April 19, 2018
News Media Contact
Mary O’Driscoll | 202-502-8680
Docket Nos. RM17-2-000, RM17-8-000
Agenda Items: E-1, E-2

FERC Issues Final Rules to Improve Regional Market Transparency, Interconnections
The Federal Energy Regulatory Commission (FERC) today issued two final rules that will improve transparency in
organized electric power markets, and help make all electricity interconnections more effective and efficient.
Transparency Final Rule
The first final rule (E-1, RM17-2-000) addresses transparency regarding uplift payments, operator-initiated
commitments and transmission constraint penalty factors in organized electric power markets. It marks the last
generic action in the initial set of price formation topics FERC identified when the price formation inquiry began in
2014.
Uplift refers to a payment that a regional grid operator makes to a resource when market revenues are insufficient to
cover the resource’s operating costs. An operator-initiated commitment is a decision to start a resource made by a
market operator when the resource is not economic, but is needed to ensure reliability. A transmission constraint
penalty factor is the maximum price that the system will pay to re-dispatch resources before allowing power flow to
exceed a transmission element’s maximum operating level.
Today’s rule finds that market operators’ practices with respect to reporting uplift payments and operator-initiated
commitments, and their tariff provisions regarding transmission constraint penalty factors, are insufficiently
transparent and result in rates that are not just and reasonable.
To address those concerns, the rule requires regional market operators to report, on a monthly basis: total uplift
payments for each transmission zone, broken out by day and uplift category; total uplift payments to each resource;
and the commitment size, transmission zone, commitment reason, and commitment start time of each operatorinitiated commitment. The rule also requires regional market operators to include in their tariffs the transmission
constraint penalty factors used in their market software, the circumstances under which those factors can set
locational marginal prices, and any processes by which they can be changed.
The Commission withdrew from the final rule a proposal that each market operator that allocates the costs of realtime uplift to deviations allocate such costs only to those market participants whose transactions are reasonably
expected to have caused the costs. Commenters had raised substantial concerns about the applicability of the
proposed reforms to certain regional markets and whether certain regional markets could implement the proposed
reforms.
-more-

Generator Interconnection Procedures and Agreements Final Rule
The second final rule (E-2, RM17-8-000) addresses reform of generator interconnection procedures and agreements for
generators of more than 20 megawatts, and adopts reforms designed to improve certainty for interconnection
customers, promote informed interconnection decisions and enhance the interconnection process. This final rule
culminates an extensive process involving a large number of stakeholders and addresses systemic inefficiencies,
including those caused or exacerbated by changing market forces and by the emergence of new technologies.
Interconnection customers have voiced concerns around a variety of issues including the frequency of delays in the
interconnection study process, the lack of transparency and consistency of information in the process and the overall
time required for new generation to connect to the grid. Transmission providers have expressed concern that the
interconnection study process can be difficult to manage because some interconnection customers submit requests for
interconnection service associated with new generating facilities that the transmission providers maintain have little
chance of reaching commercial operation. The final rule’s transparency reforms should enhance the timeliness, clarity
and consistency of information which should improve interconnection customers’ ability to assess potential generation
projects, and would mitigate factors that lead to submission of interconnection requests for generation projects that
have little chance of reaching commercial operation. The final rule’s reforms to improve certainty for interconnection
customers and enhance the interconnection process provide opportunities to bring new generation online faster and
mitigate the construction of unnecessary upgrades through interconnection service alternatives.
R-18-15

(30)


File Typeapplication/pdf
File TitleFERC Issues Final Rules to Improve Regional Market Transparency, Interconnections
SubjectFERC Issues Final Rules to Improve Regional Market Transparency, Interconnections
AuthorFERC
File Modified2018-04-18
File Created2018-04-18

© 2024 OMB.report | Privacy Policy