electronic award and
management system, and other Federal Government application and reporting systems,
require advance registration by recipients. These include:
a. Electronic Award and Management System. The administering office can provide
guidance on requirements to establish a user ID in the current FTA electronic award
and management system and will provide assistance, as needed.
FTA C 6100.1E
Page III–3
b. Unique Entity Identifier [Data Universal Numbering System (DUNS)]. OMB’s Super
Circular, 2 CFR part 200 replaces “DUNS” with “unique entity identifier.” However, in
the case of FTA, that number continues to be the “DUNS” number. In fact, OMB’s
Grants.gov website, www.grants.gov, has not yet been updated to replace the
information about the DUNS number. The Data Universal Numbering System (DUNS)
number is a unique nine-digit identification number provided by the company Dun &
Bradstreet (D&B). All entities doing business with the U.S. government can receive a
DUNS number FREE of charge and, under normal circumstances, within 1-2 business
days when using the D&B web form process. Call D&B at 866-705-5711, or use email
to [email protected], if you do not have a DUNS number. At the date of publication of
this circular, FTA is continuing to treat the DUNS number as the “unique entity
identifier” required by OMB.
You must first obtain a DUNS number in order to begin the registration process for a
number of systems in the System for Award Management (SAM). SAM is the Official
U.S. Government system that consolidates Federal procurement systems with the
Catalog of Federal Domestic Assistance (https://www.uscontractorregistration.com/)
On July 30, 2012, the Central Contractor Registration (CCR), Federal Register, and
Excluded Parties List System (EPLS) were transferred to SAM. There is NO fee to
register for this site. A DUNS number is also required to access to FTA’s current
electronic award and management system, to register with SAM, to register with
Grants.gov, and to register for the Federal Funding Accountability and Transparency
Act Subaward Reporting System (FSRS). At the date of publication of this circular,
FTA is continuing to treat the DUNS number as the “unique entity identifier” required
by OMB.
c. System for Award Management Requirements. Any organization applying for FTA
financial assistance must register in SAM and keep its registration current until it
submits its final financial report required under its cooperative agreement, grant
agreement, or other agreement with FTA or receives its final payment under the project,
whichever is later. The recipient must review and update its information in SAM at
least annually after the initial registration, and more frequently if required by changes
in its information or another provision of a Federal or federally assisted agreement, law,
regulation, or regulatory guidance.
d. Former CCR Registrants. If you had an active record in CCR, you have an active record
in SAM. You do not need to do anything in SAM at this time, unless a change in your
business circumstances requires updates to your applicant or recipient’s record(s) in
order for your applicant or recipient to be paid or to receive an award or you need to
renew your applicant or recipient’s registration prior to its expiration. SAM will send
notifications to the registered user via email 60, 30, and 15 days prior to expiration of
the entity. To update or renew your entity records(s) in SAM you will need to create a
SAM user account and link it to your migrated entity records. You do not need a user
account to search for registered entities in SAM. Instead, you can type the DUNS
number or business name into the search box.
Page III–4
f.
FTA C 6100.1E
Grants.Gov. Some funding opportunities are posted on www.grants.gov. In order to
apply through www.grants.gov, proposers should initiate the process of registering on
the www.grants.gov site well in advance of any deadline to ensure completion of
registration before the deadline for submission. Complete instructions on how to
register can be found at www.grants.gov. Please be aware that according to the
www.grants.gov website, the registration process can take between three to five
business days up to four weeks and must be completed before any application can be
submitted. Note that you must first obtain a DUNS number and then register with the
SAM before registering with www.grants.gov.
g. The Federal Funding Accountability and Transparency Act (FFATA) Subaward
Reporting System (FSRS). Recipients awarded new Federal assistance greater than or
equal to $25,000 as of October 1, 2010, are subject to FFATA subaward and executive
compensation reporting requirements as outlined in the Office of Management and
Budget’s guidance issued August 27, 2010. Instructions and the FFATA Subaward
Reporting System (FSRS) can be found at the FSRS website: https://www.fsrs.gov/.
Note that you must first obtain a DUNS number and then register with the SAM before
registering with FSRS.
5. Proposal and Pre-application Guidelines. FTA may use pre-applications to screen proposals
as part of a competitive process announced on Grants.gov and/or the Federal Register. This
process is used to select what projects will be funded. Applicants should review
requirements set forth in Grants.gov and/or the Federal Register.
a. Project Narrative. The applicant should submit a project narrative statement describing
the objective, proposed work tasks, output, and benefits of the proposed project for
which Federal assistance is being requested. The narrative should also indicate whether
matching funds would be provided, the expected duration of the project, and other
information that would assist FTA to understand and evaluate the project.
The standard submission for a project narrative statement should not exceed fifteen
pages and must include the information listed in the outline below:
(1) Project Objective. A concise statement of the intended project goal.
(2) Statement of the Problem(s). A description of the problem to be addressed by the
proposed project.
(3) Literature Review. A highly focused synopsis, with full citations, of existing
research findings, best practices, best technology, as appropriate, explaining the
FTA C 6100.1E
Page III–5
specific gap, in the literature, practice, or technology that the proposed research
would fill. Please include full citations.
(4) Project Description. A description of the proposed project including:
(a) The relationship of the proposed project to the problem(s) identified in the
statement of the problems.
(b) Identification of the activities to be undertaken in detail by major task with
principal output.
(c) Identification of the key person(s) or organization to be responsible for the
development, coordination, and management of specific activities.
(d) The geographic location of the project.
(5) Identify Major Technology Transfer/Dissemination/Outputs. For example, reports
(interim, final, or other), products, brochures, outreach meetings, and so forth.
(6) Project Schedule. A project schedule must be presented, including a schedule of
major tasks, and an overall project schedule. The schedule should be realistic.
(7) Benefits and Beneficiaries. A description of the anticipated benefits and the
targeted beneficiaries, including quantification or measure of the potential impact.
Describe specifically how the work to be performed will benefit the transit
industry. Be as specific as possible.
(8) Strategic Goals. List which goals and objectives of the latest FTA strategic
research plan will be furthered by the project and describe how the project will
measurably contribute to the objectives listed.
(9) Justification of the Project Budget. If appropriate, discuss specifics about the
proposed project budget or breakdown by the given categories and supplemental
information to justify the need for such expenditures. If the budget line items are
self-evident, no justification will be necessary. For guidance on allowable costs,
refer to the appropriate administrative circular issued by the OMB that applies. See
Chapter V, Section 4, “General Principles for Determining Allowable Costs,” of
this circular.
(10) Project Timing. If appropriate, discuss other pending projects or program activities
that may relate to and affect the timing of the proposed project. If there are no
special considerations affecting the timing of the proposed project, indicate “N/A.”
Page III–6
FTA C 6100.1E
(11) Evaluation Criteria. Address any evaluation criteria described in the announcement
if not addressed in subsections (1) to (10) above.
6. Formal Application Procedures. FTA will ask an applicant whose pre-application- has
received a favorable review to submit a formal application in FTA’s electronic award and
management system.
a. Using FTA’s Current Electronic Award and Management System. In order to submit an
application electronically, an applicant must provide the information requested by
FTA’s current electronic award and management system and follow the instructions
therein. FTA’s electronic award and management system will have a “user guide” or a
tutorial, as well as training sessions and webinars available for new users. Please
contact your FTA project manager for assistance with training issues.
b. Contents for a Formal Application. Each application must contain the following:
(1) Information normally found in the Standard Form. All information normally
required by OMB Standard Form 424, “Application for Federal Assistance,” must
be entered in the appropriate fields of FTA’s current electronic award and
management system. This information must be completed in its entirety. The
authorized official identified in the relevant authorizing resolution that is
designated to provide the annual certifications and assurances, must attest to
information pertaining to any delinquent indebtedness to the Federal Government.
An applicant must retain the original/signature authorizing resolution in its official
file (to the extent the applicant is required to obtain a resolution before it may act)
or other indicia of its authority to act, and Opinion of Counsel, unless requested in
writing by FTA. Standard Form 424 can be found at: http://www.whitehouse.gov.
(2) Project Budget. FTA has developed a single coded line item structure that can be
used for any FTA project budget. The total project budget must be allocated
between one or more of a series of scope codes and activity line items (ALIs). The
budget includes only that Federal assistance being requested from FTA with any
matching share that the applicant proposes to provide for a single, defined project.
Any potential future Federal assistance should not be included in the budget.
(a) Every project consists of: (1) one or more scopes (major code/subject area),
and (2) subdivisions (ALIs). Collectively, the scope and its group of activities
form the project tasks to be undertaken.
(b) Under the scope, a set of related activities are brought together to help achieve
the project’s purpose/scope.
FTA C 6100.1E
Page III–7
1
“55” is the scope number for most research-type projects.
2
Additionally, each scope code should be titled to reflect the research or
technical assistance/training activity (i.e., develop prototype, demonstrate
bus and so forth). ALIs may be used across these two scopes to meet the
project requirements.
(c) At a minimum, the ALIs should include the basic object class categories
normally found in the Standard Form 424A (budget information—
nonconstruction programs):
1
Personnel (managerial, technical, and professional or faculty salaries and
wages, clerical, secretarial, and clerical costs),
2
Fringe benefits,
3
Travel,
4
Equipment,
5
Supplies,
6
Contractual,
7
Other, and
8
Indirect charges.
(d) The applicant should describe the activity to be carried out for each ALI in the
text field in FTA’s current electronic award and management system, such as:
1
Who the managerial, technical, and professional staff are;
2
What equipment will be purchased;
3
What travel is anticipated; and
4
What types of contracts are expected.
(e) If applicable, the project budget must also identify the applicable cost share
ALIs and the anticipated source of the cost share (i.e., cash, in-kind
contributions).
Page III–8
FTA C 6100.1E
(f) “Fee or Profit” is not an eligible ALI for federally assisted projects
(cooperative agreements, grant agreements, and other agreements). “Fee or
Profit” is included in the ALI items because FTA uses FTA’s current
electronic award and management system to track its direct procurement
contracts.
(g) See requirements for indirect cost approval in Chapter V, Section 5, “Indirect
Costs,” of this circular if including indirect costs in the budget.
Budget Example
FTA Amount
Total Eligible
Cost
55–00 Demonstrate Fuel Cell Bus
$800,000
$1,000,000
ACTIVITY LINE ITEMS
55.14.00 Managerial, Technical, &
Professional
$300,000
$400,000
55.13.00 Clerical
50,000
50,000
55.30.00 Fringe Benefits
75,000
75,000
5,000
5,000
100,000
$200,000
55.49.00 Supplies
20,000
20,000
55.50.00 Contractual
50,000
50,000
0
0
200,000
Estimated Total Eligible Cost:
200,000
$1,000,000
Federal Share:
$800,000
Local Share:
$200,000
SCOPE
55.20.00 Travel
55.40.00 Equipment
55.70.00 Other
55.80.00 Indirect Costs
(3) Statement of Work (SOW). For example, work tasks, deliverables, and schedules,
which includes the following:
(a) Problem Statement, Objective(s), and Need for Assistance. State the principal
and subordinate objectives of the project. Identify any relevant physical,
economic, social, technological, financial, institutional, or other problems
requiring a solution. Demonstrate the need for the Federal assistance requested.
Supporting documentation or other information from concerned interests other
FTA C 6100.1E
Page III–9
than the applicant may be used. Any relevant data based on planning studies
should be included or footnoted.
(b) Results or Benefits Expected. Identify costs and benefits to be derived from the
proposed project. Describe specifically how the work to be performed will
benefit the transit industry (riders, management, employees and so forth); for
example, increase ridership, reduce initial or operating costs, improve vehicle or
system performance, improve passenger information systems, improve safety,
improve the environment, and so forth.
(c) Relation to FTA Strategic Plans. Identify how the project will support furthering
the goals and objectives of FTA’s strategic plans in a measurable manner.
(d) Work Plan/Approach.
1
Work Tasks. Outline a plan of action organized by work task in the
“Implementation Plan” pertaining to the scope and detail of how the
proposed work will be accomplished for the program, function, or activity
provided in the budget. Cite factors that might accelerate or impede the work
and the reason for taking the approach described as opposed to others.
Describe any unusual features of the project, such as design or technological
innovations, reductions in cost or time, benefits to riders, or extraordinary
social and community involvement.
2
Accomplishments. Describe the anticipated accomplishments to be achieved
in qualitative or quantitative terms. Quantitative measures could include the
number of riders, equipment reliability, and data to be gathered, or other
measures of goal achievement. When accomplishments cannot be quantified
by activity or function, list them in chronological order to show the schedule
of accomplishments and their target dates. Performance measures could
include interim report submissions.
3
Data and Measurement. Identify the kinds of data to be collected and
maintained. Discuss the criteria to be used to evaluate the results and
successes of the project. Explain the methodology that will be used to
determine if the needs identified and discussed are being met, and if the
results and benefits identified in subparagraph 2 above are being achieved.
List each organization, operator, consultant, or other key individual who will
participate in the project, along with a short description of their effort or
contribution.
Page III–10
FTA C 6100.1E
4
Project Period/Schedule/Deliverables. Identify the period of performance
and major project milestones and deliverables. Milestones include phases of
the project such as issuing the request for proposal, entering into a
subcontract, completing a literature review or surveys, or completing data
collection. Deliverables include both interim and final products such as
prototypes, equipment developed, conferences organized, training delivered,
internet pages, software, data, draft reports, and final reports. Both
milestones and deliverables will be entered into FTA’s current electronic
award and management system as part of the project milestone schedule
discussed below.
(e) Geographic Location. Give a precise location of the project and identify the
area(s) and target group(s) to be served by the proposed effort. Maps or other
graphic aids may be attached.
(f) Key Personnel. Present a brief biographical sketch of the principal investigator
or project manager with the following information: name, address, telephone
number, background, and other qualifying experience. Also, list the name and
background for other key personnel engaged in the project.
(g) Supplemental Assistance. For supplemental assistance requests, explain the
reason for the request and justify the need for additional funding. Discuss
accomplishments to date and list in chronological order a schedule of
accomplishments, progress, or milestones anticipated with the funding request.
Explain and justify significant changes in the project objectives, location,
approach, or time delays, if any. Explain the reason for other requests for
changes or amendments, if any. If the project scope or objectives have changed
or an extension of time is necessary, explain the circumstances and justify the
need for additional funding, if needed. If the total budget has been exceeded, or
if the individual budget items have changed more than the prescribed limits
contained in the Common Rules, 2 CFR part 1201 or former 49 CFR parts 18
or 19, 2 CFR part 220, 225, or 230, as applicable, explain and justify the need
for additional funding.
(h) Other Information. The FTA program office may request other information to
properly evaluate the proposed project.
(4) Project Milestone Schedule. Applicants should identify major project milestones in
the milestone section of FTA’s current electronic award and management system.
This schedule consists of estimated milestone dates for major activities and
FTA C 6100.1E
Page III–11
products and an overall project completion date. The overall project completion
date should allow for audit and closeout of all third-party contracts. For each
milestone, any detailed information should be placed in the remarks or comment
area.
(5) Intergovernmental Review of Federal Programs Process Required by Executive
Order 12372. Executive Order 12372, “Intergovernmental Review of Federal
Programs,” 31 U.S.C. 6506 note, establishes a system of intergovernmental
consultation between state and local officials that involves a state process for
reviewing Federal programs and activities. The requirement is to ensure that the
appropriate state authorities are informed about and provided an opportunity to
comment on projects for which Federal assistance is being requested within the
state. Many states have their own review procedures that describe what applicants
need to do to satisfy intergovernmental review requirements. Each applicant is
required to submit with each application a certification of compliance with this
intergovernmental review requirement. If there is no intergovernmental review
process in the applicant’s state, then programming of a project in the metropolitan
Transportation Improvement Program (TIP) and Statewide Transportation
Improvement Program (STIP), or Unified Planning Work Program (UPWP), as
appropriate, will be considered by FTA as meeting the need for intergovernmental
review. U.S. DOT has issued implementing regulations, “Intergovernmental
Review of Department of Transportation Programs and Activities,” 49 CFR
part 17.
Any comments on the proposed activities received through the state process prior
to filing the application should be included. The official list of single point of
contact (SPOC) entities can be found at the OMB website:
http://www.whitehouse.gov/omb/grants_spoc/.
States that are not listed on this webpage have chosen not to participate in the
intergovernmental review process; and, therefore, do not have an SPOC. If the
applicant is located within a state that does not have an SPOC, the applicant may
send application materials directly to FTA.
(6) Certifications and Assurances for the Current Fiscal Year. Before FTA may award
a project, the applicant must provide to FTA all certifications and assurances
required of the applicant by Federal laws and regulations. Applicants should enter
their certifications and assurances in electronic format in FTA’s current electronic
award and management system. In limited circumstances FTA may permit the
applicant to submit the signature page in hard copy. The certifications and
assurances are consolidated by FTA each Federal fiscal year (FY) into a single
document that provides the text of the certifications and assurances to be used in
Page III–12
FTA C 6100.1E
connection with all Federal assistance programs administered by FTA during that
fiscal year. The certifications and assurances are published in the Federal Register
notice, normally near the beginning of the fiscal year.
(a) Annual Submission. An applicant need only submit the certifications and
assurances once annually. FTA is required to obtain specific assurances
pertaining to FTA research programs. The certification required by U.S. DOT
regulation, “Intergovernmental Review of Department of Transportation
Programs and Activities,” 49 CFR part 17, is submitted with each application.
The certifications and assurances the applicant attests to will remain valid for
one year or until FTA publishes the next version. Recipients must also submit
annual certifications and assurances as long as the project remains active, even
if the recipient is not applying for more funding.
(b) Electronic Submittal. FTA expects applicants to submit their applications and
certifications and assurances electronically, by means of FTA’s current
electronic award and management system.
(c) Compliance. The certifications and assurances, when properly attested to and
submitted to FTA through FTA’s current electronic award and management
system, assure FTA that the applicant intends to comply with the requirements
for the specific program involved.
(d) Timing. The certifications and assurances must be submitted and attested to
annually by an applicant or recipient or with the applicant’s first Federal
assistance application in the Federal fiscal year, whichever is first.
(e) Action Required. The authorized representative of the applicant must make the
requisite certifications and assurances by:
1
Selecting each certification or assurance category that will apply to the
applicant’s projects for the fiscal year, or
2
Selecting the first item at the top of that page, signifying that the applicant
will comply with all categories of certifications and assurances, and
3
Attesting to the certifications and assurances electronically with a personal
identification number (PIN).
(f) Requirement for Current Affirmation. FTA requires a current attorney’s
affirmation of the applicant or recipient’s legal authority to certify compliance
FTA C 6100.1E
Page III–13
with the FTA’s certifications and assurances required for Federal assistance for
that fiscal year. The attorney’s affirmation from a previous year is not
acceptable.
(g) Supplementary Information. These certifications and assurances are used for all
FTA assistance programs. FTA also uses these certifications and assurances for
Federal assistance programs authorized or funded under Title 23, U.S.C.
administered by FTA.
(7) Environmental Considerations. FTA’s environmental review process has two
primary objectives: to fully disclose the probable environmental impacts resulting
from a proposed project and to develop measures that will avoid, minimize, or
mitigate adverse environmental effects. All projects seeking FTA financial
assistance require compliance with the Council on Environmental Quality’s
regulations that implement the National Environmental Policy Act (NEPA),
40 CFR 1500-1508, the joint Federal Highway Administration/Federal Transit
Administration (FHWA/FTA) “Environmental Impact and Related Procedures,”
23 CFR part 771, Efficient Environmental Reviews for Project Decisionmaking,
23 U.S.C. 139, and numerous other environmental laws, regulations, and orders,
such as Section 106 of the National Historic Preservation Act, 36 CFR part 800,
the Clean Water Act, and the Endangered Species Act. Project sponsors should
consult with the FTA regional office early in project development to identify the
appropriate class of action (categorical exclusion [CE], environmental assessment
[EA], or environmental impact statement [EIS]) for the NEPA review and any
other environmental requirements. Project sponsors should not move forward with
any steps to develop the project that would preclude the fair consideration of
alternatives (e.g., final design and construction) until FTA concludes the NEPA
process by issuing a ROD, FONSI, or CE. Property acquisition, other than for the
linear right-of-way needed for the project (as determined in close consultation with
FTA staff), should not take place until an ROD, FOSNI, or CE is issued. Please
contact the FTA office of planning and environment for further information.
(a) Typical Projects. Projects under this circular usually involve research and
technical assistance for a defined problem, technology development or
demonstration, transit service development or demonstration, changes in
administrative or institutional procedures or services, and so forth, that rarely
would have significant environmental effects. So, it is unlikely that
applicants for Sections 5312, 5313, 5314, or 5322 or other research or
technology agreements would be required to prepare an EIS. However,
the applicant and the responsible FTA official reviewing the project must
determine what Class (I, II, or III) environmental action is being considered
Page III–14
FTA C 6100.1E
and proceed accordingly. FTA’s policy is to comply with and require its
applicants and recipients to comply with all related environmental laws and
regulations, to the fullest extent possible, within any environmental document
submitted for compliance with NEPA.
(b) Classes of Environmental Actions. FTA’s environmental regulation identifies
three classes of actions requiring different levels of environmental
documentation and gives examples of typical projects in each class.
1
Class I actions are projects that have significant environmental effects and,
therefore, require preparation of an EIS. Either as a result of an EA or
because of certain project characteristics evident at the outset of project
planning, significant environmental impacts are identified or known to exist,
if an EIS will be required. For example, a demonstration or deployment
project that involves the new construction or extension of a separate
guideway or roadway for high-occupancy vehicles (HOVs) not located
within an existing highway right-of-way would typically require an EIS.
2
Class II actions are those that, normally, do not involve significant
environmental effects and, therefore, do not require any environmental
document. The joint FHWA/FTA environmental impact regulations, 23 CFR
part 771, use the term “categorical exclusion” (CE) to describe classes of
projects that do not involve significant environmental impacts and, therefore,
do not require preparation of either an EA or an EIS. CEs fall into two
categories: those that are listed specifically in 23 CFR 771.117(c), and need
no further analysis, and those that require additional documentation under
23 CFR 771.117(d) in order to assure their suitability for a CE. Applicants
should consult each list to determine whether a particular project may be
categorically excluded from the need to prepare either an EA or an EIS. For
example, projects that involve construction have greater potential for on-site
and off-site environmental impacts and, therefore, are subject to additional
analysis. Experience has shown, however, that many construction projects
can be built and operated without causing significant impacts if they are
carefully sited in areas with compatible, nonresidential land use where the
primary access roads are adequate to handle the additional bus traffic. FTA
may approve the designation of these construction projects as documented
CEs if the applicant provides an administrative record demonstrating that the
conditions stated above in this paragraph are met and that no significant
adverse effects will result.
FTA C 6100.1E
Page III–15
3
Class III actions are projects for which FTA is uncertain as to the
significance of environmental effects. An EA is required in order to
determine the significance of the effects. The joint FHWA/FTA
environmental regulations describe environmental processing for all three
classes of actions. For any project not meeting the conditions for a CE, the
applicant must, at a minimum, prepare an EA. In addition to documenting
the impacts of the proposed project, an EA requires the applicant to consider
alternatives as required by section 102(2)(E) of NEPA, 42 U.S.C. 4332(2).
An EA is also subject to public comment. Once the EA has been completed,
and when warranted, FTA may issue a Finding of No Significant Impact
(FONSI) or a mitigated FONSI which concludes the NEPA process.
4
The applicant must submit its environmental information in an electronic
window designed to accept this information within FTA’s current electronic
award and management system.
c. Possible Project Requirements. The following requirements may, or may not, apply to
the proposed project. Relevance is determined by various factors involved in the
project. Applicants should communicate with the FTA project manager in order to
develop an understanding of these requirements. If steps are not taken to meet
applicable requirements, delays may occur in project approval.
(1) Labor Protections.
(a) Davis-Bacon Act. For FTA programs, 49 U.S.C. 5333(a) imposes Davis-Bacon
Act prevailing wage requirements. This provision applies only to construction
projects. The Secretary of Transportation must ensure that laborers and
mechanics employed by contractors and subcontractors in construction work
financed with a grant or loan under this chapter are paid wages that are not less
than those prevailing on similar construction in the locality, as determined by
the Secretary of Labor under sections 3141 through 3144, 3146, and 3147 of
title 40. The Secretary of Transportation may approve a grant or loan only after
being assured that required labor standards will be maintained on the
construction work. For a labor standard under this subsection, the Secretary of
Labor has the same duties and powers stated in Reorganization Plan No. 14 of
1950 (eff. May 24, 1950, 64 Stat. 1267) and section 3145 of title 40. This
assurance is obtained when recipients execute the Master Agreement.
(b) Transit Employee Protection. Before FTA may award Federal assistance for a
Section 5312 project involving transit operations, fair and equitable
arrangements must be made to protect the interests of transit employees
Page III–16
FTA C 6100.1E
affected by the proposed FTA assistance, 49 U.S.C. 5333(b) (originally
section 13(c) of the Federal Transit Act). Those arrangements must be
certified by the Secretary of Labor as meeting the requirements of the law.
Applicants whose projects affect transit operations will need to furnish
specific information as to involvement in the project of employees who are
not managers. If applicable, this exhibit should describe the labor unions (a
list of names of the local affiliates) representing employees of the transit
system(s) affected by the project. Applicants whose projects do not affect
transit operations, and which, therefore, are not affected by this requirement,
should provide a statement to that effect. Ordinarily, Section 5333(b)
certification may not be required if the project does not involve or affect
transit operations. FTA will make a determination on the need for Department
of Labor (DOL) clearance. Applicants should consult the FTA project
manager for further information regarding the need for DOL clearance. Apart
from the need for DOL clearance, questions concerning employee protective
arrangements and related matters pertaining to transit employees should be
addressed to the Division of Statutory Programs, Office of LaborManagement Standards, U.S. Department of Labor,
http://www.dol.gov/olms/regs/compliance/compltransit.htm.
(2) Civil Rights Submission. See Chapter II, Section 4, “Civil Rights Requirements,”
of this circular.
(3) Lobbying Disclosure. Federal financial assistance may not be used to influence
any member of Congress or an officer or employee of any agency in connection
with the making of any Federal cooperative agreement, grant agreement, or other
agreement. For example, Federal funds may not be used for lobbying
congressional representatives or senators indirectly, such as by contributing to a
lobbying organization or funding a grass-roots campaign to influence legislation
(31 U.S.C. 1352). These laws do not prohibit general advocacy for transit.
Providing information to legislators about the services an applicant provides in the
community is not prohibited, nor is using other than Federal funds for lobbying, so
long as the required disclosures are made. A certification and, when appropriate, a
completed disclosure form must be submitted by the applicant in accordance with
31 U.S.C. 1352, “Limitation on use of appropriated funds to influence certain
Federal contracting and financial transactions,” and U.S. DOT implementing
regulations, “New Restrictions on Lobbying,” 49 CFR part 20. Section 1352
requires that all persons (meaning organizations, as well as individ uals) that
request or receive Federal cooperative agreements, grant agreements, or other
agreements exceeding $100,000 submit a certification that Federal appropriated
FTA C 6100.1E
Page III–17
funds were not used to influence or attempt to influence the transactions.
Applicants, recipients, and third-party contractors are required to disclose certain
lobbying activities conducted with funds derived from other than Federal sources.
If anyone is hired to lobby on behalf of the potential recipient requesting the
Federal assistance, Section 1352 requires that a disclosure statement, OMB
Standard Form LLL (rev. 7–97) “Disclosure of Lobbying Activities,” be
completed naming the lobbyists and the amounts paid to them. These requirements
also apply to subrecipients and subcontractors.
(4) Minimum Useful Life of Vehicles and Equipment. If the project requires purchase
of vehicles or equipment with an expected useful life longer than the period of
performance of the project, the recipient should propose a reasonable minimum
useful life for each such item for purposes of computing the residual Federal
interest in the item when no longer needed for the project. If FTA concurs with the
proposal, it may include a special condition in the cooperative agreement, grant
agreement, or other agreement stating the expected minimum useful life of those
items.
7. PEER REVIEW AND INDEPENDENT EVALUATION. FTA may request applicants to
participate in peer review programs, including submitting proposed statements of work to
peer review panels and participating in peer review panels of other proposals. Each
research project supported by FTA is subject to an independent evaluation within two years
after award of the agreement. The FTA project manager will provide specific instructions
for the scope and conduct of the independent evaluation.
8. COMPLETE APPLICATION. For a Federal assistance application to be complete, all
planning, programming, and ancillary activities must be completed. To merit FTA
approval, all requisite certifications, assurances, and other documentation must be
completed and the application must be sufficiently complete, with all required information
and documentation provided, except for the labor protection certification, which is issued
by DOL. All intergovernmental review and all applicable civil rights, alcohol misuse, and
prohibited drug use program requirements must have been met.
9. MASTER AGREEMENT. FTA uses an abbreviated cooperative agreement, grant
agreement, or other agreement that incorporates by reference a Master Agreement in which
most terms and conditions are stated that will apply to the cooperative agreement, grant
agreement, or other agreement used for the project. The Master Agreement incorporates
statutory and other standard conditions that are agreed to, in writing, by the recipient when
the recipient executes the cooperative agreement, grant agreement, or other agreement for
its project. FTA Master Agreements are available for review on FTA’s website,
http://www.fta.dot.gov. Each recipient is expected to retain the applicable Master
Page III–18
FTA C 6100.1E
Agreement on file. Certain types of FTA projects, for example, joint partnership projects,
may use “Other Agreements” with revised terms and conditions.
10. AWARDING INSTRUMENT. FTA can award Federal assistance through cooperative
agreements, grant agreements, or other agreements. Most research projects are awarded as
cooperative agreements because FTA anticipates substantive involvement and interest in
the results of the project. The cooperative agreement document in FTA’s current electronic
award and management system will specify both the FTA’s role and the recipient’s role. At
a minimum, the FTA role usually includes FTA’s right to participate in the redirection of
project activities. FTA will primarily use Grant Agreements for projects in which FTA
involvement is not expected to be substantial. FTA will inform the applicant, as it
completes its application, whether the project will be awarded as a cooperative agreement
or a grant agreement. Except for the inclusion of the Federal role in the project, cooperative
agreements and grant agreements are subject to the same administrative requirements, and
this circular refers to them, collectively, as Federal assistance.
11. COST SHARE. Most research programs for which funding is made available by MAP-21
requires a local share. In addition, if FTA determines that there would be a clear and direct
financial benefit to an entity under a cooperative agreement, grant agreement, or other
agreement for projects funded under the authority of 49 U.S.C. 5312 and 5313, FTA must
establish a Federal share consistent with the benefit. Cost sharing is intended to serve the
mutual interest of the Federal Government and recipient organizations by ensuring
maximum utilization of the available funding resources. Usually, the amount of cost
sharing for Section 5312, 5313, 5314, and 5322 projects is considered in the evaluation of
application proposals and determined by mutual agreement between FTA and the applicant,
and may be in the form of in-kind contributions, as well as cash.
While MAP-21 provides the local share requirements, the actual local share requirement
for a specific program may vary depending on specific language in annual appropriations
acts, MAP-21, and any subsequent amendments thereto. Therefore, to determine the proper
local share, the applicant should check the appropriate Federal Register notice for the
program, or check with FTA’s research office.
a. Establishing the Cost Share. Factors to be considered in negotiating the amount of cost
sharing include the following:
(1) Program requirements for specific programs authorized by MAP-21.
(a) Section 5312 requires a local share of no less than 20 percent of the project
costs. For low or no emission vehicle deployment projects, the local share for
vehicles complying with the Clean Air Act is 15 percent.
FTA C 6100.1E
Page III–19
(b) Section 5314 requires a local share of no less than 20 percent for grants.
(c) Section 5322(a) and (b). The Federal share of projects funded under the
human resources and training program and projects funded under the
innovative public transportation workforce development program require a
local share of 50 percent of the allowable costs of the program.
(2) Type of project and nature of the applicant.
(a) In the case of other Sections 5312 and 5314 cooperative agreements, grant
agreements, or other agreements with commercial or industrial organizations,
greater private contribution to cost sharing would be expected if the project
were likely to enhance that organization’s capability, expertise, or competitive
position to its financial advantage. Organizations predominantly engaged in
research and development with little or no production capability may not be in
a position to derive a monetary benefit from such participation. Thus, cost
participation by commercial or industrial organizations could reasonably
range from no cost to participants to as much as 50 percent or more of the
project costs.
(b) In the case of cooperative agreements or grant agreements with educational
institutions and other nonprofit organizations, a higher percentage of local
share is expected when the direct cost of the project consists primarily of the
academic year salaries of faculty members.
(3) Relative Interest of the Federal Government.
A relatively low degree of cost sharing may be appropriate if it is determined that
an area of research or initiative that requires special stimulus is in the national
interest, such as high priority research projects identified in FTA’s strategic
research plan.
(4) Risk to the applicant for the outcome of the project.
b. Third-Party Contractor/Joint Venture Participation. Third-party contractors and other
for-profit entities participating as performers or contractors in a project venture also
may affect the amount of local share to be provided. When negotiating about the extent
of cost-sharing or local share requirements, no cost or contributions counted toward
other federally assisted cost-sharing projects may be considered for the proposed FTAassisted project. Neither costs nor the values of third party, in-kind contributions
may count toward satisfying a cost-sharing or matching requirement of a Federal
or federally assisted project, if they have been or will be counted toward satisfying
Page III–20
FTA C 6100.1E
a cost-sharing or matching requirement of another Federal or federally assisted
project, a Federal procurement contract, or any other award of Federal
assistance.
c. Program Income. During the application review process, the applicant may request
authorization from FTA to use any potential program income to meet the cost-sharing
or matching requirement of the agreement. In such cases, the amount of the Federal
share proposed for the cooperative agreement or grant agreement would not be reduced
until the time of project completion, when the FTA and local share would be reduced
on a prorated basis and verified by an audit, unless FTA determines otherwise in
writing. In a few cases as authorized by Federal law, regulation, or guidance, program
income earned as a result of the project can be used to defer the cost of the project from
which the Federal assistance was derived. In other circumstances, program income can
serve as local share for other FTA-assisted projects.
Examples of potential income-producing ventures for projects include: registration fees
collected for attendance at project-sponsored conferences, training workshops, seminars
and symposiums, fees collected from certain projects, for example, revolving loan fund
and bonding assistance type projects, advertising or concession fees, or farebox
revenues resulting from a previous rants or cooperative agreement.
d. Local Share. The recipient pays for all project costs and is reimbursed in part by the
Federal Government. The portion not reimbursed by the Federal Government is
referred to as the non-Federal share or local share. The Federal Government expects to
share in the costs of all tasks of a project. The Federal Government evaluates the
quality of cost share in the following terms:
(1) High-Quality Cost Share. These are financial resources that will be expended by
the recipient on the proposed project’s SOW and will be subject to the direction of
the project management team. This basically means the funds the non-Federal
participant will spend for labor hours, materials, new equipment (prorated if
appropriate), and subcontractor efforts expended on the project’s SOW, and
restocking the parts and material consumed. High-quality cost share can include
new independent research and development funded by the recipient, but only if
those funds are offered by the proposer to be spent on the SOW, and subject to the
direction of the project management team.
(2) Low-Quality Cost Share. These are nonfinancial resources that will be expended
on the proposed project’s SOW and will be subject to the direction of the project
management team. This is typically wear-and-tear on in-place capital assets, such
as machinery or the prorated value of space used for the project.
FTA C 6100.1E
Page III–21
(3) Unacceptable Cost Share. This is a resource that either: (1) will not be expended
on the project’s SOW, or (2) will not be subject to the direction of the management
team as discussed above in paragraphs (1) and (2). Unacceptable cost share will be
subtracted from the proposer’s claimed total cost for the project, and the required
cost share will be recalculated. Unacceptable cost share examples include:
(a) Sunk costs (i.e., costs incurred before the start of the proposed project),
(b) Forgone fees or profits,
(c) Forgone general and administrative or cost of money applied to a base of
independent research and development,
(d) Bid and proposal costs,
(e) Value claimed for intellectual property or prior research, unless the value is
diminished by the project, and
(f) Parallel research or investment, for example, research or other investments
that might be related to the proposed project but which will not be part of the
SOW or subject to the direction of the project management team. Typically,
these research or investment activities will be undertaken regardless of
whether or not the proposed project proceeds. They include off-budget
resources, for example, resources that will not be used by the proposer in
implementing the SOW and will not be considered when FTA evaluates cost
share.
12. PROJECT APPROVAL.
a. Notification. After FTA has awarded Federal assistance for a project, the applicant will
be notified of the award by the FTA project manager. The award will indicate the “date
of the award” and set forth any special conditions under which the project is approved.
The date of award is the date that authorizes the recipient to incur project costs. NOTE:
A recipient of an FTA award of funding can begin work on its project, but it must
execute its cooperative agreement, grant agreement, or other agreement before FTA can
pay for any project costs incurred. Absent a letter of no prejudice, costs incurred prior
to an FTA award are not eligible project expenses.
b. Execution of the FTA Agreement. The recipient’s authorizing official should execute
the cooperative agreement, grant agreement, or other agreement by entering his or her
personal identification number (PIN) in the appropriate place, which will then appear in
Page III–22
FTA C 6100.1E
FTA’s current electronic award and management system. The recipient should contact
the FTA project manager to alert him or her, that the project has been executed.
c. Cost Eligibility and Payment Method.
(1) Absent any type of preaward authority, the recipient may begin to incur project
costs as of the date the authorized FTA official signs (or PINs) the award.
(2) Requests for reimbursements will not be honored until the Federal assistance has
been awarded by FTA and executed by the recipient.
(3) FTA will not honor project costs the recipient may incur after the project period
ends without approving an extension of the project period.
(4) For amendments, absent of any type of preaward authority, the recipient may not
incur costs using Federal assistance provided in the amendment before the award
date of the amendment.
d. Reimbursement Procedures for Research, Technical Assistance, and Training
Programs. Grant recipients of cooperative agreements for research, technical assistance,
and training programs must request reimbursements using the Department’s DELPHI
eInvoicing system. The recipients must upload invoices for review and approval to the
designated FTA Project Manager prior to receipt of payment. The Project Manager and
the Grant recipient must complete and submit a DELPHI user access form to FTA
DELPHI security officers, in the Office of Finanical Systems to gain access to the
eInvoicing system. Once the Grant recipient’s access is authorized, the eInvoicing
Helpdesk will forward a Web-based training tutorial to the recipient to assist in
navigating and processing requests for reimbursements using the eInvoicing system.
FTA C 6100.1E
Page IV–1
CHAPTER IV
PROJECT ADMINISTRATION
1. OVERVIEW. This chapter discusses the mechanics and requirements for post-award
project administration. Financial management requirements are described in Chapter V of
this circular at the time of its publication. The following sections emphasize the
requirements associated with administering and managing a federally assisted project after
Federal assistance for the cooperative agreement, grant agreement, or other agreement has
been awarded and executed in FTA’s electronic award and management system.
2. APPLICATION PROCESS. FTA provides a streamlined electronic interface between
recipients and FTA that allows complete electronic application submission, review,
approval, and management of all FTA-assisted projects. This is done through FTA’s Webbased electronic award and management system. Among other things, recipients apply for
Federal assistance, inquire about the status of projects, file the required financial status and
milestone progress reports, and submit annual certifications and assurances in FTA’s
electronic award and management system. A user guide can be found at FTA’s website in
the “Grants and Financing” section under “Apply for and Manage Grants” located at:
http://ftateamweb.fta.dot.gov/static/userguide.html.
3. PROJECT IDENTIFICATION. The recipient understands and agrees that each tangible
product resulting from FTA research program projects must contain or include an
appropriate sign, designation, or notification stating that the project has been financed with
Federal assistance provided by U.S. DOT/FTA. Unless FTA determines otherwise in
writing, this requirement applies to all equipment, prototypes, construction, reports, data,
software, internet pages, or any similar items produced in the course of the cooperative
agreement, grant agreement, or other agreement for the project that are part of the project’s
deliverables visible to the public, or are made available to other research organizations or
public transportation providers. Reports must also include the disclaimer described in
Chapter IV, subsection 4.g.
4. REPORTING REQUIREMENTS. Once a project is active, a recipient will be subject to
one or more of the following types of post-award reporting requirements, several of which
can be accomplished using FTA’s electronic award and management system. The reporting
requirements may vary depending on the size of the recipient, the type and amount of
Federal assistance a recipient receives, or the Federal interest in the project. Unless
otherwise permitted in writing, quarterly reporting is required. Please contact the FTA
administering office if there are questions regarding the applicability of the following
reporting requirements.
a. Financial and Progress Reports. FTA uses the Federal financial reports (FFRs) and
milestone progress reports (MPRs) to evaluate several elements of the project’s status,
such as the extent to which:
(1) The purposes of the project are being achieved,
Page IV–2
FTA C 6100.1E
(2) The project is progressing on time and within budget,
(3) The recipient is demonstrating competence and control in implementing the
project,
(4) The project meets all program requirements, or
(5) A problem is developing which may require FTA resources to resolve.
FTA monitors project activities to ensure proper recipient stewardship of Federal
assistance and compliance with the laws and regulations that govern its Federal
assistance programs. FTA also must be able to report on program results, industry
trends, and its own oversight responsibilities. The information FTA needs for program
forecasting, management, and reporting is furnished through FFRs and MPRs
submitted by recipients about significant events, relevant project activities, and any
changes to or variances in the project schedule or budget.
FTA staff is available to meet with recipients to agree on the appropriate level of
reporting detail and formats for reporting in FTA’s electronic award and management
system. This will ensure that FTA has the information needed to manage its overall
program.
All recipients should report significant developments or changes as they occur,
including any problems, delays or adverse conditions that may materially impair their
ability to meet the objective of the award, as well as any favorable developments that
may enable meeting time schedules and objectives sooner or at a cost substantially less
than expected in FFRs.
If necessary, attachments can accompany FFRs and MPRs by using the “paperclip” or
the “upload/manage documents” feature in FTA’s electronic award and management
system.
FTA may withhold payment for failure to submit either FFRs or MPRs in a timely
manner. In individual cases, FTA may approve extensions of report due dates for good
cause.
Report due dates and additional information about the FFRs and MPRs are described
below in subsection 4b. Please contact the administering office for questions regarding
any of these reports.
b. Report Due Dates.
(1) Quarterly Reports—FFRs and MPRs. These reports are due to FTA within thirty
days after the end of each quarter, for example, by January 30, April 30, July 30,
and October 30.
FTA C 6100.1E
Page IV–3
(2) Final Reports. Final FFRs and MPRs are due ninety calendar days after the
expiration or termination of the project.
c. Federal Financial Report (FFR). A recipient must submit an FFR for each active
cooperative agreement, grant agreement, or other agreement it has executed. The
requirement for an FFR applies to all FTA-assisted projects covered by this circular.
The FFR accompanies the MPRs (described below in subsection d) and is used to
monitor project funds. The purpose of the FFR is to provide a current, complete, and
accurate financial picture of the project. This report is submitted electronically in the
FFR section of FTA’s electronic award and management system and must be prepared
on the accrual basis of accounting: income is recognized when earned instead of when
received, and expenses are recognized when incurred instead of when paid. FTA does
not permit the FFR to be prepared in the cash method of accounting. A recipient may
keep its books on the cash basis during its accounting year. If this is the case, at the
submission of the FFR, the recipient must prepare the necessary accruals and submit
the FFR on the accrual basis of accounting.
The FFR must comply with the following requirements:
(1) All financial facts (e.g., expenditures and obligations) relating to the scope and
purpose of each financial report and applicable reporting period should be
completely and clearly displayed in the reports,
(2) Reported financial data should be accurate and up to date; the requirement for
accuracy does not rule out inclusion of reasonable estimates when precise
measurement is impractical, uneconomical, unnecessary, or conducive to delay,
(3) Financial reports should be based on the required supporting documentation
maintained in the recipient’s official financial management system that produces
information that objectively discloses financial aspects of events or transactions,
(4) Financial data reported should be derived from accounts that are maintained on a
consistent, periodic basis; material changes in accounting policies or methods and
their effect must be clearly explained,
(5) Reporting terminology used in financial reports to FTA should be consistent with
receipt and expense classifications included in the latest approved project, and
(6) Detailed instructions for completing the FFR are provided in Appendix A.
d. Milestone Progress Reports (MPR). MPRs must be submitted for all active projects
executed by the recipient and covered by this circular. The MPR is the primary written
communication between the recipient and FTA.
All recipients must complete the basic of the milestone progress report section of
FTA’s electronic award and management system and either complete the milestone
Page IV–4
FTA C 6100.1E
progress tab or attach a quarterly narrative report as directed by the FTA project
manager. Procedures for submitting MPRs are described in the user guide and are
available from the FTA administering office.
Normally a quarterly narrative report is required for research projects because it permits
the inclusion of more technical information as well as charts or photos. For projects
funded by multiple agreements, the recipient may submit one quarterly narrative report
for the entire project with prior approval of the FTA project manager. A copy must be
attached for each agreement in FTA’s electronic award and management system.
The information provided in these reports should be as complete as possible,
highlighting progress toward project objectives and any potential problem areas.
At a minimum, each quarterly narrative report should address the following:
(1) A summary narrative on task elements and milestone status of project activities
during the reporting period, including a comparison of actual accomplishments to
the objectives established for the period. Accomplishments should include items
such as:
(a) Significant results and major work tasks started, completed, or documented,
(b) The percent of the budget expended by task, if appropriate; where possible,
accomplishments should be related to expenditures for the same period,
(c) An activity schedule (bar chart or critical path exhibit) in each quarterly
report, and
(d) Expenditures incurred by each task by ALIs so that it matches with any
financial report submitted to the FTA project manager,
(2) Reasons why any project objectives are not being met, identifying problem areas
and the planned approach to resolve the problems,
(3) Significant events affecting the progress of the project, both positively and
negatively,
(4) Whether the project is within the approved project budget. If a cost overrun
appears likely, explain the reason for the overrun and the measures taken to
complete the project within budget, such as modifying or curtailing the scope of
the project or securing additional financing from sources other than FTA. NOTE:
Since the recipient agreed to carry out the project within a specific budget,
reducing the scope of a project may require renegotiating downward the project
budget and Federal share,
(5) Whether the project is on schedule. If the project completion date will be delayed,
indicate the steps taken to:
FTA C 6100.1E
Page IV–5
(a) Bring the project back on schedule, or
(b) Adjust other activities that may depend on project completion,
(6) Projected activities for the next quarter and steps anticipated in carrying them out,
and
(7) Estimated completion dates, percent completed, and Federal assistance required
for completion.
Depending on project complexity, at its discretion, FTA may also request other special
reports or quarterly project management meetings.
e. Reports of Significant Events. Unforeseen events that impact the schedule, cost,
capacity, usefulness, or purpose of the project should be reported to FTA immediately
after detection and then reflected in the next quarterly MPR. Special reports should be
submitted when:
(1) Problems, delays, or adverse conditions will affect the recipient’s ability to achieve
project objectives within the scheduled time period or within the approved project
budget. The report should discuss actions taken and/or contemplated and any
Federal assistance needed to resolve the situation; or
(2) Favorable developments will enable the recipient to achieve project goals and
complete project activities ahead of schedule or at lower cost.
f.
Federal Funding Accountability and Transparency Act (FFATA) Subaward and
Executive Compensation Reporting. Recipients awarded new Federal assistance greater
than or equal to $25,000 as of October 1, 2010, are subject to FFATA subaward and
executive compensation reporting requirements as outlined in the Office of
Management and Budget’s guidance issued August 27, 2010. These recipients must file
an FFATA subaward report by the end of the month following the month in which the
recipient awards any subaward greater than or equal to $25,000. Additionally, all
recipients must report the names and compensation of their five most highly
compensated officers, and first-tier subrecipients must report the names and
compensation of their five most highly compensated officers, if in the preceding fiscal
year they received 80 percent or more of its annual gross revenues in Federal awards;
and $25,000 or more in annual gross revenues from Federal awards; and the public does
not have access to this information about the compensation of the senior executives of
those recipients or subrecipients through periodic reports filed under section 13(a) or
15(d) of the Securities Exchange Act of 1934 (15 U.S.C. 78m(a), 78o(d)) or section
6104 of the Internal Revenue Code of 1986.
Instructions and the FFATA Subaward Reporting System (FSRS) can be found at:
https://www.fsrs.gov.
Page IV–6
FTA C 6100.1E
g. Reports and Other Materials Produced by the Recipient. All reports, presentations, and
other products resulting from FTA sponsorship reports must contain the following
acknowledgment and disclaimer:
DISCLAIMER NOTICE
This document is disseminated under the sponsorship of the United States Department
of Transportation, Federal Transit Administration, in the interest of information
exchange. The United States government assumes no liability for the contents or use
thereof.
The United States government does not endorse products or manufacturers. Any trade
or manufacturers’ names appear herein solely because they are considered essential to
the contents of the report.
h. Final Report. All recipients must submit a final report. Unless otherwise directed, any
recipients of technical assistance and training projects must submit a final narrative
progress report in FTA’s electronic award and management system detailing the actual
completion date of each task and a discussion of each task. Recipients of research and
development projects must submit a final technical report.
i.
Final and Other Major Technical Reports Produced by the Recipients. A final technical
report documenting project performance and the final results of research, development,
demonstration, deployment, or technical evaluation projects, including an executive
summary, must be submitted by the recipient or third-party contractor to the FTA
project manager at the conclusion of the project. Some projects may produce multiple
technical reports for each subtask rather than one final report covering the entire
project. For projects funded with multiple agreements, the recipient may submit one
final report for the all the projects with prior approval of the FTA project manager. A
copy must be attached for each agreement in FTA’s electronic award and management
System. All reports and supporting documentation must be provided to the FTA project
manager in an electronic/Web-ready format, as specified by FTA.
(1) National Technical Information Service (NTIS). All FTA-sponsored research,
development, demonstration, deployment, or technical evaluation documents must
be entered into the National Technical Information Service (NTIS) system. All
FTA-sponsored publications are available to the public from NTIS at
http://www.ntis.gov/.
(2) Electronic Copy of Report/Section 508 Compliant. Text supplied electronically
may be provided in one or more of the following formats to facilitate posting on
the FTA website: hypertext mark-up language (HTML), or searchable portable
document file (PDF/Adobe Acrobat). All accompanying graphics must be
provided in graphic interchange format (GIF) or joint photographic experts group
(JPEG) format or a format acceptable to FTA, in addition to their native format
(e.g., tag image file format [TIFF]).
FTA C 6100.1E
Page IV–7
(a) Electronic Published Documents (Internet). All published documents
(including graphics) must comply and be accessible in accordance with
current requirements of Section 508 of the Rehabilitation Act of 1973, as
amended. FTA must approve all documentation before distribution to the
public and it must be prepared in a format specified by FTA. FTA is required
by law to develop its website and documentation therein to meet the
requirements of Section 508 of the Rehabilitation Act, as amended (29 U.S.C.
794d).
(b) U.S. Access Board. Recipients of Federal assistance are responsible for
consulting sources such as the Access Board http://www.accessboard.gov/508.htm, and the section 508 website http://www.section508.gov.
(c) Section 508 of the Rehabilitation Act of 1973, as amended, 29 U.S.C. 794(d).
Federal agencies must make their electronic and information technology
accessible to people with disabilities in compliance with electronic and
information technology requirements. The access board has stated that,
“Section 508 [of the Rehabilitation Act] . . . applies to all Federal agencies
when they develop, procure, maintain, or use electronic and information
technology. Federal agencies must ensure that this technology is accessible to
employees and members of the public with disabilities to the extent it does not
pose an ‘undue burden.”
(3) Report Organization, Elements and Style. FTA requires all documents to be
compliant with Section 508 and meet a high standard of organization and clarity of
writing. The report must be organized with specific publication elements and
report style guide at http://www.fta.dot.gov/research/program_requirements.
Contact the FTA project manager for further information.
(4) All FTA-sponsored reports must contain the following disclaimers on the inside
front cover if published in hard copy or in a comparable prominent location if
published electronically:
DISCLAIMER NOTICE
This document is disseminated under the sponsorship of the United States
Department of Transportation, Federal Transit Administration, in the interest of
information exchange. The United States government assumes no liability for the
contents or use thereof.
The United States government does not endorse products or manufacturers. Any
trade or manufacturers’ names appear herein solely because they are considered
essential to the contents of the report.
(5) A report documentation page, Standard Form 298, “Report Documentation Page,”
must be in the front of all published research and technology reports. SF-298 is
located at: http://www.fta.dot.gov/documents/SF_298.pdf.
Page IV–8
FTA C 6100.1E
5. PRIOR APPROVALS. Prior approval requirements depend on whether the recipient is a
state or local government, in which case it is covered by 2 CFR part 1201 or former
49 CFR part 18, as applicable. If the recipient is an institution of higher education, hospital,
and other nonprofit organization, it is covered by 2 CFR part 1201 or former 49 CFR part
19. The requirements of 2 CFR part 1201 or former 49 CFR part 19 are also applied to forprofit organizations, except to the extent FTA has determined otherwise in writing. Prior
approvals is also determined by the applicable cost principles.
a. Definition of Prior Approval. “Prior approval” means prior written or electronic
approval from an authorized FTA official before the expense is incurred or action takes
place requiring prior approval. Prior approval can take the form of FTA’s acceptance of
the proposal and/or proposal budget and subsequent incorporation into the award or
written or electronic approval of a separate request submitted by the recipient.
b. Requirements for Prior Approvals. Although the wording in 2 CFR part 1201 and
former 49 CFR parts 18 and 19 is slightly different, the following actions require prior
approval for all entities unless noted.
(1) Scope or Objective Change. Change in the scope or the objective of the project or
program (even if there is no associated budget revision).
(2) Key Personnel Change. Change in a key person specified in the application or
award document.
(3) Additional Federal Assistance. The need for additional Federal assistance.
(4) Transfer of Training Allowances. The transfer of training allowances (direct
payment to trainees) to other categories of expense.
(5) Transfer of Work. Unless described in the application and specified in the
cooperative agreement, grant agreement, or other agreement, the subaward,
transfer, or contracting out of any work under an award. This provision does not
apply to the purchase of supplies, material, equipment, or general support services.
However, see the requirements for equipment below under Federal cost principles.
(6) Preaward Costs. If approved, all preaward costs are incurred at the recipient’s risk
(e.g., FTA is under no obligation to reimburse such costs if for any reason the
recipient does not receive an award, or if the award is less than anticipated and
inadequate to cover such costs).
(7) Time Extensions. To initiate an extension of the expiration date of the award.
(8) Transfers of Financial Assistance. The transfer of financial assistance between
direct cost categories and activity line items (ALIs). See “Project Budget,” Chapter
III, paragraph 6.b(2), in which the Federal share of the project exceeds $100,000
and the cumulative amount of such transfers exceeds or is expected to exceed 20
FTA C 6100.1E
Page IV–9
percent of the total budget as last approved. No transfer can be made to be used for
purposes other than those consistent with the original intent of the appropriation
and the cooperative agreement, grant agreement, or other agreement.
(9) Reduction of Effort. The absence for more than three months, or a 25 percent
reduction in time devoted to the project, by the project manager or by the principal
investigator (institutes of higher education, hospitals, nonprofits, and for-profits).
(10) Transfers Between Indirect Costs and Direct Costs. The transfer of amounts
budgeted for indirect costs to absorb increases in direct costs, or vice versa
(institutes of higher education, hospitals, nonprofits, and for-profits only).
(11) Federal Cost Principles. The inclusion of costs that require prior approval in
accordance with the cost principles. The applicable cost principles (see Chapter V
of this circular, “Financial Management”) for each type of institution lists cost
elements that require prior approval to be included in an approved project budget.
Recipients should refer to the Guidance for Grants and Agreements sections in
2 CFR part 1201 for awards and amendments made on or after December 26,
2014, to awards. Recipients of awards and amendments made before December26,
2014, to awards should refer to former 2 CFR part 220 (OMB Circular A-21,
“Cost Principles for Educational Institutions”); former 2 CFR part 225 (OMB
Circular A-87, “Cost Principles for State, Local, and Indian Tribal Governments”);
former 2 CFR part 230 (OMB Circular A-122, “Cost Principles for Non-Profit
Organizations”); or Federal acquisition regulations subpart 31.2 (48 CFR chapter I,
subpart 31.2), which covers for-profit organizations. The following list contains
examples of cost elements that might require prior approval:
(a) Capital expenditures (Note: All equipment [see Definitions] not identified and
approved in the award document requires prior approval).
(b) Costs of membership in civic, community, and social organizations as a direct
cost,
(c) Preaward costs,
(d) Proposal costs as a direct charge,
(e) Travel costs of certain officials and foreign travel,
(f) Premiums for overtime, training, and education costs, and
(g) Travel costs higher than maximum per diem rates.
c. Obtaining Prior Approval.
(1) Budget Approvals. Cost elements included in the original application and
approved project budget constitute prior approval. Prior approvals related to the
Page IV–10
FTA C 6100.1E
changes in the approved project budget or cost elements should be submitted as a
budget revision in FTA’s electronic award and management system no later than
thirty days before the proposed change (see Section 6 below, “Project
Modifications”).
(2) Other Prior Approvals. Other requests for approvals should be submitted to the
FTA administering office in writing or by email by an authorized official of the
recipient with an explanation of the prior approval requested no later than thirty
days before the proposed change.
(3) Authorized FTA Official. An authorized FTA official may grant prior approval in
writing, by email, or through approval in FTA’s electronic award and management
system.
(4) Failure to Obtain Prior Approval. Failure to obtain required prior approval from
the appropriate administering office may result in the disallowance of costs,
termination of the award, or other enforcement action within FTA’s authority.
6. PROJECT MODIFICATIONS. The recipient is responsible for controlling and monitoring
all project activities to ensure that they are carried out in accordance with the approved
project budget. The manner in which an approved project budget is initially structured
during the application phase can facilitate or impede project management, particularly
when unforeseen events require changes in the project.
Nevertheless, it may be necessary to modify a cooperative agreement, grant agreement, or
other agreement after Federal assistance has been awarded by revising the approved project
budget or amending the agreement. There are three ways to modify a project after Federal
assistance has been awarded: (1) through a budget revision, (2) through an administrative
amendment, or (3) through an amendment to the agreement. Whether a budget revision
may be permitted (with or without prior FTA approval before incurring costs), or whether
an amendment to the project will be necessary, depends on the effect of the proposed
change on the scope of the project. If an ALI is added to an existing scope, the budget
revision may be sent to the DOL for informational purposes, but the labor protection
arrangements for the original project will apply to any project modifications without further
DOL certification. Recipients should contact the administering office for questions relating
to project modification requests, including which project modification is appropriate for the
proposed action.
Project modifications are electronically submitted, reviewed, and approved in FTA’s
electronic award and management system.
a. Budget Revision.
(1) General. Budget revisions may be made as long as there is no change in the
recipient, purpose, scope codes, and Federal funding for the project, regardless of
the fiscal year the Federal assistance for which the funding was appropriated.
FTA C 6100.1E
Page IV–11
Budget revisions generally are changes to ALI amounts or descriptions. A budget
revision cannot be used to materially change the purpose or intent, such as the
scope, or Federal dollar amount of the Federal assistance award. Budget revisions
must be consistent with the activities contained in the SOW.
(2) Procedures. Recipients must submit a budget revision in FTA’s electronic award
and management system using the “revise project budget” screen. Budget revision
requests must include a reason for the revision. For each ALI being adjusted, either
by quantity or dollar amount, recipients must include a brief explanation and
impact to the project in the “details” section for the change being requested. If
necessary, additional information can be provided using the attachments feature in
FTA’s electronic award and management system. The FTA reviewer will return
incomplete budget revisions to the recipient for inclusion of additional
information. For assistance with completing budget revisions, please contact the
FTA administering office.
A recipient may request a budget revision either before or after incurring costs,
depending on the nature of the request. If the budget revision meets the criteria
outlined below in paragraph (3), FTA concurrence is required before incurring
costs associated with the proposed change.
(3) Budget Revisions that Require Prior Approval. Under certain circumstances, a
recipient must obtain FTA approval before incurring costs for proposed budget
revisions. For these projects, the proposed budget revision must be submitted in
FTA’s electronic award and management system and approved before incurring
costs associated with the budget revision. If FTA determines the proposed budget
revision does not meet the criteria for a budget revision, alternative methods for
modifying the project, such as an amendment to the cooperative agreement, grant
agreement, or other agreement, may be recommended. The FTA administering
office will make this determination during its review. Prior FTA approval must be
obtained if the proposed budget revision meets any of the following criteria:
(a) The Federal share of the project exceeds $100,000 and the cumulative amount
of such transfers exceeds or is expected to exceed 20 percent of the total
budget as last approved.
(b) The addition of an ALI to an existing scope included in the project, provided
that the request does not change the amount of Federal assistance awarded in
original the cooperative agreement, grant agreement, or other agreement or
change the scope of the project as stated in the agreement.
(c) See subsection 5b, “Requirements for Prior Approvals,” of this circular above
for a listing of other budget revisions that require prior approval.
b. Administrative Amendment. An administrative amendment is usually initiated by FTA
and may only be used when no change will result in the scope, amount, or purpose of
the project. An administrative amendment may be used to change or clarify the terms,
Page IV–12
FTA C 6100.1E
conditions or provisions of a cooperative agreement, grant agreement, or other
agreement. An administrative amendment is also used to change the year or type of
Federal assistance obligated for a project to transfer equipment from one recipient to
another, to reflect a change in the recipient or recipient’s name, or to deobligate Federal
assistance that is no longer needed to complete the scope or purpose of the approved
project.
c. Amendment to the Agreement.
(1) General. An amendment to the cooperative agreement, grant agreement, or other
agreement is required when there is either a change in the scope or an addition of
Federal assistance to an existing agreement. Amendments to those agreements are
subject to the same application requirements as a new Federal assistance request.
Amendments are subject to DOL certification, if applicable.
(2) Procedure. Recipients must submit requests for amendments to their agreements in
FTA’s electronic award and management system using the “Create Amendment”
screen. Amendments revise a cooperative agreement, grant agreement, or other
agreement, including a revised budget, and may require a change in the amount of
Federal assistance obligated under that agreement. An amendment is subject to the
same requirements as a new Federal assistance request except that the recipient
need not resubmit portions of its original application that are unaffected by the
change. The recipient must submit a detailed description of the changes and a
revised project budget. For example, in FTA’s electronic award and management
system under the project details section for the project, recipients should include a
header, “Amendment #1 (or the appropriate number),” and describe the reason for
the amendment and the changes to the project or budget or both.
(3) Change of Scope. FTA requires an amendment if the request changes the overall
scope of a project or changes the project scopes within the cooperative agreement,
grant agreement, or other agreement. Examples of changes in scope and an
exception to changes in scope that result in an amendment to the agreement
include:
(a) Examples of change in scope.
1
A change in the central tasks outlined in the SOW, or
2
The addition of a new project scope code or the deletion of a project scope
code if the deletion affects the intent or objectives of the project.
(b) Exception to change in scope. For earmarks, all changes to the project after
award of Federal assistance must be consistent with the original intent of
the congressional language. Your FTA administering office will assist you in
making this determination. For example, if the earmark is for research on fuel
cells, an amendment to the cooperative agreement, grant agreement, or other
FTA C 6100.1E
Page IV–13
agreement cannot be executed to change the scope to research on flywheels
without explicit direction from Congress to FTA to change the earmark.
(4) Change in Federal Assistance. FTA requires an amendment to the cooperative
agreement, grant agreement, or other agreement if the request changes the total
amount of Federal assistance for the agreement. The one exception is that if the
scope of a project is unchanged and the only action is the deobligation of Federal
assistance, an administrative amendment is used to process the modification. See
section 6.b, “Administrative Amendment,” of this chapter above.
7. EQUIPMENT. Certain management standards apply to equipment purchased with Federal
assistance:
a. Title. Title to equipment acquired by a recipient or subrecipient with Federal assistance
must vest in the recipient or subrecipient, respectively, subject to conditions of this
section.
b. State Recipients. A state may use, manage and dispose of equipment acquired under a
project by the state in accordance with state laws and procedures, as long as the state
complies with Federal requirements. See 2 CFR 1201 or former 49 CFR part 18, as
applicable.
c. Recipients Other than States. Other recipients must follow FTA requirements and
procedures outlined below.
(1) Use for the Project. The recipient must use the equipment in the project or program
for which it was acquired as long as needed, whether or not the project or program
continues to be supported by Federal assistance, and may not encumber the
equipment without approval of FTA. When no longer needed for the original
project or program, the recipient must use the equipment in connection with its
other federally sponsored activities, in the following order of priority:
(a) Activities sponsored by FTA, then
(b) Activities sponsored by other Federal awarding agencies.
(2) Use Outside the Project. During the time that equipment is used for the project or
program for which it was acquired, the recipient must make it available for use on
other projects or programs if such other use will not interfere with the work on the
project or program for which the equipment was originally acquired. First
preference for such other use must be given to other projects or programs
sponsored by FTA, and second preference must be given to projects or programs
sponsored by other Federal awarding agencies. If the equipment is owned by the
Federal Government, use on other activities not sponsored by the Federal
Government may be permissible if authorized by FTA. User charges must be
treated as program income.
Page IV–14
FTA C 6100.1E
(3) Fees for Other than Project Use. The recipient may not use equipment acquired
with Federal assistance to provide services to an entity for a fee that is less than
private companies charge for equivalent services, unless specifically authorized by
Federal law, for as long as the Federal Government retains an interest in the
equipment.
(4) Acquiring Replacement Property. When acquiring replacement equipment, the
recipient may use the equipment to be replaced for trade-in or sell the equipment
and use the proceeds to offset the costs of the replacement equipment, subject to
FTA approval.
(5) Property Management Standards. The recipient’s property management standards
for equipment acquired with Federal assistance and federally owned equipment
must include all of the following:
(a) Equipment Records. Accurate equipment records must be maintained and
must include the following information:
1
A description of the equipment.
2
The manufacturer’s serial number, model number, Federal stock number,
national stock number, or other identification number,
3
The source of the equipment, including the award number,
4
Whether title vests in the recipient or the Federal Government,
5
Acquisition date (or date received, if the equipment was furnished by the
Federal Government) and cost.
6
Information from which one can calculate the percentage of Federal
participation in the cost of the equipment (not applicable to equipment
furnished by the Federal Government),
7
The location and condition of the equipment and the date the information
was reported,
8
The unit acquisition cost, and
9
The Ultimate disposition data, including date of disposal and sales price,
or the method used to determine current fair market value where a
recipient compensates FTA for its share.
(b) Federal Ownership. Equipment owned by the Federal Government must be
identified to indicate Federal ownership.
FTA C 6100.1E
Page IV–15
(c) Inventory. A physical inventory of equipment must be taken and the results
reconciled with the equipment records at least once every two years. Any
differences between quantities determined by the physical inspection and
those shown in the accounting records must be investigated to determine the
causes of the difference. The recipient must, in connection with the inventory,
verify the existence, current utilization, and continued need for the equipment.
(d) Control. A control system must be in effect to ensure adequate safeguards to
prevent loss, damage, or theft of the equipment. Any loss, damage, or theft of
equipment must be investigated and fully documented. If the equipment was
owned by the Federal Government, the recipient must promptly notify the
FTA.
(e) Maintenance. Adequate maintenance procedures must be implemented to keep
the equipment in good condition.
(f) Disposition. When the recipient no longer needs the equipment, the equipment
may be used for other activities in accordance with the following standards of
the Common Rules, 2 CFR part 1201 or former 49 CFR part 18 or 19, as
applicable:
1
Items of equipment with a current per-unit fair market value of less than
$5,000 may be retained, sold, or otherwise disposed of with no further
obligation to FTA.
2
For equipment with a current per unit fair market value of $5,000 or more,
the recipient may retain the equipment for other uses provided that
compensation is made to FTA or its successor. The amount of
compensation must be computed by applying the percentage of Federal
participation in the cost of the original project or program to the current
fair market value of the equipment.
3
If the recipient has no need for the equipment, the recipient must request
disposition instructions from the FTA. FTA must determine whether the
equipment can be used to meet its requirements. If no requirement exists
within FTA, FTA must report the availability of the equipment to the
General Services Administration (GSA) by FTA to determine whether a
requirement for the equipment exists in other Federal agencies. FTA must
issue instructions to the recipient no later than 120 calendar days after the
recipient’s request and the following procedures must govern.
a
If so instructed, or if disposition instructions are not issued within 120
calendar days after the recipient’s request, the recipient must sell the
equipment and reimburse FTA an amount computed by applying to the
sales proceeds the percentage of Federal participation in the cost of the
equipmentm. However, the recipient must be permitted to deduct and
Page IV–16
FTA C 6100.1E
retain from the Federal share $500 or 10 percent of the proceeds,
whichever is less, for the recipient’s selling and handling expenses.
4
5
b
If the recipient is instructed to ship the equipment elsewhere, the
recipient FTA must reimiburse the recipient an amount which is
computed by applying the percentage of the recipient’s participation in
the cost of the equipment sold to the current fair market value of the
equipment, plus any reasonable shipping or interim storage costs
incurred.
c
If the recipient is instructed to dispose of the equipment otherwise,
FTA must reimburse the recipient the proportionate amount of the
recipient’s interest in such equipment and such costs incurred in the
disposition of that equipment.
FTA may reserve the right to transfer the title to the Federal Government
or to a third party named by the Federal Government when the third party
is otherwise eligible under existing laws. Such transfer must be subject to
the following standards:
a
The equipment must be appropriately identified in the award or
otherwise made known to the recipient in writing,
b
FTA must issue disposition instructions within 120 calendar days after
receipt of a final inventory. The final inventory must list all equipment
acquired with Federal assistance for the project and federally owned
equipment. If FTA fails to issue disposition instructions within the
120-calendar-day period, the recipient must apply the standards of this
section, as appropriate, and
c
When FTA exercises its right to take title, the equipment must be
subject to the provisions for federally owned equipment.
Sales Procedures. Where the recipient is authorized or required to sell the
equipment, proper sales procedures must be established that provide for
competition to the extent practicable and result in the highest possible
return.
(g) FTA’s Special Disposition Authority. Under 49 U.S.C. 5334(h), FTA may
authorize the recipient to transfer property acquired with financial assistance
under 49 U.S.C. chapter 53 to a local governmental authority to be used for a
public purpose with no further obligation to the Federal Government, if FTA
determines in writing that:
1
The property will remain in public use for at least five years after the date
transferred;
FTA C 6100.1E
Page IV–17
2
There is no purpose eligible for assistance under 49 U.S.C. chapter 53 for
which the property should be used;
3
The overall benefit of allowing the transfer is greater than the interest of
the Federal Government in liquidation and return of the financial interest
of the government in the property, after considering fair market value and
other factors; and
4
Through an appropriate screening or survey process, there is no interest in
acquiring the property, if land or a facility, for Federal Government use.
(h) Special Authority for Nonprofit Institutions of Higher Education or
Educational Institutions and Nonprofit Scientific Research Organizations.
FTA may vest title in tangible personal property in a nonprofit institution of
higher education or in a nonprofit organization whose primary purpose is
conducting scientific research:
1
When the property is bought with amounts provided under a cooperative
agreement, grant agreement, or direct procurement contract with the
institution or organization to conduct basic or applied scientific research,
2
When FTA decides the vesting furthers the objectives of the agency,
3
Without further obligation to the Federal Government, and
4
Under conditions FTA considers appropriate.
8. INTANGIBLE PROPERTY. Certain standards apply to intangible property resulting from
Federal assistance.
a. Recipients are subject to applicable regulations governing patents and inventions,
including governmentwide regulations issued by the Department of Commerce at
37 CFR part 401, “Rights to Inventions Made by Nonprofit Organizations and Small
Business Firms Under Government Grants, Contracts and Cooperative Agreements.”
b. The recipient may copyright any work that is subject to copyright and was developed,
or for which ownership was purchased with Federal assistance. FTA reserves a royaltyfree, nonexclusive, and irrevocable right to reproduce, publish, or otherwise use the
work for Federal purposes, and to authorize others to do so.
c. The Federal Government has the right to:
(1) Obtain, reproduce, publish, or otherwise use the data first produced under an
award, and
(2) Authorize others to receive, reproduce, publish, or otherwise use such data for
Federal purposes.
Page IV–18
FTA C 6100.1E
d. Special provisions for research, development, demonstration, deployment, and
technical evaluation projects apply. FTA’s standard position pertaining to rights in data
developed under a research, development, demonstration, deployment, or technical
evaluation project is to increase transportation knowledge, rather than limit the benefits
of the project to project participants. Therefore, FTA generally expects the recipient to
provide a report at the end of the project that FTA may publish or make available for
publication on the internet, in addition to any report that FTA may request that would
contain proprietary information.
Except to the extent that FTA determines otherwise in writing, the recipient of Federal
assistance to support a research, development, demonstration, or a special studies
project agrees that, in addition to the rights in data and copyrights that it must provide
to the Federal Government, the rights described in U.S. DOT regulations, 2 CFR
part 1201 or former 49 CFR parts 18 or 19, as applicable. However, FTA’s Master
Agreement also states the Recipient’s agreement that FTA may make available to any
FTA recipient, subrecipient, third-party contractor, third-party subcontractor, or other
participant at any tier of the project, either FTA’s license in the copyright to the subject
data or a copy of the subject data. FTA provides an exception for adaptations of
automatic data processing equipment or programs for the recipient’s use when the costs
thereof are financed through an FTA capital program.
e. In addition, in response to a Freedom of Information Act (FOIA) request for research
data relating to published research findings produced under an award that were used by
the Federal Government in developing an agency action that has the force and effect of
law, FTA must request, and the recipient must provide within a reasonable time, the
research data so that data can be made available to the public through the procedures
established under the FOIA. If FTA obtains the research data solely in response to a
FOIA request, the Federal agency may charge the requester a reasonable fee equaling
the full incremental cost of obtaining the research data. This fee should reflect costs
incurred by the agency, the recipient, and applicable subrecipients. This fee is in
addition to any fees the agency may assess under the FOIA. See 5 U.S.C. 552(a)(4)(A).
(1) The following definitions apply for purposes of this Subsection 8.e:
(a) “Research data” is defined as the recorded factual material commonly
accepted in the scientific community as necessary to validate research
findings, but not any of the following: preliminary analyses, drafts of
scientific papers, plans for future research, peer reviews, or communications
with colleagues. This “recorded” material excludes physical objects (e.g.,
laboratory samples). Research data also do not include: (1) trade secrets,
commercial information, materials necessary to be held confidential by a
researcher until they are published, or similar information that is protected
under law; and (2) personnel and medical information and similar information
the disclosure of which would constitute a clearly unwarranted invasion of
FTA C 6100.1E
Page IV–19
personal privacy, such as information that could be used to identify a
particular person in a research study.
(b) “Published” is defined as either when:
1
Research findings are published in a peer-reviewed scientific or technical
journal, or
2
A Federal agency publicly and officially cites the research findings in
support of an agency action that has the force and effect of law.
(c) “Used by the Federal Government in developing an agency action that has the
force and effect of law” is defined as when an agency publicly and officially
cites the research findings in support of an agency action that has the force
and effect of law.
f.
Title to intangible property and debt instruments acquired under an award or subaward
vests upon acquisition in the recipient. The recipient must use that property for the
originally authorized purpose and the recipient must not encumber the property without
FTA approval.
g. When no longer needed for the originally authorized purpose, disposition of the
intangible property must occur using procedures similar to those of Chapter IV,
paragraph 7.c of this circular, as applicable.
9. SUPPLIES. Certain management standards apply to supplies purchased with Federal
assistance. Supplies are all tangible personal property other than equipment with a unit
value of less than $5,000.
a. Title to supplies and other expendable property must vest in the recipient upon
acquisition. If there is a residual inventory of unused supplies exceeding $5,000 in total
aggregate fair market value upon termination or completion of the project or program,
and if the supplies are not needed for any other federally sponsored project or program,
the recipient may retain the supplies for use on federally sponsored activities or sell
them, but must, in either case, compensate the Federal Government for the Federal
share. The amount of compensation must be computed in the same manner as for
equipment.
b. The recipient may not use supplies acquired with Federal assistance to provide services
to other than Federal organizations for a fee that is less than private companies charge
for equivalent services, unless specifically authorized by Federal law as long as the
Federal Government retains an interest in the supplies.
10. THIRD-PARTY PROCUREMENT.
a. Recipient’s Administrative Responsibilities. The recipient is the responsible authority,
without recourse to FTA, regarding the settlement and satisfaction of all contractual
Page IV–20
FTA C 6100.1E
and administrative issues arising out of procurements entered in support of a project.
This includes disputes, claims, protests of award, source evaluation, or other matters of
a contractual nature. Matters concerning violation of a law are to be referred to such
Federal, state, or local authority as may have proper jurisdiction.
b. FTA Procurement Guidance. The most important and comprehensive source of thirdparty procurement information for FTA-assisted projects is contained in FTA Circular
4220.1F, “Third Party Contracting Guidance.” The circular provides guidance on
FTA’s procurement requirements in light of the Common Rules, 49 CFR part 1201 or
former 49 CFR part 18 or 19, as applicable. We strongly recommend that the recipient
thoroughly review the laws and regulations set forth in the latest edition of Appendix A
of FTA Circular 4220.1F and FTA’s recommendations within the circular on how to
comply with the statutory and regulatory requirements that apply to contracts supported
by FTA assistance.
c. Third-Party Contract Checklists. See Appendix D of FTA Circular 4220.1F, “Third
Party Contracting Guidelines,” for a list of applicable matters to be considered when
entering into third-party contracts.
11. PROJECT CLOSEOUT. Project closeout is the term used to signify the process by which
FTA determines that all activities in a project are complete and Federal assistance has been
expended. Project closeout does not preclude FTA’s ability to seek repayment or other
remedies for a recipient’s breach of project terms and conditions.
a. Recipient’s Role and Responsibilities. The recipient must initiate closeout of a project
when all approved activities are completed and the applicable Federal assistance is
expended. All closeout documentation must be submitted within ninety days of the
completion of all activities in the project or completion of the project period. This
requires notifying FTA by letter or email that the project is ready for closeout. The
recipient should electronically submit the following in FTA’s electronic award and
management system as part of the project closeout process:
(1) A final budget reflecting actual project costs by scope and activity,
(2) A final FFR,
(3) A final narrative MPR or final technical report indicating the actual completion
date of each task and a discussion of each task contained in the final budget,
(4) An inventory list of any federally owned equipment used in the project and an
inventory of equipment acquired with project funds. When the project ends, it is
FTA’s view that the project property is no longer needed for research,
development, or demonstration purposes. FTA may authorize the transfer of that
property in accordance with at 49 CFR part 1201, former 49 CFR parts 18 or 19,
49 U.S.C. 5334(g) and (h), or 31 U.S.C. 6306, as applicable. The FTA project
FTA C 6100.1E
Page IV–21
manager will issue disposition instructions within 120 calendar days after receipt
of the final inventory list,
(5) A request to deobligate any unexpended balance of Federal assistance, and
(6) Any other reports required as part of the terms and conditions of the cooperative
agreement, grant agreement, or other agreement.
b. Closeout by FTA. FTA may unilaterally initiate project closeout. Circumstances that
could cause FTA to close out a project in whole or in part at any time before project
completion include:
(1) The recipient’s failure to comply with the terms or conditions of the cooperative
agreement, grant agreement, other agreement, or other Federal requirements,
(2) Continuation of the project would not produce results commensurate with further
expenditure of Federal assistance,
(3) Federal assistance is no longer needed to accomplish the purpose of the project,
(4) Failure by the recipient to make reasonable progress to complete the approved
project activities, or
(5) A determination that the project has been essentially completed and/or approved
and Federal assistance has been substantially drawn down.
c. Adjustments to the Federal Share of Costs. Necessary adjustments to the Federal share
of project costs are made after FTA receives and reviews the required project closeout
information. Adjustments may also be necessary after the annual audit required by 2
CFR part 1201 is performed. After a project has been closed, FTA assistance is not
available for audit or other project activities. Additional information on the 2 CFR
part 1201 annual audit is contained in Chapter V, “Financial Management,” of this
circular. Any Federal assistance received for the project by the recipient but not
expended must be returned to FTA. For more information on returning Federal
assistance to FTA, see Chapter V, “Financial Management.”
12. SUSPENSION. The suspension of a cooperative agreement, grant agreement, or other
agreement is an action by FTA which temporarily suspends Federal assistance for a project
pending corrective action by the recipient or pending a decision by FTA to terminate the
agreement. If FTA determines that the recipient has failed to comply with the terms and
conditions of the agreement, including the Federal civil rights requirements, FTA notifies
the recipient in writing of its intent to suspend its Federal assistance award. FTA may
withhold further payments and/or prohibit the recipient from incurring additional
obligations pending corrective action by the recipient or a decision to terminate the
agreement for cause. This includes work being performed by third-party contractors or
consultants. Unless FTA notifies the recipient otherwise, suspension will not invalidate
Page IV–22
FTA C 6100.1E
obligations properly incurred by the recipient prior to the date of suspension to the extent
that they cannot be cancelled.
13. TERMINATION.
a. Termination for Cause. FTA may terminate a cooperative agreement, grant agreement,
or other agreement, in whole or in part, at any time before project completion,
whenever FTA determines that the recipient failed to comply with the terms and
conditions of the agreement including failure to make reasonable progress. FTA will
promptly notify the recipient in writing of its intent to terminate Federal assistance and
the reasons therefor, and the effective date. Payments made to the recipient or
recoveries by FTA are in accordance with the terms of the agreement and the legal
rights and liabilities of both parties as defined in the agreement.
b. Termination for Purposes of Law. By signing the agreement, the recipient agrees at the
outset to a termination in the event the Federal Government determines that the
purposes of the laws authorizing the project would not be adequately served by the
continuation of Federal assistance for the project.
c. Termination for Convenience. FTA and the recipient may terminate a cooperative
agreement, grant agreement, or other agreement as follows:
(1) By FTA with the consent of the recipient, in which case FTA and the recipient
must agree upon the termination conditions, including the effective date and, in the
case of partial termination, the portion to be terminated, or
(2) By the recipient upon sending to FTA written notification setting forth the reasons
for such termination, the effective date, and, in the case of partial termination, the
portion to be terminated. However, if FTA determines in the case of partial
termination that the reduced or modified portion of the project will not accomplish
the purposes for which the Federal assistance was awarded, FTA may terminate the
agreement in its entirety.
The recipient may not incur new obligations for the terminated portion of the
project after the effective date of the termination and must cancel as many
outstanding obligations as possible. FTA evaluates each obligation to determine its
eligibility for inclusion in project costs. Settlement is made in accordance with
terms and conditions of the cooperative agreement, grant agreement, or other
agreement. FTA allows full credit to the recipient for the Federal share of the
obligations (that cannot be cancelled) when properly incurred by the recipient prior
to termination.
d. Partial Termination. In some cases, FTA may deobligate FTA assistance in an approved
project before closeout because FTA assistance is no longer needed to accomplish the
purpose of the project.
FTA C 6100.1E
Page IV–23
14. RETENTION AND ACCESS REQUIREMENTS FOR RECORDS.
a. Applicability. This section applies to all financial and programmatic records,
supporting documents, statistical records, and other records of recipients. Records
retention and access requirements must apply to the recipient’s contractors,
subcontractors, and subrecipients. Recipients must include this requirement in recipient
contracts and/or subagreements. These records include:
(1) Those records required to be maintained by this circular or by the terms of the
cooperative agreement, grant agreement, other agreement, or otherwise considered
pertinent to FTA program requirements or the Master Agreement, and
(2) Those records executed electronically which may be retained in that same manner.
Copies made by microfilming, photocopying, or similar methods may be substituted for
the original records. Files must be accessible for possible review, audit, or downloading
to paper when required.
b. Length of Retention Period.
(1) Except as otherwise specified, records must be retained for three years from the
starting date as specified below in Chapter IV, subsection 14.c of this circular, and
(2) If any litigation, claim, negotiation, audit, or other action involving the records has
been started before the expiration of the three-year period, the records must be
retained for three years after completion of the action and resolution of all issues
that arise from it.
To avoid duplicate record keeping, FTA may make special arrangements with
recipients (including subrecipients, as appropriate) to retain any records that are
continually needed for joint use. FTA will request transfer of records to its custody
when it determines that the records possess long-term retention value. When the
records are transferred to or maintained by FTA, the three-year retention requirement is
not applicable to the recipient.
c.
Starting Date of Retention Period.
(1) General. The starting date for retention of records related to multiyear projects is
the date of submission of the final FFR upon project completion or, if waived, the
date it would have been due.
(2) Equipment records. The retention period for the equipment records starts from the
date of the equipment’s disposition, replacement, or transfer at FTA’s direction.
(3) Records for income transactions after project closeout. In some cases recipients
must report income after a project is closed out. Where there is such a requirement,
Page IV–24
FTA C 6100.1E
the retention period for the records pertaining to the earning of the income starts
from the end of the recipient’s fiscal year in which the income is earned.
(4) Indirect Cost Rate Proposals, Cost Allocation Plans (CAPs) and Similar Rate, and
Rate Allocation Methods. This paragraph applies to the following types of
documents and their supporting records: indirect cost rate computations or
proposals, CAPs, and any similar accounting computations or the rate at which a
particular group of costs is chargeable (such as computer usage charge back rates
or composite fringe benefit rates).
(a) If submitted for negotiation: If the proposal, plan, or other computation is
required to be submitted to the Federal Government (or to the recipient) to
form the basis for negotiation of the rate, then the three-year retention period
for its supporting records starts from the date of such submission.
(b) If not submitted for negotiation: If the proposal, plan, or other computation is
not required to be submitted to the Federal Government (or to the recipient)
for negotiation purposes, then the three-year retention period for the proposal,
plan, or computation and its supporting records starts from the end of the
fiscal year (or other accounting period) covered by the proposal, plan, or other
computation.
(5) Contract Records. The retention period for all required contract records
commences after the recipients or subrecipients make final payments and all other
pending matters are closed.
d. Substitution of Photocopies. Copies of documents may be substituted for the originals.
e. Access to Records.
(1) Records of recipients and subrecipients. FTA staff members, the U.S. DOT Office
of Inspector General, and the Comptroller General of the United States, or any of
their authorized representatives, have the right of access to any books, documents,
papers, or other records of the recipient that are pertinent to the project, in order to
perform audits, or make examinations, excerpts, or transcripts.
(2) Expiration of right of access. The right of access in this section is not limited to the
required retention period, but continues as long as the records are retained.
f.
Restrictions on Public Access. Except as provided in subsection 8.e of this chapter, the
Federal Freedom of Information Act (FOIA), 5 U.S.C. 552, does not apply to recipient
records owned and possessed by the recipient that have not been submitted to the
Federal Government. Unless required by state or local law, recipients and subrecipients
are not required to provide periodic public access to their records.
FTA C 6100.1E
Page IV–25
However, FTA may direct a recipient to provide access to those records the recipient
maintains on behalf of FTA (i.e., records required by Federal law or regulation, such as
Davis-Bacon wage records), or other records necessary to determine compliance with
Federal requirements established as conditions of eligibility for recipients of Federal
funding. FOIA, however, does apply to records the recipient submits to FTA.
FTA C 6100.1E
Page V–1
CHAPTER V
FINANCIAL MANAGEMENT
1. GENERAL. This chapter discusses the proper use and management of Federal assistance
that the Federal Transit Administration (FTA) expects from its recipients. Financial
management is one of the most important responsibilities in the management of Federal
assistance.
2. INTERNAL CONTROLS.
a. Definition. Internal controls are the organization plan, methods, and procedures
adopted by the recipient to ensure that effective control and accountability is
maintained for all recipient and subrecipient projects, cash, real and personal property,
and other assets. Recipients and subrecipients must ensure that resources are properly
used and safeguarded, and that they are used solely for authorized purposes.
b. General. FTA payments to a recipient are made electronically to meet the Federal share
of eligible expenses under a federally assisted project.
The recipient’s execution of an award of FTA assistance requires the recipient to use
the Federal assistance it receives as specified in the underlying cooperative agreement,
grant agreement, or other agreement. This creates a vested interest by the Federal
Government in unused balances of any Federal assistance, improperly applied Federal
assistance, and property or facilities purchased or otherwise acquired under the project,
whether federal assistance is received by the recipient as an advance or by
reimbursement.
Recipients and subrecipients are responsible for establishing and maintaining adequate
internal controls over all their functions that affect implementation of a federally
assisted project.
For proper project management, these controls must be used by each recipient in all its
operating, accounting, financial, and administrative systems. To assure proper
accountability for Federal assistance, internal controls must be integrated with the
management systems used by the recipient to regulate and guide its operations.
c. Objectives. Resources must be used in accordance with applicable Federal, state, and
local laws, regulations, and policies and the cooperative agreement, grant agreement, or
other agreement. Resources must be safeguarded against waste, loss, and misuse.
Reliable data on resource use and safeguards must be accumulated, maintained, and
fairly disclosed in reports to the recipient’s management and FTA. A proper system of
internal controls will help the recipient to:
(1) Operate efficiently and economically,
Page V–2
FTA C 6100.1E
(2) Keep obligations and costs within the limits of authorizations and legal
requirements, consistent with accomplishing the purpose of the project,
(3) Safeguard assets against waste, loss, and misuse,
(4) Ensure timely collection and proper accounting of the recipient’s operating and
other revenues, and
(5) Ensure accuracy and reliability in financial, statistical, and other reports.
d. Necessary Elements. Certain elements are necessary to achieve the objectives
mentioned above in subsection 2.c of this chapter of the circular and meet the standards
discussed below in subsection 2.e. The following objectives and standards facilitate the
recipient’s use of internal controls:
(1) Reasonable assurance that internal controls are an integral part of the recipient’s
management systems,
(2) A positive and supportive attitude among recipient managers and employees,
(3) Assignment of internal control functions to competent and experienced employees,
(4) Identification of specific internal control objectives to assure that needs are
identified and that valid controls are planned and implemented,
(5) Adoption of internal control policies, plans, and procedures that reasonably assure
their effectiveness, such as organizational separation of duties and physical
arrangements such as locks and fire alarms, and
(6) A regular program of testing to identify vulnerabilities in the internal control
system.
e. Standards of Internal Control and Audit Resolutions.
(1) General.
(a) Recipient management policies that govern project implementation must be
clearly stated, understood throughout the organization, and conformed to
applicable legislative and administrative requirements.
(b) The recipient’s formal organization structure must clearly define, assign, and
delegate appropriate authority for all duties.
(c) Responsibility for duties and functions must be segregated within the
organization to assure that adequate internal checks and balances exist.
Recipients should pay particular attention to authorization, performance,
recording, inventory control, and review functions to reduce the opportunity
for unauthorized or fraudulent acts.
FTA C 6100.1E
Page V–3
(d) A system of organizational planning should exist to determine financial,
property, and personnel resource needs.
(e) Written operating procedures should be simply stated, yet meet the recipient’s
operating, legal, and regulatory requirements. In developing its procedures,
the recipient should consider such factors as feasibility, cost, risk of loss or
error, and availability of suitable personnel. Other important considerations
are the prevention of illegal or unauthorized transactions or acts.
(f) The recipient’s information system must reliably provide needed operating
and financial data for decision making and performance review.
(g) The recipient must provide proper supervision, and performance must be
subject to review of an effective internal audit program.
(h) All personnel must be properly qualified for their assigned responsibilities,
duties, and functions. Education, training, experience, competence, and
integrity should be considered in assigning work. All must be held fully
accountable for the proper discharge of their assignments.
(i) Expenditures must be controlled so that construction, equipment, goods, and
services are acquired and received as contracted for (as to quality, quantity,
prices, and time of delivery). Authorizations for expenditures must conform to
applicable laws, regulations, and policies.
(j) All real property, equipment, expendables, and Federal assistance must be
safeguarded to prevent misuse, misappropriation, waste, or unwarranted
deterioration or destruction.
(2) Internal Control Self-Assessment. Recipients should evaluate their internal control
and financial management systems to ensure they are effective. To assist with the
evaluation, FTA developed an example of an internal control self-assessment
form. While designed for public transportation agencies, most of the principles
apply to other types of organizations that may also find it useful. The optional
form is designed to provide management staff with the information necessary to
evaluate their internal control and financial management system. The form is
based on the criteria for effective internal control as set forth in Internal Control—
Integrated Framework published by the Committee of Sponsoring Organizations of
the Treadway Committee (the COSO Report), as well as the criteria for effective
financial management systems established by FTA, based on the Common Grant
Rules, 49 CFR part 1201 or former 49 CFR parts 18. Recipients may access the
internal control self-assessment form at the following website:
http://www.fta.dot.gov/documents/FTA_Internal_Control_SelfAssessment_Tool.pdf.
(3) Financial Management Systems.
Page V–4
FTA C 6100.1E
(a) States. A state must expend and account for Federal assistance for its projects
in accordance with state laws and procedures for expending and accounting
for its own funds. Fiscal control and accounting procedures of the state, as
well as its subrecipients and cost-type third-party contractors, must be
sufficient to:
1
Permit preparation of reports required by the Common Rule, 49 CFR part
1201 or former 49 CFR parts 18 or 19, as applicable, and the laws
authorizing the Federal assistance, and
2
Permit the tracing of funds to a level of expenditures adequate to establish
that such Federal assistance has not been used in violation of the
restrictions and prohibitions of applicable laws.
(b) Entities Other than a State. The financial management systems of other
recipients and subrecipients must meet the following standards:
1
Financial Reporting. Accurate, current, and complete disclosure of the
financial results of federally assisted activities must be made in
accordance with financial reporting.
2
Accounting Records. Recipients and subrecipients must maintain records
that adequately identify the source and application of Federal assistance
provided for federally assisted activities. These records must contain
information pertaining to recipient or subrecipient awards and
authorizations, obligations, unobligated balances, assets, liabilities, outlays
or expenditures, and income.
3
Internal Control. Effective control and accountability must be maintained
for all cash, real and personal property, and other assets within the
recipients’ and subrecipients’ projects. Recipients and subrecipients must
adequately safeguard all such property and must assure that it is used
solely for authorized purposes.
4
Budget Control. Actual expenditure or outlays must be compared with
budgeted amounts for each recipient or subrecipient project. Financial
information must be related to performance or productivity data, including
the development of unit cost information whenever appropriate or
specifically required in the cooperative agreement, grant agreement, other
agreement, or subagreement. If the unit cost data are required, estimates
based on available documentation will be accepted whenever possible.
5
Allowable Cost. Applicable Office of Management and Budget (OMB)
cost principles, as stated in 2 CFR part 1201 or former 2 CFR part 220,
225, or 230, and Federal Acquisition Regulation (FAR) subpart 31.2,
agency program regulations, and the terms of the underlying cooperative
FTA C 6100.1E
Page V–5
agreement, grant agreement, other agreement, or subagreement determine
allowability and allocability of costs.
6
Source Documentation. Accounting records must be supported by such
source documentation as cancelled checks, paid bills, payrolls, time and
attendance records, and third-party contract and subagreement award
documents.
7
Cash Management. Procedures for minimizing the time elapsing between
the transfer of Federal assistance from the Department of the Treasury
(Treasury) and disbursement by recipients and subrecipients must be
followed whenever advance payment procedures are used. Recipients
must establish reasonable procedures to ensure that the reports on
subrecipients’ cash balances and cash disbursements are received in
sufficient time to enable them to prepare complete and accurate cash
transactions reports to FTA. When advances are made by electronic
transfer of funds methods, the recipient must make drawdowns as close as
possible to the time of making disbursements. Recipients must monitor
cash drawdowns by their subrecipients to ensure that those drawdowns
conform substantially to the same standards of timing and amount that
apply to advances to the recipients. Payments received from FTA must be
disbursed within three business days. If not disbursed within three days,
that Federal assistance becomes excess and must be returned to FTA with
interest.
3. LOCAL SHARE. The recipient agrees to provide sufficient funds or approved in-kind
resources to serve as local share for all federally assisted projects in compliance with 49
U.S.C. chapter 53. The recipient certifies that it has or will have available the proportionate
amount of non-Federal share promptly as project costs are incurred or become due, except
to the extent that the Federal Government determines in writing that the non-Federal share
may be deferred. The recipient may not use an amount as matching share for more than one
Federal or federally assisted project.
4. GENERAL PRINCIPLES FOR DETERMINING ALLOWABLE COSTS.
a. General. Recipients must follow the guidelines contained in the applicable Federal cost
principles requirements in determining whether project costs are allowable or
unallowable.
OMB Guidance for Grants and Agreements, “Cost Principles for State, Local, and
Indian Tribal Governments (OMB Circular A-87),” 2 CFR part 225,
(b) Former OMB Guidance for Grants and Agreements, “Cost Principles for
Educational Institutions (OMB Circular A-21),” 2 CFR part 220,
(c) Former OMB Guidance for Grants and Agreements, “Cost Principles for
Non-Profit Organizations (OMB Circular A-122),” 2 CFR part 230, and
Page V–6
FTA C 6100.1E
(d) FAR, at 48 CFR Chapter 1, subpart 31.2, “Contracts with Commercial
Organizations,” covers for-profit organizations.
Subrecipients must follow the cost principles applicable to them, which are not
necessarily the same as the costs principles that apply to the recipient.
Project costs must specifically relate to the purpose of the cooperative agreement, grant
agreement, or other agreement and the latest approved project budget. Recipients may
incur costs of both a direct and indirect nature. Direct costs are costs that can be
identified specifically with a particular cost objective. These costs may be charged
directly to the federally assisted project, third-party contracts, or to other programs
against which costs are finally lodged. All direct costs, even for project administration
activities, must be adequately supported with proper documentation. For example, all
labor charges must be supported with time and attendance (T&A) records. Indirect
costs must be supported by an approved CAP and/or indirect cost proposal.
Care must be exercised when incurring costs to ensure that all expenditures meet the
criteria of eligible costs. Failure to exercise proper discretion may result in expenditures
for which use of project Federal assistance cannot be authorized.
b. Allowable Costs. The criteria that govern the eligibility of project costs are listed below
in paragraphs (1) – (11). To be allowable under a Federal assistance program, costs
must meet the following general criteria:
(1) Be allocable to the award under the provisions of the applicable cost principles,
(2) Be necessary and reasonable for proper and efficient administration of the Federal
assistance program, be allowable under Federal cost principles and, except as
specifically provided in this circular, not be general expenses required to carry out
the overall responsibilities of a state or local government or other entity that is the
recipient,
(3) Be authorized or not prohibited under state or local laws or regulations,
(4) Be able to conform to any limitation or exclusions set forth in the Federal cost
principles, Federal laws, or other governing limitations as to types or amounts of
cost items,
(5) Be consistent with policies, regulations, and procedures that apply uniformly to
both federally assisted and other activities of the unit of government or other entity
of which the recipient is a part,
(6) Be treated consistently. A cost may not be assigned to a federally assisted project
as a direct cost if any other cost incurred for the same purpose in like
circumstances has been allocated to the federally assisted project as an indirect
cost,
FTA C 6100.1E
Page V–7
(7) Be determined in accordance with generally accepted accounting principles
(GAAP) appropriate to the circumstances,
(8) Not be allocable to or included as a cost of any other federally financed program in
either current or prior periods,
(9) Be net of all applicable credit,;
(10) Be adequately documented, and
(11) Not be incurred prior to the Federal assistance award unless specifically provided
for in a letter of no prejudice (LONP) or equivalent document approved by FTA,
or in the preaward authority as described in the Federal Register listing of the FTA
annual apportionments.
c. Disallowed Costs. In determining the amount of Federal assistance FTA will provide,
FTA will exclude:
(1) Any project costs incurred by the recipient prior to the date of either the FTA’s
award of Federal assistance through a grant agreement, cooperative agreement, or
other agreement or approved project budget (whichever is earlier), unless
specifically provided for in a LONP or equivalent document approved by FTA, or
in the preaward authority as described in the Federal Register listing of the annual
apportionments; and
(2) Any costs attributable to goods or services received under a third-party contract or
other arrangement that is required to be, but has not been, concurred or approved
in writing by FTA.
The recipient agrees that reimbursement of any cost in accordance with customary payment
methods for an approved cooperative agreement, grant agreement, or other agreement does
not constitute a final FTA decision about the allowability of that cost and does not
constitute a waiver of any violation by the recipient of the terms of the approved
cooperative agreement, grant agreement, or other agreement. If the Federal Government
determines that the recipient is not entitled to receive any part of the Federal assistance
requested, the Federal Government will notify the recipient stating the reasons. Project
closeout will not alter the recipient’s obligation to return any Federal assistance due to FTA
as a result of later refunds, corrections, or other transactions, or will project closeout alter
FTA’s right to disallow costs and recover Federal assistance on the basis of a later audit or
other review. Unless prohibited by law, FTA may offset any Federal assistance to be made
available under a cooperative agreement, grant agreement, or other agreement necessary to
satisfy any outstanding monetary claims that FTA may have against the recipient.
Exceptions pertaining to disallowed costs are set forth in FTA directives or in other written
Federal guidance.
5. INDIRECT COSTS.
Page V–8
FTA C 6100.1E
a. General. The applicable OMB cost principles circular as stated in 2 CFR parts 220,
225, and 230, and FAR subpart 31.2 define the allowability of indirect costs and
establish procedures for developing approved indirect cost rates. In addition, CAPs are
required for state and local governments subject to 2 CFR part 225. CAPs and/or
indirect cost proposals must be approved by FTA or another cognizant Federal agency.
b. Definitions. Indirect costs are costs that are:
(1) Incurred for a common or joint purpose benefitting more than one cost objective,
(2) Not readily assignable to the cost objectives specifically benefited, without effort
disproportionate to the results achieved, and
(3) Originating in the recipient department that is carrying out the project, as well as
those incurred by other departments in supplying goods, services, and facilities to
the recipient department.
Examples of indirect costs are administrative or operational expenses of unit heads and
their immediate staff. Principles and standards for determining costs applicable to
cooperative agreements, grant agreements, or other agreements, and direct procurement
contracts with recipients are presented in the applicable cost principles circular.
c. Cognizant Federal Agency. Cognizance is generally assigned to the Federal agency that
provides the predominant amount of Federal funding or Federal assistance involvement
with a recipient organization within a given state or locality. (OMB has assigned
cognizant audit agencies for state and local governments. See Federal Register 51 FR
552, January 6, 1986.) For educational institutions, cost negotiation cognizance is
generally assigned to either the Department of Health and Human Services (DHHS) or
the Department of Defense’s (DOD) Office of Naval Research. For those cases where a
recipient is not assigned a cognizant agency, the recipient will be under the general
oversight of the Federal agency that provides it the most Federal funds or Federal
assistance; which will also be identified as the “lead” Federal agency.
d. Types of Plans. There are two types of cost plans.
(1) Applicable to all recipients charging indirect costs is the indirect cost proposal,
which is a financial document that is updated annually at the operating agency
level, and which distributes the administrative support and/or overhead costs of
that agency to the programs (and the projects) that benefit from them.
(a) A nonprofit organization that has not previously established an indirect cost
rate with a Federal agency must submit its initial indirect cost proposal
immediately after the organization is advised that an award will be made, or
not later than three months after the effective date of the award.
(b) DHHS maintains a website on cost allocation for all the categories of
recipients, with samples of indirect cost proposals, at http://rates.psc.gov.
FTA C 6100.1E
Page V–9
(2) The second type of plan covers a CAP that distributes the costs of a state or local
government’s executive and central level support functions to those operating
organizations (usually at a lower tier level) within the government that benefit
from them. These documents are also referred to as a statewide or local-wide
CAPs (SWCAPs/LWCAPs). All SWCAPs must be submitted annually to DHHS
for approval. DHHS is the cognizant agency for all states. Similarly, the LWCAPs
of designated major cities and counties must also be submitted annually to DHHS
or to another Federal cognizant agency. The costs approved under these plans may,
at the option of the state or local government, be incorporated in the indirect cost
proposals of a recipient agency within the government.
6. PROGRAM INCOME.
a. General. FTA’s program income policy for state governments, local governments, and
Indian tribes are in the Common Rules, 49 CFR part 1201 or former 49 CFR part 18, as
applicable. Although similar, the program income requirements for institutes of higher
education, hospitals, nonprofits, and for-profits only are in 49 CFR part 1201 or former
49 CFR part 19, as applicable. Recipients are encouraged to earn income to defray
program costs. Program income means:
(1) Gross income received by the recipient or subrecipient directly produced by a
project supported activity, or
(2) Earned only as a result of the cooperative agreement, grant agreement, or other
agreement during the project period (the time between the effective date of the
project and the ending date of the project reflected in the final financial report).
b. Sources. Program income includes income:
(1) From fees for services performed,
(2) From the use or rental of real or personal property acquired with Federal
assistance,
(3) From the sale of commodities or items fabricated under a federally assisted
project, and
(4) From payments of principal and interest on loans made with Federal assistance for
the project.
Except as otherwise provided in FTA or U.S. DOT regulations, program income does
not include interest on Federal assistance, rebates, credits, discounts, refunds, and so
forth, or interest earned on any of them.
c. Cost of Producing Program Income. If authorized by Federal regulations or the
cooperative agreement, grant agreement, or other agreement, costs incident to the
Page V–10
FTA C 6100.1E
production of program income may be deducted from gross income to determine
program income.
d. Governmental Revenues. Taxes, special assessments, levies, fines, and other similar
revenues produced by a recipient or subrecipient are not program income unless the
revenues are specifically identified in the cooperative agreement, grant agreement,
other agreement, or Federal agency regulations as program income.
e. Property. Proceeds from the sale of real property or equipment will be administered in
accordance with the requirements of 49 CFR part 1201 or former 49 CFR parts 18
or 19, as applicable.
f.
Use of Program Income.
(1) States and Local Governments. FTA allows states and local governments to keep
program income and use it for allowable activities in 49 U.S.C. chapter 53; that is,
for capital, planning, or operating expenses. Unless permitted under Federal law or
regulations, program income may not be used to reduce the local share of the
project from which it was earned, but may be used in future cooperative
agreements, grant agreements, or other agreements. If recipients choose not to use
program income for public transportation purposes, then the program income must
be deducted from total allowable costs to determine the net allowable costs unless
otherwise specified in the terms and conditions of the agreement.
(2) All Other Recipients. Program income must be deducted from total allowable costs
to determine the net allowable costs unless otherwise specified in the terms and
conditions of the cooperative agreement, grant agreement, or other agreement.
(a) Research Exception. For research projects (see “Research and Development”
definition), program income must be added to the funds committed to the
project and used to further eligible project or program objectives, unless
otherwise specified in the terms and conditions of the agreement.
g. Income after the Project Period. Unless the terms and conditions of the cooperative
agreement, grant agreement, or other agreement provide otherwise, recipients have no
obligation to the Federal Government regarding program income earned after the end of
the project period.
7. ANNUAL AUDIT.
a. General. The Single Audit Act requirements of 2 CFR part 1201 and the most recent
version of the OMB “Compliance Supplement,” provide the requirements for annual
audits of Federal assistance recipients. The OMB Compliance Supplement is available
on the OMB website at http://www.whitehouse.gov/omb/circulars_default/.
FTA C 6100.1E
Page V–11
b. Requirement. Recipients that expend $750,000 or more in a year in Federal funds from
all sources must have a single audit conducted, except when they elect to have a
program-specific audit conducted.
While the single audit provisions of 2 CFR part 1201 is directed only to states, local
governments, and nonprofit organizations, FTA may also require for-profit
organizations that receive Federal funds to undertake an audit in conformance with
2 CFR part 1201 audit requirements.
FTA recipients are required to obtain the services of an independent auditor to conduct
a single audit each year in conformance with2 CFR part 1201, except if a state
constitution or law provides for a single biennial audit.
Recipients are required to submit to the FTA administering office one copy of their
annual single audit report to FTA if the audit report contains any findings and
recommendations related to the FTA program or another U.S. DOT program or, in
those cases in which the audit report does not contain any FTA findings or
recommendations, a copy of only the Federal clearinghouse transmittal sheet, “Data
Collection Form for Reporting on Audits of States, Local Governments, and Non-Profit
Organizations, OMB Form SF-SAC.”
Recipients must keep one copy of the data collection form and one copy of the audit
reporting package on file for three years from the date of submission to the Federal
clearinghouse. Pass-through entities must keep their subrecipients’ submissions on file
for three years from date of receipt.
c. Purpose. The purpose of the single annual audit report is to determine whether the
recipient:
(1) Prepared financial statements that fairly present its financial position and the
results of its financial position and the results of its financial operations in
accordance with GAAP,
(2) Has in place internal accounting and other control systems to provide reasonable
assurance that it is managing Federal financial assistance programs in compliance
with applicable laws and regulations, and
(3) Has complied with laws and regulations that may have material effect on its
financial statements and on each of its major Federal assistance programs.
The annual single audit is to be performed by an independent auditor who is required to
determine and report on whether the recipient has internal control systems that
reasonably assure it is managing its Federal assistance programs in compliance with
applicable laws and regulations.
Recipients are required to determine whether certain subrecipients have spent Federal
assistance funds they received in accordance with applicable laws and regulations.
Page V–12
FTA C 6100.1E
Audit judgment concerning the recipient’s determination is left to the independent
auditor.
d. Resolution of Audit Findings. Recipients and subrecipients are responsible for the
prompt resolution of all audit findings and recommendations. This responsibility
requires that the recipient:
(1) Promptly evaluate the report,
(2) Determine the appropriate follow-up actions and establish a date for their
completion, and
(3) Complete all required actions within the established period of time.
The recipient must resolve deficiencies or opportunities for improvement identified in
an audit. The resolution of audits begins with FTA’s report to the recipient and
continues until the recipient corrects identified deficiencies, implements needed
improvements, or demonstrates that the findings or recommendations are not valid or
do not warrant management action.
The audit is not resolved until FTA concurs in the documentation of steps taken to
implement any needed corrective actions. The recipient should monitor and report on
the status of outstanding audit findings and recommendations in its quarterly progress
reports and, where appropriate, report separately on significant events.
8. PAYMENT PROCEDURES.
a. General. Provisions in 2 CFR part 1201 or former 49 CFR parts 18 or 19, as applicable,
and 31 CFR part 205 govern payments to recipients for financing operations under a
federally assisted project and other programs. These regulations require that payment to
a recipient be limited to the minimum amounts needed and timed so as to be in accord
only with the actual, immediate cash requirements of the recipient in carrying out the
approved project.
Before a potential recipient requests FTA assistance, it should verify with the FTA
Project Manager that Federal assistance is available for the project in FTA’s electronic
award and management system . FTA assistance should not be requested in amounts
greater than the “available funds” reported in FTA’s electronic award and management
system.
b. Payment Basis. FTA makes all payments on a progress or milestone completion basis.
(1) Progress payments. FTA may make payments based on costs incurred or expected
over the requested period in the near future.
(2) Milestone completion payments. To ensure that the recipient is making adequate
progress toward project completion, FTA may require milestone completion
FTA C 6100.1E
Page V–13
payments. A schedule of project milestones is established, with estimated costs,
upon completion of which FTA will make payment. The milestone costs should be
considered estimates, not fixed costs, and FTA can only make payment for actual
and allowable costs incurred for completion of that milestone.
c. Payment Methods. FTA makes all payments for research-type projects through the
Treasury’s automated clearinghouse (ACH) method of payment, regardless of the dollar
amount involved. ACH electronically sends payment to a payee’s bank for deposit to
the payee’s bank account.
In accordance with the U.S. DOT guidelines, recipients of cooperative agreements must
register and request Federal assistance using the Delphi eInvoicing system to aid the
FTA approving official in authorizing reimbursement to the recipient. All supporting
documentation needed to support payment is required to be scanned within the
eInvoicing system to aid the FTA approving official in authorizing reimbursement to
the recipient. The Standard Form 270 (SF-270), “Request for Advance or
Reimbursement,” invoice is a component of this system and is required to be completed
when requesting Federal assistance. Instructions for completing the SF-270 can be
found in Appendix C of this circular. Recipients issued cooperative agreements
CANNOT use the Electronic Clearing House Operation (ECHO-Web) system to
drawdown Federal assistance for projects covered by this circular.
d. Excessive or Premature Withdrawals.
(1) General. For excess payments made by the Federal Government to the recipient
that do not qualify as a “claim” for purposes of the Debt Collection Act of 1982, as
amended, 31 U.S.C. 3701 et seq., the recipient agrees that the amount of interest
owed to the Federal Government depends on whether the recipient is a state or
state instrumentality.
(a) A recipient that is a state or state instrumentality agrees that interest owed to
the Federal Government will be determined in accordance with Treasury
regulations, “Rules and Procedures for Efficient Federal State Funds
Transfers,” 31 CFR part 205 that implements section 5(b) of the Cash
Management Improvement Act of 1990, as amended, 31 U.S.C. 6503(b).
(b) A recipient that is neither a state nor a state instrumentality agrees that
common law interest owed to the Federal Government will be determined in
accordance with joint Treasury/DOJ regulations, “Standards for the
Administrative Collection of Claims,” 31 CFR 901.9(i).
(2) Exceptions. The only exceptions to the requirement for prompt refunding are when
the Federal assistance involved:
(a) Will be disbursed by the recipient within seven calendar days, or
(b) Is less than $10,000 and will be disbursed within thirty calendar days.
Page V–14
FTA C 6100.1E
These exceptions to the requirement for prompt refunding should not be construed
as approval for a recipient to maintain excessive Federal assistance. They are
applicable only to excessive amounts of Federal assistance that is erroneously
drawn.
(3) Return of Federal Assistance. The return of Federal assistance is accomplished as
follows:
(a) FTA requests recipients to electronically remit the excessive cash and any
interest to FTA using the Treasury’s Pay.gov financial collection system
(https://www.Pay.Gov).
(b) Although refunds in the form of paper checks are discouraged, recipients may
mail refund checks to DOT/FAA (FTAAccount) in Oklahoma City. If a paper
check is used to refund the premature withdrawal of Federal assistance or any
interest payments, the amount of each must be separately identified and
accompanied by a letter explaining the purpose of the check(s) and identifying
the project number. A copy of the check and the letter should be sent to the
recipient’s administering office. Additional information pertaining to the
mailing of checks is located below in subsection 8.f of this chapter of this
circular.
e. Repayment to FTA. Recipient returning Federal assistance must notify FTA program
managers of plans to repay FTA. The following are possible reasons for repayments to
FTA:
(1) Insufficient funds eligible for use as local share to match Federal payments,
(2) The sale of project equipment,
(3) Excessive Federal assistance in the project account, or
(4) Duplicate payment.
f.
Repayment Procedure. Required repayments must be made promptly to FTA.
Recipients can submit repayments to FTA through the following method:
Option 1 (Preferred Method)
Plastic Card or Automatic Clearing House Payment (ACH Direct Debit)
Go to Treasury’s website, https://pay.gov.
Under Find Public Forms, Click on “Search by Agency Name”
Click on the Letter “F” for Federal Transit Administration
Click on the Name: Federal Transit Administration
FTA C 6100.1E
Page V–15
Select the appropriate Payment Form Name: FOIA Fee, Grantee Refunds/Over Payments, or
Vendor/Employees
Provide the requested information and submit. Note: If making an ACH payment from your bank
account, please select ACH Direct Debit as the payment type.
Option 2:
Mail Check payment to the following address for Paper Check Conversion (PCC) processing:
Regular Mail
Overnight Mail
DOT/FAA (FTA Account)
ESC, AMZ-300
PO BOX 269041
OKLAHOMA CITY, OK 73125
DOT/FAA (FTA Account)
ESC, AMZ-300
6500 S. MACARTHUR BLVD
HQS BLDG RM 181
OKLAHOMA CITY, OK 73169
Attn: Rhonda Manuel (405-954-8195)
g.
h. Requirement to Remit Interest. Under FTA’s Master Agreement, recipients must remit
any interest earned on excess Federal assistance drawn down but not spent for eligible
project activities or held in excess of three calendar days. Payments of interest must be
made by using the Pay.gov financial collection system.
Unless waived by FTA, interest will be calculated at rates imposed by the Treasury
(http://fms.treas.gov/) beginning on the fourth day after the Federal assistance was
deposited in the recipient’s bank or other financial depository. Upon notice by FTA to
the recipient of specific amounts due, the recipient must promptly remit to FTA any
excess Federal assistance payments, including any interest due.
i.
Deobligation of Federal Assistance . FTA reserves the right to deobligate unspent
Federal assistance prior to project closeout.
j.
Right of FTA to Terminate. The recipient agrees that, upon written notice, FTA may
suspend or terminate all or part of the Federal assistance provided herein if the recipient
is, or has been, in violation of the terms of its cooperative agreement, grant agreement,
or other agreement, or if FTA determines that the purposes of the law under which the
project is authorized would not be adequately served by continuation of Federal
assistance for the project. Any failure to make reasonable progress or other violation of
the agreement that significantly endangers substantial performance of the project must
be deemed to be a breach of the agreement.
In general, termination of any Federal assistance under the agreement will not
invalidate obligations properly incurred by the recipient and concurred in by FTA
before the termination date, to the extent those obligations cannot be canceled.
However, if FTA determines that the recipient willfully misused FTA assistance by
failing to make adequate progress; by failing to make reasonable use of the project real
Page V–16
FTA C 6100.1E
property, facilities, or equipment; or failing to honor the terms of the approved grant,
FTA reserves the right to require the recipient to refund the entire amount of Federal
assistance provided herein or any lesser amount as may be determined by FTA.
Expiration of any project time period established for this project does not by itself
constitute an expiration or termination of the agreement.
Neither the receipt by the recipient of any Federal agreement for the project nor the
closeout of Federal financial participation in the project must constitute a waiver of any
claim that FTA may otherwise have arising out of the agreement.
FTA C 6100.1E
Page V–17
This page intentionally left blank
FTA C 6100.1E
Page VI–1
CHAPTER VI
FTA OVERSIGHT
1. GENERAL. The Federal Transit Administration (FTA) may evaluate recipient adherence
to program and administrative requirements through a comprehensive oversight program.
FTA’s Master Agreement, which is incorporated by reference and made part of the
cooperative agreement, grant agreement, or other agreement, specifies these requirements.
FTA may determine compliance through self-certification, oversight review, audits, and
site visits. On an annual basis, FTA may complete an individual recipient oversight
assessment questionnaire, which serves as baseline information for each recipient’s
capacity to comply with Federal requirements and determines the risk the recipient’s
program may represent for the Federal program. Based on this information, FTA makes
decisions about which recipients will receive oversight reviews during the coming year.
Administering office staff use the information to develop oversight plans and to allocate
oversight resources for the upcoming fiscal year , which may include oversight reviews,
meetings, and/or site visits.
FTA may conduct on-site inspections of projects to evaluate the recipient’s effectiveness in
implementing the project in conformance with the cooperative agreement, grant agreement,
or other agreement. Inspection visits may be made, for example, to follow-up on
information received from the recipient about an event with significant impact on a project
or to determine whether the recipient has adequately complied with civil rights laws,
regulations, and agreements. Inspection and concurrence by FTA in project work does not
relieve the recipient of its responsibilities and liabilities as the responsible party for
carrying out the project.
2. PROGRAM SPECIFIC REVIEWS.
a. Financial Management Oversight. Under the Financial Management Oversight (FMO)
program, FTA conducts several types of reviews:
(1) Full Scope Financial Management System Review. The full scope financial
management system review requires FMO contractors to conduct a series of
interviews, full transaction reviews, and appropriate substantive tests. The
contractors determine that the recipient’s financial management system meets the
requirements of the applicable Common Rule, 2 CFR part 1201 or former 49 CFR
parts 18 or 19, as applicable. The contractors then express an objective, external,
independent professional opinion to FTA, in accordance with established public
accounting standards, on the effectiveness of the recipient’s internal control
environment. The seven standards for financial management systems are: financial
reporting, accounting records, internal control, budget control, allowable costs,
source documentation, and cash management. An average FMO review takes three
to four weeks, conducted at the recipient’s site.
Page VI–2
FTA C 6100.1E
(2) Follow-up Reviews. Follow-up reviews are performed primarily to ensure those
recommendations resulting from full scope reviews are implemented and working
properly. If performed, these reviews will occur between twelve and eighteen
month after the full scope review.
(3) Indirect Cost Allocation Plan Review. Indirect CAP reviews are performed on
CAPs submitted to the FTA for approval as the cognizant agency. The purpose of
this review is to determine whether the methodology for allocating indirect cost to
a Federal or federally assisted project is calculated in a manner consistent with the
applicable OMB circular.
(4) Special Assignment (Agreed Upon Procedures). Agreed upon procedures are
performed primarily to carry out special assignments deemed necessary as part of
the FMO program. As an example, FTA may require a review that involves the
development of procedures with the contractor in order to meet FTA engagement
objectives. While there can be varying engagements that may employ agreed upon
procedures, in most cases, FTA is concerned about whether FTA assistance were
spent according to the guidelines of the cooperative agreement, grant agreement,
or other agreement, and in accordance with the applicable cost principles. These
reviews are conducted on a case-by-case basis and are directly related to the
recipient’s financial management issues.
b. Procurement Reviews. FTA may conduct a procurement system review to ensure that
the requirements and standards of the Common Rules on administrative requirements
for federally assisted projects, 2 CFR part 1201 or former 49 CFR parts 18 or 19, as
applicable, and the most recent version of FTA Circular 4220.1, as they specifically
apply to procurements, are met. These reviews are conducted on-site and involve
review of previous typical procurements as well as documentation of policies,
processes and controls. For grantees or recipients that receive Federal assistance for
capital, planning, and/or operations, this type of review can be accomplished under
FTA’s oversight program.
c. Civil Rights Reviews. Recipients and subrecipients of Federal assistance must comply
with civil rights. FTA’s Master Agreement specifies that compliance is required and
sets forth the terms and conditions governing the administration of a public
transportation project or other projects supported with FTA financial assistance. FTA
recipients should be aware, however, that they may be subject to civil rights
requirements established and enforced by other Federal agencies that may not
recognize the FTA Master Agreement as dispositive of their responsibilities and that
some responsibilities exist independent of FTA or other Federal funding. FTA retains
the right to review recipient compliance status at any time during the life of the project.
FTA’s civil rights reviews include Title VI, Disadvantaged Business Enterprise (DBE),
Americans with Disabilities Act (ADA), and Equal Employment Opportunity (EEO)
requirements.
3. PROJECT LEVEL REVIEWS.
FTA C 6100.1E
Page VI–3
a. Specialized Oversight Strategies. From time to time, FTA has determined that a
recipient presents the need for additional specialized oversight. In a few cases, FTA has
designated a recipient or its project as a high-risk recipient under 2 CFR part 1201 or
former 49 CFR parts 18 or 19, as applicable. In these cases, FTA may impose specific
requirements as a condition of receiving FTA assistance. These conditions are usually
the result of specialized review provided by one or more or a combination of FTA
contractors.
b. Quarterly Project Management Meetings. Quarterly project management meetings may
be instituted with selected recipients. These meetings provide a forum for management
briefings, status/progress reports, discussion of accomplishments and problems, and, as
appropriate, an opportunity for site inspection. The quarterly meetings do not replace
quarterly written reports.
c. Other Project Management Meetings. Other project management meetings may be
instituted with specific recipients at other time intervals at the discretion of the FTA
administering office. These meetings provide a forum for management briefings,
status/progress reports, discussion of accomplishments and problems, and, as
appropriate, an opportunity for site inspection. The meetings do not replace quarterly
written reports.
d. Site Visits. FTA may conduct on-site inspections of projects to evaluate the recipient’s
effectiveness in implementing the project in conformance with the cooperative
agreement, grant agreement, or other agreement. Inspection visits may be made, for
example, to follow-up on information received from the recipient about an event with
significant impact on a project or to determine whether the recipient has adequately
complied with civil rights laws, regulations, and agreements. Inspection and
concurrence by FTA in project work does not relieve the recipient of its responsibilities
and liabilities as the responsible party for carrying out the project.
e. Peer Reviews. FTA may request recipients to participate in peer reviews with other
recipients or industry experts to define objectives for projects and to evaluate technical
progress. In the case that FTA intends to distribute information prepared by a recipient
that is influential or highly influential scientific research as defined by OMB’s “Final
Information Quality Bulletin for Peer Review,” dated December 16, 2004, FTA will
follow procedures for peer review outlined in that bulletin.
Page VI–4
FTA C 6100.1E
This page intentionally left blank.
FTA C 6100.1E
Appendix A
Page A–1 of 6
APPENDIX A
INSTRUCTIONS FOR COMPLETING FEDERAL FINANCIAL REPORT (FFR)
The FFR screen in FTA’s electronic award and management system consists of three tabs:
Summary, Financial Status and Remarks, and Certification.
(1) The Summary Tab:
(a) Employer Identification Number (EIN) – Enter the EIN. The EIN is also
known as a Federal tax identification number.
(b) Work in Progress/Submit Report – Select “Work in Progress” or “Submit
Report.” Select “Work in Progress” to prepare the report. Once the report is
complete and ready for submission, select “Submit Report.”
(c) Report Type – Select whether the report is quarterly, monthly, annually, or
other.
(d) Period – Enter the reporting period from the drop-down menu.
(e) Final Report? – Enter whether or not the report is final. In the drop-down
menu select, “Yes, Final Report” or “No, Not Final Report.” The report will
be final if all the activities in the grant are completed, the Federal assistance is
drawn down, there are no unliquidated obligations, and the milestones are
closed. Once the final report is submitted, the grant or cooperative agreement
is ready for closeout. Please notify your regional program manager.
(f) Indirect Expense – If a recipient is charging indirect costs to the project,
complete this section. Enter total amount of indirect expenses incurred on a
cumulative basis. Please note that a recipient must have an approved CAP in
order to incur these expenses,
1 Type – Enter indirect expense type from the drop-down menu,
2 Rate – Rate approved by the cognizant agency,
3 Base – Total base amount from which the indirect cost rate is determined,
4 Period from / Period to – The period covered by the approved rate,
5 Amount Charged – Total amount of indirect expenses charged to the
project on a cumulative basis, or
6 Federal Share – Federal share of the indirect expenses charged.
(2) The Financial Status Tab – The information in this section is compiled on a
cumulative basis, except for the three expenditures lines (lines F, G, and H).
Appendix A
Page A–2 of 6
FTA C 6100.1E
(a) Line A - Federal Cash on Hand at beginning of period – Any cash on hand at
the beginning of the project. In most instances, this line will be zero.
(b) Line B - Federal Cash Receipts –The cumulative amount of actual cash
received from FTA for this project as of the reporting period end date. Report
this amount on a cash basis.
(c) Line C - Federal Cash Disbursements – The cumulative amount of Federal
assistance disbursed as of the reporting period end date. Disbursements are the
sum of actual cash disbursements for direct charges for goods and services,
the amount of indirect expenses charged to the project, and the amount of
payments made to subrecipients and contractors. Report this amount on a cash
basis.
(d) Line D - Federal Cash on Hand at End of Period – The sum of lines A + B –
C, populated by FTA’s electronic award and management system. If there is
cash on hand at the end of the period, FTA requires an explanation in the
remarks or certification tab, explaining why the drawdown was made
prematurely or other reasons for the excess cash.
(e) Line E - Total Federal Assistance Authorized – The total amount of all
Federal assistance in the project including amendments. FTA’s electronic
award and management system populates this field.
(f) Line F - Federal Share of Expenditures – The amount FTA will participate in
the total project costs. You can enter this information in either the “This
Period” section or the “Cumulative” section, however, do not enter in both
sections. Expenditures are the total project costs (less any rebates, refunds, or
other credits) incurred on the accrual basis of accounting. Examples of
expenditures are: (1) the sum of cash disbursements for direct charges for
property and services, (2) the amount of indirect expense incurred, and (3) net
increase or decrease in accounts payable or accrued expenses.
(g) Line G - Recipient Share of Expenditures – Of the total project costs, enter the
amount the recipient will pay of the total project costs. You can enter this
information in either the “This Period” section or the “Cumulative” section.
However, do not enter in both sections. Enter the recipient share of actual cash
disbursements (less any rebates, refunds, or other credits) including payments
FTA C 6100.1E
Appendix A
Page A–3 of 6
to subrecipients and third-party contractors. This amount may include the
value of allowable third-party in-kind contributions. Note: On the final report,
this line should be equal to the total recipient share required (line N). Report
this amount on an accrual basis.
(h) Line H - Total Expenditures – The total of all expenditures (total project costs)
as of the end of the reporting period. FTA’s electronic award and management
system populates this field – lines F + G.
(i) Line I - Federal Share of Unliquidated Obligations – The Federal portion of
unliquidated obligations (binding commitments entered into for goods and
services not yet received). On the final report, this line should be zero. Report
this amount on an accrual basis. Examples of unliquidated obligations are: (1)
signed contracts for purchase of equipment when delivery has not yet
occurred, (2) contracts for services not yet rendered, (3) open purchase orders,
and (4) contract retention.
(j) Line J - Recipient Share of Unliquidated Obligations – The local share of
unliquidated obligations.
(k) Line K - Total Unliquidated Obligations – The total amount of recipient
binding commitments entered into for goods and services not yet received.
FTA’s electronic award and management system populates this field – lines I
+ J.
(l) Line L - Total Federal Share – The total FTA is expected to contribute to the
total project costs. This is the sum of Federal share of expenditures (line F)
and Federal share of unliquidated obligations (line I). FTA’s electronic award
and management system populates this field – lines F + I.
(m) Line M - Unobligated Balance of Federal Assistance – The Federal share of
the project for which the recipient has not entered into a binding commitment.
FTA’s electronic award and management system populates this field – lines E
to L.
(n) Line N - Total Recipient Share Required – The total amount required recipient
share for the cooperative agreement, grant agreement, or other agreement
including amendments. The required recipient share should include all
matching and cost sharing provided by recipients and third-party providers to
meet the level required by FTA. FTA’s electronic award and management
system populates this field.
Appendix A
Page A–4 of 6
FTA C 6100.1E
(o) Line O - Remaining Recipient Share to be Provided – The total recipient share
required (line N) minus the sum of recipient share of expenditures (line G)
and the recipient share of unliquidated obligations (line J). FTA’s electronic
award and management system populates this field.
(p) Line P - Program Income on Hand at the Beginning of the Reporting Period –
Any unspent program income on hand at the beginning of the project. In most
instances, this line will be zero.
(q) Line Q - Total Program Income Earned During the Period of Performance –
The amount of program income earned as of the end of the reporting period.
Program income is: (1) gross income received by the recipient or subrecipient
directly generated by a project supported activity, or (2) earned only as a
result of the cooperative agreement, grant agreement, or other agreement
during the project period. Examples: income from (1) fees for services
performed, (2) fees for the use or rental of real or personal property acquired
with project funds, (3) the sale of advertising and concessions, and (4) the sale
of commodities or items fabricated under a cooperative agreement, grant
agreement, or other agreement. Program income is not: (1) interest on project
funds; (2) rebates, credits, discounts, refunds, taxes, special assessments,
levies, and fines, etc. and interest earned on any of them; or (3) sale of assets.
(Proceeds from the sale of real property or equipment will be handled in
accordance with the requirements of 49 CFR part 1201 or former 49 CFR
parts 18 or 19, as applicable.)
(r) Line R - Program Income Expended in Accordance with the Deduction
Alternative – The amount of program income that was used to reduce the
Federal share of the total project cost. Only to be used if the recipient does
not exercise the provisions of the Common Rule, 2 CFR part 1201 or
former49 CFR parts 18 or 19, as applicable. As a rule of thumb, this field is
zero.
(s) Line S - Program Income Expended in Accordance with the Addition
Alternative – FTA does not allow this method; this field is zero.
(t) Line T - Program Income Expended on Allowable Transit Capital and
Operating Expenses – The amount of the program income earned that the
recipient is allowed to spend on allowable transit capital and operating
expenses as provided in the Common Rule, 2 CFR part 1201 or former
49 CFR parts 18 or 19, as applicable.
FTA C 6100.1E
Appendix A
Page A–5 of 6
(u) Line U - Unexpended Program Income – FTA’s electronic award and
management system populates this field.
(3) The remarks and certifications tab:
(a) Recipient Remarks – This box is for the recipient to provide comments and
provide any explanations or information deemed necessary for the review of
the report.
(b) Certification checkbox – Before submitting the report, check the certification
box. Please note the certification language. The name of FTA’s electronic
award and management system user and the date is automatically populated.
(c) FTA Remarks – This box is for the FTA reviewer to provide comments for
both the FFR and MPR. Once FTA completes the review of the data, the
reviewer will enter any comments in this box. The reviewer will contact the
recipient by email if FTA added comments.
Appendix A
Page A–6 of 6
FTA C 6100.1E
This page intentionally left blank.
FTA C 6100.1E
Appendix B
Page B–1 of 4
APPENDIX B
COST ALLOCATION PLANS
1. REQUIREMENTS. Recipients that intend to seek FTA reimbursement for indirect costs
must prepare a CAP and/or indirect cost rate proposal. The following are basic
requirements for preparing a CAP.
a. CAPs and indirect cost rate proposals must be updated annually.
b. The updated plans must be retained and made available for review at the recipient’s
annual single audit.
c. Updated CAPs may be used on a provisional basis for the following fiscal year with the
provision that year-end adjustments must be made to actual costs.
d. The initial plan must be approved by FTA or another cognizant Federal agency. For
subsequent approvals, please refer below to Section 5 of this Appendix.
e. Additionally, all costs in the plan must be supported by formal accounting records to
substantiate the propriety of eventual charges. The recipient’s CAP should cover all
applicable costs. It should also cover costs allocated under plans of other agencies or
organizational units which are to be included in the costs of other federally sponsored
programs. To the extent feasible, CAPs of all agencies rendering assistance to the
recipient should be presented in a single document.
2. Content. The CAP should contain, but need not be limited to the following:
a. Nature and extent of services provided and their relevance to federally sponsored
programs;
b. Items of expense to be included;
c. Methods to be used in distributing cost; and
d. Appropriate civil rights data.
3. PURPOSE OF THE CAP. The purpose of the CAP is to guide the recipients’ allocation of
costs. The plan should ensure:
a. All activities of local government departments or state agencies have been considered;
b. Distribution of indirect costs is based on a method(s) reasonably indicative of the
amount of services provided,
c. Services provided are necessary for successful conduct of Federal programs,
Appendix B
Page B–2 of 4
FTA C 6100.1E
d. Level of costs incurred are reasonable,
e. Costs of state or local centralized government services may be charged in conformance
with governmentwide cost allocations plans, and
f.
Costs claimed are allowable in accordance with the Office of Management and Budget
(OMB) Circular A–87, as applicable.
4. DEVELOPMENT OF COST ALLOCATION PLAN. In planning the development of a
CAP, recipients should develop a CAP that identifies costs of supporting service units and
allocates those costs to benefiting units on an equitable basis. The following is a list of
components that should be included in a CAP:
a. An organization chart,
b. Financial statements,
c. Cost allocation methodology,
d. Cost allocation rate proposal,
(1) Identification of costs of each type of service to be claimed,
(2) Determination of the method for allocating each type of service cost to users,
(3) Identification of units rendering/receiving service and associated costs,
(4) Description of services,
(5) Description of allocation base (consistency is important), and
(6) Summary allocation schedule for each service.
e. Proposal reconciliation with financial statements. (Note: Allocated costs must be
reasonable and traceable to the financial statements),
f.
Identification of Federal award direct cost base, and
g. Certification of conformance with U.S. OMB, “Cost Principles for State, Local, and
Indian Tribal Governments (U.S. OMB Circular A-87),” 2 CFR part 225. A proposal to
establish a CAP or an indirect cost rate proposal will be unacceptable if the certificate
of the CAP or certificate of indirect costs is omitted. The certificate must be signed on
behalf of the governmental unit by an individual at a level no lower than chief financial
officer of the governmental unit that submits the proposal or component covered by the
proposal. See also U.S. OMB, “Cost Principles for Educational Institutions (U.S. OMB
FTA C 6100.1E
Appendix B
Page B–3 of 4
Circular A-21),” 2 CFR part 220, and U.S. OMB, “Cost Principles for Nonprofit
Organizations (U.S. OMB Circular A-122),” 2 CFR part 230, which apply to project
costs incurred by a private nonprofit organization.
5. SUBMISSION OF COST ALLOCATION PLAN/INDIRECT COST RATE
PROPOSALS. U.S. OMB “Cost Principles for State, Local, and Indian Tribal
Governments” (U.S. OMB Circular A-87) requires that the plan (called a proposal) be
submitted to a recipient’s Federal cognizant agency for approval. The CAP/indirect cost
rate proposal should be submitted to the “cognizant” or “lead” Federal agency when:
a. The recipient is working on its first assistance project or has not previously had a
CAP/indirect cost rate proposal reviewed and accepted,
b. The recipient has made a change in its accounting system, thereby affecting the
previously approved CAP/indirect cost rate proposal and its basis of application,
c. The recipient’s proposed CAP/indirect cost rate proposal exceeds the amounts and rate
approved for the previous year(s) by more than 20 percent, or
d. The recipient changes the CAP/indirect cost rate proposal methodology.
6. PLAN APPROVAL. Most transit agencies are under the cognizance of the U.S. DOT.
Whenever the cognizant agency gives prior approval to a government-wide CAP or indirect
cost rate proposal, such approval is formalized, distributed to all interested Federal
agencies, and applicable to all Federal grants in accordance with U.S. OMB, “Cost
Principles for State, Local, and Indian Tribal Governments” (U.S. OMB Circular A-87).
An approved CAP or indirect cost rate proposal must be updated annually. The update
should be retained and made available for review at the time of the recipient’s
organization-wide audit.
Appendix B
Page B–4 of 4
FTA C 6100.1E
This page intentionally left blank.
FTA C 6100.1E
Appendix C
Page C–1 of 5
APPENDIX C
REQUEST FOR ADVANCE OR REIMBURSEMENT (SF–270)
1. GENERAL. The recipient agrees as follows:
a. New recipients must first provide financial information to enroll in the automated
clearinghouse (ACH) system. Assistance will be provided by Federal Aviation
Administration’s (FAA’s) Enterprise Service Center (ESC) and the administering
office.
b. To complete and attach an original Standard Form 270, “Request for Advance or
Reimbursement” (see Sample Request for Advance or Reimbursement Form [SF–270]
in Appendix C of this circular) with supporting documentation when submitting request
for reimbursement via DELPHI Ie-Invoicing System.Upon receipt of the SF-270
payment request and supporting documentation, ESC will disburse payments by ACH
deposit for all request approved by the authorized FTA Project Manager in the Delphi
e-Invoicing System. INSTRUCTIONS. Instructions for completing an SF-270 are
printed on its reverse side (see instructions for completing request for advance or
reimbursement form [SF-270] in Appendix C of this circular). In addition, the
following instructions should assist recipients in completing this form.
a. Only the total column on this form should be completed, unless the project involves
more than one funding ratio. In such instances, the other columns are also to be used.
In addition, recipients should round all figures to the nearest dollar; that is, amounts of
$0.50 or over would be rounded to the higher dollar. For example: if the other than
Federal share is computed to be $2,572.70, the amount reported would be $2,573.
b. Block #5—All requisitions should be numbered consecutively beginning with #1 as the
first requisition. Suggested format should include the fiscal year and sequential number
for each individual voucher. For example, the payment request number for the
recipient’s first voucher submitted in FY 2007 would appear on the SF-270 as follows:
2007–001.
c. Block #8—The first requisition covers the date the Federal assistance was awarded
(unless the project had preaward authority, through the end of the period for which
reimbursement is requested). When a requisition requests reimbursement only, the
“ending” date will be the same date on which outlays are reported on line 11a of this
form. If the reimbursement and/or an advance is being requested, the “ending” date
should reflect the period through which the advance is needed.
All requisition report periods should run consecutively. For example, if a requisition is
submitted for the period 1/1/07 to 3/31/07, the next requisition will begin 4/1/07.
Appendix C
Page C–2 of 5
FTA C 6100.1E
d. Block #9—The name of the recipient should be exactly as indicated on the cooperative
agreement, grant agreement, or other agreement. Recipients should avoid abbreviation
and spell out the entire name of the organization.
e. Block #11—Line A—The “as of” date should be the date for which the recipient has
actual costs recorded. This date should be the same as the “to” date, Block #8, unless
the recipient is requesting an advance.
Line B—Represents the amount applicable to program income that was required to be
used for the project or program by terms of the cooperative agreement, grant
agreement, or other agreement.
Line D—Represents the estimated expenditures for the advance period, both FTA share
and the local share.
Line F—Local share of line E, depending on the funding ratio of a particular project.
Line G—Federal share of line E, depending on the funding ratio for a particular project.
Line H—Total of previous requisition(s) submitted. This line should not represent
actual payment received because the recipient may have submitted a requisition that is
in the process of being paid. Requisition #1 on this line should be zero.
Note that the recipient should complete only the “total” column of Block #11, unless
the cooperative agreement, grant agreement, or other agreement specified that there is
more than one funding source supporting the project. In such cases, separate columns
should be utilized for each funding source.
Line I—Federal share now requested represents the total amount of the SF-270
reimbursement that will be forwarded to the recipient.
4. REVIEW OF THE SF-270. Each SF-270 for Federal assistance will be reviewed in light of
the periodic milestone progress reports (MPRs) and financial reports required for each
project. Changes requiring amendments to the cooperative agreement, grant agreement, or
other agreement or prior approval of a budget revision must be approved before Federal
assistance for these changes are requisitioned.
FTA C 6100.1E
Sample Request for Advance or Reimbursement Form (SF–270)
Appendix C
Page C–3 of 5
Appendix C
Page C–4 of 5
FTA C 6100.1E
INSTRUCTIONS FOR COMPLETING REQUEST FOR ADVANCE OR
REIMBURSEMENT FORM (SF–270)
FTA C 6100.1E
Appendix C
Page C–5 of 5
This page intentionally left blank.
FTA C 6100.1E
Appendix D
Page D–1 of 8
APPENDIX D
PREPARATION INSTRUCTIONS FOR FTA FINAL REPORTS
1. UNIFORM STYLE AND FORMAT FOR FINAL REPORTS. FTA has adopted a uniform
style and format for its final reports for the purpose of fostering ease of information
retrieval, technical merit, clarity of writing, quality control, and processing in information
systems, as well as for assuring timely delivery and permanent access to these documents.
The uniform style distinguishes these documents as FTA products.
2. FTA ROLE. FTA is responsible for final editing and design of final reports resulting from
FTA-sponsored research and technical assistance. FTA will produce these final reports in
PDF format and will post them on the FTA website at
http://www.fta.dot.gov/about/research_reports_and_publications and other locations. FTA
will ensure that all final reports are compliant with Section 508 of the Rehabilitation Act of
1973 (described in more detail below).
3. RECIPIENT ROLE. The recipient is responsible for preparing and delivering to FTA in
electronic format draft final reports with all required components as described below. After
FTA editorial review, the recipient is responsible for responding to FTA requests for
additional information, clarification, and editorial changes during final processing of the
draft report.
4. LIMITED PRINTING OF HARD COPY DOCUMENTS. To promote efficient spending in
the Federal Government, Executive Order 13589 directs agencies to provide written
information electronically and limit the publication and printing of hard copy documents. If
FTA determines that a report will also be printed, printing is the responsibility of the FTA
project manager or the author. The FTA will provide the design and files necessary for
printing if requested at the time of final report submission.
5. STYLE, CONTENT, AND FORMAT OF DRAFT FINAL REPORTS.
a. File Format. Recipients must submit draft final reports electronically in two formats:
one file using Word 2007 or later and one file as a PDF.
b. Orthography. Spelling, definition, and compounding of words should follow MerriamWebster’s Collegiate Dictionary, 11th edition.
c. Units of Measure. Measurements may appear in both SI (metric) and U.S. customary
units, with the measurement unit of the original research followed by the equivalent
conversion in parentheses.
d. Content Components. Reports must include each of the following elements in the
following order:
Appendix D
Page D–2 of 8
FTA C 6100.1E
(1) Title Page
(2) Report Documentation Page (Standard Form 298), submitted in a separate Word
file, as found at http://www.fta.dot.gov/research/program_requirements
(3) Table of Contents
(4) List of Figures
(5) List of Tables
(6) Foreword (optional)
(7) Acknowledgments
(8) Abstract
(9) Executive Summary
(10) Main body of text, separated into titled sections and subsections as appropriate;
numbering should not be used for subsections
(11) Appendices (if needed)
(12) Glossary of Terms (if needed)
(13) References
e. Text Format
(1) Layout: 8.5" × 11", portrait orientation
(2) Margins: 1" on top, bottom, left, and right
(3) Font: Arial, 11 pt
(4) Alignment: Left, one column
(5) Spacing: Single
(6) Paragraph indents: None
(7) Headers/footers: None (other than page numbering)
(8) Headings:
(a) First-level head (bold type, capitalize each word, on separate line)
FTA C 6100.1E
Appendix D
Page D–3 of 8
(b) Second-level subhead (bold italics type, only first word capped, on separate
line)
(c) Third-level subhead (italics type, only first word capped, on separate line)
(9) Tables and Figures
Tables and figures should be included within the text and appear immediately after
the paragraph in which they first are indicated, when possible. Titling should be as
follows:
(a) Tables. Title above table; bold type; capitalize each word; numbering
corresponds to section/chapter (5-1, 5-2, etc.); no punctuation after number or
at end of title
Table D-1 Example of a Table Title
Categories
Values
(b) Figures. Title below figure; bold type; capitalize each word; numbering
corresponds to section/chapter (3-1, 3-2, etc.); no punctuation after figure
number; period at end of title
6
5
4
Series 1
3
Series 2
2
Series 3
1
0
Category 1 Category 2 Category 3 Category 4
Figure D-1 Example of a Figure Title.
(c) Illustrations, Photographs, and Videos
1
Each chart, figure, photo, illustration, video, and table must have a distinct
title.
Appendix D
Page D–4 of 8
FTA C 6100.1E
2
Each image requires Section 508–compliant alternative text.
3
All charts, tables, and graphs must be submitted separately in Microsoft
Excel file containing the data points used to create each chart, table, or
graph.
4
Illustrations and photographs must be submitted separately in an image
file format (TIFF, JPEG, AI, or EPS) and must include all sources and
written permissions for use.
5
Images must have at least 72 ppi (pixels per inch), and it is strongly
preferred that they be 96 ppi at the size they will be displayed on the page
(i.e., if the final display image will be 4" × 6", it needs to be 96 ppi at 4" ×
6"). As a general rule, images found on the internet should not be used, as
these are typically of lower resolution and quality. For reports that will
also be professionally printed, all images MUST have a minimum of 300
ppi at the size the image will be displayed on the page.
6
Illustrations and photographs to be used for the cover page must be
representative of the report’s content and with no writing on the image.
The image must be in color with a resolution of at least 300 ppi, measure
8"W × 6"H, and include all sources and written permissions. Please
indicate the correct accreditation for the image.
7
Videos must be submitted separately in a video file format (MPG, MOV,
WMV, or AVI) and must include all sources and written permissions for
use. A written script of any video(s) must be included for 508 compliance
purposes.
(d) References
1
Footnotes should appear at the bottom of the page on which they are cited
(not as endnotes).
2
References should be numbered sequentially in order of their appearance
in the text, in brackets with an Arabic numeral, e.g., [22]. References
should not be denoted with superscripts.
3
References should be listed in sequential order at the end of the document
using The Chicago Manual of Style format.
4
References should not include personal communications, telephone
conversations, or similar material that would not be available to readers
electronically or in printed form in a library or from the originating
agency. Instead, cite the author’s name and “unpublished data” in
parentheses (in both text and References at end).
FTA C 6100.1E
Appendix D
Page D–5 of 8
(e) Alternative Text Guidelines. Alternative (alt) text is text associated with an
image that serves the same purpose and conveys the same essential
information as the image. In situations where the image is not available to the
reader (perhaps because they have turned off images in their web browser or
are using a screen reader due to a visual impairment), the alternative text
ensures no information or functionality is lost. The following guidelines
should be used when writing alt text:
1
Alt text should describe all the important information in the image but not
every physical detail, only what is important to its meaning and
understanding.
2
Alt text should not duplicate information provided in the content of the
page or in the caption.
3
Alt text should begin with the figure number and a word that describes the
type of image, e.g., “Figure 5-1 is a graph of . . .” or “Figure 2-3 is a photo
of. . . .”
4
For a simple or decorative image, such as a logo, provide only a brief
description. If more information would be useful to convey the meaning of
the image, this should be included. Purely decorative images, which add
no meaningful information to a page, such as bullets or page dividers, do
not require alt text.
5
Alt text for images that contain detailed information, such as a technical
diagram, chart, or graph, must include all relevant data, unless already
described in the page text.
6
Images that are linked must include a description of the destination or the
purpose of the link.
7
Information that would benefit both sighted viewers and those using
screen readers should not be included in alt text but should be included in
the image’s caption. The alt text and caption should supplement each
other, with the alt text written for screen readers and the captions written
for all readers.
8
References should use italics, not underlining, where appropriate.
9
Inserting alt text:
a
Word 2007: Right-click on the image, select Size. Select “Alt Text”
and replace the image file name that automatically appears with
appropriate alt text.
Appendix D
Page D–6 of 8
FTA C 6100.1E
b
f.
Word 2010: Right-click on the image, select Format Picture. Select
“Alt Text,” then “Description” and add the appropriate alt text.
Report Summary. All reports must be accompanied by a one- to two-page summary of
the information contained in the report. In 350 to 800 words, the summary should
include the following information:
(1) FTA Report Title
(2) Background: In one to two paragraphs, this section provides information detailing
the history of the problem and the rationale for conducting the research or for the
content of the report.
(3) Objectives: In one paragraph with bulleted items as needed, this section briefly
explains the objectives of the research or content of the report. Specific objectives
should be cast under the overall objectives.
(4) Findings and Conclusions: In two to four paragraphs in general and accessible
language, this section provides the findings and conclusions of the report and
should address the issues raised in the objectives section.
(5) Benefits: In two to three paragraphs, this section discusses the value of the
findings in terms such as the following: How will the findings be used? Are they
already being used? How will they affect FTA business? What are the safety,
economic, or efficiency benefits?
(6) Project Information: The following language should be included in the summary:
This research project was conducted by (name of Principal Investigator) of the
(contracting organization). For more information, contact FTA Project Manager
(name of FTA Project Manager) at (FTA Project Manager’s phone number and
email address).
These instructions can be found at http://www.fta.dot.gov/research/program_requirements .
Questions regarding report formatting guidelines should be directed to your FTA project
manager.
FTA C 6100.1E
Appendix D
Page D–7 of 8
FTA Report Preparation Checklist
Report Title: _________________________________________________________________
Project Manager: _____________________________________________________________
Final Output: ☐ PDF ONLY ☐ PDF and PRINTED
Required Report Components
Title Page
Report Documentation Page (in Word)
Table of Contents
List of Figures
List of Tables
Acknowledgments/Foreword
Abstract
Executive Summary
Main Body
Appendices (if needed)
Glossary (if needed)
References
Illustrations & Photos
508-compliant alternative text for all
illustrations and photos provided in
separate Word file
Illustrations/photos submitted separately in
image file format (TIFF, JPEG, AI, EPS)
with sources (and credits for photos, if
appropriate)
All images 72 ppi or higher (300 ppi or
higher if report will be professionally
printed)
Videos submitted separately, with sources
and written permissions
Written script of video
Cover image at least 8'' × 6'' at 300 ppi with
no writing on image
Sources, permissions, and photo credits for
cover image
Tables and Figures
Report Summary
Distinct title for each table and figure
One to two pages (800 words) maximum
508-compliant alternative text (for all
figures)
Background
Charts and tables submitted separately and
include all data points
Objectives
Findings and Conclusions (with single
summary sentence)
Benefits
Project Info
Appendix D
Page D–8 of 8
FTA C 6100.1E
This page intentionally left blank.
FTA C 6100.1E
INDEX
Page 1 of 4
INDEX
SUBJECT AND LOCATION IN CIRCULAR
Access Requirements for Records, IV–22
Accrual Basis of Accounting, IV–3, A–2
Adjustments to Federal Share of Costs, IV–
21
Administering Office, II–4, IV–1, IV–2, IV–
3, IV–10, IV–11, IV–12, V–11, V–14,
VI–1, VI–3
Administrative Amendment, IV–10, IV–11,
IV–13
Age Discrimination in Employment Act
(ADEA), II–7
Agreement, II–2, II–3, II–5, II–9, III–1, III–
2, III–7, III–16, III–17, III–18, III–19, III–
21, IV–1, IV–3, IV–4, IV–6, IV–8, IV–
10, IV–11, IV–12, IV–17, IV–20, IV–21,
IV–22, V–1, V–3, V–4, V–5, V–6, V–7,
V–9, V–10, V–15, VI–1, VI–2, VI–3, A–
4, C–2, C–3
Allowable Costs, III–5, III–18, V–5, V–6,
V–10, V–13, C–1
Amendment to the Agreement, IV–10, IV–
12
Americans with Disabilities Act, VI–2
Americans with Disabilities Act of 1990
(ADA), II–5, II–6
Annual Audit, V–10, V–11
Applicant, I–3
Definition, I–3
Application Instructions, 1, III–1
Application Process, III–1, IV–1
Audit Report, V–11
Audit Resolutions, V–2
Authorizing Legislation, I–1
Awarding Instrument, III–17
Background, I–1, A–1
Budget Revision, II–4, IV–8, IV–9, IV–10,
IV–11, C–3
Cancellation, 1
Certifications and Assurances, II–2, II–3,
III–2, III–6, III–11, III–12, IV–1
Change in Federal Assistance, IV–12
Civil Rights Requirements, II–5, III–16, IV–
21, VI–2
Civil Rights Reviews, VI–2
Civil Rights Submission, III–16
CloseOut by FTA, IV–20
Cognizant Federal Agency, V–8, B–1
Common Rule, IV–15, IV–19, V–3, V–4,
V–9, VI–2
Complete Application, III–17
Cooperative Agreement, II–2, II–3, II–5, II–
9, III–1, III–2, III–7, III–16, III–17, III–
18, III–19, IV–1, IV–3, IV–8, IV–11, IV–
12, IV–17, IV–20, IV–21, IV–22, V–1,
V–3, V–4, V–5, V–6, V–7, V–9, V–10,
V–15, VI–1, VI–3, A–3, A–4, C–2, C–3
Cost Allocation Plans (CAPs), II–3, IV–23,
V–9, B–1
Cost Share, III–7, III–18, III–20, III–21
Cross-Cutting Requirements, II–9
Davis-Bacon Act, III–15
Definitions, I–2, IV–18, V–8
De-obligation of Funds, V–15
Department of Health and Human Services
(DHHS), V–8
Department of Labor (DOL), III–15, III–16
Department of Transportation (DOT), II–6,
III–11, IV–6, IV–7, V–9, B–3
Determining Allowable Costs, III–5, V–5
Disadvantaged Business Enterprise (DBE),
II–8, VI–2
Goals, II–8
Disallowed Costs, V–7
DOL Clearance, III–16
Educational Institutions, III–19, IV–9, IV–
17, V–5, V–8
Electronic Award and Management System,
I–4, III–1, III–2, III–3, III–5, III–6, III–7,
III–9, III–10, III–11, III–12, III–15, III–
17, III–21, IV–1, IV–2, IV–3, IV–4, IV–
INDEX
Page 2 of 4
6, IV–9, IV–10, IV–11, IV–12, IV–20, V–
12, A–1, A–2, A–3, A–4, A–5
Employer Identification Number (EIN), A–1
Environmental Assessment (EA), III–13
Environmental Considerations, III–12
Environmental Impact Statement (EIS), III–
13, III–14
Equal Employment Opportunity, II–7
Equal Employment Opportunity (EEO), VI–
2
Equal Employment Opportunity (EEO)
Requirements, II–7
Equal Employment Opportunity
Commission (EEOC), II–7
Equipment, II–3, III–6, III–7, III–8, III–9,
III–20, IV–1, IV–8, IV–11, IV–13, IV–
14, IV–15, IV–16, IV–18, IV–19, IV–20,
IV–23, V–3, V–10, V–14, V–15, A–3, A–
4
Fair Market Value, IV–14, IV–15, IV–16,
IV–19
Federal Assistance, 1, II–2, II–4, III–1, III–
2, III–3, III–4, III–5, III–10, III–11, III–
12, III–15, III–17, III–18, III–21, III–22,
IV–1, IV–2, IV–5, IV–8, IV–10, IV–11,
IV–12, IV–13, IV–14, IV–16, IV–17, IV–
18, IV–19, IV–20, IV–21, IV–22, V–1,
V–4, V–5, V–6, V–7, V–8, V–9, V–10,
V–11, V–12, V–13, V–15, VI–2, C–2
Federal Cooperative Agreement, III–16
Federal Financial Report, I–3
Federal Highway Administration (FHWA),
III–14
Federal Register Notice, 1, III–11
Federal Transit Act, III–15
Federal Transit Administration (FTA), 1, I–
1, I–2, II–1, II–2, II–3, II–4, II–9, III–1,
III–2, III–4, III–5, III–6, III–7, III–9, III–
10, III–11, III–12, III–13, III–14, III–15,
III–17, III–18, III–19, III–21, III–22, IV–
1, IV–2, IV–3, IV–4, IV–5, IV–6, IV–7,
IV–8, IV–10, IV–11, IV–12, IV–13, IV–
14, IV–15, IV–16, IV–17, IV–19, IV–20,
IV–21, IV–22, IV–23, IV–24, V–1, V–5,
V–7, V–8, V–9, V–10, V–11, V–12, V–
FTA C 6100.1E
13, V–14, V–15, VI–1, VI–2, VI–3, A–2,
A–3, A–4, A–5, B–1, C–1, C–2, C–3
Final Report, III–9, IV–2, IV–6, A–1, A–3
Financial Management, II–2, II–4, III–1,
IV–3, IV–9, IV–21, V–1, V–3, V–4
Financial Management Oversight (FMO),
VI–1
Financial Management Systems, V–3, V–4
Financial Status Tab, A–1
Finding of No Significant Impact (FONSI),
III–14
Fiscal Year, IV–5, IV–10, C–1
Fiscal Year (FY), VI–1
Formal Application Procedures, III–5
Freedom of Information Act (FOIA), IV–18,
IV–24
FTA Circulars, II–2
FTA Oversight, II–2, VI–1
FTA Procurement Guidance, IV–19
General Services Administration (GSA),
IV–15
Grant, II–2, II–3, II–5, III–1, III–2, III–3,
III–7, III–16, III–17, III–18, III–19, IV–1,
IV–3, IV–8, IV–9, IV–11, IV–12, IV–15,
IV–17, IV–19, IV–20, IV–21, IV–22, V–
1, V–3, V–4, V–5, V–6, V–7, V–8, V–9,
V–10, V–15, VI–1, VI–2, VI–3, A–1, A–
2, A–3, A–4, B–3, C–2, C–3
Grant Agreement, II–2, II–3, III–1, III–2,
III–7, III–17, III–18, III–19, IV–1, IV–3,
IV–8, IV–11, IV–12, IV–17, IV–20, IV–
21, IV–22, V–1, V–4, V–5, V–6, V–7, V–
9, V–10, V–15, VI–1, VI–3, A–3, A–4,
C–2, C–3
Grant Period, I–5
Grant Scope, I–5
Grantee, I–7, VI–2, A–1, A–2, A–3, A–4,
A–5
Grants.gov, I–2, III–2, III–4
High Quality Cost Share, III–20
How to Contact FTA, I–1
Incidental Use of Project Property and
Equipment, I–5
Intangible Property, IV–17, IV–19
Internal Control Self-Assessment, V–3
FTA C 6100.1E
Internal Controls, V–1, V–2
Introduction, I–1, A–1
Joint Venture Participation, III–19
Key Person, I–5, III–4, III–10, IV–8
Labor Protection, III–17
Labor Protections, III–15
Lobbying Disclosure, III–16
Low Quality Cost Share, III–20
Management Meetings, IV–5, VI–3
Management Responsibilities, 1
Master Agreement, II–9, III–2, III–15, III–
17, IV–22, V–15, VI–1, VI–2
Milestone Progress Report, II–5, III–2, IV–
1, IV–3, C–3
Moving Ahead for Progress in the 21st
Century Act (MAP-21), 1
National Environmental Policy Act (NEPA),
III–13, III–14
National Research Programs, 1, II–1, III–11
National Technical Information Service
(NTIS), IV–6
Nondiscrimination, II–5, II–6, II–7, II–8
Age, II–5, II–7
Disability, II–7
Sex, II–5, II–7
Title VI, II–6
Office of Management and Budget (OMB),
II–3, III–3, IV–5, V–4, B–2
Office of Naval Research, V–8
OMB Standard Form 424, III–5
Other Agreement, I–3
Other project management meetings, VI–3
Partial Termination, IV–22
Payment Procedures, V–5, V–12
Peer Review, III–17, IV–18
Possible Project Requirements, III–15
Prior Approval, II–4, IV–4, IV–6, IV–7, IV–
8, IV–9, IV–10, IV–11, B–3, C–3
Procurement Reviews, VI–2
Program Fraud Civil Remedies Act, II–9
Program Income, III–19, IV–13, V–9, V–10,
A–4, C–2
Program Overview, II–1
Program Specific Reviews, VI–1
INDEX
Page 3 of 4
Progress Reports, III–2, IV–1, V–12, VI–3,
C–3
Progress Reports (PRs), II–5, IV–1
Project, 1, II–2, II–3, II–4, II–5, III–1, III–2,
III–4, III–5, III–6, III–7, III–8, III–9, III–
10, III–11, III–12, III–13, III–14, III–15,
III–16, III–17, III–18, III–19, III–20, III–
21, III–22, IV–1, IV–2, IV–3, IV–4, IV–
5, IV–6, IV–7, IV–8, IV–9, IV–10, IV–
11, IV–12, IV–13, IV–15, IV–16, IV–17,
IV–18, IV–19, IV–20, IV–21, IV–22, IV–
23, IV–24, V–1, V–2, V–4, V–5, V–6, V–
7, V–8, V–9, V–10, V–12, V–13, V–14,
V–15, VI–1, VI–2, VI–3, A–1, A–2, A–3,
A–4, B–3, C–1, C–2, C–3
Project Administration, II–2, IV–1, V–6
Project Amendment, II–4
Project Approval, III–2, III–15, III–21
Project Budget, II–3, III–2, III–5, III–6, III–
7, IV–4, IV–5, IV–8, IV–11, IV–12, V–6,
V–7, C–1
Project Closeout, IV–20, IV–21, IV–23, V–
7, V–15
Project Identification, IV–1
Project Level Reviews, VI–3
Project Management Meetings, IV–5, VI–3
Project Management Responsibilities, 1
Project Manager, III–10, III–15, III–16, III–
21, IV–3, IV–4, IV–6, IV–7, IV–9, IV–
20, C–1
Project Milestone Schedule, III–9, III–10
Project Modifications, IV–9, IV–10
Project Narrative Statement, III–4
Project Period, III–9, III–22, IV–20, V–9,
V–10
Project Property, II–3, IV–20
Project Proposal Procedures, III–4
Project Requirements, III–2, III–6, III–15
Project Scope, IV–11, IV–12
Public Transportation, I–1, II–5, IV–1, V–3,
V–10, VI–2
Quarterly Narrative Report, IV–4
Quarterly Narrative Reports, II–5, IV–3
quarterly project management meetings, IV–
5
INDEX
Page 4 of 4
Quarterly project management meetings,
VI–3
Quarterly Project Management Meetings,
IV–5, VI–3
Real Property, V–3, V–10, V–15, A–4
recipient, B–3
Recipient, 1, II–2, II–3, II–4, II–5, II–6, II–
7, II–8, II–9, III–2, III–3, III–11, III–12,
III–13, III–15, III–16, III–17, III–18, III–
20, III–21, III–22, IV–1, IV–2, IV–3, IV–
4, IV–5, IV–6, IV–7, IV–8, IV–9, IV–10,
IV–11, IV–12, IV–13, IV–14, IV–15, IV–
16, IV–17, IV–18, IV–19, IV–20, IV–21,
IV–22, IV–23, IV–24, V–1, V–2, V–3,
V–4, V–5, V–6, V–7, V–8, V–9, V–10,
V–11, V–12, V–13, V–14, V–15, VI–1,
VI–2, VI–3, A–1, A–2, A–3, A–4, A–5,
B–1, B–2, B–3, C–1, C–2
Rehabilitation Act, II–7, IV–6, IV–7
Rehabilitation Act of 1973, II–5
Remaining Federal Interest for Dispositions
before the End of Useful Life, I–7
Remarks and Certifications Tab, A–5
Repayment, IV–20, V–14
Report Due Dates, IV–2
Report Organization, IV–7
Reporting Requirements, 1, II–3, III–3, IV–
1, IV–5
Reports, II–3, II–4, II–5, III–2, III–4, III–9,
IV–1, IV–2, IV–3, IV–4, IV–5, IV–6, IV–
7, IV–20, V–1, V–2, V–4, V–5, V–12,
VI–3, C–3
Reports of Significant Events, IV–5
Requirement to Remit Interest, V–15
Research and Development, III–19, III–20,
III–21, IV–6, V–10
research, development, demonstration, and
deployment, II–1
Responsibilities of Project Management, II–
2
Responsibilities to Limited English
Proficient (LEP) Persons, II–6
Retention of Records, IV–23
FTA C 6100.1E
Reviews, II–2, II–4, II–5, IV–18, IV–21,
VI–1, VI–2, VI–3
Right of FTA to Terminate, V–15
Sales Proceeds, IV–15
Scope of the Project, I–7, IV–4, IV–10, IV–
11
Similar Rate, and Rate Allocation Methods,
IV–23
Site Visits, VI–1, VI–3
Special Disposition Authority, IV–16
Specialized Oversight Strategies, VI–3
State Recipient, IV–13, See also, Recipient
Statement of Work (SOW), III–8, III–20,
III–21, IV–10, IV–12
Statewide Transportation Improvement
Program, III–11
Statutory Authority, II–1
straight line depreciation, I–8
Strategic Research Plan, III–5, III–18, III–19
Subrecipient, II–2, II–3, II–4, II–5, II–6, II–
7, II–8, III–16, IV–13, IV–18, IV–22, IV–
23, IV–24, V–1, V–4, V–5, V–6, V–9, V–
10, V–11, V–12, VI–2, A–2, A–3, A–4
Summary Tab, IV–3, A–1
Supplies, III–7, III–8, IV–8, IV–19
Third Party Contract Provisions, IV–20
Third Party Procurement, IV–19
Title to Equipment, IV–13
Title VI of the Civil Rights Act of 1964, II–
6
Title VII of the Civil Rights Act of 1964, II–
7
Transit, 1, III–5, III–13, III–15, III–16, III–
20, IV–6, IV–7, V–14, A–4, B–3
Transit Employee Protection, III–15
U.S. Access Board, IV–7
Unacceptable Cost Share, III–20
Unified Planning Work Program (UPWP),
III–11
Unliquidated Obligations, A–1, A–3, A–4
Waiver, 1, II–4, V–7, V–15
Withdrawals, II–3, V–13
File Type | application/pdf |
File Title | FTA Circular 6100.1E Proposed |
Subject | FTA Circular 6100.1D Research, Technical Assistance, and Training Programs: Application Instructions and Project Management Gui |
Author | USDOT User |
File Modified | 2015-04-20 |
File Created | 2015-04-20 |