Download:
pdf |
pdfPrint Form
U.S. Army Corps of Engineers (USACE)
CORPS WATER INFRASTRUCTURE FINANCING PROGRAM
PRELIMINARY APPLICATION
Save As
E-mail
OMB Control No. 0710-XXXX
Approval Expires:
The proponent agency is Headquarters USACE CECW.
DATA REQUIRED BY THE PRIVACY ACT OF 1974
Authority
Pub.L. 113 - 121 5001-5035, Water Resources Reform and Development Act of 2014; Water Infrastructure Finance and
Innovation Act of 2014 (WIFIA, 33 U.S.C. 3901 -3914).
Principal Purpose The preliminary application has four primary purposes: 1) validate the eligibility of the prospective borrower and the proposed
project, 2) perform a preliminary creditworthiness assessment, 3) perform a preliminary engineering and environmental feasibility
assessment, and 4) evaluate the project against the selection criteria and identify which projects USACE will invite to submit
applications. The preliminary application addresses the Corps Water Infrastructure Financing Program (CWIFP) eligibility criteria,
CWIFP selection criteria, and identifies other specific information that must be provided to USACE to be considered for credit
assistance. This serves to provide USACE with sufficient information to make a project selection and invite prospective borrowers
to submit applications.
Routine Uses
Information will be shared with the USACE CWIFP team to review and process the application. Personally Identifiable
Information will not be shared outside the USACE CWIFP team.
Disclosure
Voluntary, however incomplete submissions may delay or disqualify the project.
Introduction: Prospective borrowers seeking Water Infrastructure Finance and Innovation Act (WIFIA) credit assistance for water resource
infrastructure projects must complete and submit a CWIFP preliminary application to the U.S. Army Corps of Engineers (USACE). Based on the
information provided in the preliminary application, USACE will invite selected prospective borrowers to submit an application for CWIFP credit
assistance. USACE will only select those eligible projects that it expects to proceed to closing.
Purpose: The preliminary application has four primary purposes: 1) validate the eligibility of the prospective borrower and the proposed project, 2)
perform a preliminary creditworthiness assessment, 3) perform a preliminary engineering and environmental feasibility assessment, and 4) evaluate
the project against the selection criteria and identify which projects USACE will invite to submit applications. The preliminary application addresses the
CWIFP eligibility criteria, CWIFP selection criteria, and identifies other specific information that must be provided to USACE to be considered for credit
assistance. This serves to provide USACE with sufficient information to make a project selection and invite prospective borrowers to submit
applications.
Format: To be considered for CWIFP credit assistance, prospective borrowers must submit a preliminary application that describes: 1) the prospective
borrower and the plans for the proposed project(s); 2) the proposed financial plan; 3) the status of the reports and studies required for the project(s);
and 4) how the project meets the selection criteria of the CWIFP credit program. Please reference the latest Notice of Funding Availability (NOFA), the
CWIFP program guide, and frequently asked questions (FAQ) available at https://www.usace.army.mil/Missions/Civil-Works/Infrastructure/
revolutionize/CWIFP/ for additional instructions and information.
Responses to all of the questions should be included in this form. Upon completion, the total length of the preliminary application form should not
exceed 25 pages, excluding any attachments. Font size should not be smaller than 11-point Calibri.
Selection: Due to the wide variety of projects eligible for CWIFP assistance, in some cases USACE may request additional information to supplement
the preliminary application so it may complete its analysis. USACE will invite some eligible prospective borrowers to submit applications based on its
selection process.
Submission: Preliminary applications must be submitted to USACE by the deadline stated in the Notice of Funding Availability (NOFA). Source
documents may be draft or preliminary. Please provide the most recent version available at the time of submission.
The documents must be uploaded onto an external hard drive and mailed to the following street address: USACE CWIFP Team, CECW-I (3K87), 441
G Street NW Washington, DC 20314. Upon receipt, USACE will provide a confirmation notification. If prospective borrowers have questions on
completing this preliminary application, please consult the CWIFP website or contact the CWIFP office point of contact at
[email protected].
Confidential Business Information (CBI): An applicant may assert a business confidentiality claim covering part or all of the information submitted to
USACE as part of its application by providing a transmittal letter along with the application describing the proprietary information and the reason why it
is considered to be proprietary. The applicant may indicate the confidential information by placing (or attaching to) a cover sheet, stamped or typed
legend, or other suitable form of notice employing language such as trade secret, proprietary, or company confidential. The applicant should also state
whether it desires confidential treatment until a certain date or until the occurrence of a certain event. The applicant should be aware that USACE may
be required to disclose the confidential materials under the Freedom of Information Act. Otherwise, information that is not accompanied by a business
confidentiality claim when it is received by USACE may be made available to the public by USACE without further notice to the applicant.
More information about CBI is available in the CWIFP handbook and frequently asked questions (FAQ) available at https://www.usace.army.mil/
Missions/Civil-Works/Infrastructure/revolutionize/CWIFP
Agency Disclosure Notice: The public reporting burden for this collection of information, 0710-XXXX, is estimated to average 50 hours per response,
including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and
reviewing the collection of information. Send comments regarding the burden estimate or burden reduction suggestions to the Department of Defense,
Washington Headquarters Services, at [email protected]. Respondents should be aware that
notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not
display a currently valid OMB control number.
PLEASE DO NOT RETURN YOUR RESPONSE TO THE ABOVE ADDRESS. Responses should be sent to U.S. Army Corps of Engineers, 441 G.
Street N.W., Washington, D.C. 20314 Attn: CECW-I (3K87).
Warning: Falsification or misrepresentation of information or failure to file or report information required to be reported may be the basis for denial of
financial assistance by USACE. Knowing and willful falsification of information required to be submitted and false statements to a Federal Agency may
also subject you to criminal prosecution. See, for example, 18 U.S.C. §1001.
ENG FORM 6177, OCT 2020
PREVIOUS EDITIONS ARE OBSOLETE.
Page
1 of
9
Print Form
Save As
E-mail
Preliminary Application
Provide the following information in this form or as narrative answers. Narrative answers can reference source documents (include the name of the
document and relevant pages or sections). Provide any referenced documents as attachments.
I. Prospective Borrower Information
1. Legal Name:
2. Other Names:
3. Department and Division Name:
4. Business Street Address:
5. Mailing Street Address (if different from above):
6. Website:
7. Employer/Taxpayer Identification Number (EIN/TIN):
8. Dun and Bradstreet Data Universal Number System (DUNS) number:
9. Type of Project(s) (select all that apply):
Flood Damage Reduction
Hurricane and Storm Damage Reduction
Environmental Restoration
Coastal or Inland Harbor Navigation Improvement
Inland and Intracoastal Waterways Navigation Improvement
Acquisition of Real Property or Interest in Real Property
Other:
10. Type of Entity
Corporation
Partnership
Joint Venture
Trust
Federal, State, or Local Governmental Entity, Agency, or Instrumentality
Tribal Government or Consortium of Tribal Governments
State Infrastructure Finance Authority
11. Describe the organizational structure of the prospective borrower. If multiple parties are involved in the project's construction, maintenance,
and operation, describe the project's risk allocation framework.
ENG FORM 6177, OCT 2020
Page
2 of
9
Print Form
Save As
E-mail
12. On which date (month and year) is the prospective borrower able to submit a completed application?
13. On which date (month and year) is the prospective borrower planning to close on the CWIFP loan?
II: Project Plan
1. Project Name (for purposes of identification assign a short name to the project):
2. Project Website(s):
3. Brief Description of the Project:
4. Brief the Project Purpose
5. Project Location. Include a project map(s) for all project components:
6. Locality(s) (i.e., district, region, locale) project(s) will serve:
7. Estimated Population served by the project(s), if applicable:
8. Planned Project Delivery Method:
Design-Build
Design-Bid-Build
Design-Bid-Finance
Construction Manager At-Risk
Other:
9. Project Schedule
Project Name
ENG FORM 6177, OCT 2020
Planning
Design
Permitting
Construction
Page
3 of
9
Print Form
Save As
E-mail
11. Is this project Federally Authorized by Congress?
Yes
No
12. Is the project Federally Authorized by any Federal entity? If so, which agency?
13. as the prospective borrower consulted with any USACE Districts and/or Divisions offices? If so, provide the contact information for the project
manager and/or the regulatory point of contact.
14. Provide any analysis completed in support of the project(s) scope, cost, schedule, contingency plans, and status of project design (including a
consideration for cost overruns). Additionally, please provide any alternative analysis and the justification for selected approach. List referenced
documents below and provide as attachments.
15. Discuss issues that may affect the development and financing of the project(s) (e.g., community support, pending legislation, litigation, etc.)
16. Describe community outreach efforts conducted to date and planned for the project(s).
17. be the operation and maintenance of the project(s), including any contractual arrangements that may impact the operation of the project(s).
18. Describe authorizing actions (e.g., local vote, board vote, ordinance, etc.) that would need to occur to enter into a loan agreement with the
CWIFP.
ENG FORM 6177, OCT 2020
Page
4 of
9
Print Form
Save As
E-mail
19. Is the project currently undergoing, or has previously undergone, environmental review by a State or Federal agency?
a.
Yes If so, describe the status of the environmental review. Provide relevant environmental review documents as attachments.
b.
No
If not, describe any potential environmental impacts related to NEPA, NHPA Section 106, or ESA Section 103.
20. Describe the status of any permits and approvals that the project(s) may require.
Major Permits or Approvals Required
Approving Authority
Status
Expected Approval Date
III. Financing Plan
1. Complete the sources and uses of funds table for the construction period(s), including the requested CWIFP assistance.
Sources Category
Estimated Dollar Amount ($)
Percentage of Total (%)
Estimated Dollar Amount ($)
Percentage of Total (%)
1. CWIFP Loan
2. Revenue Bonds
3. Federal Grants
4. Other Federal Funding
5. State-Appropriated Funding
6. Borrower Cash
7. Other:
8. Other:
TOTAL SOURCES
Sources Category
1. Construction
2. Design
3. Planning
4. Land Acquisition
5. Other Capital Costs
6. Contingency
7. Total Capital Costs
8. Other:
9. Other:
10. Ineligible Costs (if applicable)
TOTAL USES
ENG FORM 6177, OCT 2020
Page
5 of
9
Print Form
Save As
E-mail
2. Provide a narrative on the dedicated source of repayment for the CWIFP loan, including how the revenues are generated, historic receipts and
assumptions related to future growth.
3. Identify the sources of security for the CWIFP loan, addressing all sources of repayment, how such sources will be secured, the relationship
(lien priority) of the CWIFP loan to existing and future borrowings secured by the same source of repayment.
4. Provide any existing ratings on the security pledged for repayment of the CWIFP loan (if available) or a description of how the senior debt
obligations will garner an investment grade rating. Attach rating letters, if available.
5. Describe the availability and credit terms of the other project funding sources presented in the sources and uses of funds table requested under
Question 3 above.
6. Describe the requested terms of the CWIFP credit assistance, including:
a. Assumed disbursement period.
b. Whether interest will capitalize during construction.
c. Amortization structure (e.g., straight-line or sculpted).
d. Repayment term and maturity date (years).
e. State whether the CWIFP loan will be issued on a senior or subordinate lien.
f. Identify key covenants supporting credit quality (e.g., rate covenant).
ENG FORM 6177, OCT 2020
Page
6 of
9
Print Form
Save As
E-mail
7. Provide year-end audited financial statements for the past two years, as available as an attachment. If applicable, provide an additional two
years of financial statements for special backing entities.
8. Attach a summary financial pro forma which presents key revenue, expense, and debt repayment assumptions for the revenue pledged to repay
the CWIFP loan including ten forecast years and up to three years of historical data, as available. The pro forma should be provided in an
editable Microsoft Excel format, not in PDF or "values" format. The pro forma should include at a minimum the following:
a.
Sources of revenue.
b.
Operations and maintenance expenses.
c.
Dedicated source(s) of repayment.
d.
Capital expenditures.
e.
Debt service payments and reserve transfers, broken down by funding source and including the CWIFP credit assistance.
f.
Projected debt service coverage ratios for total existing debt and the CWIFP debt.
g.
The borrower's debt balances broken down by funding sources.
h.
Equity distributions, if applicable.
IV. Selection Criteria
For each selection criterion, provide a response explaining the extent to which the project seeking the CWIFP loan relates to the criterion.
1. National or Regional Significance
The extent to which the project is nationally or regionally significant, with respect to the generation of economic and public benefits, such as (1)
the reduction of flood risk, (2) the improvement of water quality and quantity, including aquifer recharge, (3) the restoration of degraded aquatic
ecosystem structures, and (4) the support of domestic and international commerce.
2.. Financing Plan
The extent to which the project financing plan includes public or private financing in addition to CWIFP credit assistance.
3. Readiness to Proceed
The likelihood that CWIFP credit assistance would enable the project to proceed at an earlier date than the project would otherwise be able to
proceed.
4. New or Innovative Approaches
The extent to which the project uses new or innovative approaches.
5. Required Budget Authority
The amount of budget authority required to fund the CWIFP Federal credit instrument.
6. Protection Against Extreme Weather Events and Protection of the Environment
The extent to which the project (1) protects against extreme weather event, such as floods or hurricanes, or (2) helps maintain or protect the
environment.
7. Serves Energy Exploration or Production Areas
The extent to which a project serves regions with significant energy exploration, development, or production areas.
8. Serves Regions with Water Resource Challenges
The extent to which a project serves regions with significant water resource challenges, including the need to address (1) water quantity
concerns related to groundwater, surface water, or other water sources, (2) significant flood risk, (3) water resource challenges identified in
existing regional, State, or multistate agreements, or (4) water resources with exceptional recreational value or ecological assistance.
9. Addresses Identified Priorities
The extent to which the project addresses identified municipal, State, or regional priorities.
10. Readiness to Proceed
The readiness of the project to proceed toward development, including a demonstration by the obligor that there is a reasonable expectation
that the contracting process for construction of the project can commence by not later than 90 days after the date on which a Federal credit
instrument is obligated for the project under CWIFP.
11. Reduction of Federal Assistance
The extent to which CWIFP credit assistance reduces the contribution of Federal assistance to the project.
ENG FORM 6177, OCT 2020
Page
7 of
9
Print Form
Save As
E-mail
12. Serves Economically Disadvantaged Communities
The extent to which the project serves economically disadvantaged communities, defined as communities where the median household income
is less than 80% of the State median household income.
13. Non-Federal Ownership, Operation, and Maintenance
The extent to which the project will be non-Federally owned, operated and maintained.
V. Contact Information
1. Primary point of contact
Name:
Title:
Organization:
Street Address:
City/State/Zip:
Phone:
E-mail:
2. Secondary point of contact
Name:
Title:
Organization:
Street Address:
City/State/Zip:
Phone:
E-mail:
VI. Federal Requirements
1. National Environmental Policy Act: The interested party acknowledges that any project receiving credit assistance under this program must
comply with all provisions of the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.)
2. American Iron and Steel: The interested party acknowledges that any project receiving credit assistance under this program for the
construction, alteration, maintenance, or repair of a project may only use iron and steel products produced in the United States and must
comply with all applicable guidance.
3. Prevailing Wages: The interested party acknowledges that all laborers and mechanics employed by contractors or subcontractors on projects
receiving credit assistance under this program shall be paid wages at rates not less than those prevailing for the same type of work on similar
construction in the immediate locality, as determined by the Secretary of Labor, in accordance with sections 3141-3144, 3146, and 3147 of Title
40 (Davis-Bacon wage rules).
4. Lobbying: Section 1352 of Title 31, United States Code provides that none of the funds appropriated by any Act of Congress may be expended
by a recipient of a contract, grant, loan, or cooperative agreement to pay any person for influencing or attempting to influence an officer or
employee of any Federal agency, a Member of Congress, or an employee of a Member of Congress in connection with the award or making of
a Federal contract, grant, loan, or cooperative agreement or the modification thereof. This provision is interpreted to include the use of
appropriated funds to influence or attempt to influence the selection for assistance under the CWIFP.
CWIFP interested parties must file a declaration: (a) with the submission of an application for CWIFP credit assistance; (b) upon receipt of
CWIFP credit assistance (unless the information contained in the declaration accompanying the CWIFP application has not materially
changed); and (c) at the end of each calendar quarter in which there occurs any event that materially affects the accuracy of the information
contained in any declaration previously filed in connection with the CWIFP credit assistance.
ENG FORM 6177, OCT 2020
Page
8 of
9
Print Form
Save As
E-mail
The undersigned certifies, to the best of his or her knowledge and belief, that:
1. No Federal appropriated funds have been paid or will be paid, by or on behalf of the undersigned, to any person for influencing or
attempting to influence an officer or employee of an agency, a Member of Congress, an officer or employee of Congress, or an
employee of a Member of Congress in connection with the awarding of any Federal contract, the making of any Federal grant, the
making of any Federal loan, the entering into of any cooperative agreement, and the extension, continuation, renewal, amendment, or
modification of any Federal contract, grant, loan, or cooperative agreement.
2. If any funds other than Federal appropriated funds have been paid or will be paid to any person for influencing or attempting to
influence an officer or employee of any agency, a Member of Congress, an officer or employee of Congress, or an employee of a
Member of Congress in connection with this Federal contract, grant, loan, or cooperative agreement, the undersigned shall complete
and submit Standard Form-LLL, “Disclosure Form to Report Lobbying,” in accordance with its instructions.
3. The undersigned shall require that the language of this certification be included in the award documents for all subawards at all tiers
(including subcontracts, subgrants, and contracts under grants, loans, and cooperative agreements) and that all subrecipients shall
certify and disclose accordingly.
This certification is a material representation of fact upon which reliance was placed when this transaction was made or entered into.
Submission of this certification is a prerequisite for making or entering into this transaction imposed by section 1352, title 31, U.S. Code.
Any person who fails to file the required certification shall be subject to a civil penalty of not less than $10,000 and not more than
$100,000 for each such failure.
5. Debarment: The undersigned further certifies that it is not currently, nor has it been in the preceding three years: 1) debarred, suspended, or
declared ineligible from participating in any Federal program; 2) formally proposed for debarment, with a final determination still pending; 3)
voluntarily excluded from participation in a Federal transaction; or 4) indicted, convicted, or had a civil judgment rendered against it for any of
the offenses listed in the Regulations Governing Debarment and Suspension (Governmentwide Nonprocurement Debarment and Suspension
Regulations: 2 C.F.R. Part 180 and Part 1532.
6. Default/Delinquency: The undersigned further certifies that neither it nor any of its subsidiaries or affiliates are currently in default or delinquent
on any debt or loans provided or guaranteed by the Federal Government.
7. Other Federal Requirements: The interested party acknowledges that it must comply with all other federal statutes and regulations, as
applicable.
8. Signature: By submitting this preliminary application, the undersigned certifies that the facts stated and the certifications and representations
made in this preliminary application are true, to the best of the interested party's knowledge and belief after due inquiry, and that the interested
party has not omitted any material facts. The undersigned is an authorized representative of the interested party.
Name:
Title:
Organization:
Street Address:
City/State/Zip:
Phone:
E-mail:
Name
ENG FORM 6177, OCT 2020
Date
Signature
Page
9 of
9
File Type | application/pdf |
File Title | CORPS WATER INFRASTRUCTURE FINANCING PROGRAM APPLICATION |
Subject | CORPS WATER INFRASTRUCTURE FINANCING PROGRAM APPLICATION |
Author | Darwin Chen |
File Modified | 2020-10-06 |
File Created | 2020-10-06 |