Table 1: Annual Respondent Burden and Cost – NESHAP for Paints and Allied Products Manufacturing Area Source Category (40 CFR Part 63, Subpart CCCCCCC) (Renewal)



































TECH 117.92

Burden Item (A) Hours
per occurrence
(B) No. of occurrences
per respondent
per year
(C) Hours
per respondent
per year (A x B)
(D) Respondents
per yeara
(E) Technical hours per year (C x D) (F) Management hours per year (E x 0.05) (G) Clerical hours per year (E x 0.1) (H) Total costs per year ($)b
MNG 147.4

1. Applications N/A







CLER 57.02

2. Survey and studies N/A










3. Acquisition, installation, and utilization of technical systems N/A










4. Reporting requirements











A. Familiarization with the regulatory requirement 2 1 2 22 44 2.2 4.4 $5,763.65



B. Required activities











Initial notificationc 1 1 1 0 0 0 0 $0



Notification of compliance statusc 1 1 1 0 0 0 0 $0



Annual compliance certificationd 1 1 1 22 22 1.10 2.2 $2,881.82



Report of exceedencesd 2 1 2 22 44 2.2 4.4 $5,763.65



C. Create information See 4B










D. Gather existing information See 4B










E. Write report See 4B










Reporting subtotal



127 $14,409.12



5. Recordkeeping requirements











A. Familiarization with the regulartory requirement See 4A










B. Plan activities See 5E










C. Implement activities See 5E










D. Develop record system See 5E










E. Time to enter information











Records of all information required by standards 0.25 1 0.25 219 54.8 2.74 5.48 $7,171.81



F. Time and cost to perform VE observatione 1 1 1 219 219 11.0 22 $102,052.25



G. Time to adjust existing ways to comply with previous applicable regulations N/A










H. Time to transmit or disclose information 0.25 1 0.25 219 54.8 2.74 5.48 $7,171.81



I. Time for audits N/A










Recordkeeping subtotal



378 $116,395.87



TOTAL ANNUAL BURDEN AND COSTS (rounded): f



500 $131,000



Capital and O&M Cost (see Section 6(b)(iii)):






$0



TOTAL COST: f






$131,000
1 hrs/response














Assumptions:











a We have assumed that there are 219 existing facilities that are subject to the rule, and that no new major sources per year will become subject over the 3 year-period of this ICR. We assume that 10 percent of foundries will be required to respond and will refamiliarize with the rule requirements each year.



b This ICR uses the following labor rates: Technical $117.92 ($56.15 + 110%); Managerial $147.40 ($70.19+ 110%); and Clerical $57.02 ($27.15 + 110%). These rates are from the United States Department of Labor, Bureau of Labor Statistics, June 2018, “Table 2. Civilian Workers, by occupational and industry group.” The rates are from column 1, “Total compensation.” The rates have been increased by 110 percent to account for the benefit packages available to those employed by private industry. This ICR assumes that Managerial hours are 5 percent of Technical hours, and Clerical hours are 10 percent of Technical hours.



c This burden item applies to new facilities only. No new facilities are expected over the three-year period of this ICR.



d This report does not need to be submitted unless a deviation from the requirements of this subpart has occurred. We estimate that 10 percent of the foundries will experience deviations.



e Cost includes $335 per facility to certify technical person in VE (EPA Method 9) testing.



f Totals have been rounded to 3 significant figures. Figures may not add exactly due to rounding.



Sheet 2: Agency

Table 2: Average Annual EPA Burden and Cost – NESHAP for Paints and Allied Products Manufacturing Area Source Category (40 CFR Part 63, Subpart CCCCCCC) (Renewal)
































TECH 48.75










MNG 65.71
Burden Item (A) EPA Hours per Occurrence (B) No. of occurrences
per plant
per year
(C) EPA hours
per plant
per year (A x B)
(D) Plants
per yeara
(E) EPA
technical hours
per year (C x D)
(F) EPA
managerial hours
per year (E x 0.05)
(G) EPA
clerical hours
per year (E x 0.1)
(H) Total cost
per yearb
($)

CLER 26.38
Report review










Initial notificationc 1 1 1 0 0 0 0 $0


Notification of compliance statusc 2 1 2 0 0 0 0 $0


Annual compliance certificationd 2 1 2 22 44 2.2 4.4 $2,405.63


Report of exceedanced 2 1 2 22 44 2.2 4.4 $2,405.63


TOTAL ANNUAL BURDEN e



100 $4,810


























Assumptions:










a We have assumed that there are 219 existing facilities that are subject to the rule, and that no new major sources per year will become subject over the 3 year-period of this ICR. We assume that 10 percent of foundries will be required to respond.


b This cost is based on the average hourly labor rate as follows: Technical $48.75 (GS-12, Step 1, $30.47 + 60%); Managerial $65.71 (GS-13, Step 5, $41.07 + 60%); and Clerical $26.38 (GS-6, Step 3, $16.49 + 60%). This ICR assumes that Managerial hours are 5 percent of Technical hours, and Clerical hours are 10 percent of Technical hours. These rates are from the OPM, 2018 General Schedule, which excludes locality rates of pay. The rates have been increased by 60 percent to account for the benefit packages available to government employees.


c This burden item applies to new facilities only. No new facilities are expected over the three-year period of this ICR.


d This report does not need to be submitted unless a deviation from the requirements of this subpart has occurred. We estimate that 10 percent of the foundries will experience deviations.


e Totals have been rounded to 3 significant figures. Figures may not add exactly due to rounding.