Calculation Tables for ICR 2050.06

Copy of 2050 06 calculations table.xlsx

NESHAP for Taconite Iron Ore Processing (40 CFR part 63 subpart RRRRR) (Renewal)

Calculation Tables for ICR 2050.06

OMB: 2060-0538

Document [xlsx]
Download: xlsx | pdf

Overview

Table 1
Table 2


Sheet 1: Table 1

Table 1: Annual Respondent Burden and Cost – NESHAP for Taconite Iron Ore Processing (40 CFR Part 63, Subpart RRRRR) (Renewal)














103.97 129.93 51.79


Burden Item (A)
Respondent Hours per Occurrence
(B)
Number of Occurrences per Respondent per Year
(C)
Hours per Respondent per Year
(C=AxB)
(D) Number of Respondents per Year a (E)
Technical Hours per Year
(E=CxD)
(F)
Management Hours per Year
(F=Ex0.05)
(G)
Clerical Hours per Year
(G=Ex0.1)
(H)
Total Labor Costs per Year b


1. Applications N/A








2. Survey and Studies N/A








3. Reporting Requirements









A. Familiarize with regulatory requirements c 2 1 2 4 8 0.4 0.8 $925.16

B. Required activities









Performance test – facility labor e 40 1 40 1.6 64 3.2 6.4 $7,401.31

Startup , shutdown, and malfunction plan 40 1 40 1.6 64 3.2 6.4 $7,401.31

C. Create information See 4B








D. Gather existing information See 4B








E. Write reports









Initial notification d 2 1 2 0 0 0 0 $0

Compliance extension request d 2 1 2 0 0 0 0 $0

Site-specific test plan f 40 1 40 0.32 12.8 0.64 1.28 $1,480.26

Operation and maintenance plan d, g 40 1 40 0 0 0 0 $0

Fugitive dust emission control plan d, h 20 1 20 0 0 0 0 $0

Site-specific monitoring plan d, i 80 1 80 0 0 0 0 $0

Semiannual compliance reports 8 2 16 4 64 3.2 6.4 $7,401.31

Petition for alternative monitoring requirements 40 1 40 0 0 0 0 $0

Notification of performance test j 4 3 12 1.6 19.2 0.96 1.92 $2,220.39

Subtotal for Reporting Requirements



267 $26,830

4. Recordkeeping requirements









A. Familiarize with regulatory requirements c See 3A








B. Plan activities 3 1 3 0 0 0 0 $0

C. Develop record system 16 1 16 0 0 0 0 $0

D. Time to train personnel 3 1 3 0 0 0 0 $0

E. Time to transmit or disclose information 1 2 2 4 8 0.4 0.8 $925.16

F. Time for audits N/A








Subtotal for Recordkeeping Requirements



9 $925

Total Labor Burden and Cost (rounded) k



276 $27,800

Total Capital and O&M Costs (rounded) k






$298,000
21
Grand Total (rounded) k






$326,000
hr/response











Assumptions:









a We have assumed that the average number of respondent that will be subject to the rule will be the eight existing respondents. There will be no additional new sources per year that will become subject to the rule over the three-year period of this ICR.









b This ICR uses the following labor rates: Technical $103.97 ($49.51 + 110%); Managerial $129.93 ($61.87+ 110%); and Clerical $51.79 ($24.66 + 110%). These rates are from the United States Department of Labor, Bureau of Labor Statistics, June 2014, “Table 2. Civilian Workers, by occupational and industry group.” The rates are from column 1, “Total compensation.” The rates have been increased by 110 percent to account for the benefit packages available to those employed by private industry. This ICR assumes that Managerial hours are 5 percent of Technical hours, and Clerical hours are 10 percent of Technical hours.









c This ICR assumes all respondents will have to familiarize with the regulatory requirements each year.









d This is a one-time activity.









e We have assumed that it will take 40 hours for each facility to complete performance test, and that performance tests are repeated every two of five years. Therefore, an average of 1.6 facilities per year will complete performance tests (2 performance test/5 years*4 facilities).









f We have assumed that 20 percent of all sources will send in a site-specific test plan.









g We have assumed that each respondent will take 40 hours to write the operation and maintenance plan.









h We have assumed that each respondent will take 20 hours to write the fugitive dust emission control plan.









i We have assumed that each respondent will take 80 hours to complete the site-specific monitoring plan report.









j We have assumed that each respondent will take 4 hours to complete the notification of performance test report.









k Totals have been rounded to 3 significant figures. Figures may not add exactly due to rounding.










Sheet 2: Table 2

Table 2: Average Annual EPA Burden and Cost – NESHAP for Taconite Iron Ore Processing (40 CFR Part 63, Subpart RRRRR) (Renewal)












46.67 62.9 25.25
Burden Item (A)
EPA Hours per Occurrence
(B)
Number of Occurrences per Plant per Year
(C)
EPA Hours per Plant per Year
(C=AxB)
(D)
Plants per Year a
(E)
Technical Hoursper Year
(E=CxD)
(F)
Management Hours per Year
(F=Ex0.05)
(G)
Clerical Hoursper Year
(G=Ex0.1)
(H)
Costs per Year ($) b









Initial performance tests c, d 8 7 56 0 0 0 0 $0
Report Review







Initial notification c 2 1 2 0 0 0 0 $0
Notification of initial performance test c 2 3 6 0 0 0 0 $0
Fugitive dust emissions control plan e 10 1 10 0 0 0 0 $0
Compliance extension request 2 1 2 0 0 0 0 $0
Site-specific test plan f 10 1 10 0.32 3.2 0.16 0.32 $167.49
Operation and maintenance plan c, f 10 1 10 0 0 0 0 $0
Site-specific monitoring plan c, f 10 1 10 0 0 0 0 $0
Petition for alternative monitoring requirements 5 1 5 0 0 0 0 $0
Review of semiannual compliance report 4 2 8 4 32 1.6 3.2 $1,674.88
Review of startup, shutdown, and malfunction plan g 10 1 10 1.6 16 0.8 1.6 $837.44
Total Labor Burden and Cost (rounded) h



59 $2,680









Assumptions:







a We have assumed that the average number of respondents that will be subject to the rule will be the eight existing respondents. There will be no additional new sources per year that will become subject to the rule over the three-year period of this ICR.







b This cost is based on the average hourly labor rate as follows: Technical $46.67 (GS-12, Step 1, $29.17 + 60%); Managerial $62.90 (GS-13, Step 5, $39.31 + 60%); and Clerical $25.25 (GS-6, Step 3, $15.78 + 60%). This ICR assumes that Managerial hours are 5 percent of Technical hours, and Clerical hours are 10 percent of Technical hours. These rates are from the OPM, 2014 General Schedule, which excludes locality rates of pay. The rates have been increased by 60 percent to account for the benefit packages available to government employees.







c This is a one-time only activity.







d We have assumed that the initial performance test/occurrences per respondent are based on the following: (27 indurating furnaces and ore dryer Method 5 PM
tests + 58 OCH and PH Method 5 PM tests) for a total of 85 Method 5 PM tests for three years. 85tests/3 years = 28 Method 5 PM tests/year. (28 Method 5
PM tests/year)/(4 plants) = 7 Method 5 PM tests per year per plant.








e We have assumed that each of the fugitive dust emissions control plan will be unchanged.







f We have assumed that it will take each respondent 10 hours to review the plan.







g We have assumed that 40 percent of respondents will submit startup, shutdown, and malfunction plan/reports.







h Totals have been rounded to 3 significant figures. Figures may not add exactly due to rounding.