Implementation Plan
Implementation Plan
Project 2009-02 Real-time Reliability Monitoring and Analysis Capabilities
Requested Approvals
•
•
IRO-018-1 - Reliability Coordinator Real-time Reliability Monitoring and Analysis Capabilities
TOP-010-1 - Real-time Reliability Monitoring and Analysis Capabilities
Requested Retirements
•
None
Prerequisite Approval
•
None
Revisions to Defined Terms in the NERC Glossary
None
Applicable Entities
•
•
•
Reliability Coordinators
Transmission Operators
Balancing Authorities
Effective Date
IR O-018-1
• All Requirements shall become effective on the first day of the first calendar quarter that is 18
months after the date that this standard is approved by an applicable governmental authority or
as otherwise provided for in a jurisdiction where approval by an applicable governmental authority
is required for a standard to go into effect. Where approval by an applicable governmental
authority is not required, all Requirements shall become effective on the first day of the first
calendar quarter that is 18 months after the date this standard is adopted by the NERC Board of
Trustees or as otherwise provided for in that jurisdiction.
TOP-010-1
• All Requirements shall become effective on the first day of the first calendar quarter that is 18
months after the date that this standard is approved by an applicable governmental authority or
as otherwise provided for in a jurisdiction where approval by an applicable governmental authority
is required for a standard to go into effect. Where approval by an applicable governmental
authority is not required, all Requirements shall become effective on the first day of the first
calendar quarter that is 18 months after the date that this standard is adopted by the NERC Board
of Trustees or as otherwise provided for in that jurisdiction.