10 CFR Part 50, Domestic Licensing of Production and Utilization Facilities

ICR 201908-3150-002

OMB: 3150-0011

Federal Form Document

Forms and Documents
Document
Name
Status
Supplementary Document
2019-02-28
Supplementary Document
2019-02-28
Supporting Statement A
2019-04-26
IC Document Collections
ICR Details
3150-0011 201908-3150-002
Historical Active 201801-3150-004
NRC
10 CFR Part 50, Domestic Licensing of Production and Utilization Facilities
Revision of a currently approved collection   No
Regular
Approved without change 08/09/2019
Retrieve Notice of Action (NOA) 08/09/2019
OMB notes that these revisions are required by a forthcoming final rule (RIN 3150-AJ49) that has not yet published in the Federal Register. OMB preapproves the revised information collection, provided that there are no substantive changes in the published final rule relative to the draft final rule provided as a supplementary document in this package.
  Inventory as of this Action Requested Previously Approved
08/31/2021 06/30/2021 06/30/2021
43,678 0 43,623
3,731,355 0 3,708,530
272,036 0 269,617

MITIGATION OF BEYOND-DESIGN-BASIS EVENTS FINAL RULE The U.S. Nuclear Regulatory Commission (NRC) is amending its regulations to establish regulatory requirements to mitigate beyond-design-basis events. The information collection requirements associated with the rule include reviewing the rule provisions to ensure that current practices satisfy the requirements of the rule; maintaining records of procedures, and program changes. The NRC anticipates that some changes may be needed to procedures, programs, or plans.

PL: Pub.L. 83 - 703 68 Stat. 919 Name of Law: Atomic Energy Act of 1954
   PL: Pub.L. 109 - 58 119 Stat 594 Name of Law: Energy Policy Act of 2005
  
None

3150-AJ49 Final or interim final rulemaking 84 FR 39684 08/09/2019

No

1
IC Title Form No. Form Name
10 CFR Part 50, Domestic Licensing of Production and Utilization Facilities

  Total Approved Previously Approved Change Due to New Statute Change Due to Agency Discretion Change Due to Adjustment in Estimate Change Due to Potential Violation of the PRA
Annual Number of Responses 43,678 43,623 0 55 0 0
Annual Time Burden (Hours) 3,731,355 3,708,530 0 22,825 0 0
Annual Cost Burden (Dollars) 272,036 269,617 0 2,419 0 0
Yes
Changing Regulations
No
The estimated burden for the information collections associated with the MBDBE final rule is 22,825 hours. This estimate is composed of one-time and ongoing annual reporting and recordkeeping requirements. This increases the burden for Part 50 information collections from 3,708,530 hours to 3,731,355 hours. There is no increase in the number of responses to the Part 50 information collection, as the 55 recordkeepers are already keeping other records under this collection. The information collection requirements associated with the rule include reviewing the rule provisions to ensure that current practices satisfy the requirements of the rule; maintaining records of procedures, and program changes. The NRC anticipates that some changes may be needed to procedures, programs, or plans.

$65,369,702
No
    No
    No
No
No
No
Uncollected
Timothy Reed 3014151462 [email protected]

  No

On behalf of this Federal agency, I certify that the collection of information encompassed by this request complies with 5 CFR 1320.9 and the related provisions of 5 CFR 1320.8(b)(3).
The following is a summary of the topics, regarding the proposed collection of information, that the certification covers:
 
 
 
 
 
 
 
    (i) Why the information is being collected;
    (ii) Use of information;
    (iii) Burden estimate;
    (iv) Nature of response (voluntary, required for a benefit, or mandatory);
    (v) Nature and extent of confidentiality; and
    (vi) Need to display currently valid OMB control number;
 
 
 
If you are unable to certify compliance with any of these provisions, identify the item by leaving the box unchecked and explain the reason in the Supporting Statement.