Burden Calculation Tables

0659t14_calcs.xlsx

NSPS for Surface Coating of Large Appliances (40 CFR part 60, subpart SS) (Renewal)

Burden Calculation Tables

OMB: 2060-0108

Document [xlsx]
Download: xlsx | pdf

Overview

Table 1
Table 2
Capital & O&M
# Responses


Sheet 1: Table 1

Table 1: Annual Respondent Burden and Cost – NSPS for Surface Coating of Large Appliances (40 CFR Part 60, Subpart SS)
(Renewal)












BURDEN ITEM Person‑Hours per occurrence
(A)
Number of occurrences per year
(B)
Person‑Hours per respondent per year
(C=AxB)
(C)
Respondents per Year a
(D)
Technical Person Hours per Year
(E=CxD)
(E)
Managerial Person Hours per Year
(F=Ex0.05)
(F)
Clerical Person Hours per Year
(G=Ex0.10)
(G)
Annual Costs per Year b
(H)

Managerial
(per hour)
Technical
(per hour)
Clerical
(per hour)
1. Applications N/A







$147.40 $117.92 $57.02
2. Survey and Studies N/A










3. Reporting requirements











A. Familiarization with regulatory requirements 1 1 1 72 72 3.6 7.2 $9,431.02
Respondant Rates
(Source: United States Department of Labor, Bureau of Labor Statistics, June 2018, “Table 2. Civilian Workers, by occupational and industry group.”)
B. Required Activities








Labor Type Total Compensation ($/hr) Loaded Rate (Rate + 110%rate)
Initial Performance Tests 60 1 60 0 0 0 0 $0
Mgmt. $70.19 $147.40
Repeat Performance Tests 60 0.2 12 0 0 0 0 $0
Tech. $56.15 $117.92
C. Gather Existing Information See 3b







Cler. $27.15 $57.02
D. Write Report











Notification of Construction/ Reconstruction 2 1 2 0 0 0 0 $0



Notification of Initial Performance Test 2 1 2 0 0 0 0 $0



Notification of Actual Startup 2 1 2 0 0 0 0 $0



Report of Performance Test See 3b










Semiannual Report c 5 2 10 72 720 36 72 $94,310.24



Quarterly Excess Emissions Report and Semiannual Monitoring Systems Performance Report d 4 2 8 15 120 6 12 $15,718.37



Subtotal for Reporting Requirements



1,049 $119,460



4. Recordkeeping requirements




A. Familiarization with regulatory requirements See 3b










B. Plan activities See 3b










C. Implement activities











Monthly Performance Test e 1 12 12 72 864 43.2 86.4 $113,172.29



D. Develop record system N/A










Records of Operating Parameter f 0.25 250 62.5 72 4500 225 450 $589,439.03



Subtotal for Recordkeeping Requirements



6,169 $702,611



TOTAL LABOR BURDEN AND COST (rounded)g



7,220 $822,000



TOTAL CAPITAL AND O&M COST (rounded)g




$8,400



GRAND TOTAL (rounded)g




$830,000
















Assumptions:











a We have assumed that there are approximately 72 existing sources currently subject to this rule, with no additional new sources becoming subject to the rule over the three-year period of this ICR.



b This ICR uses the following labor rates: $147.40 per hour for Executive, Administrative, and Managerial labor; $117.92 per hour for Technical labor, and $57.02 per hour for Clerical labor. These rates are from the United States Department of Labor, Bureau of Labor Statistics, June 2018, “Table 2. Civilian Workers, by Occupational and Industry group.” The rates are from “column 1, Total Compensation." The rates have been increased by 110% to account for the benefit packages available to those employed by private industry.



c We have assumed that each respondent will take 5 hours twice per year to complete the semiannual report.



d We have assumed that 15 respondents will take 4 hours twice per year to write the excess emission report and temperature variance report. We have assumed that 20 percent of respondents (0.20*72=14.4 facilities) will exceed the emission standard in 40 CFR 60.452 at least once in each of two quarterly reporting periods, so will be required to write the quarterly excess emission report in 40 CFR 60.455(b) twice per year. We have assumed that 5% of respondents (i.e., 0.05*72=4 facilities) use incineration, and that 20% of these 4 respondents with incineration (0.20*4=0.8) will exceed their temperature limit during both 6-month periods of each year, so will be required to prepare semiannual monitoring exceedance reports twice per year under 40 CFR 60.455(c). (14.4 respondents + 0.8 respondents =15 respondents)



e We have assumed that each respondent will take one hour once per month to record the monthly performance test.



f We have assumed that each respondent will take 0.25 hours 250 times per year to record operating parameter.



g Totals have been rounded to 3 significant figures. Figures may not add exactly due to rounding.




Sheet 2: Table 2

Table 2: Average Annual EPA Burden and Cost – NSPS for Surface Coating of Large Appliances (40 CFR Part 60, Subpart SS) (Renewal)











Activity EPA Hours per Occurrence
(A)
Number of occurrences per year
(B)
EPA Person Hours per Year
(C=AxB)
(C)
Respondents per Year
(D) a
Technical Person Hours per Year
(E=CxD)
(E)
Managerial Person Hours per Year
(F=Ex0.05)
(F)
Clerical Person Hours per Year
(G=Ex0.10)
(G)
Annual Costs ($/year) b
(H)

Managerial
(per hour)
Technical
(per hour)
Clerical
(per hour)
Required activities








$65.71 $48.75 $26.38
Initial performance test 24 1 24 0 0 0 0 $0.00



Repeat performance test 24 0.2 4.8 0 0 0 0 $0.00
Agency Rates
Source: Office of Personnel Management (OPM), 2018 General Schedule
Report review









Hourly Mean Wage With Fringe & Overhead
Notification of Construction/ Reconstruction 2 1 2 0 0 0 0 $0.00
(GS- 12, step 1) - Tech. 30.47 $48.75
Notification of Actual Startup 0.5 1 0.5 0 0 0 0 $0.00
(GS- 13, step 5) - Mgmt. 41.07 $65.71
Notification of Initial Performance Test 0.5 1 0.5 0 0 0 0 $0.00
(GS-6, step 3) - Cler. 16.49 $26.38
Performance Test Results 8 1.2 9.6 0 0 0 0 $0.00



Semiannual Reports c 2 2 4 72 288 14.4 28.8 $15,746.69



Quarterly Excess Emissions Report and Semiannual Monitoring Systems Performance Report e 2 2 4 15 60 3 6 $3,280.56



TOTAL ANNUAL BURDEN AND COST (rounded) e



400 $19,000
















Assumptions:











a We have assumed that there are approximately 72 existing sources currently subject to this rule. There will be no additional new sources that will become subject to the rule over the three-year period of this ICR.



b This cost is based on the following labor rates: Managerial rate of $65.71 (GS-13, Step 5, $41.07 + 60%), Technical rate of $48.75 (GS-12, Step 1, $30.47 + 60%), and Clerical rate of $26.38 (GS-6, Step 3, $16.49 + 60%). The rates have been increased by 60 percent to account for the benefit packages available to government employees. These rates are from the Office of Personnel Management (OPM), 2018 General Schedule, which excludes locality rates of pay.



c We have assumed that EPA will take two hours twice per year to review semiannual reports.



d We have assumed that EPA will take 2 hours twice per year to review quarterly excess emissions and semiannual monitoring systems performance reports. We have assumed that 20 percent of respondents (0.20*72=14.4 facilities) will exceed the emission standard in 40 CFR 60.452 once per 6-month reporting period and be required to write the excess emission report in 40 CFR 60.455(b) twice per year. We have assumed that 5% of respondents (i.e., 0.05*72=4 facilities) use incineration, and that 20% of these 4 respondents with incineration (0.20*4=0.8) will exceed their temperature limit during both 6-month periods of each year and be required to prepare semiannual monitoring exceedance report twice per year under 40 CFR 60.455(c). (14.4 respondents + 0.8 respondnents =15 respondents)



e Totals have been rounded to 3 significant figures. Figures may not add exactly due to rounding.




Sheet 3: Capital & O&M

Capital/Startup vs. Operation and Maintenance (O&M) Costs
(A)
Continuous Monitoring Device
(B)
Capital/Startup Cost for One Respondent
(C)
Number of New Respondents
(D)
Total Capital/Startup Cost
(B x C)
(E)
Annual O&M Costs for One Respondent
(F)
Number of Respondents with O&M a
(G)
Total O&M
(E x F)
Temperature 8,000 0 $0 $2,100 4 $8,400
a We are assuming that only 5% of facilities use incineration.

Sheet 4: # Responses

Total Annual Responses
(A) (B) (C) (D) (E)
Information Collection Activity Number of Respondents Number of Responses Number of Existing Respondents That Keep Records But Do Not Submit Reports Total Annual Responses
E=(BxC)+D
Notification of construction/ reconstruction 0 1 0 0
Notification of performance test 0 1 0 0
Notification of actual startup 0 1 0 0
Report of performance test 0 1.2 0 0
Semiannual report 72 2 0 144
Quarterly Excess Emissions Report and Semiannual Monitoring Systems Performance Report 15 2 0 30



Total 174





Total Respondent Hours: 7,217


Hours Per Response: 41


File Typeapplication/vnd.openxmlformats-officedocument.spreadsheetml.sheet
File Modified0000-00-00
File Created0000-00-00

© 2024 OMB.report | Privacy Policy