787 Supplement A to Construction Contract RUS Form 515

Telecommunications System Construction Policies and Procedures

RUS-787

Telecommunications System Construction Policies and Procedures

OMB: 0572-0059

Document [pdf]
Download: pdf | pdf
According to the Paperwork Reduction Act of 1995, an agency may not conduct or sponsor, and a person is not required to respond to, a
collection of information unless it displays a valid OMB control number. The valid OMB control number for this information collection Is
0572-0059. The time required to complete this information collection is estimated to average 0.1 of an hour per response, including the time for
reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection
of Information.

SUPPLEMENT A TO CONSTRUCTION CONTRACT*
RUS FORM 515
The Bidder agrees that the following provisions shall be a part of the Proposal to which this
Supplement is attached and shall supersede all provisions of the Proposal which are inconsistent
herewith:
1. The following Section 24 shall be added on Page 116:
24(a) The Bidder understands and agrees that, if this Proposal is accepted, the Owner shall
furnish to the Bidder the materials set forth in the attached ''List of Owner's Materials
on Hand'' and the Bidder will give a receipt therefore in writing to the Owner. The
Bidder further agrees, at its expense and on behalf of the Owner, to promptly receive,
unload, transport and handle all materials and equipment on the ''List of Materials
Ordered by Owner but Not Delivered'' when delivered and shall be responsible for
demurrage, if any, and will promptly forward to the Owner the Bidder's receipt in
writing for such materials. The materials referred to above are on hand at, or will be
delivered to, the locations specified in the attached Lists and the Bidder will use such
materials in constructing the Project.
(b)

The Contractor's Bond shall be in a penal sum of not less than the contract price,
which is the sum of all labor and materials including owner-furnished materials
covered by this Supplement A.

(c)

The references in the Construction Agreement to "materials," except in Article IV
Section 1 (0, Page 125, shall be understood to mean only materials to be furnished by
the Bidder.

(d)

The value of the completed Assembly Units certified to by the Bidder each month
pursuant to Article 111, Section I (a) Pages 121 and 122, of the Construction
Agreement shall be reduced by an amount equal to the value of the materials installed
by the Bidder during the preceding month which have been furnished by the Owner or
the delivery of which has been accepted by the Bidder on behalf of the Owner. Only
95 percent of the remainder shall be paid prior to the completion of the Project. The
value of such materials for the purpose of this Supplement shall be computed on the
basis of the unit prices stated in the attached Lists, and not on the Bidder's material
unit bid prices. Materials, if any, not required for the Project, which have been
furnished to the Bidder by the Owner or delivery of which has been accepted by the
Bidder on behalf of the Owner, shall be returned to the Owner by the Bidder upon
completion of the construction of the Project. The value of all materials not installed
in the Project or returned to the Owner shall be deducted from the final payment to
the Bidder.

*Insert Supplement A and Attachments immediately in front of the Proposed Summary Page 107 in the
Contractor's Proposal Section of RUS Form 515
RUS Form 787 (Rev. 3-95)

(e)

The Owner shall furnish such materials, if any, as may be required for the Project in
excess of the quantities set forth in the attached Lists. In such event, the value of such
excess materials shall be determined on the basis of the unit prices stated in the
attached Lists and payments to the Bidder on account of such excess materials
furnished by the Owner shall be reduced in the manner provided in paragraph (d)
above.

2. Section 15, Page 114, shall be revised to read as follows:
15. The unit prices for Assembly Units in this Contractor's Proposal include provisions for
the payment of all moneys which will be payable by the Bidder or the Owner in
connection with the construction of the Project on account of taxes imposed by any
taxing authority upon the sale, purchase or use of materials, supplies and equipment or
services or labor of installation thereof, to be incorporated in the project as part of
such Assembly Units. The Bidder agrees to pay all such taxes except on Owner
Furnished Materials and it is understood that, as to Owner Furnished Materials, the
values stated in the attached ''List of Owner's Materials on Hand'' and ''List of
Materials Ordered by Owner but Not Delivered'' include such taxes, if applicable. The
Bidder will furnish to the appropriate taxing authorities all required information and
reports pertaining to materials used in construction of the project except as to Owner
Furnished Materials.

Bidder
By
Date
Title
Owner
By
Date
Tide

RUS Form 787 (Rev. 3-95)


File Typeapplication/pdf
File Modified0000-00-00
File Created0000-00-00

© 2024 OMB.report | Privacy Policy