NSPS for Commercial and Industrial Solid Waste Incineration (CISWI) units (40 CFR part 60, subpart CCCC) (Renewal)

Burden calculations

OMB: 2060-0662

Document [xlsx]
Download: xlsx | pdf

Overview

Table 1
Table 2
O&M


Sheet 1: Table 1

Table 1: Annual Respondent Burden and Cost – NSPS for Commercial and Industrial Solid Waste Incineration (CISWI) Units (40 CFR Part 60, Subpart CCCC) (Renewal)















Burden Item (A) (B) (C) (D) (E) (F) (G) (H)


Respondent Hours per Occurrence Number of Occurrences Per Respondent Per Year Hours Per Respondent Per Year
(C=AxB)
Number of Respondents Per Year a Technical Hours Per Year
(E=CxD)
Management Hours Per Year
(F=Ex0.05)
Clerical Hours Per Year
(G=Ex0.1)
Total Labor Costs Per Year b


1. Applications N/A







Labor Rates
2. Surveys and Studies N/A







Management $141.06
3. Reporting Requirements








Technical $120.27
A. Familiarize with regulatory requirements c 1 1 1 11 11 0.55 1.1 $1,465.09
Clerical $58.67
B. Required Activities










1) Initial stack test and report (PM, dioxins/furans, opacity, HCl, Cd, Pb, Hg, CO, NOx, and SO2) See Capital/ Startup Costs 1






2) Annual stack test and test report (PM, HCl, Opacity, and Fugitive Ash) See O&M Costs 10






3) Operator training and qualification










a) Establish and teach operator qualification course d 64 1 64 1 64 3.2 6.4 $8,524.16


b) Obtain operator qualification d 72 1 72 1 72 3.6 7.2 $9,589.68


c) Annual refresher course 12 1 12 10 120 6 12 $15,982.80


d) Initial review of site-specific information See 3A









e) Annual review of site-specific information 8 1 8 10 80 4 8 $10,655.20


4) Establish operating parameters (maximum and minimum) d 40 1 40 1 40 2 4 $5,327.60


5) Continuous parameter monitoring (including CEMS)










a) Initial monitoring 17 1 17 1 17 0.85 1.7 $2,264.23


b) Annual monitoring 17 1 17 10 170 8.5 17 $22,642.30


C. Create Information See 3B









D. Gather Information See 3E









E. Report Preparation










1) Notification of initial performance test d










a) Pollutants, fugitive ash emissions 2 1 2 1 2 0.1 0.2 $266.38


b) Fugitive Ash Emissions 1 1 1 1 1 0.05 0.1 $133.19


2) Notification of initial CMS Demonstration d 2 1 2 1 2 0.1 0.2 $266.38


3) Report of initial performance test d










a) Pollutants, fugitive ash emissions 8 1 8 1 8 0.4 0.8 $1,065.52


b) Fugitive Ash Emissions 2 1 2 1 2 0.1 0.2 $266.38


4) Report of initial CMS demonstration See Capital/ Startup Costs

1






5) Report prior to construction (includes siting analysis) d 160 1 160 1 160 8 16 $21,310.40


6) Report prior to initial start-up d, e










a) Without site specific parameter petition 6 1 6 0.67 4 0.2 0.4 $532.76


b) With site specific parameter petition 14 1 14 0.33 4.7 0.23 0.47 $621.55


7) Report of initial stack test See 3B(1)









8) Report established values for site-specific operating parameters See 3B(4)









9) Waste management plan d 160 1 160 1 160 8 16 $21,310.40


10) Annual Report: Results of performance tests conducted during the year 40 1 40 10 400 20 40 $53,276.00


11) Notification for qualified operators that are off-site for more than 2 weeks f 8 2 16 1 16 0.8 1.6 $2,131.04


12) Status report for qualified operators that are off-site for more than 2 weeks f 8 2 16 1 16 0.8 1.6 $2,131.04


13) Semiannual report of emissions/parameter exceedances g 24 2 48 1.1 52.8 2.64 5.28 $7,032.43


Subtotal for Reporting Requirements



1,613 $186,795


4. Recordkeeping Requirements



A. Familiarize with regulatory requirements See 3A









B. Plan Activities See 3B









C. Implement Activities See 3B









D. Develop Record System N/A









E. Record Information










1) Records of operating parameters See 3B(5b)









2) Records of periods for which minimum amount of data on operating parameters were not obtained g 0.5 52 26 1.1 28.6 1.43 2.86 $3,809.23


3) Records of malfunction of the unit g 1.5 1 1.5 1.1 1.65 0.0825 0.165 $219.76


4) Records of exceedances of the operating parameters g 1.5 2 3 1.1 3.3 0.165 0.33 $439.53


5) Records of stack tests See 3E









6) Records of siting analysis See 3E









7) Records of persons who have reviewed operating procedures 1 1 1 11 11 0.55 1.1 $1,465.09


8) Records of persons who have completed operator training 1 1 1 11 11 0.55 1.1 $1,465.09


9) Records of persons who meet operator qualification criteria 1 1 1 11 11 0.55 1.1 $1,465.09


10) Records of monitoring device calibration See 3B









11) Records of site-specific documentation e 24 1 24 0.33 8 0.4 0.8 $1,065.52


F. Personnel Training See 3B









G. Time for Audits N/A









Subtotal for Recordkeeping Requirements



86 $9,929


Total Labor Burden and Costs (rounded) h



1,700 $197,000


Total Capital and O&M Cost (rounded) h






$769,000


Grand Total (rounded) h






$970,000














Assumptions:










a We assume there are 10 existing sources subject to the rule and 1 additional new source per year (one new respondent) will become subject to the rule during the three-year period of this ICR.


b This ICR uses the following labor rates for privately-owned sources: $141.06 for managerial, $120.27 for technical, and $58.67 for clerical labor. These rates are from the United States Department of Labor, Bureau of Labor Statistics, June 2019, “Table 2. Civilian Workers, by occupational and industry group.” The rates are from column 1, “Total compensation.” The rates have been increased by 110 percent to account for the benefit packages available to those employed by private industry.


c We assume that all sources will have to familiarize with the regulatory requirements each year.


d These are one-time only costs associated with the startup of a new source. We assume there will be 1 new respondent per year.


e We assume that one-third of the facilities will petition for site-specific parameters.


f We assume that 10 percent of the existing facilities would not have a qualified operator available for more than two weeks at least once a year (Note: each deviation requires 2 notifications, 1 for when the deviation occurs and 1 for when operation resumes). We also assume that each deviation will require only two status reports.


g We assume that 10 percent of all facilities (both new and existing) would have a malfunction or an exceedance during the year.


h Totals have been rounded to 3 significant figures. Figures may not add exactly due to rounding.



Sheet 2: Table 2

Table 2: Average Annual EPA Burden and Cost – NSPS for Commercial and Industrial Solid Waste Incineration (CISWI) Units (40 CFR Part 60, Subpart CCCC) (Renewal)















Burden Item (A) (B) (C) (D) (E) (F) (G) (H)


EPA Hours per Occurrence Number of Occurrences Per Respondent Per Year EPA Hours Per Respondent Per Year
(C=AxB)
Number of Respondents Per Year a Technical Hours Per Year
(E=CXD)
Management Hours Per Year
(F=Ex0.05)
Clerical Hours Per Year
(G=Ex0.1)
Total Costs, $ b


1. Applications N/A







Labor Rates
2. Familiarize with regulatory requirements 16 1 16 0 0 0 0 $0
Management $66.62
3. Required Activities








Technical $49.44
A. Observe initial stack tests (PM, dioxins/furans, opacity, HCl, Cd, Pb, Hg, CO, NOx, and SO2) c 48 1 48 0.2 9.6 0.48 0.96 $532
Clerical $26.75
B. Excess emissions -- Enforcement Activities d 24 1 24 1.1 26.4 1.32 2.64 $1,464


C. Create Information N/A









D. Gather Information N/A









E. Report Reviews










1) Review waste management plan and siting analysis e 8 1 8 1 8 0.4 0.8 $444


2) Review report submitted prior to initial startup e 2 1 2 1 2 0.1 0.2 $111


3) Review initial stack test report e 40 1 40 1 40 2 4 $2,218


4) Review annual compliance report 8 1 8 10 80 4 8 $4,436


5) Review semi-annual excess emission and parameter exceedance report d 16 1 16 1.1 17.6 0.88 1.76 $976


6) Review notifications and status reports for qualified operators off-site f 4 4 16 1 16 0.8 1.6 $887


F. Prepare annual summary report g 200 1 200 1 200 10 20 $11,089


TOTAL (rounded) h



460 $22,200














Assumptions:










a We assume there are 10 existing sources subject to the rule and 1 additional new source per year (one new respondent) will become subject to the rule during the three-year period of this ICR.


b This ICR uses the following labor rates: $66.62 for managerial, $49.44 for technical, and $26.75 for clerical labor. These rates are from the Office of Personnel Management (OPM), 2019 General Schedule, which excludes locality rates of pay. The rates have been increased by 60 percent to account for the benefit packages available to government employees.


c Assumes EPA personnel attend 20 percent of the stack tests. We estimate initial stack test observations will take 48 hours per plant.


d Assume that 10 percent of all facilities (both existing and new) have an exceedance during the year.


e These are one-time only costs associated with the startup of a new source. We assume there will be 1 new respondent per year.


f We assume that 10 percent of the existing facilities would not have a qualified operator available for more than two weeks at least once a year (Note: each deviation requires 2 notifications, 1 for when the deviation occurs and 1 for when operation resumes). We also assume that each deviation will require only two status reports.


g We assume that each state (i.e., 50 respondents) will take 4 hours to prepare an annual summary of progress for implementing state plans.


h Totals have been rounded to 3 significant figures. Figures may not add exactly due to rounding.



Sheet 3: O&M

Total Annual Responses



(A) (B) (C) (D) (E)



Information Collection Activity Number of Respondents Number of Responses Number of Existing Respondents That Keep Records But Do Not Submit Reports Total Annual Responses E=(BxC)+D



Report prior to construction (includes siting analysis) 1 1 0 1



Report prior to initial start-up 1 1 0 1



Notification of initial performance test 1 1 0 1



Notification of initial CMS Demonstration 1 1 0 1



Report of initial performance test 1 1 0 1



Report established values for site-specific operating parameters 1 1 0 1



Waste management plan 1 1 0 1



Annual Report a 10 1 0 10



Notification for qualified operators that are off-site for more than 2 weeks b 1 2 0 2



Status report for qualified operators that are off-site for more than 2 weeks b 1 2 0 2



Semiannual report of deviations: emissions/parameter exceedances c 1.1 2 0 2.2






Total 23



a We estimate 10 existing respondents have to submit annual reports.







b We assume that these activities will apply to 10 percent of existing facilities







c We assume that 10 percent of all facilities (both new and existing) would have a malfunction or an exceedance during the year.

























Number of Respondents



Respondents That Submit Reports Respondents That Do Not Submit Any Reports




(A) (B) (C) (D) (E)


Year Number of New Respondents 1 Number of Existing Respondents Number of Existing Respondents that keep records but do not submit reports Number of Existing Respondents That Are Also New Respondents Number of Respondents (E=A+B+C-D)


1 1 9 0 0 10


2 1 10 0 0 11


3 1 11 0 0 12


Average 1 10 0 0 11


New respondents include sources with constructed, reconstructed and modified affected facilities.


































Capital/Startup vs. Operation and Maintenance (O&M) Costs

(A) (B) (C) (D) (E) (F) (G)

Continuous Monitoring Device Capital/Startup Cost for One Respondent Number of New Respondents Total Capital/Startup Cost, (B X C) Annual O&M Costs for One Respondent Number of Respondents with O&M Total O&M,
(E X F)


Bag Leak Detectors $3,500 1 $3,500 $9,700 10 $97,000

CO CEMS $12,600 1 $12,600 $41,400 10 $414,000

ACI Monitors $0 1 $0 $4,200 10 $42,000

Stack Tests $55,000 1 $55,000 $14,533 10 $145,330

Postage for Performance Tests $7.50 1 $8 $7.50 10 $75

Postage for Semiannual Reports $0 0 $0 $15 1 $15



Total $71,100
Total a $698,000
$769,000
a Totals have been rounded to 3 significant figures. Figures may not add exactly due to rounding.

























Summary of Annual Respondent Burden and Cost – NSPS for Commercial and Industrial Solid Waste Incineration (CISWI) Units (40 CFR Part 60, Subpart CCCC) (Renewal)









Number of Respondents Number of Responses Reporting Hours Recordkeeping Hours Total Hours Labor Costs Non-Labor (Capital/Startup and O&M) Costs Total Costs Hours per Response
10 23 1,613 86 1,700 $197,000 $769,000 $970,000 73