Form 787 - Supplement A to Constrctn. Contract RUS Form 515

Form_787-SUPPLEMENT A-ToConstructn.Contract - RUS FORM515.pdf

The Rural eConnectivity Pilot Program ( ReConnect Program).

Form 787 - Supplement A to Constrctn. Contract RUS Form 515

OMB: 0572-0152

Document [pdf]
Download: pdf | pdf
According to the Paperwork Reduction Act of 1995, an agency may not conduct or sponsor, and a person is not required to respond to, a
collection of information unless it displays a valid 0MB control number. The valid 0MB control number for this information collection Is
0572-0059. The time required_ to complete this information collection is estimated to average 0.1 ofan hour per response, including the time for
rev1ewmg mstructtons, searchmg extstmg data sources, gathermg and mamtammg the data needed, and completing and reviewing the collection
oflnformalion.

SUPPLEMENT A TO CONSTRUCTION CONTRACT*
RUS FORM515
The Bidder agrees that the following provisions shall be a part of the Proposal to which this
Supplement is attached and shall supersede all provisions of the Proposal which are inconsistent
herewith:
1. The following Section 24 shall be added on Page 116:
24(a) The Bidder understands and agrees that, if this Proposal is accepted, the Owner shall
furnish to the Bidder the materials set forth in the attached "List of Owner's Materials
on Hand" and the Bidder will give a receipt therefore in writing to the Owner. The
Bidder further agrees, at its expense and on behalf of the Owner, to promptly
receive, unload, transport and handle all materials and equipment on the "List of
Materials Ordered by Owner but Not Delivered" when delivered and shall be
responsible for demurrage, if any, and will promptly forward to the Owner the
Bidder's receipt in writing for such materials. The materials referred to above are on
hand at, or will be delivered to, the locations specified in the attached Lists and the
Bidder will use such materials in constructing the Project.

(b)

The Contractor's Bond shall be in a penal sum of not less than the contract price,
which is the sum of all labor and materials including owner-furnished materials
covered by this Supplement A

(c) ] The references in the Construction Agreement to "materials," except in Article IV
Section 1 (0, Page 125, shall be understood to mean only materials to be furnished by
the Bidder.

(d)

The value of the completed Assembly Units certified to by the Bidder each month
pursuant to Article 111, Section I (a) Pages 121 and 122, of the Construction
Agreement shall be reduced by an amount equal to the value of the materials installed
by the Bidder during the preceding month which have been furnished by the Owner or
the delivery of which has been accepted by the Bidder on behalf of the Owner. Only
95 percent of the remainder shall be paid prior to the completion of the Project. The
value of such materials for the purpose of this Supplement shall be computed on the
basis of the unit prices stated in the attached Lists, and not on the Bidder's material
unit bid prices. Materials, if any, not required for the Project, which have been
furnished to the Bidder by the Owner or delivery of which has been accepted by the
Bidder on behalf of the Owner, shall be returned to the Owner by the Bidder upon
completion of the construction of the Project. The value of all materials not installed
in the Project or returned to the Owner shall be deducted from the final payment to
the Bidder.

*Insert Supplement A and Attachments immediately in front of the Proposed Summary Page 107 in the
�
Contractor's Proposal Section ofRUS Form 515
�
RUS Form 787 (Rev. 3-95)


File Typeapplication/pdf
File TitleRUS form 787
File Modified2017-08-22
File Created2017-08-22

© 2024 OMB.report | Privacy Policy