FERC-500, (Proposed Rule in RM20-21-000) Application for License/Relicense for Water Projects with More than 10 Megawatt (MW) Capacity

18 CFR 4.202

OMB: 1902-0058

Document [docx]
Download: docx | pdf

Electronic Code of Federal Regulations (eCFR) Page 1 of 1

ELECTRONIC CODE OF FEDERAL REGULATIONS

e-CFR data is current as of May 14, 2021

Title 18Chapter ISubchapter BPart 4Subpart L → §4.202

Title 18: Conservation of Power and Water Resources

PART 4—LICENSES, PERMITS, EXEMPTIONS, AND DETERMINATION OF

PROJECT COSTS

Subpart L—Application for Amendment of License

Shape1

§4.202 Alteration and extension of license.

  1. If it is determined that approval of the application for amendment of license would constitute a significant alteration of license pursuant to section 6 of the Act, 16 U.S.C. 799, public notice of such application shall be given at least 30 days prior to action upon the application.

  2. Any application for extension of time fixed in the license for commencement or completion of construction of project works must be filed with the Commission not less than three months prior to the date or dates so fixed.

[Order 184, 46 FR 55943, Nov. 13, 1981] Need assistance?

https://www.ecfr.gov/cgi-bin/text-idx?SID=e60079701f6cfdee05ccdc0714c061ca&mc=tru... 5/18/2021

File Typeapplication/vnd.openxmlformats-officedocument.wordprocessingml.document
File Titlehttps://www.ecfr.gov/cgi-bin/text-idx?SID=e60079701f6cfdee05ccd
Authorjnsed34
File Modified0000-00-00
File Created2021-06-15

© 2024 OMB.report | Privacy Policy