Download:
docx |
pdf
Large
Generator Interconnection Agreement (LGIA) and Large
Generator Interconnection Procedures (LGIP) for Small Generators,
prior to Final Rule RM16-6-000
The
attached LGIA and LGIP were in place prior to the Final Rule in
RM16-6-000.
These
documents do not include the changes made to LGIA and LGIP by Order
No. 842, Final Rule re the Essential Reliability Services and the
Evolving Bulk-Power System -- Primary Frequency Response under
RM16-6, 162 FERC ¶ 61,128, issued February 15, 2018, located at
https://elibrary.ferc.gov/idmws/file_list.asp?document_id=14643623
The
modifications made to SGIA and SGIP by Order No. 842 are included in
the order.
Updated
September 26, 2016
Note:
This version of the Standard Large Generator Interconnection
Agreement reflects Commission action in Order Nos. 2003, 661, 764,
and 827.
Appendix 6 to the Standard Large
Generator Interconnection Procedures
STANDARD LARGE GENERATOR
INTERCONNECTION AGREEMENT
(LGIA)
TABLE OF CONTENTS
Page
Recitals - 1 -
Article
1. Definitions -
2 -
Article
2. Effective
Date, Term, and Termination - 11 -
2.1 Effective
Date - 11 -
2.2 Term
of Agreement - 12 -
2.3 Termination
Procedures. - 12 -
2.3.1 Written
Notice - 12 -
2.3.2 Default -
12 -
2.4 Termination
Costs - 12 -
2.5 Disconnection -
13 -
2.6 Survival -
13 -
Article
3. Regulatory
Filings - 14 -
3.1 Filing -
14 -
Article 4. Scope
of Service - 14 -
4.1 Interconnection
Product Options - 14 -
4.1.1 Energy
Resource Interconnection Service - 14 -
4.1.1.1
The Product - 14 -
4.1.1.2
Transmission Delivery Service Implications - 14 -
4.1.2 Network
Resource Interconnection Service - 15 -
4.1.2.1
The Product - 15 -
4.1.2.2
Transmission Delivery Service Implications - 16 -
4.2 Provision
of Service - 18 -
4.3 Performance
Standards - 18 -
4.4 No
Transmission Delivery Service. - 18 -
4.5 Interconnection
Customer Provided Services - 18 -
Article 5.
Interconnection Facilities Engineering, Procurement, and
Construction -
18 -
5.1 Options -
18 -
5.1.1 Standard
Option - 18 -
5.1.2 Alternate
Option - 19 -
5.1.3 Option
to Build - 19 -
5.1.4 Negotiated
Option - 19 -
5.2 General
Conditions Applicable to Option to Build - 20 -
5.3 Liquidated
Damages - 21 -
5.4 Power
System Stabilizers - 22 -
5.5 Equipment
Procurement - 23 -
5.6 Construction
Commencement - 23 -
5.7 Work
Progress - 24 -
5.8 Information
Exchange - 24 -
5.9 Limited
Operation - 24 -
5.10 Interconnection
Customer's Interconnection Facilities ('ICIF') - 24 -
5.10.1
Interconnection Customer's Interconnection Facility Specifications -
24 -
5.10.2
Transmission Provider's Review - 25 -
5.10.3
ICIF Construction - 25 -
5.11 Transmission
Provider's Interconnection Facilities Construction - 25 -
5.12 Access
Rights - 26 -
5.13 Lands
of Other Property Owners - 26 -
5.14 Permits -
26 -
5.15 Early
Construction of Base Case Facilities - 27 -
5.16 Suspension -
27 -
5.17 Taxes -
27 -
5.17.1
Interconnection Customer Payments Not Taxable - 28 -
5.17.2
Representations and Covenants - 28 -
5.17.3
Indemnification for the Cost Consequences of Current Tax Liability
Imposed Upon the Transmission Provider - 28 -
5.17.4
Tax Gross-Up Amount - 29 -
5.17.5
Private Letter Ruling or Change or Clarification of Law - 30 -
5.17.6
Subsequent Taxable Events - 31 -
5.17.7
Contests - 31 -
5.17.8
Refund - 32 -
5.17.9
Taxes Other Than Income Taxes - 33 -
5.17.10
Transmission Owners Who Are Not Transmission
Providers -
34 -
5.18 Tax
Status - 34 -
5.19 Modification -
34 -
5.19.1
General - 34 -
5.19.2
Standards - 35 -
5.19.3
Modification Costs - 35 -
Article
6. Testing
and Inspection - 35 -
6.1 Pre-Commercial
Operation Date Testing and Modifications - 35 -
6.2 Post-Commercial
Operation Date Testing and Modifications - 36 -
6.3 Right
to Observe Testing - 36 -
6.4 Right
to Inspect - 36 -
Article
7. Metering -
36 -
7.1 General -
36 -
7.2 Check
Meters - 37 -
7.3 Standards -
37 -
7.4 Testing
of Metering Equipment - 37 -
7.5 Metering
Data - 38 -
Article
8. Communications -
38 -
8.1 Interconnection
Customer Obligations - 38 -
8.2 Remote
Terminal Unit. - 38 -
8.3 No
Annexation - 39 -
8.4. Provision
of Data from a Variable Energy Resource - 39 -
Article
9. Operations -
39 -
9.1 General -
40 -
9.2 Control
Area Notification - 40 -
9.3 Transmission
Provider Obligations - 40 -
9.4 Interconnection
Customer Obligations - 40 -
9.5 Start-Up
and Synchronization - 40 -
9.6 Reactive
Power - 41 -
9.6.1 Power
Factor Design Criteria - 41 -
9.6.1.1
Synchronous Generation - 41 -
9.6.1.2
Non-Synchronous Generation - 41 -
9.6.2 Voltage
Schedules - 41 -
9.6.2.1
Governors and Regulators - 42 -
9.6.3 Payment
for Reactive Power - 42 -
9.7 Outages
and Interruptions - 43 -
9.7.1 Outages -
43 -
9.7.1.1
Outage Authority and Coordination - 43 -
9.7.1.2
Outage Schedules - 43 -
9.7.1.3
Outage Restoration - 44 -
9.7.2 Interruption
of Service - 44 -
9.7.3 Under-Frequency
and Over Frequency Conditions - 45 -
9.7.4 System
Protection and Other Control Requirements. - 45 -
9.7.4.1
System Protection Facilities - 45 -
9.7.5 Requirements
for Protection - 46 -
9.7.6 Power
Quality. - 47 -
9.8 Switching
and Tagging Rules - 47 -
9.9 Use
of Interconnection Facilities by Third Parties - 47 -
9.9.1 Purpose
of Interconnection Facilities - 47 -
9.9.2 Third
Party Users - 47 -
9.10 Disturbance
Analysis Data Exchange - 48 -
Article
10. Maintenance -
48 -
10.1 Transmission
Provider Obligations - 48 -
10.2 Interconnection
Customer Obligations - 48 -
10.3 Coordination -
48 -
10.4 Secondary
Systems - 48 -
10.5 Operating
and Maintenance Expenses - 49 -
Article
11. Performance
Obligation - 49 -
11.1 Interconnection
Customer Interconnection Facilities - 49 -
11.2 Transmission
Provider's Interconnection Facilities - 49 -
11.3 Network
Upgrades and Distribution Upgrades - 49 -
11.4 Transmission
Credits. - 49 -
11.4.1
Repayment of Amounts Advanced for Network Upgrades - 49 -
11.4.2
Special Provisions for Affected Systems - 51 -
11.5 Provision
of Security - 51 -
11.6 Interconnection
Customer Compensation - 52 -
11.6.1 Interconnection
Customer Compensation for Actions During Emergency Condition -
52 -
Article
12. Invoice -
52 -
12.1 General -
52 -
12.2 Final
Invoice - 53 -
12.3 Payment -
53 -
12.4 Disputes -
53 -
Article
13. Emergencies -
53 -
13.1 Definition -
53 -
13.2 Obligations -
54 -
13.3 Notice -
54 -
13.4 Immediate
Action - 54 -
13.5 Transmission
Provider Authority. - 54 -
13.5.1
General - 54 -
13.5.2
Reduction and Disconnection - 55 -
13.6 Interconnection
Customer Authority - 56 -
13.7 Limited
Liability - 56 -
Article
14. Regulatory
Requirements and Governing Law - 56 -
14.1 Regulatory
Requirements - 56 -
14.2 Governing
Law - 56 -
Article
15. Notices. -
57 -
15.1 General -
57 -
15.2 Billings
and Payments - 57 -
15.3 Alternative
Forms of Notice - 57 -
15.4 Operations
and Maintenance Notice - 57 -
Article 16. Force
Majeure - 57 -
Article
17. Default -
58 -
17.1 Default -
58 -
17.1.1
General - 58 -
17.1.2
Right to Terminate - 58 -
Article
18. Indemnity,
Consequential Damages and Insurance - 59 -
18.1 Indemnity -
59 -
18.1.1
Indemnified Person - 59 -
18.1.2
Indemnifying Party - 59 -
18.1.3
Indemnity Procedures - 59 -
18.2 Consequential
Damages - 60 -
18.3 Insurance -
61 -
Article
19. Assignment -
63 -
Article
20. Severability -
63 -
Article
21. Comparability -
64 -
Article
22. Confidentiality -
64 -
22.1 Confidentiality -
64 -
22.1.1
Term - 64 -
22.1.2
Scope - 64 -
22.1.3
Release of Confidential Information - 65 -
22.1.4
Rights - 65 -
22.1.5
No Warranties - 65 -
22.1.6
Standard of Care - 66 -
22.1.7
Order of Disclosure - 66 -
22.1.8
Termination of Agreement - 66 -
22.1.9
Remedies - 66 -
22.1.10
Disclosure to FERC, its Staff, or a State - 67 -
Article
23. Environmental
Releases - 68 -
Article
24. Information
Requirements - 68 -
24.1 Information
Acquisition - 68 -
24.2 Information
Submission by Transmission Provider - 68 -
24.3 Updated
Information Submission by Interconnection Customer - 69 -
24.4 Information
Supplementation - 69 -
Article
25. Information
Access and Audit Rights - 70 -
25.1 Information
Access - 70 -
25.2 Reporting
of Non-Force Majeure Events - 70 -
25.3 Audit
Rights - 70 -
25.4 Audit
Rights Periods - 71 -
25.4.1
Audit Rights Period for Construction-Related Accounts and Records -
71 -
25.4.2
Audit Rights Period for All Other Accounts and Records - 71 -
25.5 Audit
Results - 71 -
Article
26. Subcontractors -
72 -
26.1 General -
72 -
26.2 Responsibility
of Principal - 72 -
26.3 No
Limitation by Insurance - 72 -
Article
27. Disputes -
72 -
27.1 Submission -
72 -
27.2 External
Arbitration Procedures - 72 -
27.3 Arbitration
Decisions - 73 -
27.4 Costs -
73 -
Article
28. Representations,
Warranties, and Covenants - 73 -
28.1 General -
73 -
28.1.1
Good Standing - 74 -
28.1.2
Authority - 74 -
28.1.3
No Conflict - 74 -
28.1.4
Consent and Approval - 74 -
Article 29. Joint
Operating Committee - 74 -
Article
30. Miscellaneous -
75 -
30.1 Binding
Effect - 75 -
30.2 Conflicts -
76 -
30.3 Rules
of Interpretation - 76 -
30.4 Entire
Agreement - 76 -
30.5 No
Third Party Beneficiaries - 76 -
30.6 Waiver -
77 -
30.7 Headings -
77 -
30.8 Multiple
Counterparts - 77 -
30.9 Amendment -
77 -
30.10 Modification
by the Parties - 77 -
30.11 Reservation
of Rights - 77 -
30.12 No
Partnership - 78 -
Appendix
A - Interconnection Facilities, Network Upgrades, and Distribution
Upgrades
Appendix
B – Milestones
Appendix
C – Interconnection Details
Appendix
D – Security Arrangements Details
Appendix
E – Commercial Operation Date
Appendix
F – Addresses for Delivery of Notices and Billings
Appendix
G – Interconnection Requirements for a Wind Generating Plant
STANDARD LARGE GENERATOR
INTERCONNECTION AGREEMENT
THIS
STANDARD LARGE GENERATOR INTERCONNECTION AGREEMENT ("Agreement")
is made and entered into this ____ day of ___________
20__,
by and between _______________________, a
____________________________
organized
and existing under the laws of the State/Commonwealth of
________________
("Interconnection
Customer" with a Large Generating Facility), and
__________________________________________,
a ___________________________
organized
and existing under the laws of the State/Commonwealth of
________________
("Transmission
Provider and/or Transmission Owner"). Interconnection Customer
and Transmission Provider each may be referred to as a "Party"
or collectively as the "Parties."
Recitals
WHEREAS, Transmission Provider operates the Transmission
System; and
WHEREAS, Interconnection Customer intends to own, lease
and/or control and operate the Generating Facility identified as a
Large Generating Facility in Appendix C to this Agreement; and,
WHEREAS, Interconnection Customer and Transmission Provider
have agreed to enter into this Agreement for the purpose of
interconnecting the Large Generating Facility with the Transmission
System;
NOW, THEREFORE, in consideration of and subject to the mutual
covenants contained herein, it is agreed:
When
used in this Standard Large Generator Interconnection Agreement,
terms with initial capitalization that are not defined in Article 1
shall have the meanings specified in the Article in which they are
used or the Open Access Transmission Tariff (Tariff).
Article 1. Definitions
Adverse
System Impact shall mean the negative effects due to technical or
operational limits on conductors or equipment being exceeded that may
compromise the safety and reliability of the electric system.
Affected
System shall mean an electric system other than the Transmission
Provider's Transmission System that may be affected by the proposed
interconnection.
Affected
System Operator shall mean the entity that operates an Affected
System.
Affiliate
shall mean, with respect to a corporation, partnership or other
entity, each such other corporation, partnership or other entity that
directly or indirectly, through one or more intermediaries, controls,
is controlled by, or is under common control with, such corporation,
partnership or other entity.
Ancillary
Services shall mean those services that are necessary to support
the transmission of capacity and energy from resources to loads while
maintaining reliable operation of the Transmission Provider's
Transmission System in accordance with Good Utility Practice.
Applicable
Laws and Regulations shall mean all duly promulgated applicable
federal, state and local laws, regulations, rules, ordinances, codes,
decrees, judgments, directives, or judicial or administrative orders,
permits and other duly authorized actions of any Governmental
Authority.
Applicable
Reliability Council shall mean the reliability council applicable
to the Transmission System to which the Generating Facility is
directly interconnected.
Applicable
Reliability Standards shall mean the requirements and guidelines
of NERC, the Applicable Reliability Council, and the Control Area of
the Transmission System to which the Generating Facility is directly
interconnected.
Base
Case shall mean the base case power flow, short circuit, and
stability data bases used for the Interconnection Studies by the
Transmission Provider or Interconnection Customer.
Breach
shall mean the failure of a Party to perform or observe any material
term or condition of the Standard Large Generator Interconnection
Agreement.
Breaching
Party shall mean a Party that is in Breach of the Standard Large
Generator Interconnection Agreement.
Business
Day shall mean Monday through Friday, excluding Federal Holidays.
Calendar
Day shall mean any day including Saturday, Sunday or a Federal
Holiday.
Clustering
shall mean the process whereby a group of Interconnection Requests is
studied together, instead of serially, for the purpose of conducting
the Interconnection System Impact Study.
Commercial
Operation shall mean the status of a Generating Facility that has
commenced generating electricity for sale, excluding electricity
generated during Trial Operation.
Commercial
Operation Date of a unit shall mean the date on which the
Generating Facility commences Commercial Operation as agreed to by
the Parties pursuant to Appendix E to the Standard Large Generator
Interconnection Agreement.
Confidential
Information shall mean any confidential, proprietary or trade
secret information of a plan, specification, pattern, procedure,
design, device, list, concept, policy or compilation relating to the
present or planned business of a Party, which is designated as
confidential by the Party supplying the information, whether conveyed
orally, electronically, in writing, through inspection, or otherwise.
Control
Area shall mean an electrical system or systems bounded by
interconnection metering and telemetry, capable of controlling
generation to maintain its interchange schedule with other Control
Areas and contributing to frequency regulation of the
interconnection. A Control Area must be certified by the Applicable
Reliability Council.
Default
shall mean the failure of a Breaching Party to cure its Breach in
accordance with Article 17 of the Standard Large Generator
Interconnection Agreement.
Dispute
Resolution shall mean the procedure for resolution of a dispute
between the Parties in which they will first attempt to resolve the
dispute on an informal basis.
Distribution
System shall mean the Transmission Provider's facilities and
equipment used to transmit electricity to ultimate usage points such
as homes and industries directly from nearby generators or from
interchanges with higher voltage transmission networks which
transport bulk power over longer distances. The voltage levels at
which distribution systems operate differ among areas.
Distribution
Upgrades shall mean the additions, modifications, and upgrades to
the Transmission Provider's Distribution System at or beyond the
Point of Interconnection to facilitate interconnection of the
Generating Facility and render the transmission service necessary to
effect Interconnection Customer's wholesale sale of electricity in
interstate commerce. Distribution Upgrades do not include
Interconnection Facilities.
Effective
Date shall mean the date on which the Standard Large Generator
Interconnection Agreement becomes effective upon execution by the
Parties subject to acceptance by FERC, or if filed unexecuted, upon
the date specified by FERC.
Emergency
Condition shall mean a condition or situation: (1) that in the
judgment of the Party making the claim is imminently likely to
endanger life or property; or (2) that, in the case of a Transmission
Provider, is imminently likely (as determined in a non-discriminatory
manner) to cause a material adverse effect on the security of, or
damage to Transmission Provider's Transmission System, Transmission
Provider's Interconnection Facilities or the electric systems of
others to which the Transmission Provider's Transmission System is
directly connected; or (3) that, in the case of Interconnection
Customer, is imminently likely (as determined in a non-discriminatory
manner) to cause a material adverse effect on the security of, or
damage to, the Generating Facility or Interconnection Customer's
Interconnection Facilities. System restoration and black start shall
be considered Emergency Conditions; provided, that Interconnection
Customer is not obligated by the Standard Large Generator
Interconnection Agreement to possess black start capability.
Energy
Resource Interconnection Service shall mean an Interconnection
Service that allows the Interconnection Customer to connect its
Generating Facility to the Transmission Provider's Transmission
System to be eligible to deliver the Generating Facility's electric
output using the existing firm or nonfirm capacity of the
Transmission Provider's Transmission System on an as available basis.
Energy Resource Interconnection Service in and of itself does not
convey transmission service.
Engineering
& Procurement (E&P) Agreement shall mean an agreement
that authorizes the Transmission Provider to begin engineering and
procurement of long lead-time items necessary for the establishment
of the interconnection in order to advance the implementation of the
Interconnection Request.
Environmental
Law shall mean Applicable Laws or Regulations relating to
pollution or protection of the environment or natural resources.
Federal
Power Act shall mean the Federal Power Act, as amended, 16 U.S.C.
§§ 791a et seq.
FERC
shall mean the Federal Energy Regulatory Commission (Commission) or
its successor.
Force
Majeure shall mean any act of God, labor disturbance, act of the
public enemy, war, insurrection, riot, fire, storm or flood,
explosion, breakage or accident to machinery or equipment, any order,
regulation or restriction imposed by governmental, military or
lawfully established civilian authorities, or any other cause beyond
a Party's control. A Force Majeure event does not include acts of
negligence or intentional wrongdoing by the Party claiming Force
Majeure.
Generating
Facility shall mean Interconnection Customer's device for the
production of electricity identified in the Interconnection Request,
but shall not include the Interconnection Customer's Interconnection
Facilities.
Generating
Facility Capacity shall mean the net capacity of the Generating
Facility and the aggregate net capacity of the Generating Facility
where it includes multiple energy production devices.
Good
Utility Practice shall mean any of the practices, methods and
acts engaged in or approved by a significant portion of the electric
industry during the relevant time period, or any of the practices,
methods and acts which, in the exercise of reasonable judgment in
light of the facts known at the time the decision was made, could
have been expected to accomplish the desired result at a reasonable
cost consistent with good business practices, reliability, safety and
expedition. Good Utility Practice is not intended to be limited to
the optimum practice, method, or act to the exclusion of all others,
but rather to be acceptable practices, methods, or acts generally
accepted in the region.
Governmental
Authority shall mean any federal, state, local or other
governmental regulatory or administrative agency, court, commission,
department, board, or other governmental subdivision, legislature,
rulemaking board, tribunal, or other governmental authority having
jurisdiction over the Parties, their respective facilities, or the
respective services they provide, and exercising or entitled to
exercise any administrative, executive, police, or taxing authority
or power; provided, however, that such term does not include
Interconnection Customer, Transmission Provider, or any Affiliate
thereof.
Hazardous
Substances shall mean any chemicals, materials or substances
defined as or included in the definition of "hazardous
substances," "hazardous wastes," "hazardous
materials," "hazardous constituents," "restricted
hazardous materials," "extremely hazardous substances,"
"toxic substances," "radioactive substances,"
"contaminants," "pollutants," "toxic
pollutants" or words of similar meaning and regulatory effect
under any applicable Environmental Law, or any other chemical,
material or substance, exposure to which is prohibited, limited or
regulated by any applicable Environmental Law.
Initial
Synchronization Date shall mean the date upon which the
Generating Facility is initially synchronized and upon which Trial
Operation begins.
In-Service
Date shall mean the date upon which the Interconnection Customer
reasonably expects it will be ready to begin use of the Transmission
Provider's Interconnection Facilities to obtain back feed power.
Interconnection
Customer shall mean any entity, including the Transmission
Provider, Transmission Owner or any of the Affiliates or subsidiaries
of either, that proposes to interconnect its Generating Facility with
the Transmission Provider's Transmission System.
Interconnection
Customer's Interconnection Facilities shall mean all facilities
and equipment, as identified in Appendix A of the Standard Large
Generator Interconnection Agreement, that are located between the
Generating Facility and the Point of Change of Ownership, including
any modification, addition, or upgrades to such facilities and
equipment necessary to physically and electrically interconnect the
Generating Facility to the Transmission Provider's Transmission
System. Interconnection Customer's Interconnection Facilities are
sole use facilities.
Interconnection
Facilities shall mean the Transmission Provider's Interconnection
Facilities and the Interconnection Customer's Interconnection
Facilities. Collectively, Interconnection Facilities include all
facilities and equipment between the Generating Facility and the
Point of Interconnection, including any modification, additions or
upgrades that are necessary to physically and electrically
interconnect the Generating Facility to the Transmission Provider's
Transmission System. Interconnection Facilities are sole use
facilities and shall not include Distribution Upgrades, Stand Alone
Network Upgrades or Network Upgrades.
Interconnection
Facilities Study shall mean a study conducted by the Transmission
Provider or a third party consultant for the Interconnection Customer
to determine a list of facilities (including Transmission Provider's
Interconnection Facilities and Network Upgrades as identified in the
Interconnection System Impact Study), the cost of those facilities,
and the time required to interconnect the Generating Facility with
the Transmission Provider's Transmission System. The scope of the
study is defined in Section 8 of the Standard Large Generator
Interconnection Procedures.
Interconnection
Facilities Study Agreement shall mean the form of agreement
contained in Appendix 4 of the Standard Large Generator
Interconnection Procedures for conducting the Interconnection
Facilities Study.
Interconnection
Feasibility Study shall mean a preliminary evaluation of the
system impact and cost of interconnecting the Generating Facility to
the Transmission Provider's Transmission System, the scope of which
is described in Section 6 of the Standard Large Generator
Interconnection Procedures.
Interconnection
Feasibility Study Agreement shall mean the form of agreement
contained in Appendix 2 of the Standard Large Generator
Interconnection Procedures for conducting the Interconnection
Feasibility Study.
Interconnection
Request shall mean an Interconnection Customer's request, in the
form of Appendix 1 to the Standard Large Generator Interconnection
Procedures, in accordance with the Tariff, to interconnect a new
Generating Facility, or to increase the capacity of, or make a
Material Modification to the operating characteristics of, an
existing Generating Facility that is interconnected with the
Transmission Provider's Transmission System.
Interconnection
Service shall mean the service provided by the Transmission
Provider associated with interconnecting the Interconnection
Customer's Generating Facility to the Transmission Provider's
Transmission System and enabling it to receive electric energy and
capacity from the Generating Facility at the Point of
Interconnection, pursuant to the terms of the Standard Large
Generator Interconnection Agreement and, if applicable, the
Transmission Provider's Tariff.
Interconnection
Study shall mean any of the following studies: the
Interconnection Feasibility Study, the Interconnection System Impact
Study, and the Interconnection Facilities Study described in the
Standard Large Generator Interconnection Procedures.
Interconnection
System Impact Study shall mean an engineering study that
evaluates the impact of the proposed interconnection on the safety
and reliability of Transmission Provider's Transmission System and,
if applicable, an Affected System. The study shall identify and
detail the system impacts that would result if the Generating
Facility were interconnected without project modifications or system
modifications, focusing on the Adverse System Impacts identified in
the Interconnection Feasibility Study, or to study potential impacts,
including but not limited to those identified in the Scoping Meeting
as described in the Standard Large Generator Interconnection
Procedures.
Interconnection
System Impact Study Agreement shall mean the form of agreement
contained in Appendix 3 of the Standard Large Generator
Interconnection Procedures for conducting the Interconnection System
Impact Study.
IRS
shall mean the Internal Revenue Service.
Joint
Operating Committee shall be a group made up of representatives
from Interconnection Customers and the Transmission Provider to
coordinate operating and technical considerations of Interconnection
Service.
Large
Generating Facility shall mean a Generating Facility having a
Generating Facility Capacity of more than 20 MW.
Loss
shall mean any and all losses relating to injury to or death of any
person or damage to property, demand, suits, recoveries, costs and
expenses, court costs, attorney fees, and all other obligations by or
to third parties, arising out of or resulting from the other Party's
performance, or non-performance of its obligations under the Standard
Large Generator Interconnection Agreement on behalf of the
indemnifying Party, except in cases of gross negligence or
intentional wrongdoing by the indemnifying Party.
Material
Modification shall mean those modifications that have a material
impact on the cost or timing of any Interconnection Request with a
later queue priority date.
Metering
Equipment shall mean all metering equipment installed or to be
installed at the Generating Facility pursuant to the Standard Large
Generator Interconnection Agreement at the metering points, including
but not limited to instrument transformers, MWh-meters, data
acquisition equipment, transducers, remote terminal unit,
communications equipment, phone lines, and fiber optics.
NERC
shall mean the North American Electric Reliability Council or its
successor organization.
Network
Resource shall mean any designated generating resource owned,
purchased, or leased by a Network Customer under the Network
Integration Transmission Service Tariff. Network Resources do not
include any resource, or any portion thereof, that is committed for
sale to third parties or otherwise cannot be called upon to meet the
Network Customer's Network Load on a non-interruptible basis.
Network
Resource Interconnection Service shall mean an Interconnection
Service that allows the Interconnection Customer to integrate its
Large Generating Facility with the Transmission Provider's
Transmission System (1) in a manner comparable to that in which the
Transmission Provider integrates its generating facilities to serve
native load customers; or (2) in an RTO or ISO with market based
congestion management, in the same manner as Network Resources.
Network Resource Interconnection Service in and of itself does not
convey transmission service.
Network
Upgrades shall mean the additions, modifications, and upgrades to
the Transmission Provider's Transmission System required at or beyond
the point at which the Interconnection Facilities connect to the
Transmission Provider's Transmission System to accommodate the
interconnection of the Large Generating Facility to the Transmission
Provider's Transmission System.
Notice
of Dispute shall mean a written notice of a dispute or claim that
arises out of or in connection with the Standard Large Generator
Interconnection Agreement or its performance.
Optional
Interconnection Study shall mean a sensitivity analysis based on
assumptions specified by the Interconnection Customer in the Optional
Interconnection Study Agreement.
Optional
Interconnection Study Agreement shall mean the form of agreement
contained in Appendix 5 of the Standard Large Generator
Interconnection Procedures for conducting the Optional
Interconnection Study.
Party
or Parties shall mean Transmission Provider, Transmission Owner,
Interconnection Customer or any combination of the above.
Point
of Change of Ownership shall mean the point, as set forth in
Appendix A to the Standard Large Generator Interconnection Agreement,
where the Interconnection Customer's Interconnection Facilities
connect to the Transmission Provider's Interconnection Facilities.
Point
of Interconnection shall mean the point, as set forth in Appendix
A to the Standard Large Generator Interconnection Agreement, where
the Interconnection Facilities connect to the Transmission Provider's
Transmission System.
Queue
Position shall mean the order of a valid Interconnection Request,
relative to all other pending valid Interconnection Requests, that is
established based upon the date and time of receipt of the valid
Interconnection Request by the Transmission Provider.
Reasonable
Efforts shall mean, with respect to an action required to be
attempted or taken by a Party under the Standard Large Generator
Interconnection Agreement, efforts that are timely and consistent
with Good Utility Practice and are otherwise substantially equivalent
to those a Party would use to protect its own interests.
Scoping
Meeting shall mean the meeting between representatives of the
Interconnection Customer and Transmission Provider conducted for the
purpose of discussing alternative interconnection options, to
exchange information including any transmission data and earlier
study evaluations that would be reasonably expected to impact such
interconnection options, to analyze such information, and to
determine the potential feasible Points of Interconnection.
Site
Control shall mean documentation reasonably demonstrating: (1)
ownership of, a leasehold interest in, or a right to develop a site
for the purpose of constructing the Generating Facility; (2) an
option to purchase or acquire a leasehold site for such purpose; or
(3) an exclusivity or other business relationship between
Interconnection Customer and the entity having the right to sell,
lease or grant Interconnection Customer the right to possess or
occupy a site for such purpose.
Small
Generating Facility shall mean a Generating Facility that has a
Generating Facility Capacity of no more than 20 MW.
Stand
Alone Network Upgrades shall mean Network Upgrades that an
Interconnection Customer may construct without affecting day-to-day
operations of the Transmission System during their construction.
Both the Transmission Provider and the Interconnection Customer must
agree as to what constitutes Stand Alone Network Upgrades and
identify them in Appendix A to the Standard Large Generator
Interconnection Agreement.
Standard
Large Generator Interconnection Agreement (LGIA) shall mean the
form of interconnection agreement applicable to an Interconnection
Request pertaining to a Large Generating Facility that is included in
the Transmission Provider's Tariff.
Standard
Large Generator Interconnection Procedures (LGIP) shall mean the
interconnection procedures applicable to an Interconnection Request
pertaining to a Large Generating Facility that are included in the
Transmission Provider's Tariff.
System
Protection Facilities shall mean the equipment, including
necessary protection signal communications equipment, required to
protect (1) the Transmission Provider's Transmission System from
faults or other electrical disturbances occurring at the Generating
Facility and (2) the Generating Facility from faults or other
electrical system disturbances occurring on the Transmission
Provider's Transmission System or on other delivery systems or other
generating systems to which the Transmission Provider's Transmission
System is directly connected.
Tariff
shall mean the Transmission Provider's Tariff through which open
access transmission service and Interconnection Service are offered,
as filed with FERC, and as amended or supplemented from time to time,
or any successor tariff.
Transmission
Owner shall mean an entity that owns, leases or otherwise
possesses an interest in the portion of the Transmission System at
the Point of Interconnection and may be a Party to the Standard Large
Generator Interconnection Agreement to the extent necessary.
Transmission
Provider shall mean the public utility (or its designated agent)
that owns, controls, or operates transmission or distribution
facilities used for the transmission of electricity in interstate
commerce and provides transmission service under the Tariff. The
term Transmission Provider should be read to include the Transmission
Owner when the Transmission Owner is separate from the Transmission
Provider.
Transmission
Provider's Interconnection Facilities shall mean all facilities
and equipment owned, controlled or operated by the Transmission
Provider from the Point of Change of Ownership to the Point of
Interconnection as identified in Appendix A to the Standard Large
Generator Interconnection Agreement, including any modifications,
additions or upgrades to such facilities and equipment. Transmission
Provider's Interconnection Facilities are sole use facilities and
shall not include Distribution Upgrades, Stand Alone Network Upgrades
or Network Upgrades.
Transmission
System shall mean the facilities owned, controlled or operated by
the Transmission Provider or Transmission Owner that are used to
provide transmission service under the Tariff.
Trial
Operation shall mean the period during which Interconnection
Customer is engaged in on-site test operations and commissioning of
the Generating Facility prior to Commercial Operation.
Variable
Energy Resource shall mean a device for the production of
electricity that is characterized by an energy source that: (1) is
renewable; (2) cannot be stored by the facility owner or operator;
and (3) has variability that is beyond the control of the facility
owner or operator.
Article 2. Effective Date,
Term, and Termination
2.1 Effective Date. This LGIA
shall become effective upon execution by the Parties subject to
acceptance by FERC (if applicable), or if filed unexecuted, upon the
date specified by FERC. Transmission Provider shall promptly file
this LGIA with FERC upon execution in accordance with Article 3.1, if
required.
2.2 Term of Agreement. Subject to
the provisions of Article 2.3, this LGIA shall remain in effect for a
period of ten (10) years from the Effective Date or such other longer
period as Interconnection Customer may request (Term
to be specified in individual agreements)
and shall be automatically renewed for each successive one-year
period thereafter.
2.3 Termination Procedures.
2.3.1 Written Notice. This LGIA
may be terminated by Interconnection Customer after giving
Transmission Provider ninety (90) Calendar Days advance written
notice, or by Transmission Provider notifying FERC after the
Generating Facility permanently ceases Commercial Operation.
2.3.2 Default. Either Party may
terminate this LGIA in accordance with Article 17.
2.3.3 Notwithstanding
Articles 2.3.1 and 2.3.2, no termination shall become effective until
the Parties have complied with all Applicable Laws and Regulations
applicable to such termination, including the filing with FERC of a
notice of termination of this LGIA, which notice has been accepted
for filing by FERC.
2.4 Termination Costs. If a Party
elects to terminate this Agreement pursuant to Article 2.3 above,
each Party shall pay all costs incurred (including any cancellation
costs relating to orders or contracts for Interconnection Facilities
and equipment) or charges assessed by the other Party, as of the date
of the other Party's receipt of such notice of termination, that are
the responsibility of the Terminating Party under this LGIA. In the
event of termination by a Party, the Parties shall use commercially
Reasonable Efforts to mitigate the costs, damages and charges arising
as a consequence of termination. Upon termination of this LGIA,
unless otherwise ordered or approved by FERC:
2.4.1 With respect to any portion
of Transmission Provider's Interconnection Facilities that have not
yet been constructed or installed, Transmission Provider shall to the
extent possible and with Interconnection Customer's authorization
cancel any pending orders of, or return, any materials or equipment
for, or contracts for construction of, such facilities; provided that
in the event Interconnection Customer elects not to authorize such
cancellation, Interconnection Customer shall assume all payment
obligations with respect to such materials, equipment, and contracts,
and Transmission Provider shall deliver such material and equipment,
and, if necessary, assign such contracts, to Interconnection Customer
as soon as practicable, at Interconnection Customer's expense. To
the extent that Interconnection Customer has already paid
Transmission Provider for any or all such costs of materials or
equipment not taken by Interconnection Customer, Transmission
Provider shall promptly refund such amounts to Interconnection
Customer, less any costs, including penalties incurred by
Transmission Provider to cancel any pending orders of or return such
materials, equipment, or contracts.
If an Interconnection Customer terminates this LGIA, it shall be
responsible for all costs incurred in association with that
Interconnection Customer's interconnection, including any
cancellation costs relating to orders or contracts for
Interconnection Facilities and equipment, and other expenses
including any Network Upgrades for which Transmission Provider has
incurred expenses and has not been reimbursed by Interconnection
Customer.
2.4.2 Transmission Provider may,
at its option, retain any portion of such materials, equipment, or
facilities that Interconnection Customer chooses not to accept
delivery of, in which case Transmission Provider shall be responsible
for all costs associated with procuring such materials, equipment, or
facilities.
2.4.3 With respect to any portion
of the Interconnection Facilities, and any other facilities already
installed or constructed pursuant to the terms of this LGIA,
Interconnection Customer shall be responsible for all costs
associated with the removal, relocation or other disposition or
retirement of such materials, equipment, or facilities.
2.5 Disconnection. Upon
termination of this LGIA, the Parties will take all appropriate steps
to disconnect the Large Generating Facility from the Transmission
System. All costs required to effectuate such disconnection shall be
borne by the terminating Party, unless such termination resulted from
the non-terminating Party's Default of this LGIA or such
non-terminating Party otherwise is responsible for these costs under
this LGIA.
2.6 Survival. This LGIA shall
continue in effect after termination to the extent necessary to
provide for final billings and payments and for costs incurred
hereunder, including billings and payments pursuant to this LGIA; to
permit the determination and enforcement of liability and
indemnification obligations arising from acts or events that occurred
while this LGIA was in effect; and to permit each Party to have
access to the lands of the other Party pursuant to this LGIA or other
applicable agreements, to disconnect, remove or salvage its own
facilities and equipment.
Article 3. Regulatory Filings
3.1 Filing. Transmission Provider
shall file this LGIA (and any amendment hereto) with the appropriate
Governmental Authority, if required. Interconnection Customer may
request that any information so provided be subject to the
confidentiality provisions of Article 22. If Interconnection
Customer has executed this LGIA, or any amendment thereto,
Interconnection Customer shall reasonably cooperate with Transmission
Provider with respect to such filing and to provide any information
reasonably requested by Transmission Provider needed to comply with
applicable regulatory requirements.
Article 4. Scope of Service
4.1 Interconnection Product Options. Interconnection
Customer has selected the following (checked) type of Interconnection
Service:
4.1.1 Energy Resource Interconnection Service.
4.1.1.1 The Product. Energy
Resource Interconnection Service allows Interconnection Customer to
connect the Large Generating Facility to the Transmission System and
be eligible to deliver the Large Generating Facility's output using
the existing firm or non-firm capacity of the Transmission System on
an "as available" basis. To the extent Interconnection
Customer wants to receive Energy Resource Interconnection Service,
Transmission Provider shall construct facilities identified in
Attachment A.
4.1.1.2 Transmission Delivery Service Implications. Under
Energy Resource Interconnection Service, Interconnection Customer
will be eligible to inject power from the Large Generating Facility
into and deliver power across the interconnecting Transmission
Provider's Transmission System on an "as available" basis
up to the amount of MWs identified in the applicable stability and
steady state studies to the extent the upgrades initially required to
qualify for Energy Resource Interconnection Service have been
constructed. Where eligible to do so (e.g.,
PJM, ISO-NE, NYISO), Interconnection Customer may place a bid to sell
into the market up to the maximum identified Large Generating
Facility output, subject to any conditions specified in the
interconnection service approval, and the Large Generating Facility
will be dispatched to the extent Interconnection Customer's bid
clears. In all other instances, no transmission delivery service
from the Large Generating Facility is assured, but Interconnection
Customer may obtain Point-to-Point Transmission Service, Network
Integration Transmission Service, or be used for secondary network
transmission service, pursuant to Transmission Provider's Tariff, up
to the maximum output identified in the stability and steady state
studies. In those instances, in order for Interconnection Customer
to obtain the right to deliver or inject energy beyond the Large
Generating Facility Point of Interconnection or to improve its
ability to do so, transmission delivery service must be obtained
pursuant to the provisions of Transmission Provider's Tariff. The
Interconnection Customer's ability to inject its Large Generating
Facility output beyond the Point of Interconnection, therefore, will
depend on the existing capacity of Transmission Provider's
Transmission System at such time as a transmission service request is
made that would accommodate such delivery. The provision of firm
Point-to-Point Transmission Service or Network Integration
Transmission Service may require the construction of additional
Network Upgrades.
4.1.2 Network Resource Interconnection Service.
4.1.2.1 The Product. Transmission
Provider must conduct the necessary studies and construct the Network
Upgrades needed to integrate the Large Generating Facility (1) in a
manner comparable to that in which Transmission Provider integrates
its generating facilities to serve native load customers; or (2) in
an ISO or RTO with market based congestion management, in the same
manner as all Network Resources. To the extent Interconnection
Customer wants to receive Network Resource Interconnection Service,
Transmission Provider shall construct the facilities identified in
Attachment A to this LGIA.
4.1.2.2 Transmission Delivery Service Implications. Network
Resource Interconnection Service allows Interconnection Customer's
Large Generating Facility to be designated by any Network Customer
under the Tariff on Transmission Provider's Transmission System as a
Network Resource, up to the Large Generating Facility's full output,
on the same basis as existing Network Resources interconnected to
Transmission Provider's Transmission System, and to be studied as a
Network Resource on the assumption that such a designation will
occur. Although Network Resource Interconnection Service does not
convey a reservation of transmission service, any Network Customer
under the Tariff can utilize its network service under the Tariff to
obtain delivery of energy from the interconnected Interconnection
Customer's Large Generating Facility in the same manner as it
accesses Network Resources. A Large Generating Facility receiving
Network Resource Interconnection Service may also be used to provide
Ancillary Services after technical studies and/or periodic analyses
are performed with respect to the Large Generating Facility's ability
to provide any applicable Ancillary Services, provided that such
studies and analyses have been or would be required in connection
with the provision of such Ancillary Services by any existing Network
Resource. However, if an Interconnection Customer's Large Generating
Facility has not been designated as a Network Resource by any load,
it cannot be required to provide Ancillary Services except to the
extent such requirements extend to all generating facilities that are
similarly situated. The provision of Network Integration
Transmission Service or firm Point-to-Point Transmission Service may
require additional studies and the construction of additional
upgrades. Because such studies and upgrades would be associated with
a request for delivery service under the Tariff, cost responsibility
for the studies and upgrades would be in accordance with FERC's
policy for pricing transmission delivery services.
Network Resource Interconnection Service does not necessarily provide
Interconnection Customer with the capability to physically deliver
the output of its Large Generating Facility to any particular load on
Transmission Provider's Transmission System without incurring
congestion costs. In the event of transmission constraints on
Transmission Provider's Transmission System, Interconnection
Customer's Large Generating Facility shall be subject to the
applicable congestion management procedures in Transmission
Provider's Transmission System in the same manner as Network
Resources.
There is no requirement either at the time of study or
interconnection, or at any point in the future, that Interconnection
Customer's Large Generating Facility be designated as a Network
Resource by a Network Service Customer under the Tariff or that
Interconnection Customer identify a specific buyer (or sink). To the
extent a Network Customer does designate the Large Generating
Facility as a Network Resource, it must do so pursuant to
Transmission Provider's Tariff.
Once an Interconnection Customer satisfies the requirements for
obtaining Network Resource Interconnection Service, any future
transmission service request for delivery from the Large Generating
Facility within Transmission Provider's Transmission System of any
amount of capacity and/or energy, up to the amount initially studied,
will not require that any additional studies be performed or that any
further upgrades associated with such Large Generating Facility be
undertaken, regardless of whether or not such Large Generating
Facility is ever designated by a Network Customer as a Network
Resource and regardless of changes in ownership of the Large
Generating Facility. However, the reduction or elimination of
congestion or redispatch costs may require additional studies and the
construction of additional upgrades.
To the extent Interconnection Customer enters into an arrangement for
long term transmission service for deliveries from the Large
Generating Facility outside Transmission Provider's Transmission
System, such request may require additional studies and upgrades in
order for Transmission Provider to grant such request.
4.2 Provision of Service. Transmission
Provider shall provide Interconnection Service for the Large
Generating Facility at the Point of Interconnection.
4.3 Performance Standards. Each
Party shall perform all of its obligations under this LGIA in
accordance with Applicable Laws and Regulations, Applicable
Reliability Standards, and Good Utility Practice, and to the extent a
Party is required or prevented or limited in taking any action by
such regulations and standards, such Party shall not be deemed to be
in Breach of this LGIA for its compliance therewith. If such Party
is a Transmission Provider or Transmission Owner, then that Party
shall amend the LGIA and submit the amendment to FERC for approval.
4.4 No Transmission Delivery Service. The
execution of this LGIA does not constitute a request for, nor the
provision of, any transmission delivery service under Transmission
Provider's Tariff, and does not convey any right to deliver
electricity to any specific customer or Point of Delivery.
4.5 Interconnection Customer Provided Services. The
services provided by Interconnection Customer under this LGIA are set
forth in Article 9.6 and Article 13.5.1. Interconnection Customer
shall be paid for such services in accordance with Article 11.6.
Article 5. Interconnection Facilities Engineering, Procurement, and
Construction
5.1 Options. Unless otherwise
mutually agreed to between the Parties, Interconnection Customer
shall select the In-Service Date, Initial Synchronization Date, and
Commercial Operation Date; and either Standard Option or Alternate
Option set forth below for completion of Transmission Provider's
Interconnection Facilities and Network Upgrades as set forth in
Appendix A, Interconnection Facilities and Network Upgrades, and such
dates and selected option shall be set forth in Appendix B,
Milestones.
5.1.1 Standard Option. Transmission
Provider shall design, procure, and construct Transmission Provider's
Interconnection Facilities and Network Upgrades, using Reasonable
Efforts to complete Transmission Provider's Interconnection
Facilities and Network Upgrades by the dates set forth in Appendix B,
Milestones. Transmission Provider shall not be required to undertake
any action which is inconsistent with its standard safety practices,
its material and equipment specifications, its design criteria and
construction procedures, its labor agreements, and Applicable Laws
and Regulations. In the event Transmission Provider reasonably
expects that it will not be able to complete Transmission Provider's
Interconnection Facilities and Network Upgrades by the specified
dates, Transmission Provider shall promptly provide written notice to
Interconnection Customer and shall undertake Reasonable Efforts to
meet the earliest dates thereafter.
5.1.2 Alternate Option. If the
dates designated by Interconnection Customer are acceptable to
Transmission Provider, Transmission Provider shall so notify
Interconnection Customer within thirty (30) Calendar Days, and shall
assume responsibility for the design, procurement and construction of
Transmission Provider's Interconnection Facilities by the designated
dates.
If Transmission Provider subsequently fails to complete Transmission
Provider's Interconnection Facilities by the In-Service Date, to the
extent necessary to provide back feed power; or fails to complete
Network Upgrades by the Initial Synchronization Date to the extent
necessary to allow for Trial Operation at full power output, unless
other arrangements are made by the Parties for such Trial Operation;
or fails to complete the Network Upgrades by the Commercial Operation
Date, as such dates are reflected in Appendix B, Milestones;
Transmission Provider shall pay Interconnection Customer liquidated
damages in accordance with Article 5.3, Liquidated Damages, provided,
however, the dates designated by Interconnection Customer shall be
extended day for day for each day that the applicable RTO or ISO
refuses to grant clearances to install equipment.
5.1.3 Option to Build. If the
dates designated by Interconnection Customer are not acceptable to
Transmission Provider, Transmission Provider shall so notify
Interconnection Customer within thirty (30) Calendar Days, and unless
the Parties agree otherwise, Interconnection Customer shall have the
option to assume responsibility for the design, procurement and
construction of Transmission Provider's Interconnection Facilities
and Stand Alone Network Upgrades on the dates specified in Article
5.1.2. Transmission Provider and Interconnection Customer must agree
as to what constitutes Stand Alone Network Upgrades and identify such
Stand Alone Network Upgrades in Appendix A. Except for Stand Alone
Network Upgrades, Interconnection Customer shall have no right to
construct Network Upgrades under this option.
5.1.4 Negotiated Option. If
Interconnection Customer elects not to exercise its option under
Article 5.1.3, Option to Build, Interconnection Customer shall so
notify Transmission Provider within thirty (30) Calendar Days, and
the Parties shall in good faith attempt to negotiate terms and
conditions (including revision of the specified dates and liquidated
damages, the provision of incentives or the procurement and
construction of a portion of Transmission Provider's Interconnection
Facilities and Stand Alone Network Upgrades by Interconnection
Customer) pursuant to which Transmission Provider is responsible for
the design, procurement and construction of Transmission Provider's
Interconnection Facilities and Network Upgrades. If the Parties are
unable to reach agreement on such terms and conditions, Transmission
Provider shall assume responsibility for the design, procurement and
construction of Transmission Provider's Interconnection Facilities
and Network Upgrades pursuant to 5.1.1, Standard Option.
5.2 General Conditions Applicable to Option to Build. If
Interconnection Customer assumes responsibility for the design,
procurement and construction of Transmission Provider's
Interconnection Facilities and Stand Alone Network Upgrades,
(1) Interconnection Customer shall engineer, procure equipment, and
construct Transmission Provider's Interconnection Facilities and
Stand Alone Network Upgrades (or portions thereof) using Good Utility
Practice and using standards and specifications provided in advance
by Transmission Provider;
(2) Interconnection Customer's engineering, procurement and
construction of Transmission Provider's Interconnection Facilities
and Stand Alone Network Upgrades shall comply with all requirements
of law to which Transmission Provider would be subject in the
engineering, procurement or construction of Transmission Provider's
Interconnection Facilities and Stand Alone Network Upgrades;
(3) Transmission Provider shall review and approve the engineering
design, equipment acceptance tests, and the construction of
Transmission Provider's Interconnection Facilities and Stand Alone
Network Upgrades;
(4) prior to commencement of construction, Interconnection Customer
shall provide to Transmission Provider a schedule for construction of
Transmission Provider's Interconnection Facilities and Stand Alone
Network Upgrades, and shall promptly respond to requests for
information from Transmission Provider;
(5) at any time during construction, Transmission Provider shall have
the right to gain unrestricted access to Transmission Provider's
Interconnection Facilities and Stand Alone Network Upgrades and to
conduct inspections of the same;
(6) at any time during construction, should any phase of the
engineering, equipment procurement, or construction of Transmission
Provider's Interconnection Facilities and Stand Alone Network
Upgrades not meet the standards and specifications provided by
Transmission Provider, Interconnection Customer shall be obligated to
remedy deficiencies in that portion of Transmission Provider's
Interconnection Facilities and Stand Alone Network Upgrades;
(7) Interconnection Customer shall indemnify Transmission Provider
for claims arising from Interconnection Customer's construction of
Transmission Provider's Interconnection Facilities and Stand Alone
Network Upgrades under the terms and procedures applicable to Article
18.1 Indemnity;
(8) Interconnection Customer shall transfer control of Transmission
Provider's Interconnection Facilities and Stand Alone Network
Upgrades to Transmission Provider;
(9) Unless Parties otherwise agree, Interconnection Customer shall
transfer ownership of Transmission Provider's Interconnection
Facilities and Stand-Alone Network Upgrades to Transmission Provider;
(10) Transmission Provider shall approve and accept for operation and
maintenance Transmission Provider's Interconnection Facilities and
Stand Alone Network Upgrades to the extent engineered, procured, and
constructed in accordance with this Article 5.2; and
(11) Interconnection Customer shall deliver to Transmission Provider
"as-built" drawings, information, and any other documents
that are reasonably required by Transmission Provider to assure that
the Interconnection Facilities and Stand-Alone Network Upgrades are
built to the standards and specifications required by Transmission
Provider.
5.3 Liquidated Damages. The actual
damages to Interconnection Customer, in the event Transmission
Provider's Interconnection Facilities or Network Upgrades are not
completed by the dates designated by Interconnection Customer and
accepted by Transmission Provider pursuant to subparagraphs 5.1.2 or
5.1.4, above, may include Interconnection Customer's fixed operation
and maintenance costs and lost opportunity costs. Such actual
damages are uncertain and impossible to determine at this time.
Because of such uncertainty, any liquidated damages paid by
Transmission Provider to Interconnection Customer in the event that
Transmission Provider does not complete any portion of Transmission
Provider's Interconnection Facilities or Network Upgrades by the
applicable dates, shall be an amount equal to ½ of 1 percent
per day of the actual cost of Transmission Provider's Interconnection
Facilities and Network Upgrades, in the aggregate, for which
Transmission Provider has assumed responsibility to design, procure
and construct.
However, in no event shall the total liquidated damages exceed 20
percent of the actual cost of Transmission Provider's Interconnection
Facilities and Network Upgrades for which Transmission Provider has
assumed responsibility to design, procure, and construct. The
foregoing payments will be made by Transmission Provider to
Interconnection Customer as just compensation for the damages caused
to Interconnection Customer, which actual damages are uncertain and
impossible to determine at this time, and as reasonable liquidated
damages, but not as a penalty or a method to secure performance of
this LGIA. Liquidated damages, when the Parties agree to them, are
the exclusive remedy for the Transmission Provider's failure to meet
its schedule.
No liquidated damages shall be paid to Interconnection Customer if:
(1) Interconnection Customer is not ready to commence use of
Transmission Provider's Interconnection Facilities or Network
Upgrades to take the delivery of power for the Large Generating
Facility's Trial Operation or to export power from the Large
Generating Facility on the specified dates, unless Interconnection
Customer would have been able to commence use of Transmission
Provider's Interconnection Facilities or Network Upgrades to take the
delivery of power for Large Generating Facility's Trial Operation or
to export power from the Large Generating Facility, but for
Transmission Provider's delay; (2) Transmission Provider's failure to
meet the specified dates is the result of the action or inaction of
Interconnection Customer or any other Interconnection Customer who
has entered into an LGIA with Transmission Provider or any cause
beyond Transmission Provider's reasonable control or reasonable
ability to cure; (3) the Interconnection Customer has assumed
responsibility for the design, procurement and construction of
Transmission Provider's Interconnection Facilities and Stand Alone
Network Upgrades; or (4) the Parties have otherwise agreed.
5.4 Power System Stabilizers. The
Interconnection Customer shall procure, install, maintain and operate
Power System Stabilizers in accordance with the guidelines and
procedures established by the Applicable Reliability Council.
Transmission Provider reserves the right to reasonably establish
minimum acceptable settings for any installed Power System
Stabilizers, subject to the design and operating limitations of the
Large Generating Facility. If the Large Generating Facility's Power
System Stabilizers are removed from service or not capable of
automatic operation, Interconnection Customer shall immediately
notify Transmission Provider's system operator, or its designated
representative. The requirements of this paragraph shall not apply
to wind generators.
5.5 Equipment Procurement. If
responsibility for construction of Transmission Provider's
Interconnection Facilities or Network Upgrades is to be borne by
Transmission Provider, then Transmission Provider shall commence
design of Transmission Provider's Interconnection Facilities or
Network Upgrades and procure necessary equipment as soon as
practicable after all of the following conditions are satisfied,
unless the Parties otherwise agree in writing:
5.5.1 Transmission Provider has
completed the Facilities Study pursuant to the Facilities Study
Agreement;
5.5.2 Transmission Provider has
received written authorization to proceed with design and procurement
from Interconnection Customer by the date specified in Appendix B,
Milestones; and
5.5.3 Interconnection Customer has
provided security to Transmission Provider in accordance with Article
11.5 by the dates specified in Appendix B, Milestones.
5.6 Construction Commencement. Transmission
Provider shall commence construction of Transmission Provider's
Interconnection Facilities and Network Upgrades for which it is
responsible as soon as practicable after the following additional
conditions are satisfied:
5.6.1 Approval of the appropriate
Governmental Authority has been obtained for any facilities requiring
regulatory approval;
5.6.2 Necessary real property
rights and rights-of-way have been obtained, to the extent required
for the construction of a discrete aspect of Transmission Provider's
Interconnection Facilities and Network Upgrades;
5.6.3 Transmission Provider has
received written authorization to proceed with construction from
Interconnection Customer by the date specified in Appendix B,
Milestones; and
5.6.4 Interconnection Customer has
provided security to Transmission Provider in accordance with Article
11.5 by the dates specified in Appendix B, Milestones.
5.7 Work Progress. The Parties
will keep each other advised periodically as to the progress of their
respective design, procurement and construction efforts. Either
Party may, at any time, request a progress report from the other
Party. If, at any time, Interconnection Customer determines that the
completion of Transmission Provider's Interconnection Facilities will
not be required until after the specified In-Service Date,
Interconnection Customer will provide written notice to Transmission
Provider of such later date upon which the completion of Transmission
Provider's Interconnection Facilities will be required.
5.8 Information Exchange. As soon
as reasonably practicable after the Effective Date, the Parties shall
exchange information regarding the design and compatibility of the
Parties' Interconnection Facilities and compatibility of the
Interconnection Facilities with Transmission Provider's Transmission
System, and shall work diligently and in good faith to make any
necessary design changes.
5.9 Limited Operation. If any of
Transmission Provider's Interconnection Facilities or Network
Upgrades are not reasonably expected to be completed prior to the
Commercial Operation Date of the Large Generating Facility,
Transmission Provider shall, upon the request and at the expense of
Interconnection Customer, perform operating studies on a timely basis
to determine the extent to which the Large Generating Facility and
Interconnection Customer's Interconnection Facilities may operate
prior to the completion of Transmission Provider's Interconnection
Facilities or Network Upgrades consistent with Applicable Laws and
Regulations, Applicable Reliability Standards, Good Utility Practice,
and this LGIA. Transmission Provider shall permit Interconnection
Customer to operate the Large Generating Facility and Interconnection
Customer's Interconnection Facilities in accordance with the results
of such studies.
5.10 Interconnection Customer's Interconnection Facilities ('ICIF').
Interconnection Customer shall, at
its expense, design, procure, construct, own and install the ICIF, as
set forth in Appendix A, Interconnection Facilities, Network Upgrades
and Distribution Upgrades.
5.10.1 Interconnection Customer's Interconnection Facility
Specifications. Interconnection
Customer shall submit initial specifications for the ICIF, including
System Protection Facilities, to Transmission Provider at least one
hundred eighty (180) Calendar Days prior to the Initial
Synchronization Date; and final specifications for review and comment
at least ninety (90) Calendar Days prior to the Initial
Synchronization Date. Transmission Provider shall review such
specifications to ensure that the ICIF are compatible with the
technical specifications, operational control, and safety
requirements of Transmission Provider and comment on such
specifications within thirty (30) Calendar Days of Interconnection
Customer's submission. All specifications provided hereunder shall
be deemed confidential.
5.10.2 Transmission Provider's Review. Transmission
Provider's review of Interconnection Customer's final specifications
shall not be construed as confirming, endorsing, or providing a
warranty as to the design, fitness, safety, durability or reliability
of the Large Generating Facility, or the ICIF. Interconnection
Customer shall make such changes to the ICIF as may reasonably be
required by Transmission Provider, in accordance with Good Utility
Practice, to ensure that the ICIF are compatible with the technical
specifications, operational control, and safety requirements of
Transmission Provider.
5.10.3 ICIF Construction. The
ICIF shall be designed and constructed in accordance with Good
Utility Practice. Within one hundred twenty (120) Calendar Days
after the Commercial Operation Date, unless the Parties agree on
another mutually acceptable deadline, Interconnection Customer shall
deliver to Transmission Provider "as-built" drawings,
information and documents for the ICIF, such as: a one-line diagram,
a site plan showing the Large Generating Facility and the ICIF, plan
and elevation drawings showing the layout of the ICIF, a relay
functional diagram, relaying AC and DC schematic wiring diagrams and
relay settings for all facilities associated with Interconnection
Customer's step-up transformers, the facilities connecting the Large
Generating Facility to the step-up transformers and the ICIF, and the
impedances (determined by factory tests) for the associated step-up
transformers and the Large Generating Facility. The Interconnection
Customer shall provide Transmission Provider specifications for the
excitation system, automatic voltage regulator, Large Generating
Facility control and protection settings, transformer tap settings,
and communications, if applicable.
5.11 Transmission Provider's Interconnection Facilities
Construction. Transmission
Provider's Interconnection Facilities shall be designed and
constructed in accordance with Good Utility Practice. Upon request,
within one hundred twenty (120) Calendar Days after the Commercial
Operation Date, unless the Parties agree on another mutually
acceptable deadline, Transmission Provider shall deliver to
Interconnection Customer the following "as-built" drawings,
information and documents for Transmission Provider's Interconnection
Facilities [include appropriate drawings and relay diagrams].
Transmission Provider will obtain control of Transmission Provider's
Interconnection Facilities and Stand Alone Network Upgrades upon
completion of such facilities.
5.12 Access Rights. Upon
reasonable notice and supervision by a Party, and subject to any
required or necessary regulatory approvals, a Party ("Granting
Party") shall furnish
at no cost
to the other Party
("Access Party") any rights of
use, licenses, rights of
way and easements with respect to lands owned or controlled by the
Granting Party, its agents (if allowed under the applicable agency
agreement), or any Affiliate, that are necessary to enable the Access
Party to obtain ingress and egress to construct, operate, maintain,
repair, test (or witness testing), inspect, replace or remove
facilities and equipment to: (i) interconnect the Large Generating
Facility with the Transmission System; (ii) operate and maintain the
Large Generating Facility, the Interconnection Facilities and the
Transmission System; and (iii) disconnect or remove the Access
Party's facilities and equipment upon termination of this LGIA. In
exercising such licenses, rights of way and easements, the Access
Party shall not unreasonably disrupt or interfere with normal
operation of the Granting Party's business and shall adhere to the
safety rules and procedures established in advance, as may be changed
from time to time, by the Granting Party and provided to the Access
Party.
5.13 Lands of Other Property Owners. If
any part of Transmission Provider or Transmission Owner's
Interconnection Facilities and/or Network Upgrades is to be installed
on property owned by persons other than Interconnection Customer or
Transmission Provider or Transmission Owner, Transmission Provider or
Transmission Owner shall at Interconnection Customer's expense use
efforts, similar in nature and extent to those that it typically
undertakes on its own behalf or on behalf of its Affiliates,
including use of its eminent domain authority, and to the extent
consistent with state law, to procure from such persons any rights of
use, licenses, rights of way and easements that are necessary to
construct, operate, maintain, test, inspect, replace or remove
Transmission Provider or Transmission Owner's Interconnection
Facilities and/or Network Upgrades upon such property.
5.14 Permits. Transmission
Provider or Transmission Owner and Interconnection Customer shall
cooperate with each other in good faith in obtaining all permits,
licenses, and authorizations that are necessary to accomplish the
interconnection in compliance with Applicable Laws and Regulations.
With respect to this paragraph, Transmission Provider or Transmission
Owner shall provide permitting assistance to Interconnection Customer
comparable to that provided to Transmission Provider's own, or an
Affiliate's generation.
5.15 Early Construction of Base Case Facilities. Interconnection
Customer may request Transmission Provider to construct, and
Transmission Provider shall construct, using Reasonable Efforts to
accommodate Interconnection Customer's In-Service Date, all or any
portion of any Network Upgrades required for Interconnection Customer
to be interconnected to the Transmission System which are included in
the Base Case of the Facilities Study for Interconnection Customer,
and which also are required to be constructed for another
Interconnection Customer, but where such construction is not
scheduled to be completed in time to achieve Interconnection
Customer's In-Service Date.
5.16 Suspension. Interconnection
Customer reserves the right, upon written notice to Transmission
Provider, to suspend at any time all work by Transmission Provider
associated with the construction and installation of Transmission
Provider's Interconnection Facilities and/or Network Upgrades
required under this LGIA with the condition that Transmission System
shall be left in a safe and reliable condition in accordance with
Good Utility Practice and Transmission Provider's safety and
reliability criteria. In such event, Interconnection Customer shall
be responsible for all reasonable and necessary costs which
Transmission Provider (i) has incurred pursuant to this LGIA prior to
the suspension and (ii) incurs in suspending such work, including any
costs incurred to perform such work as may be necessary to ensure the
safety of persons and property and the integrity of the Transmission
System during such suspension and, if applicable, any costs incurred
in connection with the cancellation or suspension of material,
equipment and labor contracts which Transmission Provider cannot
reasonably avoid; provided, however, that prior to canceling or
suspending any such material, equipment or labor contract,
Transmission Provider shall obtain Interconnection Customer's
authorization to do so.
Transmission Provider shall invoice Interconnection Customer for such
costs pursuant to Article 12 and shall use due diligence to minimize
its costs. In the event Interconnection Customer suspends work by
Transmission Provider required under this LGIA pursuant to this
Article 5.16, and has not requested Transmission Provider to
recommence the work required under this LGIA on or before the
expiration of three (3) years following commencement of such
suspension, this LGIA shall be deemed terminated. The three-year
period shall begin on the date the suspension is requested, or the
date of the written notice to Transmission Provider, if no effective
date is specified.
5.17 Taxes.
5.17.1 Interconnection Customer Payments Not Taxable. The
Parties intend that all payments or property transfers made by
Interconnection Customer to Transmission Provider for the
installation of Transmission Provider's Interconnection Facilities
and the Network Upgrades shall be non-taxable, either as
contributions to capital, or as an advance, in accordance with the
Internal Revenue Code and any applicable state income tax laws and
shall not be taxable as contributions in aid of construction or
otherwise under the Internal Revenue Code and any applicable state
income tax laws.
5.17.2 Representations and Covenants. In
accordance with IRS Notice 2001-82 and IRS Notice 88-129,
Interconnection Customer represents and covenants that (i) ownership
of the electricity generated at the Large Generating Facility will
pass to another party prior to the transmission of the electricity on
the Transmission System, (ii) for income tax purposes, the amount of
any payments and the cost of any property transferred to Transmission
Provider for Transmission Provider's Interconnection Facilities will
be capitalized by Interconnection Customer as an intangible asset and
recovered using the straight-line method over a useful life of twenty
(20) years, and (iii) any portion of Transmission Provider's
Interconnection Facilities that is a "dual-use intertie,"
within the meaning of IRS Notice 88-129, is reasonably expected to
carry only a de minimis amount of electricity in the direction of the
Large Generating Facility. For this purpose, "de minimis
amount" means no more than 5 percent of the total power flows in
both directions, calculated in accordance with the "5 percent
test" set forth in IRS Notice 88-129. This is not intended to
be an exclusive list of the relevant conditions that must be met to
conform to IRS requirements for non-taxable treatment.
At Transmission Provider's request, Interconnection Customer shall
provide Transmission Provider with a report from an independent
engineer confirming its representation in clause (iii), above.
Transmission Provider represents and covenants that the cost of
Transmission Provider's Interconnection Facilities paid for by
Interconnection Customer will have no net effect on the base upon
which rates are determined.
5.17.3 Indemnification for the Cost Consequences of Current Tax
Liability Imposed Upon the Transmission Provider. Notwithstanding
Article 5.17.1, Interconnection Customer shall protect, indemnify and
hold harmless Transmission Provider from the cost consequences of any
current tax liability imposed against Transmission Provider as the
result of payments or property transfers made by Interconnection
Customer to Transmission Provider under this LGIA for Interconnection
Facilities, as well as any interest and penalties, other than
interest and penalties attributable to any delay caused by
Transmission Provider.
Transmission Provider shall not include a gross-up for the cost
consequences of any current tax liability in the amounts it charges
Interconnection Customer under this LGIA unless (i) Transmission
Provider has determined, in good faith, that the payments or property
transfers made by Interconnection Customer to Transmission Provider
should be reported as income subject to taxation or (ii) any
Governmental Authority directs Transmission Provider to report
payments or property as income subject to taxation; provided,
however, that Transmission Provider may require Interconnection
Customer to provide security for Interconnection Facilities, in a
form reasonably acceptable to Transmission Provider (such as a
parental guarantee or a letter of credit), in an amount equal to the
cost consequences of any current tax liability under this Article
5.17. Interconnection Customer shall reimburse Transmission Provider
for such costs on a fully grossed-up basis, in accordance with
Article 5.17.4, within thirty (30) Calendar Days of receiving written
notification from Transmission Provider of the amount due, including
detail about how the amount was calculated.
The indemnification obligation shall terminate at the earlier of (1)
the expiration of the ten year testing period and the applicable
statute of limitation, as it may be extended by Transmission Provider
upon request of the IRS, to keep these years open for audit or
adjustment,
or (2) the occurrence of a subsequent taxable event and the payment
of any related indemnification obligations as contemplated by this
Article 5.17.
5.17.4 Tax Gross-Up Amount. Interconnection
Customer's liability for the cost consequences of any current tax
liability under this Article 5.17 shall be calculated on a fully
grossed-up basis. Except as may otherwise be agreed to by the
parties, this means that Interconnection Customer will pay
Transmission Provider, in addition to the amount paid for the
Interconnection Facilities and Network Upgrades, an amount equal to
(1) the current taxes imposed on Transmission Provider ("Current
Taxes") on the excess of (a) the gross income realized by
Transmission Provider as a result of payments or property transfers
made by Interconnection Customer to Transmission Provider under this
LGIA (without regard to any payments under this Article 5.17) (the
"Gross Income Amount") over (b) the present value of
future tax deductions for depreciation that will be available as a
result of such payments or property transfers (the "Present
Value Depreciation Amount"), plus (2) an additional amount
sufficient to permit Transmission Provider to receive and retain,
after the payment of all Current Taxes, an amount equal to the net
amount described in clause (1).
For this purpose, (i) Current Taxes shall be computed based on
Transmission Provider's composite federal and state tax rates at the
time the payments or property transfers are received and Transmission
Provider will be treated as being subject to tax at the highest
marginal rates in effect at that time (the "Current Tax Rate"),
and (ii) the Present Value Depreciation Amount shall be computed by
discounting Transmission Provider's anticipated tax depreciation
deductions as a result of such payments or property transfers by
Transmission Provider's current weighted average cost of capital.
Thus, the formula for calculating Interconnection Customer's
liability to Transmission Owner pursuant to this Article 5.17.4 can
be expressed as follows: (Current Tax Rate x (Gross Income Amount –
Present Value of Tax Depreciation))/(1-Current Tax Rate).
Interconnection Customer's estimated tax liability in the event taxes
are imposed shall be stated in Appendix A, Interconnection
Facilities, Network Upgrades and Distribution Upgrades.
5.17.5 Private Letter Ruling or Change or Clarification of Law. At
Interconnection Customer's request and expense, Transmission Provider
shall file with the IRS a request for a private letter ruling as to
whether any property transferred or sums paid, or to be paid, by
Interconnection Customer to Transmission Provider under this LGIA are
subject to federal income taxation. Interconnection Customer will
prepare the initial draft of the request for a private letter ruling,
and will certify under penalties of perjury that all facts
represented in such request are true and accurate to the best of
Interconnection Customer's knowledge. Transmission Provider and
Interconnection Customer shall cooperate in good faith with respect
to the submission of such request.
Transmission Provider shall keep Interconnection Customer fully
informed of the status of such request for a private letter ruling
and shall execute either a privacy act waiver or a limited power of
attorney, in a form acceptable to the IRS, that authorizes
Interconnection Customer to participate in all discussions with the
IRS regarding such request for a private letter ruling. Transmission
Provider shall allow Interconnection Customer to attend all meetings
with IRS officials about the request and shall permit Interconnection
Customer to prepare the initial drafts of any follow-up letters in
connection with the request.
5.17.6 Subsequent Taxable Events. If,
within 10 years from the date on which the relevant Transmission
Provider's Interconnection Facilities are placed in service, (i)
Interconnection Customer Breaches the covenants contained in Article
5.17.2, (ii) a "disqualification event" occurs within the
meaning of IRS Notice 88-129, or (iii) this LGIA terminates and
Transmission Provider retains ownership of the Interconnection
Facilities and Network Upgrades, Interconnection Customer shall pay a
tax gross-up for the cost consequences of any current tax liability
imposed on Transmission Provider, calculated using the methodology
described in Article 5.17.4 and in accordance with IRS Notice 90-60.
5.17.7 Contests. In the event
any Governmental Authority determines that Transmission Provider's
receipt of payments or property constitutes income that is subject to
taxation, Transmission Provider shall notify Interconnection
Customer, in writing, within thirty (30) Calendar Days of receiving
notification of such determination by a Governmental Authority. Upon
the timely written request by Interconnection Customer and at
Interconnection Customer's sole expense, Transmission Provider may
appeal, protest, seek abatement of, or otherwise oppose such
determination. Upon Interconnection Customer's written request and
sole expense, Transmission Provider may file a claim for refund with
respect to any taxes paid under this Article 5.17, whether or not it
has received such a determination. Transmission Provider reserves
the right to make all decisions with regard to the prosecution of
such appeal, protest, abatement or other contest, including the
selection of counsel and compromise or settlement of the claim, but
Transmission Provider shall keep Interconnection Customer informed,
shall consider in good faith suggestions from Interconnection
Customer about the conduct of the contest, and shall reasonably
permit Interconnection Customer or an Interconnection Customer
representative to attend contest proceedings.
Interconnection Customer shall pay to Transmission Provider on a
periodic basis, as invoiced by Transmission Provider, Transmission
Provider's documented reasonable costs of prosecuting such appeal,
protest, abatement or other contest. At any time during the contest,
Transmission Provider may agree to a settlement either with
Interconnection Customer's consent or after obtaining written advice
from nationally-recognized tax counsel, selected by Transmission
Provider, but reasonably acceptable to Interconnection Customer, that
the proposed settlement represents a reasonable settlement given the
hazards of litigation. Interconnection Customer's obligation shall
be based on the amount of the settlement agreed to by Interconnection
Customer, or if a higher amount, so much of the settlement that is
supported by the written advice from nationally-recognized tax
counsel selected under the terms of the preceding sentence. The
settlement amount shall be calculated on a fully grossed-up basis to
cover any related cost consequences of the current tax liability.
Any settlement without Interconnection Customer's consent or such
written advice will relieve Interconnection Customer from any
obligation to indemnify Transmission Provider for the tax at issue in
the contest.
5.17.8 Refund. In the event that
(a) a private letter ruling is issued to Transmission Provider which
holds that any amount paid or the value of any property transferred
by Interconnection Customer to Transmission Provider under the terms
of this LGIA is not subject to federal income taxation, (b) any
legislative change or administrative announcement, notice, ruling or
other determination makes it reasonably clear to Transmission
Provider in good faith that any amount paid or the value of any
property transferred by Interconnection Customer to Transmission
Provider under the terms of this LGIA is not taxable to Transmission
Provider, (c) any abatement, appeal, protest, or other contest
results in a determination that any payments or transfers made by
Interconnection Customer to Transmission Provider are not subject to
federal income tax, or (d) if Transmission Provider receives a refund
from any taxing authority for any overpayment of tax attributable to
any payment or property transfer made by Interconnection Customer to
Transmission Provider pursuant to this LGIA, Transmission Provider
shall promptly refund to Interconnection Customer the following:
(i) any payment made by Interconnection Customer under this Article
5.17 for taxes that is attributable to the amount determined to be
non-taxable, together with interest thereon,
(ii) interest on any amounts paid by Interconnection Customer to
Transmission Provider for such taxes which Transmission Provider did
not submit to the taxing authority, calculated in accordance with the
methodology set forth in FERC's regulations at 18 CFR
§35.19a(a)(2)(iii) from the date payment was made by
Interconnection Customer to the date Transmission Provider refunds
such payment to Interconnection Customer, and
(iii) with respect to any such taxes paid by Transmission Provider,
any refund or credit Transmission Provider receives or to which it
may be entitled from any Governmental Authority, interest (or that
portion thereof attributable to the payment described in clause (i),
above) owed to Transmission Provider for such overpayment of taxes
(including any reduction in interest otherwise payable by
Transmission Provider to any Governmental Authority resulting from an
offset or credit); provided, however, that Transmission
Provider will remit such amount promptly to Interconnection Customer
only after and to the extent that Transmission Provider has received
a tax refund, credit or offset from any Governmental Authority for
any applicable overpayment of income tax related to Transmission
Provider's Interconnection Facilities.
The intent of this provision is to leave the Parties, to the extent
practicable, in the event that no taxes are due with respect to any
payment for Interconnection Facilities and Network Upgrades
hereunder, in the same position they would have been in had no such
tax payments been made.
5.17.9 Taxes Other Than Income Taxes. Upon
the timely request by Interconnection Customer, and at
Interconnection Customer's sole expense, Transmission Provider may
appeal, protest, seek abatement of, or otherwise contest any tax
(other than federal or state income tax) asserted or assessed against
Transmission Provider for which Interconnection Customer may be
required to reimburse Transmission Provider under the terms of this
LGIA. Interconnection Customer shall pay to Transmission Provider on
a periodic basis, as invoiced by Transmission Provider, Transmission
Provider's documented reasonable costs of prosecuting such appeal,
protest, abatement, or other contest. Interconnection
Customer and Transmission Provider shall cooperate in good faith with
respect to any such contest. Unless the payment of such taxes is a
prerequisite to an appeal or abatement or cannot be deferred, no
amount shall be payable by Interconnection Customer to Transmission
Provider for such taxes until they are assessed by a final,
non-appealable order by any court or agency of competent
jurisdiction. In the event that a tax payment is withheld and
ultimately due and payable after appeal, Interconnection Customer
will be responsible for all taxes, interest and penalties, other than
penalties attributable to any delay caused by Transmission Provider.
5.17.10 Transmission Owners Who Are Not Transmission Providers. If
Transmission Provider is not the same entity as the Transmission
Owner, then (i) all references in this Article 5.17 to Transmission
Provider shall be deemed also to refer to and to include the
Transmission Owner, as appropriate, and (ii) this LGIA shall not
become effective until such Transmission Owner shall have agreed in
writing to assume all of the duties and obligations of Transmission
Provider under this Article 5.17 of this LGIA.
5.18 Tax Status. Each Party shall
cooperate with the other to maintain the other Party's tax status.
Nothing in this LGIA is intended to adversely affect any Transmission
Provider's tax exempt status with respect to the issuance of bonds
including, but not limited to, Local Furnishing Bonds.
5.19 Modification.
5.19.1 General. Either Party may
undertake modifications to its facilities. If a Party plans to
undertake a modification that reasonably may be expected to affect
the other Party's facilities, that Party shall provide to the other
Party sufficient information regarding such modification so that the
other Party may evaluate the potential impact of such modification
prior to commencement of the work. Such information shall be deemed
to be confidential hereunder and shall include information concerning
the timing of such modifications and whether such modifications are
expected to interrupt the flow of electricity from the Large
Generating Facility. The Party desiring to perform such work shall
provide the relevant drawings, plans, and specifications to the other
Party at least ninety (90) Calendar Days in advance of the
commencement of the work or such shorter period upon which the
Parties may agree, which agreement shall not unreasonably be
withheld, conditioned or delayed.
In the case of Large Generating Facility modifications that do not
require Interconnection Customer to submit an Interconnection
Request, Transmission Provider shall provide, within thirty (30)
Calendar Days (or such other time as the Parties may agree), an
estimate of any additional modifications to the Transmission System,
Transmission Provider's Interconnection Facilities or Network
Upgrades necessitated by such Interconnection Customer modification
and a good faith estimate of the costs thereof.
5.19.2 Standards. Any additions,
modifications, or replacements made to a Party's facilities shall be
designed, constructed and operated in accordance with this LGIA and
Good Utility Practice.
5.19.3 Modification Costs. Interconnection
Customer shall not be directly assigned for the costs of any
additions, modifications, or replacements that Transmission Provider
makes to Transmission Provider's Interconnection Facilities or the
Transmission System to facilitate the interconnection of a third
party to Transmission Provider's Interconnection Facilities or the
Transmission System, or to provide transmission service to a third
party under Transmission Provider's Tariff. Interconnection Customer
shall be responsible for the costs of any additions, modifications,
or replacements to Interconnection Customer's Interconnection
Facilities that may be necessary to maintain or upgrade such
Interconnection Customer's Interconnection Facilities consistent with
Applicable Laws and Regulations, Applicable Reliability Standards or
Good Utility Practice.
Article 6. Testing and Inspection
6.1 Pre-Commercial Operation Date Testing and Modifications. Prior
to the Commercial Operation Date, Transmission Provider shall test
Transmission Provider's Interconnection Facilities and Network
Upgrades and Interconnection Customer shall test the Large Generating
Facility and Interconnection Customer's Interconnection Facilities to
ensure their safe and reliable operation. Similar testing may be
required after initial operation. Each Party shall make any
modifications to its facilities that are found to be necessary as a
result of such testing. Interconnection Customer shall bear the cost
of all such testing and modifications. Interconnection Customer
shall generate test energy at the Large Generating Facility only if
it has arranged for the delivery of such test energy.
6.2 Post-Commercial Operation Date Testing and Modifications. Each
Party shall at its own expense perform routine inspection and testing
of its facilities and equipment in accordance with Good Utility
Practice as may be necessary to ensure the continued interconnection
of the Large Generating Facility with the Transmission System in a
safe and reliable manner. Each Party shall have the right, upon
advance written notice, to require reasonable additional testing of
the other Party's facilities, at the requesting Party's expense, as
may be in accordance with Good Utility Practice.
6.3 Right to Observe Testing. Each
Party shall notify the other Party in advance of its performance of
tests of its Interconnection Facilities. The other Party has the
right, at its own expense, to observe such testing.
6.4 Right to Inspect. Each Party
shall have the right, but shall have no obligation to: (i) observe
the other Party's tests and/or inspection of any of its System
Protection Facilities and other protective equipment, including Power
System Stabilizers; (ii) review the settings of the other
Party's System Protection Facilities and other protective equipment;
and (iii) review the other Party's maintenance records relative
to the Interconnection Facilities, the System Protection Facilities
and other protective equipment. A Party may exercise these rights
from time to time as it deems necessary upon reasonable notice to the
other Party. The exercise or non-exercise by a Party of any such
rights shall not be construed as an endorsement or confirmation of
any element or condition of the Interconnection Facilities or the
System Protection Facilities or other protective equipment or the
operation thereof, or as a warranty as to the fitness, safety,
desirability, or reliability of same. Any information that a Party
obtains through the exercise of any of its rights under this Article
6.4 shall be deemed to be Confidential Information and treated
pursuant to Article 22 of this LGIA.
Article 7. Metering
7.1 General. Each Party shall
comply with the Applicable Reliability Council requirements. Unless
otherwise agreed by the Parties, Transmission Provider shall install
Metering Equipment at the Point of Interconnection prior to any
operation of the Large Generating Facility and shall own, operate,
test and maintain such Metering Equipment. Power flows to and from
the Large Generating Facility shall be measured at or, at
Transmission Provider's option, compensated to, the Point of
Interconnection. Transmission Provider shall provide metering
quantities, in analog and/or digital form, to Interconnection
Customer upon request. Interconnection Customer shall bear all
reasonable documented costs associated with the purchase,
installation, operation, testing and maintenance of the Metering
Equipment.
7.2 Check Meters. Interconnection
Customer, at its option and expense, may install and operate, on its
premises and on its side of the Point of Interconnection, one or more
check meters to check Transmission Provider's meters. Such check
meters shall be for check purposes only and shall not be used for the
measurement of power flows for purposes of this LGIA, except as
provided in Article 7.4 below. The check meters shall be subject at
all reasonable times to inspection and examination by Transmission
Provider or its designee. The installation, operation and
maintenance thereof shall be performed entirely by Interconnection
Customer in accordance with Good Utility Practice.
7.3 Standards. Transmission
Provider shall install, calibrate, and test revenue quality Metering
Equipment in accordance with applicable ANSI standards.
7.4 Testing of Metering Equipment. Transmission
Provider shall inspect and test all Transmission Provider-owned
Metering Equipment upon installation and at least once every two (2)
years thereafter. If requested to do so by Interconnection Customer,
Transmission Provider shall, at Interconnection Customer's expense,
inspect or test Metering Equipment more frequently than every two (2)
years. Transmission Provider shall give reasonable notice of the
time when any inspection or test shall take place, and
Interconnection Customer may have representatives present at the test
or inspection. If at any time Metering Equipment is found to be
inaccurate or defective, it shall be adjusted, repaired or replaced
at Interconnection Customer's expense, in order to provide accurate
metering, unless the inaccuracy or defect is due to Transmission
Provider's failure to maintain, then Transmission Provider shall pay.
If Metering Equipment fails to register, or if the measurement made
by Metering Equipment during a test varies by more than two percent
from the measurement made by the standard meter used in the test,
Transmission Provider shall adjust the measurements by correcting all
measurements for the period during which Metering Equipment was in
error by using Interconnection Customer's check meters, if installed.
If no such check meters are installed or if the period cannot be
reasonably ascertained, the adjustment shall be for the period
immediately preceding the test of the Metering Equipment equal to
one-half the time from the date of the last previous test of the
Metering Equipment.
7.5 Metering Data. At
Interconnection Customer's expense, the metered data shall be
telemetered to one or more locations designated by Transmission
Provider and one or more locations designated by Interconnection
Customer. Such telemetered data shall be used, under normal
operating conditions, as the official measurement of the amount of
energy delivered from the Large Generating Facility to the Point of
Interconnection.
Article 8. Communications
8.1 Interconnection Customer Obligations. Interconnection
Customer shall maintain satisfactory operating communications with
Transmission Provider's Transmission System dispatcher or
representative designated by Transmission Provider. Interconnection
Customer shall provide standard voice line, dedicated voice line and
facsimile communications at its Large Generating Facility control
room or central dispatch facility through use of either the public
telephone system, or a voice communications system that does not rely
on the public telephone system. Interconnection Customer shall also
provide the dedicated data circuit(s) necessary to provide
Interconnection Customer data to Transmission Provider as set forth
in Appendix D, Security Arrangements Details. The data
circuit(s) shall extend from the Large Generating Facility to the
location(s) specified by Transmission Provider. Any required
maintenance of such communications equipment shall be performed by
Interconnection Customer. Operational communications shall be
activated and maintained under, but not be limited to, the following
events: system paralleling or separation, scheduled and unscheduled
shutdowns, equipment clearances, and hourly and daily load data.
8.2 Remote Terminal Unit. Prior to
the Initial Synchronization Date of the Large Generating Facility, a
Remote Terminal Unit, or equivalent data collection and transfer
equipment acceptable to the Parties, shall be installed by
Interconnection Customer, or by Transmission Provider at
Interconnection Customer's expense, to gather accumulated and
instantaneous data to be telemetered to the location(s) designated by
Transmission Provider through use of a dedicated point-to-point data
circuit(s) as indicated in Article 8.1. The communication
protocol for the data circuit(s) shall be specified by Transmission
Provider. Instantaneous bi-directional analog real power and
reactive power flow information must be telemetered directly to the
location(s) specified by Transmission Provider.
Each Party will promptly advise the other Party if it detects or
otherwise learns of any metering, telemetry or communications
equipment errors or malfunctions that require the attention and/or
correction by the other Party. The Party owning such equipment shall
correct such error or malfunction as soon as reasonably feasible.
8.3 No Annexation. Any and all
equipment placed on the premises of a Party shall be and remain the
property of the Party providing such equipment regardless of the mode
and manner of annexation or attachment to real property, unless
otherwise mutually agreed by the Parties.
8.4. Provision of Data from a Variable Energy
Resource. The Interconnection
Customer whose Generating Facility is a Variable Energy Resource
shall provide meteorological and forced outage data to the
Transmission Provider to the extent necessary for the Transmission
Provider’s development and deployment of power production
forecasts for that class of Variable Energy Resources. The
Interconnection Customer with a Variable Energy Resource having wind
as the energy source, at a minimum, will be required to provide the
Transmission Provider with site-specific meteorological data
including: temperature, wind speed, wind direction, and atmospheric
pressure. The Interconnection Customer with a Variable Energy
Resource having solar as the energy source, at a minimum, will be
required to provide the Transmission Provider with site-specific
meteorological data including: temperature, atmospheric pressure,
and irradiance. The Transmission Provider and Interconnection
Customer whose Generating Facility is a Variable Energy Resource
shall mutually agree to any additional meteorological data that are
required for the development and deployment of a power production
forecast. The Interconnection Customer whose Generating Facility is
a Variable Energy Resource also shall submit data to the Transmission
Provider regarding all forced outages to the extent necessary for the
Transmission Provider’s development and deployment of power
production forecasts for that class of Variable Energy Resources.
The exact specifications of the meteorological and forced outage data
to be provided by the Interconnection Customer to the Transmission
Provider, including the frequency and timing of data submittals,
shall be made taking into account the size and configuration of the
Variable Energy Resource, its characteristics, location, and its
importance in maintaining generation resource adequacy and
transmission system reliability in its area. All requirements for
meteorological and forced outage data must be commensurate with the
power production forecasting employed by the Transmission Provider.
Such requirements for meteorological and forced outage data are set
forth in Appendix C, Interconnection Details, of this LGIA, as they
may change from time to time.
Article 9. Operations
9.1 General. Each Party shall
comply with the Applicable Reliability Council requirements. Each
Party shall provide to the other Party all information that may
reasonably be required by the other Party to comply with Applicable
Laws and Regulations and Applicable Reliability Standards.
9.2 Control Area Notification. At
least three months before Initial Synchronization Date,
Interconnection Customer shall notify Transmission Provider in
writing of the Control Area in which the Large Generating Facility
will be located. If Interconnection Customer elects to locate the
Large Generating Facility in a Control Area other than the Control
Area in which the Large Generating Facility is physically located,
and if permitted to do so by the relevant transmission tariffs, all
necessary arrangements, including but not limited to those set forth
in Article 7 and Article 8 of this LGIA, and remote Control Area
generator interchange agreements, if applicable, and the appropriate
measures under such agreements, shall be executed and implemented
prior to the placement of the Large Generating Facility in the other
Control Area.
9.3 Transmission Provider Obligations. Transmission
Provider shall cause the Transmission System and Transmission
Provider's Interconnection Facilities to be operated, maintained and
controlled in a safe and reliable manner and in accordance with this
LGIA. Transmission Provider may provide operating instructions to
Interconnection Customer consistent with this LGIA and Transmission
Provider's operating protocols and procedures as they may change from
time to time. Transmission Provider will consider changes to its
operating protocols and procedures proposed by Interconnection
Customer.
9.4 Interconnection Customer Obligations. Interconnection
Customer shall at its own expense operate, maintain and control the
Large Generating Facility and Interconnection Customer's
Interconnection Facilities in a safe and reliable manner and in
accordance with this LGIA. Interconnection Customer shall operate
the Large Generating Facility and Interconnection Customer's
Interconnection Facilities in accordance with all applicable
requirements of the Control Area of which it is part, as such
requirements are set forth in Appendix C, Interconnection Details, of
this LGIA. Appendix C, Interconnection Details, will be modified to
reflect changes to the requirements as they may change from time to
time. Either Party may request that the other Party provide copies
of the requirements set forth in Appendix C, Interconnection Details,
of this LGIA.
9.5 Start-Up and Synchronization. Consistent
with the Parties' mutually acceptable procedures, Interconnection
Customer is responsible for the proper synchronization of the Large
Generating Facility to Transmission Provider's Transmission System.
9.6 Reactive Power.
9.6.1 Power Factor Design Criteria.
9.6.1.1 Synchronous Generation. Interconnection
Customer shall design the Large Generating Facility to maintain a
composite power delivery at continuous rated power output at the
Point of Interconnection at a power factor within the range of 0.95
leading to 0.95 lagging, unless the Transmission Provider has
established different requirements that apply to all synchronous
generators in the Control Area on a comparable basis.
9.6.1.2 Non-Synchronous Generation. Interconnection
Customer shall design the Large Generating Facility to maintain a
composite power delivery at continuous rated power output at the
high-side of the generator substation at a power factor within the
range of 0.95 leading to 0.95 lagging, unless the Transmission
Provider has established a different power factor range that applies
to all non-synchronous generators in the Control Area on a comparable
basis. This power factor range standard shall be dynamic and can be
met using, for example, power electronics designed to supply this
level of reactive capability (taking into account any limitations due
to voltage level, real power output, etc.) or fixed and switched
capacitors, or a combination of the two. This requirement shall only
apply to newly interconnecting non-synchronous generators that have
not yet executed a Facilities Study Agreement as of the effective
date of the Final Rule establishing this requirement (Order No. 827).
9.6.2 Voltage Schedules. Once
Interconnection Customer has synchronized the Large Generating
Facility with the Transmission System, Transmission Provider shall
require Interconnection Customer to operate the Large Generating
Facility to produce or absorb reactive power within the design
limitations of the Large Generating Facility set forth in Article
9.6.1 (Power Factor Design Criteria). Transmission Provider's
voltage schedules shall treat all sources of reactive power in the
Control Area in an equitable and not unduly discriminatory manner.
Transmission Provider shall exercise Reasonable Efforts to provide
Interconnection Customer with such schedules at least one (1) day in
advance, and may make changes to such schedules as necessary to
maintain the reliability of the Transmission System. Interconnection
Customer shall operate the Large Generating Facility to maintain the
specified output voltage or power factor at the Point of
Interconnection within the design limitations of the Large Generating
Facility set forth in Article 9.6.1 (Power Factor Design Criteria).
If Interconnection Customer is unable to maintain the specified
voltage or power factor, it shall promptly notify the System
Operator.
9.6.2.1 Governors and Regulators. Whenever
the Large Generating Facility is operated in parallel with the
Transmission System and the speed governors (if installed on the
generating unit pursuant to Good Utility Practice) and voltage
regulators are capable of operation, Interconnection Customer shall
operate the Large Generating Facility with its speed governors and
voltage regulators in automatic operation. If the Large Generating
Facility's speed governors and voltage regulators are not capable of
such automatic operation, Interconnection Customer shall immediately
notify Transmission Provider's system operator, or its designated
representative, and ensure that such Large Generating Facility's
reactive power production or absorption (measured in MVARs) are
within the design capability of the Large Generating Facility's
generating unit(s) and steady state stability limits.
Interconnection Customer shall not cause its Large Generating
Facility to disconnect automatically or instantaneously from the
Transmission System or trip any generating unit comprising the Large
Generating Facility for an under or over frequency condition unless
the abnormal frequency condition persists for a time period beyond
the limits set forth in ANSI/IEEE Standard C37.106, or such other
standard as applied to other generators in the Control Area on a
comparable basis.
9.6.3 Payment for Reactive Power. Transmission
Provider is required to pay Interconnection Customer for reactive
power that Interconnection Customer provides or absorbs from the
Large Generating Facility when Transmission Provider requests
Interconnection Customer to operate its Large Generating Facility
outside the range specified in Article 9.6.1, provided that if
Transmission Provider pays its own or affiliated generators for
reactive power service within the specified range, it must also pay
Interconnection Customer. Payments shall be pursuant to Article 11.6
or such other agreement to which the Parties have otherwise agreed.
9.7 Outages and Interruptions.
9.7.1 Outages.
9.7.1.1 Outage Authority and Coordination. Each
Party may in accordance with Good Utility Practice in coordination
with the other Party remove from service any of its respective
Interconnection Facilities or Network Upgrades that may impact the
other Party's facilities as necessary to perform maintenance or
testing or to install or replace equipment. Absent an Emergency
Condition, the Party scheduling a removal of such facility(ies) from
service will use Reasonable Efforts to schedule such removal on a
date and time mutually acceptable to the Parties. In all
circumstances, any Party planning to remove such facility(ies) from
service shall use Reasonable Efforts to minimize the effect on the
other Party of such removal.
9.7.1.2 Outage Schedules. Transmission
Provider shall post scheduled outages of its transmission facilities
on the OASIS. Interconnection Customer shall submit its planned
maintenance schedules for the Large Generating Facility to
Transmission Provider for a minimum of a rolling twenty-four month
period. Interconnection Customer shall update its planned
maintenance schedules as necessary. Transmission Provider may
request Interconnection Customer to reschedule its maintenance as
necessary to maintain the reliability of the Transmission System;
provided, however, adequacy of generation supply shall not be a
criterion in determining Transmission System reliability.
Transmission Provider shall compensate Interconnection Customer for
any additional direct costs that Interconnection Customer incurs as a
result of having to reschedule maintenance, including any additional
overtime, breaking of maintenance contracts or other costs above and
beyond the cost Interconnection Customer would have incurred absent
Transmission Provider's request to reschedule maintenance.
Interconnection Customer will not be eligible to receive
compensation, if during the twelve (12) months prior to the date of
the scheduled maintenance, Interconnection Customer had modified its
schedule of maintenance activities.
9.7.1.3 Outage Restoration. If
an outage on a Party's Interconnection Facilities or Network Upgrades
adversely affects the other Party's operations or facilities, the
Party that owns or controls the facility that is out of service shall
use Reasonable Efforts to promptly restore such facility(ies) to a
normal operating condition consistent with the nature of the outage.
The Party that owns or controls the facility that is out of service
shall provide the other Party, to the extent such information is
known, information on the nature of the Emergency Condition, an
estimated time of restoration, and any corrective actions required.
Initial verbal notice shall be followed up as soon as practicable
with written notice explaining the nature of the outage.
9.7.2 Interruption of Service. If
required by Good Utility Practice to do so, Transmission Provider may
require Interconnection Customer to interrupt or reduce deliveries of
electricity if such delivery of electricity could adversely affect
Transmission Provider's ability to perform such activities as are
necessary to safely and reliably operate and maintain the
Transmission System. The following provisions shall apply to any
interruption or reduction permitted under this Article 9.7.2:
9.7.2.1 The interruption or
reduction shall continue only for so long as reasonably necessary
under Good Utility Practice;
9.7.2.2 Any such interruption or
reduction shall be made on an equitable, non-discriminatory basis
with respect to all generating facilities directly connected to the
Transmission System;
9.7.2.3 When the interruption or
reduction must be made under circumstances which do not allow for
advance notice, Transmission Provider shall notify Interconnection
Customer by telephone as soon as practicable of the reasons for the
curtailment, interruption, or reduction, and, if known, its expected
duration. Telephone notification shall be followed by written
notification as soon as practicable;
9.7.2.4 Except during the
existence of an Emergency Condition, when the interruption or
reduction can be scheduled without advance notice, Transmission
Provider shall notify Interconnection Customer in advance regarding
the timing of such scheduling and further notify Interconnection
Customer of the expected duration. Transmission Provider shall
coordinate with Interconnection Customer using Good Utility Practice
to schedule the interruption or reduction during periods of least
impact to Interconnection Customer and Transmission Provider;
9.7.2.5 The Parties shall
cooperate and coordinate with each other to the extent necessary in
order to restore the Large Generating Facility, Interconnection
Facilities, and the Transmission System to their normal operating
state, consistent with system conditions and Good Utility Practice.
9.7.3 Under-Frequency and Over Frequency Conditions. The
Transmission System is designed to automatically activate a load-shed
program as required by the Applicable Reliability Council in the
event of an under-frequency system disturbance. Interconnection
Customer shall implement under-frequency and over-frequency relay set
points for the Large Generating Facility as required by the
Applicable Reliability Council to ensure "ride through"
capability of the Transmission System. Large Generating Facility
response to frequency deviations of pre-determined magnitudes, both
under-frequency and over-frequency deviations, shall be studied and
coordinated with Transmission Provider in accordance with Good
Utility Practice. The term "ride through" as used herein
shall mean the ability of a Generating Facility to stay connected to
and synchronized with the Transmission System during system
disturbances within a range of under-frequency and over-frequency
conditions, in accordance with Good Utility Practice.
9.7.4 System Protection and Other Control Requirements.
9.7.4.1 System Protection Facilities. Interconnection
Customer shall, at its expense, install, operate and maintain System
Protection Facilities as a part of the Large Generating Facility or
Interconnection Customer's Interconnection Facilities. Transmission
Provider shall install at Interconnection Customer's expense any
System Protection Facilities that may be required on Transmission
Provider's Interconnection Facilities or the Transmission System as a
result of the interconnection of the Large Generating Facility and
Interconnection Customer's Interconnection Facilities.
9.7.4.2 Each Party's protection
facilities shall be designed and coordinated with other systems in
accordance with Good Utility Practice.
9.7.4.3 Each Party shall be
responsible for protection of its facilities consistent with Good
Utility Practice.
9.7.4.4 Each Party's protective
relay design shall incorporate the necessary test switches to perform
the tests required in Article 6. The required test switches will be
placed such that they allow operation of lockout relays while
preventing breaker failure schemes from operating and causing
unnecessary breaker operations and/or the tripping of Interconnection
Customer's units.
9.7.4.5 Each Party will test,
operate and maintain System Protection Facilities in accordance with
Good Utility Practice.
9.7.4.6 Prior to the In-Service
Date, and again prior to the Commercial Operation Date, each Party or
its agent shall perform a complete calibration test and functional
trip test of the System Protection Facilities. At intervals
suggested by Good Utility Practice and following any apparent
malfunction of the System Protection Facilities, each Party shall
perform both calibration and functional trip tests of its System
Protection Facilities. These tests do not require the tripping of
any in-service generation unit. These tests do, however, require
that all protective relays and lockout contacts be activated.
9.7.5 Requirements for Protection.
In compliance with Good Utility Practice, Interconnection Customer
shall provide, install, own, and maintain relays, circuit breakers
and all other devices necessary to remove any fault contribution of
the Large Generating Facility to any short circuit occurring on the
Transmission System not otherwise isolated by Transmission Provider's
equipment, such that the removal of the fault contribution shall be
coordinated with the protective requirements of the Transmission
System. Such protective equipment shall include, without limitation,
a disconnecting device or switch with load-interrupting capability
located between the Large Generating Facility and the Transmission
System at a site selected upon mutual agreement (not to be
unreasonably withheld, conditioned or delayed) of the Parties.
Interconnection Customer shall be responsible for protection of the
Large Generating Facility and Interconnection Customer's other
equipment from such conditions as negative sequence currents, over-
or under-frequency, sudden load rejection, over- or under-voltage,
and generator loss-of-field. Interconnection Customer shall be
solely responsible to disconnect the Large Generating Facility and
Interconnection Customer's other equipment if conditions on the
Transmission System could adversely affect the Large Generating
Facility.
9.7.6 Power Quality. Neither
Party's facilities shall cause excessive voltage flicker nor
introduce excessive distortion to the sinusoidal voltage or current
waves as defined by ANSI Standard C84.1-1989, in accordance with IEEE
Standard 519, or any applicable superseding electric industry
standard. In the event of a conflict between ANSI Standard
C84.1-1989, or any applicable superseding electric industry standard,
ANSI Standard C84.1-1989, or the applicable superseding electric
industry standard, shall control.
9.8 Switching and Tagging Rules. Each
Party shall provide the other Party a copy of its switching and
tagging rules that are applicable to the other Party's activities.
Such switching and tagging rules shall be developed on a
non-discriminatory basis. The Parties shall comply with applicable
switching and tagging rules, as amended from time to time, in
obtaining clearances for work or for switching operations on
equipment.
9.9 Use of Interconnection Facilities by Third Parties.
9.9.1 Purpose of Interconnection Facilities. Except
as may be required by Applicable Laws and Regulations, or as
otherwise agreed to among the Parties, the Interconnection Facilities
shall be constructed for the sole purpose of interconnecting the
Large Generating Facility to the Transmission System and shall be
used for no other purpose.
9.9.2 Third Party Users. If
required by Applicable Laws and Regulations or if the Parties
mutually agree, such agreement not to be unreasonably withheld, to
allow one or more third parties to use Transmission Provider's
Interconnection Facilities, or any part thereof, Interconnection
Customer will be entitled to compensation for the capital expenses it
incurred in connection with the Interconnection Facilities based upon
the pro rata use of the Interconnection Facilities by Transmission
Provider, all third party users, and Interconnection Customer, in
accordance with Applicable Laws and Regulations or upon some other
mutually-agreed upon methodology. In addition, cost responsibility
for ongoing costs, including operation and maintenance costs
associated with the Interconnection Facilities, will be allocated
between Interconnection Customer and any third party users based upon
the pro rata use of the Interconnection Facilities by Transmission
Provider, all third party users, and Interconnection Customer, in
accordance with Applicable Laws and Regulations or upon some other
mutually agreed upon methodology. If the issue of such compensation
or allocation cannot be resolved through such negotiations, it shall
be submitted to FERC for resolution.
9.10 Disturbance Analysis Data Exchange. The
Parties will cooperate with one another in the analysis of
disturbances to either the Large Generating Facility or Transmission
Provider's Transmission System by gathering and providing access to
any information relating to any disturbance, including information
from oscillography, protective relay targets, breaker operations and
sequence of events records, and any disturbance information required
by Good Utility Practice.
Article 10. Maintenance
10.1 Transmission Provider Obligations. Transmission
Provider shall maintain the Transmission System and Transmission
Provider's Interconnection Facilities in a safe and reliable manner
and in accordance with this LGIA.
10.2 Interconnection Customer Obligations. Interconnection
Customer shall maintain the Large Generating Facility and
Interconnection Customer's Interconnection Facilities in a safe and
reliable manner and in accordance with this LGIA.
10.3 Coordination. The Parties
shall confer regularly to coordinate the planning, scheduling and
performance of preventive and corrective maintenance on the Large
Generating Facility and the Interconnection Facilities.
10.4 Secondary Systems. Each Party
shall cooperate with the other in the inspection, maintenance, and
testing of control or power circuits that operate below 600 volts, AC
or DC, including, but not limited to, any hardware, control or
protective devices, cables, conductors, electric raceways, secondary
equipment panels, transducers, batteries, chargers, and voltage and
current transformers that directly affect the operation of a Party's
facilities and equipment which may reasonably be expected to impact
the other Party. Each Party shall provide advance notice to the
other Party before undertaking any work on such circuits, especially
on electrical circuits involving circuit breaker trip and close
contacts, current transformers, or potential transformers.
10.5 Operating and Maintenance Expenses. Subject
to the provisions herein addressing the use of facilities by others,
and except for operations and maintenance expenses associated with
modifications made for providing interconnection or transmission
service to a third party and such third party pays for such expenses,
Interconnection Customer shall be responsible for all reasonable
expenses including overheads, associated with: (1) owning, operating,
maintaining, repairing, and replacing Interconnection Customer's
Interconnection Facilities; and (2) operation, maintenance, repair
and replacement of Transmission Provider's Interconnection
Facilities.
Article 11. Performance Obligation
11.1 Interconnection Customer Interconnection Facilities.
Interconnection Customer shall
design, procure, construct, install, own and/or control
Interconnection Customer Interconnection Facilities described in
Appendix A, Interconnection Facilities, Network Upgrades and
Distribution Upgrades, at its sole expense.
11.2 Transmission Provider's Interconnection Facilities.
Transmission Provider or
Transmission Owner shall design, procure, construct, install, own
and/or control the Transmission Provider's Interconnection Facilities
described in Appendix A, Interconnection Facilities, Network Upgrades
and Distribution Upgrades, at the sole expense of the Interconnection
Customer.
11.3 Network Upgrades and Distribution Upgrades. Transmission
Provider or Transmission Owner shall design, procure, construct,
install, and own the Network Upgrades and Distribution Upgrades
described in Appendix A, Interconnection Facilities, Network Upgrades
and Distribution Upgrades. The Interconnection Customer shall be
responsible for all costs related to Distribution Upgrades. Unless
Transmission Provider or Transmission Owner elects to fund the
capital for the Network Upgrades, they shall be solely funded by
Interconnection Customer.
11.4 Transmission Credits.
11.4.1 Repayment of Amounts Advanced for Network Upgrades.
Interconnection Customer shall be
entitled to a cash repayment, equal to the total amount paid to
Transmission Provider and Affected System Operator, if any, for the
Network Upgrades, including any tax gross-up or other tax-related
payments associated with Network Upgrades, and not refunded to
Interconnection Customer pursuant to Article 5.17.8 or otherwise, to
be paid to Interconnection Customer on a dollar-for-dollar basis for
the non-usage sensitive portion of transmission charges, as payments
are made under Transmission Provider's Tariff and Affected System's
Tariff for transmission services with respect to the Large Generating
Facility. Any repayment shall include interest calculated in
accordance with the methodology set forth in FERC=s
regulations at 18 C.F.R. '35.19a(a)(2)(iii)
from the date of any payment for Network Upgrades through the date on
which the Interconnection Customer receives a repayment of such
payment pursuant to this subparagraph. Interconnection Customer may
assign such repayment rights to any person.
Notwithstanding the foregoing, Interconnection Customer, Transmission
Provider, and Affected System Operator may adopt any alternative
payment schedule that is mutually agreeable so long as Transmission
Provider and Affected System Operator take one of the following
actions no later than five years from the Commercial Operation Date:
(1) return to Interconnection Customer any amounts advanced for
Network Upgrades not previously repaid, or (2) declare in writing
that Transmission Provider or Affected System Operator will continue
to provide payments to Interconnection Customer on a
dollar-for-dollar basis for the non-usage sensitive portion of
transmission charges, or develop an alternative schedule that is
mutually agreeable and provides for the return of all amounts
advanced for Network Upgrades not previously repaid; however, full
reimbursement shall not extend beyond twenty (20) years from the
Commercial Operation Date..
If the Large Generating Facility fails to achieve commercial
operation, but it or another Generating Facility is later constructed
and makes use of the Network Upgrades, Transmission Provider and
Affected System Operator shall at that time reimburse Interconnection
Customer for the amounts advanced for the Network Upgrades. Before
any such reimbursement can occur, the Interconnection Customer, or
the entity that ultimately constructs the Generating Facility, if
different, is responsible for identifying the entity to which
reimbursement must be made.
11.4.2 Special Provisions for Affected Systems. Unless
Transmission Provider provides, under the LGIA, for the repayment of
amounts advanced to Affected System Operator for Network Upgrades,
Interconnection Customer and Affected System Operator shall enter
into an agreement that provides for such repayment. The agreement
shall specify the terms governing payments to be made by
Interconnection Customer to the Affected System Operator as well as
the repayment by the Affected System Operator.
11.4.3 Notwithstanding any other
provision of this LGIA, nothing herein shall be construed as
relinquishing or foreclosing any rights, including but not limited to
firm transmission rights, capacity rights, transmission congestion
rights, or transmission credits, that Interconnection Customer, shall
be entitled to, now or in the future under any other agreement or
tariff as a result of, or otherwise associated with, the transmission
capacity, if any, created by the Network Upgrades, including the
right to obtain cash reimbursements or transmission credits for
transmission service that is not associated with the Large Generating
Facility.
11.5 Provision of Security. At
least thirty (30) Calendar Days prior to the commencement of the
procurement, installation, or construction of a discrete portion of a
Transmission Provider's Interconnection Facilities, Network Upgrades,
or Distribution Upgrades, Interconnection Customer shall provide
Transmission Provider, at Interconnection Customer's option, a
guarantee, a surety bond, letter of credit or other form of security
that is reasonably acceptable to Transmission Provider and is
consistent with the Uniform Commercial Code of the jurisdiction
identified in Article 14.2.1. Such security for payment shall be in
an amount sufficient to cover the costs for constructing, procuring
and installing the applicable portion of Transmission Provider's
Interconnection Facilities, Network Upgrades, or Distribution
Upgrades and shall be reduced on a dollar-for-dollar basis for
payments made to Transmission Provider for these purposes.
In
addition:
11.5.1 The guarantee must be made
by an entity that meets the creditworthiness requirements of
Transmission Provider, and contain terms and conditions that
guarantee payment of any amount that may be due from Interconnection
Customer, up to an agreed-to maximum amount.
11.5.2 The letter of credit must
be issued by a financial institution reasonably acceptable to
Transmission Provider and must specify a reasonable expiration date.
11.5.3 The surety bond must be
issued by an insurer reasonably acceptable to Transmission Provider
and must specify a reasonable expiration date.
11.6 Interconnection Customer Compensation. If
Transmission Provider requests or directs Interconnection Customer to
provide a service pursuant to Articles 9.6.3 (Payment for Reactive
Power), or 13.5.1 of this LGIA, Transmission Provider shall
compensate Interconnection Customer in accordance with
Interconnection Customer's applicable rate schedule then in effect
unless the provision of such service(s) is subject to an RTO or ISO
FERC-approved rate schedule. Interconnection Customer shall serve
Transmission Provider or RTO or ISO with any filing of a proposed
rate schedule at the time of such filing with FERC. To the extent
that no rate schedule is in effect at the time the Interconnection
Customer is required to provide or absorb any Reactive Power under
this LGIA, Transmission Provider agrees to compensate Interconnection
Customer in such amount as would have been due Interconnection
Customer had the rate schedule been in effect at the time service
commenced; provided, however, that such rate schedule must be filed
at FERC or other appropriate Governmental Authority within sixty (60)
Calendar Days of the commencement of service.
11.6.1 Interconnection Customer Compensation for Actions During
Emergency Condition. Transmission
Provider or RTO or ISO shall compensate Interconnection Customer for
its provision of real and reactive power and other Emergency
Condition services that Interconnection Customer provides to support
the Transmission System during an Emergency Condition in accordance
with Article 11.6.
Article 12. Invoice
12.1 General. Each Party shall
submit to the other Party, on a monthly basis, invoices of amounts
due for the preceding month. Each invoice shall state the month to
which the invoice applies and fully describe the services and
equipment provided. The Parties may discharge mutual debts and
payment obligations due and owing to each other on the same date
through netting, in which case all amounts a Party owes to the other
Party under this LGIA, including interest payments or credits, shall
be netted so that only the net amount remaining due shall be paid by
the owing Party.
12.2 Final Invoice. Within six
months after completion of the construction of Transmission
Provider's Interconnection Facilities and the Network Upgrades,
Transmission Provider shall provide an invoice of the final cost of
the construction of Transmission Provider's Interconnection
Facilities and the Network Upgrades and shall set forth such costs in
sufficient detail to enable Interconnection Customer to compare the
actual costs with the estimates and to ascertain deviations, if any,
from the cost estimates. Transmission Provider shall refund to
Interconnection Customer any amount by which the actual payment by
Interconnection Customer for estimated costs exceeds the actual costs
of construction within thirty (30) Calendar Days of the issuance of
such final construction invoice.
12.3 Payment. Invoices shall be
rendered to the paying Party at the address specified in Appendix F.
The Party receiving the invoice shall pay the invoice within thirty
(30) Calendar Days of receipt. All payments shall be made in
immediately available funds payable to the other Party, or by wire
transfer to a bank named and account designated by the invoicing
Party. Payment of invoices by either Party will not constitute a
waiver of any rights or claims either Party may have under this LGIA.
12.4 Disputes. In the event of a
billing dispute between Transmission Provider and Interconnection
Customer, Transmission Provider shall continue to provide
Interconnection Service under this LGIA as long as Interconnection
Customer: (i) continues to make all payments not in dispute; and (ii)
pays to Transmission Provider or into an independent escrow account
the portion of the invoice in dispute, pending resolution of such
dispute. If Interconnection Customer fails to meet these two
requirements for continuation of service, then Transmission Provider
may provide notice to Interconnection Customer of a Default pursuant
to Article 17. Within thirty (30) Calendar Days after the resolution
of the dispute, the Party that owes money to the other Party shall
pay the amount due with interest calculated in accord with the
methodology set forth in FERC's regulations at 18 CFR §
35.19a(a)(2)(iii).
Article 13. Emergencies
13.1 Definition. "Emergency
Condition" shall mean a condition or situation: (i) that in the
judgment of the Party making the claim is imminently likely to
endanger life or property; or (ii) that, in the case of
Transmission Provider, is imminently likely (as determined in a
non-discriminatory manner) to cause a material adverse effect on the
security of, or damage to the Transmission System, Transmission
Provider's Interconnection Facilities or the Transmission Systems of
others to which the Transmission System is directly connected; or
(iii) that, in the case of Interconnection Customer, is
imminently likely (as determined in a non-discriminatory manner) to
cause a material adverse effect on the security of, or damage to, the
Large Generating Facility or Interconnection Customer's
Interconnection Facilities' System restoration and black start shall
be considered Emergency Conditions; provided, that Interconnection
Customer is not obligated by this LGIA to possess black start
capability.
13.2 Obligations. Each Party shall
comply with the Emergency Condition procedures of the applicable
ISO/RTO, NERC, the Applicable Reliability Council, Applicable Laws
and Regulations, and any emergency procedures agreed to by the Joint
Operating Committee.
13.3 Notice. Transmission Provider
shall notify Interconnection Customer promptly when it becomes aware
of an Emergency Condition that affects Transmission Provider's
Interconnection Facilities or the Transmission System that may
reasonably be expected to affect Interconnection Customer's operation
of the Large Generating Facility or Interconnection Customer's
Interconnection Facilities. Interconnection Customer shall notify
Transmission Provider promptly when it becomes aware of an Emergency
Condition that affects the Large Generating Facility or
Interconnection Customer's Interconnection Facilities that may
reasonably be expected to affect the Transmission System or
Transmission Provider's Interconnection Facilities. To the extent
information is known, the notification shall describe the Emergency
Condition, the extent of the damage or deficiency, the expected
effect on the operation of Interconnection Customer's or Transmission
Provider's facilities and operations, its anticipated duration and
the corrective action taken and/or to be taken. The initial notice
shall be followed as soon as practicable with written notice.
13.4 Immediate Action. Unless, in
Interconnection Customer's reasonable judgment, immediate action is
required, Interconnection Customer shall obtain the consent of
Transmission Provider, such consent to not be unreasonably withheld,
prior to performing any manual switching operations at the Large
Generating Facility or Interconnection Customer's Interconnection
Facilities in response to an Emergency Condition either declared by
Transmission Provider or otherwise regarding the Transmission System.
13.5 Transmission Provider Authority.
13.5.1 General. Transmission
Provider may take whatever actions or inactions with regard to the
Transmission System or Transmission Provider's Interconnection
Facilities it deems necessary during an Emergency Condition in order
to (i) preserve public health and safety, (ii) preserve the
reliability of the Transmission System or Transmission Provider's
Interconnection Facilities, (iii) limit or prevent damage, and
(iv) expedite restoration of service.
Transmission Provider shall use Reasonable Efforts to minimize the
effect of such actions or inactions on the Large Generating Facility
or Interconnection Customer's Interconnection Facilities.
Transmission Provider may, on the basis of technical considerations,
require the Large Generating Facility to mitigate an Emergency
Condition by taking actions necessary and limited in scope to remedy
the Emergency Condition, including, but not limited to, directing
Interconnection Customer to shut-down, start-up, increase or decrease
the real or reactive power output of the Large Generating Facility;
implementing a reduction or disconnection pursuant to Article 13.5.2;
directing Interconnection Customer to assist with blackstart (if
available) or restoration efforts; or altering the outage schedules
of the Large Generating Facility and Interconnection Customer's
Interconnection Facilities. Interconnection Customer shall comply
with all of Transmission Provider's operating instructions concerning
Large Generating Facility real power and reactive power output within
the manufacturer's design limitations of the Large Generating
Facility's equipment that is in service and physically available for
operation at the time, in compliance with Applicable Laws and
Regulations.
13.5.2 Reduction and Disconnection. Transmission
Provider may reduce Interconnection Service or disconnect the Large
Generating Facility or Interconnection Customer's Interconnection
Facilities, when such, reduction or disconnection is necessary under
Good Utility Practice due to Emergency Conditions. These rights are
separate and distinct from any right of curtailment of Transmission
Provider pursuant to Transmission Provider's Tariff. When
Transmission Provider can schedule the reduction or disconnection in
advance, Transmission Provider shall notify Interconnection Customer
of the reasons, timing and expected duration of the reduction or
disconnection. Transmission Provider shall coordinate with
Interconnection Customer using Good Utility Practice to schedule the
reduction or disconnection during periods of least impact to
Interconnection Customer and Transmission Provider. Any reduction or
disconnection shall continue only for so long as reasonably necessary
under Good Utility Practice. The Parties shall cooperate with each
other to restore the Large Generating Facility, the Interconnection
Facilities, and the Transmission System to their normal operating
state as soon as practicable consistent with Good Utility Practice.
13.6 Interconnection Customer Authority. Consistent
with Good Utility Practice and the LGIA and the LGIP, Interconnection
Customer may take actions or inactions with regard to the Large
Generating Facility or Interconnection Customer's Interconnection
Facilities during an Emergency Condition in order to (i) preserve
public health and safety, (ii) preserve the reliability of the
Large Generating Facility or Interconnection Customer's
Interconnection Facilities, (iii) limit or prevent damage, and
(iv) expedite restoration of service. Interconnection Customer
shall use Reasonable Efforts to minimize the effect of such actions
or inactions on the Transmission System and Transmission Provider's
Interconnection Facilities. Transmission Provider shall use
Reasonable Efforts to assist Interconnection Customer in such
actions.
13.7 Limited Liability. Except as
otherwise provided in Article 11.6.1 of this LGIA, neither Party
shall be liable to the other for any action it takes in responding to
an Emergency Condition so long as such action is made in good faith
and is consistent with Good Utility Practice.
Article 14. Regulatory Requirements and Governing Law
14.1 Regulatory Requirements. Each
Party's obligations under this LGIA shall be subject to its receipt
of any required approval or certificate from one or more Governmental
Authorities in the form and substance satisfactory to the applying
Party, or the Party making any required filings with, or providing
notice to, such Governmental Authorities, and the expiration of any
time period associated therewith. Each Party shall in good faith
seek and use its Reasonable Efforts to obtain such other approvals.
Nothing in this LGIA shall require Interconnection Customer to take
any action that could result in its inability to obtain, or its loss
of, status or exemption under the Federal Power Act, the Public
Utility Holding Company Act of 1935, as amended, or the Public
Utility Regulatory Policies Act of 1978.
14.2 Governing Law.
14.2.1 The validity,
interpretation and performance of this LGIA and each of its
provisions shall be governed by the laws of the state where the Point
of Interconnection is located, without regard to its conflicts of law
principles.
14.2.2 This LGIA is subject to
all Applicable Laws and Regulations.
14.2.3 Each Party expressly
reserves the right to seek changes in, appeal, or otherwise contest
any laws, orders, rules, or regulations of a Governmental Authority.
Article 15. Notices.
15.1 General. Unless otherwise
provided in this LGIA, any notice, demand or request required or
permitted to be given by either Party to the other and any instrument
required or permitted to be tendered or delivered by either Party in
writing to the other shall be effective when delivered and may be so
given, tendered or delivered, by recognized national courier, or by
depositing the same with the United States Postal Service with
postage prepaid, for delivery by certified or registered mail,
addressed to the Party, or personally delivered to the Party, at the
address set out in Appendix F, Addresses for Delivery of Notices and
Billings.
Either Party may change the notice information in this LGIA by giving
five (5) Business Days written notice prior to the effective date of
the change.
15.2 Billings and Payments. Billings
and payments shall be sent to the addresses set out in Appendix F.
15.3 Alternative Forms of Notice. Any
notice or request required or permitted to be given by a Party to the
other and not required by this Agreement to be given in writing may
be so given by telephone, facsimile or email to the telephone numbers
and email addresses set out in Appendix F.
15.4 Operations and Maintenance Notice . Each
Party shall notify the other Party in writing of the identity of the
person(s) that it designates as the point(s) of contact with respect
to the implementation of Articles 9 and 10.
Article 16. Force Majeure
16.1 Force Majeure.
16.1.1 Economic hardship is not
considered a Force Majeure event.
16.1.2 Neither Party shall be
considered to be in Default with respect to any obligation hereunder,
(including obligations under Article 4), other than the obligation to
pay money when due, if prevented from fulfilling such obligation by
Force Majeure. A Party unable to fulfill any obligation hereunder
(other than an obligation to pay money when due) by reason of Force
Majeure shall give notice and the full particulars of such Force
Majeure to the other Party in writing or by telephone as soon as
reasonably possible after the occurrence of the cause relied upon.
Telephone notices given pursuant to this article shall be confirmed
in writing as soon as reasonably possible and shall specifically
state full particulars of the Force Majeure, the time and date when
the Force Majeure occurred and when the Force Majeure is reasonably
expected to cease. The Party affected shall exercise due diligence
to remove such disability with reasonable dispatch, but shall not be
required to accede or agree to any provision not satisfactory to it
in order to settle and terminate a strike or other labor disturbance.
Article 17. Default
17.1 Default
17.1.1 General. No Default shall
exist where such failure to discharge an obligation (other than the
payment of money) is the result of Force Majeure as defined in this
LGIA or the result of an act of omission of the other Party. Upon a
Breach, the non-breaching Party shall give written notice of such
Breach to the breaching Party. Except as provided in Article 17.1.2,
the breaching Party shall have thirty (30) Calendar Days from receipt
of the Default notice within which to cure such Breach; provided
however, if such Breach is not capable of cure within thirty (30)
Calendar Days, the breaching Party shall commence such cure within
thirty (30) Calendar Days after notice and continuously and
diligently complete such cure within ninety (90) Calendar Days from
receipt of the Default notice; and, if cured within such time, the
Breach specified in such notice shall cease to exist.
17.1.2 Right to Terminate. If a
Breach is not cured as provided in this article, or if a Breach is
not capable of being cured within the period provided for herein, the
non-breaching Party shall have the right to declare a Default and
terminate this LGIA by written notice at any time until cure occurs,
and be relieved of any further obligation hereunder and, whether or
not that Party terminates this LGIA, to recover from the breaching
Party all amounts due hereunder, plus all other damages and remedies
to which it is entitled at law or in equity. The provisions of this
article will survive termination of this LGIA.
Article 18. Indemnity,
Consequential Damages and Insurance
18.1 Indemnity. The Parties shall
at all times indemnify, defend, and hold the other Party harmless
from, any and all damages, losses, claims, including claims and
actions relating to injury to or death of any person or damage to
property, demand, suits, recoveries, costs and expenses, court costs,
attorney fees, and all other obligations by or to third parties,
arising out of or resulting from the other Party's action or
inactions of its obligations under this LGIA on behalf of the
Indemnifying Party, except in cases of gross negligence or
intentional wrongdoing by the indemnified Party.
18.1.1 Indemnified Person. If an
Indemnified Person is entitled to indemnification under this Article
18 as a result of a claim by a third party, and the Indemnifying
Party fails, after notice and reasonable opportunity to proceed under
Article 18.1, to assume the defense of such claim, such Indemnified
Person may at the expense of the Indemnifying Party contest, settle
or consent to the entry of any judgment with respect to, or pay in
full, such claim.
18.1.2 Indemnifying Party. If an
Indemnifying Party is obligated to indemnify and hold any Indemnified
Person harmless under this Article 18, the amount owing to the
Indemnified Person shall be the amount of such Indemnified Person's
actual Loss, net of any insurance or other recovery.
18.1.3 Indemnity Procedures. Promptly
after receipt by an Indemnified Person of any claim or notice of the
commencement of any action or administrative or legal proceeding or
investigation as to which the indemnity provided for in Article 18.1
may apply, the Indemnified Person shall notify the Indemnifying Party
of such fact. Any failure of or delay in such notification shall not
affect a Party's indemnification obligation unless such failure or
delay is materially prejudicial to the Indemnifying Party.
The Indemnifying Party shall have the right to assume the defense
thereof with counsel designated by such Indemnifying Party and
reasonably satisfactory to the Indemnified Person. If the defendants
in any such action include one or more Indemnified Persons and the
Indemnifying Party and if the Indemnified Person reasonably concludes
that there may be legal defenses available to it and/or other
Indemnified Persons which are different from or additional to those
available to the Indemnifying Party, the Indemnified Person shall
have the right to select separate counsel to assert such legal
defenses and to otherwise participate in the defense of such action
on its own behalf. In such instances, the Indemnifying Party shall
only be required to pay the fees and expenses of one additional
attorney to represent an Indemnified Person or Indemnified Persons
having such differing or additional legal defenses.
The Indemnified Person shall be entitled, at its expense, to
participate in any such action, suit or proceeding, the defense of
which has been assumed by the Indemnifying Party. Notwithstanding
the foregoing, the Indemnifying Party (i) shall not be entitled to
assume and control the defense of any such action, suit or
proceedings if and to the extent that, in the opinion of the
Indemnified Person and its counsel, such action, suit or proceeding
involves the potential imposition of criminal liability on the
Indemnified Person, or there exists a conflict or adversity of
interest between the Indemnified Person and the Indemnifying Party,
in such event the Indemnifying Party shall pay the reasonable
expenses of the Indemnified Person, and (ii) shall not settle or
consent to the entry of any judgment in any action, suit or
proceeding without the consent of the Indemnified Person, which shall
not be reasonably withheld, conditioned or delayed.
18.2 Consequential Damages. Other
than the Liquidated Damages heretofore described, in no event shall
either Party be liable under any provision of this LGIA for any
losses, damages, costs or expenses for any special, indirect,
incidental, consequential, or punitive damages, including but not
limited to loss of profit or revenue, loss of the use of equipment,
cost of capital, cost of temporary equipment or services, whether
based in whole or in part in contract, in tort, including negligence,
strict liability, or any other theory of liability; provided,
however, that damages for which a Party may be liable to the other
Party under another agreement will not be considered to be special,
indirect, incidental, or consequential damages hereunder.
18.3 Insurance. Each party shall,
at its own expense, maintain in force throughout the period of this
LGIA, and until released by the other Party, the following minimum
insurance coverages, with insurers authorized to do business in the
state where the Point of Interconnection is located:
18.3.1 Employers' Liability and
Workers' Compensation Insurance providing statutory benefits in
accordance with the laws and regulations of the state in which the
Point of Interconnection is located.
18.3.2 Commercial General
Liability Insurance including premises and operations, personal
injury, broad form property damage, broad form blanket contractual
liability coverage (including coverage for the contractual
indemnification) products and completed operations coverage, coverage
for explosion, collapse and underground hazards, independent
contractors coverage, coverage for pollution to the extent normally
available and punitive damages to the extent normally available and a
cross liability endorsement, with minimum limits of One Million
Dollars ($1,000,000) per occurrence/One Million Dollars ($1,000,000)
aggregate combined single limit for personal injury, bodily injury,
including death and property damage.
18.3.3 Comprehensive Automobile
Liability Insurance for coverage of owned and non-owned and hired
vehicles, trailers or semi-trailers designed for travel on public
roads, with a minimum, combined single limit of One Million Dollars
($1,000,000) per occurrence for bodily injury, including death, and
property damage.
18.3.4 Excess Public Liability
Insurance over and above the Employers' Liability Commercial General
Liability and Comprehensive Automobile Liability Insurance coverage,
with a minimum combined single limit of Twenty Million Dollars
($20,000,000) per occurrence/Twenty Million Dollars ($20,000,000)
aggregate.
18.3.5 The Commercial General
Liability Insurance, Comprehensive Automobile Insurance and Excess
Public Liability Insurance policies shall name the other Party, its
parent, associated and Affiliate companies and their respective
directors, officers, agents, servants and employees ("Other
Party Group") as additional insured. All policies shall contain
provisions whereby the insurers waive all rights of subrogation in
accordance with the provisions of this LGIA against the Other Party
Group and provide thirty (30) Calendar Days advance written notice to
the Other Party Group prior to anniversary date of cancellation or
any material change in coverage or condition.
18.3.6 The Commercial General
Liability Insurance, Comprehensive Automobile Liability Insurance and
Excess Public Liability Insurance policies shall contain provisions
that specify that the policies are primary and shall apply to such
extent without consideration for other policies separately carried
and shall state that each insured is provided coverage as though a
separate policy had been issued to each, except the insurer's
liability shall not be increased beyond the amount for which the
insurer would have been liable had only one insured been covered.
Each Party shall be responsible for its respective deductibles or
retentions.
18.3.7 The Commercial General
Liability Insurance, Comprehensive Automobile Liability Insurance and
Excess Public Liability Insurance policies, if written on a Claims
First Made Basis, shall be maintained in full force and effect for
two (2) years after termination of this LGIA, which coverage may be
in the form of tail coverage or extended reporting period coverage if
agreed by the Parties.
18.3.8 The requirements contained
herein as to the types and limits of all insurance to be maintained
by the Parties are not intended to and shall not in any manner, limit
or qualify the liabilities and obligations assumed by the Parties
under this LGIA.
18.3.9 Within ten (10) days
following execution of this LGIA, and as soon as practicable after
the end of each fiscal year or at the renewal of the insurance policy
and in any event within ninety (90) days thereafter, each Party shall
provide certification of all insurance required in this LGIA,
executed by each insurer or by an authorized representative of each
insurer.
18.3.10 Notwithstanding the
foregoing, each Party may self-insure to meet the minimum insurance
requirements of Articles 18.3.2 through 18.3.8 to the extent it
maintains a self-insurance program; provided that, such Party's
senior secured debt is rated at investment grade or better by
Standard & Poor's and that its self-insurance program meets the
minimum insurance requirements of Articles 18.3.2 through 18.3.8.
For any period of time that a Party's senior secured debt is unrated
by Standard & Poor's or is rated at less than investment grade by
Standard & Poor's, such Party shall comply with the insurance
requirements applicable to it under Articles 18.3.2 through 18.3.9.
In the event that a Party is permitted to self-insure pursuant to
this article, it shall notify the other Party that it meets the
requirements to self-insure and that its self-insurance program meets
the minimum insurance requirements in a manner consistent with that
specified in Article 18.3.9.
18.3.11 The Parties agree to
report to each other in writing as soon as practical all accidents or
occurrences resulting in injuries to any person, including death, and
any property damage arising out of this LGIA.
Article 19. Assignment
19.1 Assignment. This LGIA may be
assigned by either Party only with the written consent of the other;
provided that either Party may assign this LGIA without the consent
of the other Party to any Affiliate of the assigning Party with an
equal or greater credit rating and with the legal authority and
operational ability to satisfy the obligations of the assigning Party
under this LGIA; and provided further that Interconnection Customer
shall have the right to assign this LGIA, without the consent of
Transmission Provider, for collateral security purposes to aid in
providing financing for the Large Generating Facility, provided that
Interconnection Customer will promptly notify Transmission Provider
of any such assignment. Any financing arrangement entered into by
Interconnection Customer pursuant to this article will provide that
prior to or upon the exercise of the secured party's, trustee's or
mortgagee's assignment rights pursuant to said arrangement, the
secured creditor, the trustee or mortgagee will notify Transmission
Provider of the date and particulars of any such exercise of
assignment right(s), including providing the Transmission Provider
with proof that it meets the requirements of Articles 11.5 and 18.3.
Any attempted assignment that violates this article is void and
ineffective. Any assignment under this LGIA shall not relieve a
Party of its obligations, nor shall a Party's obligations be
enlarged, in whole or in part, by reason thereof. Where required,
consent to assignment will not be unreasonably withheld, conditioned
or delayed.
Article 20. Severability
20.1 Severability. If any
provision in this LGIA is finally determined to be invalid, void or
unenforceable by any court or other Governmental Authority having
jurisdiction, such determination shall not invalidate, void or make
unenforceable any other provision, agreement or covenant of this
LGIA; provided that if Interconnection Customer (or any third party,
but only if such third party is not acting at the direction of
Transmission Provider) seeks and obtains such a final determination
with respect to any provision of the Alternate Option (Article
5.1.2), or the Negotiated Option (Article 5.1.4), then none of these
provisions shall thereafter have any force or effect and the Parties'
rights and obligations shall be governed solely by the Standard
Option (Article 5.1.1).
Article 21. Comparability
21.1 Comparability. The Parties
will comply with all applicable comparability and code of conduct
laws, rules and regulations, as amended from time to time.
Article 22. Confidentiality
22.1 Confidentiality. Confidential
Information shall include, without limitation, all information
relating to a Party's technology, research and development, business
affairs, and pricing, and any information supplied by either of the
Parties to the other prior to the execution of this LGIA.
Information is Confidential Information only if it is clearly
designated or marked in writing as confidential on the face of the
document, or, if the information is conveyed orally or by inspection,
if the Party providing the information orally informs the Party
receiving the information that the information is confidential.
If requested by either Party, the other Party shall provide in
writing, the basis for asserting that the information referred to in
this Article 22 warrants confidential treatment, and the requesting
Party may disclose such writing to the appropriate Governmental
Authority. Each Party shall be responsible for the costs associated
with affording confidential treatment to its information.
22.1.1 Term. During the term of
this LGIA, and for a period of three (3) years after the expiration
or termination of this LGIA, except as otherwise provided in this
Article 22, each Party shall hold in confidence and shall not
disclose to any person Confidential Information.
22.1.2 Scope. Confidential
Information shall not include information that the receiving Party
can demonstrate: (1) is generally available to the public other than
as a result of a disclosure by the receiving Party; (2) was in the
lawful possession of the receiving Party on a non-confidential basis
before receiving it from the disclosing Party; (3) was supplied to
the receiving Party without restriction by a third party, who, to the
knowledge of the receiving Party after due inquiry, was under no
obligation to the disclosing Party to keep such information
confidential; (4) was independently developed by the receiving Party
without reference to Confidential Information of the disclosing
Party; (5) is, or becomes, publicly known, through no wrongful act or
omission of the receiving Party or Breach of this LGIA; or (6) is
required, in accordance with Article 22.1.7 of the LGIA, Order of
Disclosure, to be disclosed by any Governmental Authority or is
otherwise required to be disclosed by law or subpoena, or is
necessary in any legal proceeding establishing rights and obligations
under this LGIA. Information designated as Confidential Information
will no longer be deemed confidential if the Party that designated
the information as confidential notifies the other Party that it no
longer is confidential.
22.1.3 Release of Confidential Information. Neither
Party shall release or disclose Confidential Information to any other
person, except to its Affiliates (limited by the Standards of Conduct
requirements), subcontractors, employees, consultants, or to parties
who may be or considering providing financing to or equity
participation with Interconnection Customer, or to potential
purchasers or assignees of Interconnection Customer, on a
need-to-know basis in connection with this LGIA, unless such person
has first been advised of the confidentiality provisions of this
Article 22 and has agreed to comply with such provisions.
Notwithstanding the foregoing, a Party providing Confidential
Information to any person shall remain primarily responsible for any
release of Confidential Information in contravention of this Article
22.
22.1.4 Rights. Each Party
retains all rights, title, and interest in the Confidential
Information that each Party discloses to the other Party. The
disclosure by each Party to the other Party of Confidential
Information shall not be deemed a waiver by either Party or any other
person or entity of the right to protect the Confidential Information
from public disclosure.
22.1.5 No Warranties. By
providing Confidential Information, neither Party makes any
warranties or representations as to its accuracy or completeness. In
addition, by supplying Confidential Information, neither Party
obligates itself to provide any particular information or
Confidential Information to the other Party nor to enter into any
further agreements or proceed with any other relationship or joint
venture.
22.1.6 Standard of Care. Each
Party shall use at least the same standard of care to protect
Confidential Information it receives as it uses to protect its own
Confidential Information from unauthorized disclosure, publication or
dissemination. Each Party may use Confidential Information solely to
fulfill its obligations to the other Party under this LGIA or its
regulatory requirements.
22.1.7 Order of Disclosure. If a
court or a Government Authority or entity with the right, power, and
apparent authority to do so requests or requires either Party, by
subpoena, oral deposition, interrogatories, requests for production
of documents, administrative order, or otherwise, to disclose
Confidential Information, that Party shall provide the other Party
with prompt notice of such request(s) or requirement(s) so that the
other Party may seek an appropriate protective order or waive
compliance with the terms of this LGIA. Notwithstanding the absence
of a protective order or waiver, the Party may disclose such
Confidential Information which, in the opinion of its counsel, the
Party is legally compelled to disclose. Each Party will use
Reasonable Efforts to obtain reliable assurance that confidential
treatment will be accorded any Confidential Information so furnished.
22.1.8 Termination of Agreement. Upon
termination of this LGIA for any reason, each Party shall, within ten
(10) Calendar Days of receipt of a written request from the other
Party, use Reasonable Efforts to destroy, erase, or delete (with such
destruction, erasure, and deletion certified in writing to the other
Party) or return to the other Party, without retaining copies
thereof, any and all written or electronic Confidential Information
received from the other Party.
22.1.9 Remedies. The Parties
agree that monetary damages would be inadequate to compensate a Party
for the other Party's Breach of its obligations under this Article
22. Each Party accordingly agrees that the other Party shall be
entitled to equitable relief, by way of injunction or otherwise, if
the first Party Breaches or threatens to Breach its obligations under
this Article 22, which equitable relief shall be granted without bond
or proof of damages, and the receiving Party shall not plead in
defense that there would be an adequate remedy at law. Such remedy
shall not be deemed an exclusive remedy for the Breach of this
Article 22, but shall be in addition to all other remedies available
at law or in equity. The Parties further acknowledge and agree that
the covenants contained herein are necessary for the protection of
legitimate business interests and are reasonable in scope. No Party,
however, shall be liable for indirect, incidental, or consequential
or punitive damages of any nature or kind resulting from or arising
in connection with this Article 22.
22.1.10 Disclosure to FERC, its Staff, or a State. Notwithstanding
anything in this Article 22 to the contrary, and pursuant to 18 CFR
section 1b.20, if FERC or its staff, during the course of an
investigation or otherwise, requests information from one of the
Parties that is otherwise required to be maintained in confidence
pursuant to this LGIA, the Party shall provide the requested
information to FERC or its staff, within the time provided for in the
request for information. In providing the information to FERC or its
staff, the Party must, consistent with 18 CFR section 388.112,
request that the information be treated as confidential and
non-public by FERC and its staff and that the information be withheld
from public disclosure. Parties are prohibited from notifying the
other Party to this LGIA prior to the release of the Confidential
Information to FERC or its staff. The Party shall notify the other
Party to the LGIA when it is notified by FERC or its staff that a
request to release Confidential Information has been received by
FERC, at which time either of the Parties may respond before such
information would be made public, pursuant to 18 CFR section 388.112.
Requests from a state regulatory body conducting a confidential
investigation shall be treated in a similar manner if consistent with
the applicable state rules and regulations.
22.1.11 Subject to the exception
in Article 22.1.10, any information that a Party claims is
competitively sensitive, commercial or financial information under
this LGIA ("Confidential Information") shall not be
disclosed by the other Party to any person not employed or retained
by the other Party, except to the extent disclosure is (i) required
by law; (ii) reasonably deemed by the disclosing Party to be required
to be disclosed in connection with a dispute between or among the
Parties, or the defense of litigation or dispute; (iii) otherwise
permitted by consent of the other Party, such consent not to be
unreasonably withheld; or (iv) necessary to fulfill its obligations
under this LGIA or as a transmission service provider or a Control
Area operator including disclosing the Confidential Information to an
RTO or ISO or to a regional or national reliability organization.
The Party asserting confidentiality shall notify the other Party in
writing of the information it claims is confidential. Prior to any
disclosures of the other Party's Confidential Information under this
subparagraph, or if any third party or Governmental Authority makes
any request or demand for any of the information described in this
subparagraph, the disclosing Party agrees to promptly notify the
other Party in writing and agrees to assert confidentiality and
cooperate with the other Party in seeking to protect the Confidential
Information from public disclosure by confidentiality agreement,
protective order or other reasonable measures.
Article 23. Environmental Releases
23.1 Each Party shall notify the
other Party, first orally and then in writing, of the release of any
Hazardous Substances, any asbestos or lead abatement activities, or
any type of remediation activities related to the Large Generating
Facility or the Interconnection Facilities, each of which may
reasonably be expected to affect the other Party. The notifying
Party shall: (i) provide the notice as soon as practicable, provided
such Party makes a good faith effort to provide the notice no later
than twenty-four hours after such Party becomes aware of the
occurrence; and (ii) promptly furnish to the other Party copies of
any publicly available reports filed with any Governmental
Authorities addressing such events.
Article 24. Information Requirements
24.1 Information Acquisition. Transmission
Provider and Interconnection Customer shall submit specific
information regarding the electrical characteristics of their
respective facilities to each other as described below and in
accordance with Applicable Reliability Standards.
24.2 Information Submission by Transmission Provider. The
initial information submission by Transmission Provider shall occur
no later than one hundred eighty (180) Calendar Days prior to Trial
Operation and shall include Transmission System information necessary
to allow Interconnection Customer to select equipment and meet any
system protection and stability requirements, unless otherwise agreed
to by the Parties. On a monthly basis Transmission Provider shall
provide Interconnection Customer a status report on the construction
and installation of Transmission Provider's Interconnection
Facilities and Network Upgrades, including, but not limited to, the
following information: (1) progress to date; (2) a description of the
activities since the last report (3) a description of the action
items for the next period; and (4) the delivery status of equipment
ordered.
24.3 Updated Information Submission by Interconnection Customer. The
updated information submission by Interconnection Customer, including
manufacturer information, shall occur no later than one hundred
eighty (180) Calendar Days prior to the Trial Operation.
Interconnection Customer shall submit a completed copy of the Large
Generating Facility data requirements contained in Appendix 1 to the
LGIP. It shall also include any additional information provided to
Transmission Provider for the Feasibility and Facilities Study.
Information in this submission shall be the most current Large
Generating Facility design or expected performance data. Information
submitted for stability models shall be compatible with Transmission
Provider standard models. If there is no compatible model,
Interconnection Customer will work with a consultant mutually agreed
to by the Parties to develop and supply a standard model and
associated information.
If Interconnection Customer's data is materially different from what
was originally provided to Transmission Provider pursuant to the
Interconnection Study Agreement between Transmission Provider and
Interconnection Customer, then Transmission Provider will conduct
appropriate studies to determine the impact on Transmission Provider
Transmission System based on the actual data submitted pursuant to
this Article 24.3. The Interconnection Customer shall not begin
Trial Operation until such studies are completed.
24.4 Information Supplementation. Prior
to the Operation Date, the Parties shall supplement their information
submissions described above in this Article 24 with any and all
"as-built" Large Generating Facility information or
"as-tested" performance information that differs from the
initial submissions or, alternatively, written confirmation that no
such differences exist. The Interconnection Customer shall conduct
tests on the Large Generating Facility as required by Good Utility
Practice such as an open circuit "step voltage" test on the
Large Generating Facility to verify proper operation of the Large
Generating Facility's automatic voltage regulator.
Unless otherwise agreed, the test conditions shall include: (1) Large
Generating Facility at synchronous speed; (2) automatic voltage
regulator on and in voltage control mode; and (3) a five percent
change in Large Generating Facility terminal voltage initiated by a
change in the voltage regulators reference voltage. Interconnection
Customer shall provide validated test recordings showing the
responses of Large Generating Facility terminal and field voltages.
In the event that direct recordings of these voltages is impractical,
recordings of other voltages or currents that mirror the response of
the Large Generating Facility's terminal or field voltage are
acceptable if information necessary to translate these alternate
quantities to actual Large Generating Facility terminal or field
voltages is provided. Large Generating Facility testing shall be
conducted and results provided to Transmission Provider for each
individual generating unit in a station.
Subsequent to the Operation Date, Interconnection Customer shall
provide Transmission Provider any information changes due to
equipment replacement, repair, or adjustment. Transmission Provider
shall provide Interconnection Customer any information changes due to
equipment replacement, repair or adjustment in the directly connected
substation or any adjacent Transmission Provider-owned substation
that may affect Interconnection Customer's Interconnection Facilities
equipment ratings, protection or operating requirements. The Parties
shall provide such information no later than thirty (30) Calendar
Days after the date of the equipment replacement, repair or
adjustment.
Article 25. Information Access and Audit Rights
25.1 Information Access. Each
Party (the "disclosing Party") shall make available to the
other Party information that is in the possession of the disclosing
Party and is necessary in order for the other Party to: (i) verify
the costs incurred by the disclosing Party for which the other Party
is responsible under this LGIA; and
(ii) carry out its obligations and responsibilities under
this LGIA. The Parties shall not use such information for purposes
other than those set forth in this Article 25.1 and to enforce their
rights under this LGIA.
25.2 Reporting of Non-Force Majeure Events. Each
Party (the "notifying Party") shall notify the other Party
when the notifying Party becomes aware of its inability to comply
with the provisions of this LGIA for a reason other than a Force
Majeure event. The Parties agree to cooperate with each other and
provide necessary information regarding such inability to comply,
including the date, duration, reason for the inability to comply, and
corrective actions taken or planned to be taken with respect to such
inability to comply. Notwithstanding the foregoing, notification,
cooperation or information provided under this article shall not
entitle the Party receiving such notification to allege a cause for
anticipatory breach of this LGIA.
25.3 Audit Rights. Subject to the
requirements of confidentiality under Article 22 of this LGIA, each
Party shall have the right, during normal business hours, and upon
prior reasonable notice to the other Party, to audit at its own
expense the other Party's accounts and records pertaining to either
Party's performance or either Party's satisfaction of obligations
under this LGIA. Such audit rights shall include audits of the other
Party's costs, calculation of invoiced amounts, Transmission
Provider's efforts to allocate responsibility for the provision of
reactive support to the Transmission System, Transmission Provider's
efforts to allocate responsibility for interruption or reduction of
generation on the Transmission System, and each Party's actions in an
Emergency Condition. Any audit authorized by this article shall be
performed at the offices where such accounts and records are
maintained and shall be limited to those portions of such accounts
and records that relate to each Party's performance and satisfaction
of obligations under this LGIA. Each Party shall keep such accounts
and records for a period equivalent to the audit rights periods
described in Article 25.4.
25.4 Audit Rights Periods.
25.4.1 Audit Rights Period for Construction-Related Accounts and
Records. Accounts and records
related to the design, engineering, procurement, and construction of
Transmission Provider's Interconnection Facilities and Network
Upgrades shall be subject to audit for a period of twenty-four months
following Transmission Provider's issuance of a final invoice in
accordance with Article 12.2.
25.4.2 Audit Rights Period for All Other Accounts and Records.
Accounts and records related to
either Party's performance or satisfaction of all obligations under
this LGIA other than those described in Article 25.4.1 shall be
subject to audit as follows: (i) for an audit relating to cost
obligations, the applicable audit rights period shall be twenty-four
months after the auditing Party's receipt of an invoice giving rise
to such cost obligations; and (ii) for an audit relating to all other
obligations, the applicable audit rights period shall be twenty-four
months after the event for which the audit is sought.
25.5 Audit Results. If an audit by
a Party determines that an overpayment or an underpayment has
occurred, a notice of such overpayment or underpayment shall be given
to the other Party together with those records from the audit which
support such determination.
Article 26. Subcontractors
26.1 General. Nothing in this LGIA
shall prevent a Party from utilizing the services of any
subcontractor as it deems appropriate to perform its obligations
under this LGIA; provided, however, that each Party shall require its
subcontractors to comply with all applicable terms and conditions of
this LGIA in providing such services and each Party shall remain
primarily liable to the other Party for the performance of such
subcontractor.
26.2 Responsibility of Principal. The
creation of any subcontract relationship shall not relieve the hiring
Party of any of its obligations under this LGIA. The hiring Party
shall be fully responsible to the other Party for the acts or
omissions of any subcontractor the hiring Party hires as if no
subcontract had been made; provided, however, that in no event shall
Transmission Provider be liable for the actions or inactions of
Interconnection Customer or its subcontractors with respect to
obligations of Interconnection Customer under Article 5 of this LGIA.
Any applicable obligation imposed by this LGIA upon the hiring Party
shall be equally binding upon, and shall be construed as having
application to, any subcontractor of such Party.
26.3 No Limitation by Insurance. The
obligations under this Article 26 will not be limited in any way by
any limitation of subcontractor's insurance.
Article 27. Disputes
27.1 Submission. In the event
either Party has a dispute, or asserts a claim, that arises out of or
in connection with this LGIA or its performance, such Party (the
"disputing Party") shall provide the other Party with
written notice of the dispute or claim ("Notice of Dispute").
Such dispute or claim shall be referred to a designated senior
representative of each Party for resolution on an informal basis as
promptly as practicable after receipt of the Notice of Dispute by the
other Party. In the event the designated representatives are unable
to resolve the claim or dispute through unassisted or assisted
negotiations within thirty (30) Calendar Days of the other Party's
receipt of the Notice of Dispute, such claim or dispute may, upon
mutual agreement of the Parties, be submitted to arbitration and
resolved in accordance with the arbitration procedures set forth
below. In the event the Parties do not agree to submit such claim or
dispute to arbitration, each Party may exercise whatever rights and
remedies it may have in equity or at law consistent with the terms of
this LGIA.
27.2 External Arbitration Procedures. Any
arbitration initiated under this LGIA shall be conducted before a
single neutral arbitrator appointed by the Parties. If the Parties
fail to agree upon a single arbitrator within ten (10) Calendar Days
of the submission of the dispute to arbitration, each Party shall
choose one arbitrator who shall sit on a three-member arbitration
panel. The two arbitrators so chosen shall within twenty (20)
Calendar Days select a third arbitrator to chair the arbitration
panel. In either case, the arbitrators shall be knowledgeable in
electric utility matters, including electric transmission and bulk
power issues, and shall not have any current or past substantial
business or financial relationships with any party to the arbitration
(except prior arbitration). The arbitrator(s) shall provide each of
the Parties an opportunity to be heard and, except as otherwise
provided herein, shall conduct the arbitration in accordance with the
Commercial Arbitration Rules of the American Arbitration Association
("Arbitration Rules") and any applicable FERC regulations
or RTO rules; provided, however, in the event of a conflict between
the Arbitration Rules and the terms of this Article 27, the terms of
this Article 27 shall prevail.
27.3 Arbitration Decisions. Unless
otherwise agreed by the Parties, the arbitrator(s) shall render a
decision within ninety (90) Calendar Days of appointment and shall
notify the Parties in writing of such decision and the reasons
therefor. The arbitrator(s) shall be authorized only to interpret
and apply the provisions of this LGIA and shall have no power to
modify or change any provision of this Agreement in any manner. The
decision of the arbitrator(s) shall be final and binding upon the
Parties, and judgment on the award may be entered in any court having
jurisdiction. The decision of the arbitrator(s) may be appealed
solely on the grounds that the conduct of the arbitrator(s), or the
decision itself, violated the standards set forth in the Federal
Arbitration Act or the Administrative Dispute Resolution Act. The
final decision of the arbitrator must also be filed with FERC if it
affects jurisdictional rates, terms and conditions of service,
Interconnection Facilities, or Network Upgrades.
27.4 Costs. Each Party shall be
responsible for its own costs incurred during the arbitration process
and for the following costs, if applicable: (1) the cost of the
arbitrator chosen by the Party to sit on the three member panel and
one half of the cost of the third arbitrator chosen; or (2) one half
the cost of the single arbitrator jointly chosen by the Parties.
Article 28. Representations, Warranties, and Covenants
28.1 General. Each Party makes the
following representations, warranties and covenants:
28.1.1 Good Standing. Such
Party is duly organized, validly existing and in good standing under
the laws of the state in which it is organized, formed, or
incorporated, as applicable; that it is qualified to do business in
the state or states in which the Large Generating Facility,
Interconnection Facilities and Network Upgrades owned by such Party,
as applicable, are located; and that it has the corporate power and
authority to own its properties, to carry on its business as now
being conducted and to enter into this LGIA and carry out the
transactions contemplated hereby and perform and carry out all
covenants and obligations on its part to be performed under and
pursuant to this LGIA.
28.1.2 Authority. Such Party has
the right, power and authority to enter into this LGIA, to become a
Party hereto and to perform its obligations hereunder. This LGIA is
a legal, valid and binding obligation of such Party, enforceable
against such Party in accordance with its terms, except as the
enforceability thereof may be limited by applicable bankruptcy,
insolvency, reorganization or other similar laws affecting creditors'
rights generally and by general equitable principles (regardless of
whether enforceability is sought in a proceeding in equity or at
law).
28.1.3 No Conflict. The
execution, delivery and performance of this LGIA does not violate or
conflict with the organizational or formation documents, or bylaws or
operating agreement, of such Party, or any judgment, license, permit,
order, material agreement or instrument applicable to or binding upon
such Party or any of its assets.
28.1.4 Consent and Approval. Such
Party has sought or obtained, or, in accordance with this LGIA will
seek or obtain, each consent, approval, authorization, order, or
acceptance by any Governmental Authority in connection with the
execution, delivery and performance of this LGIA, and it will provide
to any Governmental Authority notice of any actions under this LGIA
that are required by Applicable Laws and Regulations.
Article 29. Joint Operating Committee
29.1 Joint Operating Committee. Except
in the case of ISOs and RTOs, Transmission Provider shall constitute
a Joint Operating Committee to coordinate operating and technical
considerations of Interconnection Service. At least six (6) months
prior to the expected Initial Synchronization Date, Interconnection
Customer and Transmission Provider shall each appoint one
representative and one alternate to the Joint Operating Committee.
Each Interconnection Customer shall notify Transmission Provider of
its appointment in writing. Such appointments may be changed at any
time by similar notice. The Joint Operating Committee shall meet as
necessary, but not less than once each calendar year, to carry out
the duties set forth herein. The Joint Operating Committee shall
hold a meeting at the request of either Party, at a time and place
agreed upon by the representatives. The Joint Operating Committee
shall perform all of its duties consistent with the provisions of
this LGIA. Each Party shall cooperate in providing to the Joint
Operating Committee all information required in the performance of
the Joint Operating Committee's duties. All decisions and
agreements, if any, made by the Joint Operating Committee, shall be
evidenced in writing. The duties of the Joint Operating Committee
shall include the following:
29.1.1 Establish data
requirements and operating record requirements.
29.1.2 Review the requirements,
standards, and procedures for data acquisition equipment, protective
equipment, and any other equipment or software.
29.1.3 Annually review the one
(1) year forecast of maintenance and planned outage schedules of
Transmission Provider's and Interconnection Customer's facilities at
the Point of Interconnection.
29.1.4 Coordinate the scheduling
of maintenance and planned outages on the Interconnection Facilities,
the Large Generating Facility and other facilities that impact the
normal operation of the interconnection of the Large Generating
Facility to the Transmission System.
29.1.5 Ensure that information is
being provided by each Party regarding equipment availability.
29.1.6 Perform such other duties
as may be conferred upon it by mutual agreement of the Parties.
Article 30. Miscellaneous
30.1 Binding Effect. This LGIA and
the rights and obligations hereof, shall be binding upon and shall
inure to the benefit of the successors and assigns of the Parties
hereto.
30.2 Conflicts. In the event of a
conflict between the body of this LGIA and any attachment, appendices
or exhibits hereto, the terms and provisions of the body of this LGIA
shall prevail and be deemed the final intent of the Parties.
30.3 Rules of Interpretation. This
LGIA, unless a clear contrary intention appears, shall be construed
and interpreted as follows: (1) the singular number includes the
plural number and vice versa; (2) reference to any person includes
such person's successors and assigns but, in the case of a Party,
only if such successors and assigns are permitted by this LGIA, and
reference to a person in a particular capacity excludes such person
in any other capacity or individually; (3) reference to any agreement
(including this LGIA), document, instrument or tariff means such
agreement, document, instrument, or tariff as amended or modified and
in effect from time to time in accordance with the terms thereof and,
if applicable, the terms hereof; (4) reference to any Applicable Laws
and Regulations means such Applicable Laws and Regulations as
amended, modified, codified, or reenacted, in whole or in part, and
in effect from time to time, including, if applicable, rules and
regulations promulgated thereunder; (5) unless expressly stated
otherwise, reference to any Article, Section or Appendix means such
Article of this LGIA or such Appendix to this LGIA, or such Section
to the LGIP or such Appendix to the LGIP, as the case may be; (6)
"hereunder", "hereof", "herein",
"hereto" and words of similar import shall be deemed
references to this LGIA as a whole and not to any particular Article
or other provision hereof or thereof; (7) "including" (and
with correlative meaning "include") means including without
limiting the generality of any description preceding such term; and
(8) relative to the determination of any period of time, "from"
means "from and including", "to" means "to
but excluding" and "through" means "through and
including".
30.4 Entire Agreement. This LGIA,
including all Appendices and Schedules attached hereto, constitutes
the entire agreement between the Parties with reference to the
subject matter hereof, and supersedes all prior and contemporaneous
understandings or agreements, oral or written, between the Parties
with respect to the subject matter of this LGIA. There are no other
agreements, representations, warranties, or covenants which
constitute any part of the consideration for, or any condition to,
either Party's compliance with its obligations under this LGIA.
30.5 No Third Party Beneficiaries. This
LGIA is not intended to and does not create rights, remedies, or
benefits of any character whatsoever in favor of any persons,
corporations, associations, or entities other than the Parties, and
the obligations herein assumed are solely for the use and benefit of
the Parties, their successors in interest and, where permitted, their
assigns.
30.6 Waiver. The failure of a
Party to this LGIA to insist, on any occasion, upon strict
performance of any provision of this LGIA will not be considered a
waiver of any obligation, right, or duty of, or imposed upon, such
Party.
Any waiver at any time by either Party of its rights with respect to
this LGIA shall not be deemed a continuing waiver or a waiver with
respect to any other failure to comply with any other obligation,
right, duty of this LGIA. Termination or Default of this LGIA for
any reason by Interconnection Customer shall not constitute a waiver
of Interconnection Customer's legal rights to obtain an
interconnection from Transmission Provider. Any waiver of this LGIA
shall, if requested, be provided in writing.
30.7 Headings. The descriptive
headings of the various Articles of this LGIA have been inserted for
convenience of reference only and are of no significance in the
interpretation or construction of this LGIA.
30.8 Multiple Counterparts. This
LGIA may be executed in two or more counterparts, each of which is
deemed an original but all constitute one and the same instrument.
30.9 Amendment. The Parties may by
mutual agreement amend this LGIA by a written instrument duly
executed by the Parties.
30.10 Modification by the Parties. The
Parties may by mutual agreement amend the Appendices to this LGIA by
a written instrument duly executed by the Parties. Such amendment
shall become effective and a part of this LGIA upon satisfaction of
all Applicable Laws and Regulations.
30.11 Reservation of Rights. Transmission
Provider shall have the right to make a unilateral filing with FERC
to modify this LGIA with respect to any rates, terms and conditions,
charges, classifications of service, rule or regulation under section
205 or any other applicable provision of the Federal Power Act and
FERC's rules and regulations thereunder, and Interconnection Customer
shall have the right to make a unilateral filing with FERC to modify
this LGIA pursuant to section 206 or any other applicable provision
of the Federal Power Act and FERC's rules and regulations thereunder;
provided that each Party shall have the right to protest any such
filing by the other Party and to participate fully in any proceeding
before FERC in which such modifications may be considered. Nothing
in this LGIA shall limit the rights of the Parties or of FERC under
sections 205 or 206 of the Federal Power Act and FERC's rules and
regulations thereunder, except to the extent that the Parties
otherwise mutually agree as provided herein.
30.12 No Partnership. This LGIA
shall not be interpreted or construed to create an association, joint
venture, agency relationship, or partnership between the Parties or
to impose any partnership obligation or partnership liability upon
either Party. Neither Party shall have any right, power or authority
to enter into any agreement or undertaking for, or act on behalf of,
or to act as or be an agent or representative of, or to otherwise
bind, the other Party.
IN WITNESS WHEREOF, the Parties have executed this LGIA in
duplicate originals, each of which shall constitute and be an
original effective Agreement between the Parties.
[Insert
name of Transmission Provider or Transmission Owner, if applicable]
By:
By: ______________________________
Title:
Title:
_____________________________
Date:
Date:
_____________________________
[Insert
name of Interconnection Customer]
By:
Title:
Date:
Appendix A to LGIA
Interconnection Facilities, Network Upgrades and Distribution
Upgrades
1.
Interconnection Facilities:
(a)
[insert Interconnection Customer's Interconnection Facilities]:
(b)
[insert Transmission Provider's Interconnection Facilities]:
2.
Network Upgrades:
(a)
[insert Stand Alone Network Upgrades]:
(b)
[insert Other Network Upgrades]:
3.
Distribution Upgrades:
Appendix B to LGIA
Milestones
Appendix C to LGIA
Interconnection Details
Appendix D to LGIA
Security Arrangements Details
Infrastructure
security of Transmission System equipment and operations and control
hardware and software is essential to ensure day-to-day Transmission
System reliability and operational security. FERC will expect all
Transmission Providers, market participants, and Interconnection
Customers interconnected to the Transmission System to comply with
the recommendations offered by the President's Critical
Infrastructure Protection Board and, eventually, best practice
recommendations from the electric reliability authority. All public
utilities will be expected to meet basic standards for system
infrastructure and operational security, including physical,
operational, and cyber-security practices.
Appendix E to LGIA
Commercial Operation Date
This
Appendix E is a part of the LGIA between Transmission Provider and
Interconnection Customer.
[Date]
[Transmission
Provider Address]
Re: _____________
Large Generating Facility
Dear
_______________:
On
[Date] [Interconnection Customer] has completed Trial Operation
of Unit No. ___. This letter confirms that [Interconnection
Customer] commenced Commercial Operation of Unit No. ___ at the Large
Generating Facility, effective as of [Date plus one day].
Thank
you.
[Signature]
[Interconnection
Customer Representative]
Appendix F to LGIA
Addresses for Delivery of Notices and Billings
Notices:.
Transmission
Provider:
[To
be supplied.]
Interconnection
Customer:
[To
be supplied.]
Billings
and Payments:
Transmission
Provider:
[To
be supplied.]
Interconnection
Customer:
[To
be supplied.]
Alternative
Forms of Delivery of Notices (telephone, facsimile or email):
Transmission
Provider:
[To
be supplied.]
Interconnection
Customer:
[To
be supplied.]
APPENDIX G
INTERCONNECTION REQUIREMENTS FOR A WIND GENERATING PLANT
Appendix G sets forth requirements and provisions specific to a wind
generating plant. All other requirements of this LGIA continue to
apply to wind generating plant interconnections.
A. Technical Standards Applicable to a Wind Generating
Plant
i. Low Voltage Ride-Through (LVRT) Capability
A wind generating plant shall be able to remain online during
voltage disturbances up to the time periods and associated voltage
levels set forth in the standard below. The LVRT standard provides
for a transition period standard and a post-transition period
standard.
Transition Period LVRT Standard
The transition period standard applies to wind generating plants
subject to FERC Order 661 that have either: (i) interconnection
agreements signed and filed with the Commission, filed with the
Commission in unexecuted form, or filed with the Commission as
non-conforming agreements between January 1, 2006 and December 31,
2006, with a scheduled in-service date no later than December 31,
2007, or (ii) wind
generating turbines subject to a wind turbine procurement contract
executed prior to December 31, 2005, for delivery through 2007.
1. Wind generating plants are required to remain in-service during
three-phase faults with normal clearing (which is a time period of
approximately 4 – 9 cycles) and single line to ground faults
with delayed clearing, and subsequent post-fault voltage recovery to
prefault voltage unless clearing the fault effectively disconnects
the generator from the system. The clearing time requirement for a
three-phase fault will be specific to the wind generating plant
substation location, as determined by and documented by the
transmission provider. The maximum clearing time the wind generating
plant shall be required to withstand for a three-phase fault shall be
9 cycles at a voltage as low as 0.15 p.u., as measured at the high
side of the wind generating plant step-up transformer (i.e.
the transformer that steps the voltage up to the transmission
interconnection voltage or “GSU”), after which, if the
fault remains following the location-specific normal clearing time
for three-phase faults, the wind generating plant may disconnect from
the transmission system.
2. This requirement does not apply to faults that would occur between
the wind generator terminals and the high side of the GSU or to
faults that would result in a voltage lower than 0.15 per unit on the
high side of the GSU serving the facility.
3. Wind generating plants may be tripped after the fault period if
this action is intended as part of a special protection system.
4. Wind generating plants may meet the LVRT requirements of this
standard by the performance of the generators or by installing
additional equipment (e.g., Static VAr Compensator, etc.)
within the wind generating plant or by a combination of generator
performance and additional equipment.
5. Existing individual generator units that are, or have been,
interconnected to the network at the same location at the effective
date of the Appendix G LVRT
Standard are exempt from meeting the Appendix G LVRT Standard for the
remaining life of the existing generation equipment. Existing
individual generator units that are replaced are required to meet the
Appendix G LVRT Standard.
Post-transition Period LVRT Standard
All wind generating plants subject to FERC Order No. 661 and not
covered by the transition period described above must meet the
following requirements:
1. Wind generating plants are required to remain in-service during
three-phase faults with normal clearing (which is a time period of
approximately 4 – 9 cycles) and single line to ground faults
with delayed clearing, and subsequent post-fault voltage recovery to
prefault voltage unless clearing the fault effectively disconnects
the generator from the system. The clearing time requirement for a
three-phase fault will be specific to the wind generating plant
substation location, as determined by and documented by the
transmission provider. The maximum clearing time the wind generating
plant shall be required to withstand for a three-phase fault shall be
9 cycles after which, if the fault remains following the
location-specific normal clearing time for three-phase faults, the
wind generating plant may disconnect from the transmission system. A
wind generating plant shall remain interconnected during such a fault
on the transmission system for a voltage level as low as zero volts,
as measured at the high voltage side of the wind GSU.
2. This requirement does not apply to faults that would occur between
the wind generator terminals and the high side of the GSU.
3. Wind generating plants may be tripped after the fault period if
this action is intended as part of a special protection system.
4. Wind generating plants may meet the LVRT requirements of this
standard by the performance of the generators or by installing
additional equipment (e.g., Static VAr Compensator) within the
wind generating plant or by a combination of generator performance
and additional equipment.
5. Existing individual generator units that are, or have been,
interconnected to the network at the same location at the effective
date of the Appendix G LVRT Standard are exempt from meeting the
Appendix G LVRT Standard for the remaining life of the existing
generation equipment. Existing individual generator units that are
replaced are required to meet the Appendix G LVRT Standard.
ii. Power Factor Design Criteria (Reactive Power)
The
following reactive power requirements apply only to a newly
interconnecting wind generating plant that has executed a Facilities
Study Agreement as of the effective date of the Final Rule
establishing the reactive power requirements for non-synchronous
generators in section 9.6.1 of this LGIA (Order No. 827). A wind
generating plant to which this provision applies shall maintain a
power factor within the range of 0.95 leading to 0.95 lagging,
measured at the Point of Interconnection as defined in this LGIA, if
the Transmission Provider’s System Impact Study shows that such
a requirement is necessary to ensure safety or reliability. The
power factor range standard can be met by using, for example, power
electronics designed to supply this level of reactive capability
(taking into account any limitations due to voltage level, real power
output, etc.) or fixed and switched capacitors if agreed to by the
Transmission Provider, or a combination of the two. The
Interconnection Customer shall not disable power factor equipment
while the wind plant is in operation. Wind plants shall also be able
to provide sufficient dynamic voltage support in lieu of the power
system stabilizer and automatic voltage regulation at the generator
excitation system if the System Impact Study shows this to be
required for system safety or reliability.
iii. Supervisory Control and Data Acquisition (SCADA)
Capability
The
wind plant shall provide SCADA capability to transmit data and
receive instructions from the Transmission Provider to protect system
reliability. The Transmission Provider and the wind plant
Interconnection Customer shall determine what SCADA information is
essential for the proposed wind plant, taking into account the size
of the plant and its characteristics, location, and importance in
maintaining generation resource adequacy and transmission system
reliability in its area.
File Type | application/vnd.openxmlformats-officedocument.wordprocessingml.document |
Author | Gretchen Kershaw |
File Modified | 0000-00-00 |
File Created | 2021-01-21 |