9000-0029 Supporting Statement

9000-0029 Supporting Statement.doc

Extraordinary Contractual Action Requests - FAR Sections Affected: 50.103-3, 50.103-4, 50.104-3, and 52.250-1

OMB: 9000-0029

Document [doc]
Download: doc | pdf



SUPPORTING STATEMENT

FOR INFORMATION COLLECTION SUBMISSION 9000-0029, EXTRAORDINARY CONTRACTUAL ACTION REQUESTS


A. Justification.


1. Administrative requirements. This request covers the collection of information under 50 U.S.C. 1431 et seq. and Executive Order (EO) 10789 dated November 14, 1958, as amended by E.O. 12919 dated June 3, 1994, EO 13232 dated October 20, 2001, and EO 13286 dated February 28, 2003, that allows contracts to be entered into, amended, or modified in order to facilitate national defense.

This authority applies to the Government Printing Office; the Department of Homeland Security; the Tennessee Valley Authority; the National Aeronautics and Space Administration; the Department of Defense; the Department of the Army; the Department of the Navy; the Department of the Air Force; the Department of the Treasury; the Department of the Interior; the Department of Agriculture; the Department of Commerce; and the Department of Transportation. Also included is the Department of Energy for functions transferred to that Department from other authorized agencies and any other agency that may be authorized by the President.

In order for a firm to be granted relief under the Act, specific evidence must be submitted which supports the firm's assertion that relief is appropriate and that the matter cannot be disposed of under the terms of the contract.

FAR 50.103-3 specifies the minimum information that a contractor must include in a request for contract adjustment in accordance with FAR 50-103-1 and 50.103-2.

FAR 50-103-4 sets forth additional information that the contracting officer or other agency official may request from the contractor to support any request made under FAR 50.103-3.

FAR 50.104-3 sets forth the information that the contractor shall include in a request for the indemnification clause to cover unusually hazardous or nuclear risks.

FAR 52.250-1, Indemnification under Public Law 850804, requires in paragraph (g) that the contractor shall promptly notify the contracting officer of any claim or action against, or loss by, the contractor or any subcontractors that may reasonably to involve indemnification under the clause.


2. Uses of information. The information is used by the Government to determine if relief can be granted under the Act and to determine the appropriate type and amount of relief.


3. Consideration of information technology. We use improved information technology to the maximum extent practicable. Where both the Government agency and contractors are capable of electronic interchange, the contractors may submit this information collection requirement electronically.


4. Describe efforts to identify duplication. This requirement is being issued under the Federal Acquisition Regulation (FAR), which has been developed to standardize Federal procurement practices and eliminate unnecessary duplication.


5. If the collection of information impacts small businesses or other entities, describe methods used to minimize burden. The burden applied to small businesses is the minimum consistent with applicable laws, Executive orders, regulations, and prudent business practices.


6. Describe consequence to Federal program or policy activities if the collection is not conducted or is conducted less frequently. This information is only collected when the contractor needs to request a contract adjustment, when the contractor requests inclusion of the clause 52.250-1, or when the contractor needs to report any claim, loss, or damage covered by the clause. Collection of information on a less frequent basis is not practical.


7. Special circumstances for collection. Collection is consistent with guidelines in 5 CFR 1320.6.


8. Efforts to consult with persons outside the agency. A notice was published in the Federal Register at 81 FR 7798 on February 16, 2016. No comments were received. A 30-day notice was published in the Federal Register at 81 FR 24816 on August 27, 2016.


9. Explanation of any decision to provide any payment or gift to respondents, other than remuneration of contractors or grantees. Not applicable.


10. Describe assurance of confidentiality provided to respondents. This information is disclosed only to the extent consistent with prudent business practices and current regulations.


11. Additional justification for questions of a sensitive nature. No sensitive questions are involved.


12 & 13. Estimated total annual public hour and cost burden. The clearance for FY 2013 did not break out separate estimates for the various requirements in part 50 and 52.250-1. We estimate very few requests for adjustment under FAR 50.103. The estimates for respondents and responses under 50.104 and 52.250-1 are based on extrapolation from data reported by the Department of Defense for FY 2015. The estimated average hours per response has been increased based on the advice of subject matter experts.

a. FAR 50.103-3 and 50.103-4

Estimated respondents/yr...................... 10

Responses annually................................ x 1

Total annual responses.......................... 10

Estimated hrs/response......................... x 24

Estimated total burden/hrs.................... 240
Average wages/hr.($33.72/hr.+36% OH)**.........
x __ $ 46

Estimated cost to public* ...... $11,040


b. FAR 50.104-3

Estimated respondents/yr...................... 18

Responses per respondent................................ x 8

Total annual responses.......................... 144

Estimated hrs/response......................... x 40

Estimated total burden/hrs.................... 5,760 Average
wages/hr.($33.72/hr.+36% OH)**.........
x __ $ 46

Estimated cost to public* ...... $264,960


c. FAR 52.250-1

Estimated respondents/yr...................... 10*

Responses per respondent................................ x 1

Total annual responses.......................... 10

Estimated hrs/response......................... x 80

Estimated total burden/hrs.................... 800
Average wages/hr.($33.72/hr.+36% OH)**.........
x __ $ 46

Estimated cost to public* ...... $36,800

This is a subset of the 18 respondents in b.

d. Total

Estimated respondents/yr...................... 28

Responses per respondent................................ x 5.9*

Total annual responses.......................... 164

Estimated hrs/response......................... x 41.5*

Estimated total burden/hrs.................... 6,800
Average wages/hr.($33.72/hr.+36% OH)**........ .
x __ $ 46

Estimated cost to public* ...... $312,800

The estimated cost per response is $1907.31.


*weighted average


* The estimated cost to public is a rate equivalent to a GS-12, Step 5 or $33.72/hour (from the 2016 OPM GS Salary Table), added overhead at 36 percent (the OMB-mandated burden rate of 36.25% for A-76 public-private competitions of 36.25, rounded to 36%), and rounded average wage to the nearest whole dollar, or $46/hour.


14. Estimated cost to the Government. Time required for Governmentwide review is estimated at 16 hours per response.


Annual Reporting Burden and Cost

a. FAR 50..103-3 and 50.103-4

Annual responses.......................... 10

Estimated hrs/response......................... x 24

Estimated total burden/hrs.................... 240
Average wages/hr.($33.72hr.+36% OH)**.........
x __ $ 46

Estimated cost to government* ...... $11,040


b. FAR 50.104-3
Annual responses.......................... 144

Estimated hrs/response......................... x 20

Estimated total burden/hrs.................... 2,880

Average wages/hr.($30.72hr.+36% OH)**......... x __ $ 46

Estimated cost to government * ...... $132,480


c. FAR 52.2450-1

Annual responses.......................... 10

Estimated hrs/response......................... x 80

Estimated total burden/hrs.................... 800
Average wages/hr.($33.72hr.+36% OH)**.......
x _ $ 46

Estimated cost to government * ...... $36,800

d. Total

Total annual responses.......................... 164

Estimated hrs/response......................... x 23.9*

Estimated total burden/hrs.................... 3,920
Average wages/hr.($30.81hr.+36% OH)**........
x __ $ 46

Estimated cost to government * ...... $180,320

*weighted average


* The estimated cost to government is a rate equivalent to a GS-12, Step 5 or $33.72/hour (from the 2016 OPM GS Salary Table), added overhead at 36 percent (the OMB-mandated burden rate of 36.25% for A-76 public-private competitions rounded to 36%), and rounded average wage to the nearest whole dollar, or $46/hour.


15. Explain reasons for program changes or adjustments reported in Item 13 or 14. This submission requests an extension of an information collection requirement in the FAR. For greater accuracy, the Burdens associated with FAR subpart 501. And 52.250-1 have been separately identified and evaluated. There is no program change. The estimated number of respondents has decreased from 100 to 28, but the estimated number of total responses has increased from 100 to 164, because we now estimate about 6 responses per respondent, rather than 1. The weighted average of hours per response has increased from 16 to about 41.5 hours. This results in an increase of estimated total burden hours from 1,600 hours to 6,800 hours. These adjustments are based on DoD reported data for 2015 and the advice of subject matter experts.


16. Outline plans for published results of information collections. Results will not be tabulated or published.


17. Approval not to display expiration date. Not applicable.


18. Explanation of exception to certification statement. Not applicable.


B. Collections of Information Employing Statistical
Methods.

Statistical methods are not used in this information collection.





5


File Typeapplication/msword
File TitleSUPPORTING STATEMENT
AuthorNetwork Administrator
Last Modified ByNicoleDBynum
File Modified2016-04-27
File Created2016-04-20

© 2024 OMB.report | Privacy Policy