ANNUAL REPORTING REQUIREMENTS (Recurring Information Collection Requirements) |
||||||||
Supporting Statement Section | Rule Section | Description | Number of Respondents | Responses per Respondent | Total Number of Responses | Burden per Response | Total Annual Burden Hours | Total Cost @ $279/Hour |
2 | 50.33(a)-(d), (g), (j) | Early Site Permit application - general information | - | - | - | 360.0 | - | $- |
50.33(a)-(d), (j) | Standard Design Certification application - general information | 1.0 | 0.3 | 0.3 | 450.0 | 148.5 | $41,432 | |
50.33(a)-(d), (g), (j) | Combined OL application - general information | - | - | - | 2,700.0 | - | $- | |
50.33(a)-(d), (j) | Standard Design Approval application - general information | 1.0 | 0.3 | 0.3 | 450.0 | 148.5 | $41,432 | |
50.33(a)-(d), (j) | Manfacturing License application - general information | - | - | - | 450.0 | - | $- | |
50.33(a)-(d), (h), (j) | NPUF Construction Permit application - general information | - | - | - | 2,700.0 | - | $- | |
50.33(a)-(d), (h), (j) | NPUF Operating License application - general information | - | - | - | 2,700.0 | - | $- | |
50.33(a)-(d), (h)-(j) | Nuclear Power Plant Construction Permit application - general information | - | - | - | 2,700.0 | - | $- | |
50.33(a)-(d), (g)-(j) | Nuclear Power Plant Operating License application - technical information | - | - | - | 2,700.0 | - | $- | |
50.33(f) | Financial qualification information as requested by the Commission | - | - | - | 3,580.0 | - | $- | |
50.34 | NPUF Construction Permit application - general information (PSAR) | - | - | - | 14,000.0 | - | $- | |
50.34 | NPUF Operating License application - technical information (FSAR) | - | - | - | 7,000.0 | - | $- | |
50.34 | Nuclear Power Plant Construction Permit application - general information (PSAR) | - | - | - | 90,000.0 | - | $- | |
50.34 | Nuclear Power Plant Operating License application - technical information (FSAR) | - | - | - | 40,000.0 | - | $- | |
50.54(bb) | Decommissioned plants submit program for managing and funding irradiated fuel following permanent cessation of operation of the reactor | - | - | - | 250.0 | - | $- | |
50.59(c), 50.90, 50.91(a), (b) | License Amendments | 164.0 | 6.0 | 984.0 | 313.0 | 307,992.0 | $85,929,768 | |
50.59(c), 50.90, 50.91(a), (b) | License Amendments - Topical Reports | 15.0 | 1.0 | 15.0 | 400.0 | 6,000.0 | $1,674,000 | |
50.74 | Notification within 30 days of a change in status of a licensed reactor operator or senior operator. | 201.0 | 1.0 | 201.0 | 1.0 | 201.0 | $56,079 | |
50.80(b) | License Transfers | 8.0 | 1.0 | 8.0 | 540.0 | 4,320.0 | $1,205,280 | |
50.36,50.36A, 50.36B & Appendix I | Technical Specifications | 164.0 | 5.0 | 820.0 | 168.0 | 137,760.0 | $38,435,040 | |
50.36,50.36A, 50.36B, 50.36C & Appendix I | Technical Specifications - Risk Informed Completion Times (RICT) Program | 5.0 | 1.0 | 5.0 | 60.0 | 300.0 | $83,700 | |
50.34(c) & (d) & 50.54(p) - Burden covered under 10 CFR 73.67 approved by OMB under Clearance No. 3150-0151 | Physical security and safeguards contingency plans (operating power reactors) | - | 1.0 | - | 29.0 | - | $- | |
50.34(c) & (d) & 50.54(p) - Burden covered under 10 CFR 73.67 approved by OMB under Clearance No. 3150-0151 | Physical security and safeguards contingency plans (decommissioned/shutdown power reactors) | - | - | - | 29.0 | - | $- | |
50.34(c) & (d) & 50.54(p) - Burden covered under 10 CFR 73.67 approved by OMB under Clearance No. 3150-0151 | Physical security and safeguards contingency plans (nonpower reactors) | - | 1.0 | - | 29.0 | - | $- | |
50.35(b) | Periodic reports of the progress and results of research and development programs designed to resolve safety questions | - | - | - | 100.0 | - | $- | |
50.54(w)(3) | Annual report on the source of property and damage insurance | 118.0 | 1.0 | 118.0 | 4.0 | 472.0 | $131,688 | |
10 CFR 50.54(w)(4) | Cleanup plan outlining the steps and costs needed to complete decontamination and cleanup following an accident | - | - | - | 2,000.0 | - | $- | |
3 | 50.33(k) | Contents of applications | 1.0 | 1.0 | 1.0 | 200.0 | 200.0 | $55,800 |
50.75 | Decommissioning planning | 89.0 | 1.0 | 89.0 | 5.0 | 445.0 | $124,155 | |
50.82 | Termination of license | 5.0 | 1.0 | 5.0 | 680.0 | 3,400.0 | $948,600 | |
4 | 50.71(b)& Appendix C | Annual financial reporting | 60.0 | 1.0 | 60.0 | 1.0 | 60.0 | $16,740 |
50.76 | Submission of financial qualifications information within 75 days prior to ceasing to be an electric utility | - | - | - | 33.0 | - | $- | |
50.71(e) | Updated FSAR (operating reactors) | 51.0 | 1.0 | 51.0 | 900.0 | 45,900.0 | $12,806,100 | |
50.71(e) | Updated FSAR (power reactors that have ceased operating) | 16.0 | 1.0 | 16.0 | 225.0 | 3,600.0 | $1,004,400 | |
50.72 & 50.54(z) | Notification of Events | 120.0 | 2.0 | 240.0 | 1.00 | 240.0 | $66,960 | |
10 CFR Part 50, Appendix E, Paragraph E.9.d | Daily testing of the ENS system by the HOO, submission of voluntary reactor status and grid information | 91.0 | 365.0 | 33,215.0 | 0.083 | 2,757.0 | $769,203 | |
Appendix E, VI.1 Periodic Testing | Quarterly testing of Emergency Response Data System | 120.0 | 4.0 | 480.0 | 2.0 | 960.0 | $267,840 | |
Appendix E, VI.3 a&b | HW/SW changes affecting ERDS DPLs and communication | 9.0 | 1.0 | 9.0 | 4.0 | 36.0 | $10,044 | |
50.72(a) | Emergency Response Data System reports | 7.0 | 1.0 | 7.0 | 4.0 | 28.0 | $7,812 | |
50.70 | Team Inspections | 51.0 | 1.0 | 51.0 | 160.0 | 8,160.0 | $2,276,640 | |
50.70 | Other Inspections (e.g. Resident, Supplemental, Special and Infrequently Performed, Temporary Instructions, and Reactive) | 51.0 | 1.0 | 51.0 | 45.0 | 2,295.0 | $640,305 | |
50.69(g) | Submission of event report to submit a licensee event report for any event or condition that would have prevented RISC-1 and RISC-2 structures, systems, and components from performing a safety-significant function | 10.0 | 1.0 | 10.0 | 600.0 | 6,000.0 | $1,674,000 | |
5 | 50.54(cc) | Bankruptcy Notifications | - | - | - | 1.0 | - | $- |
50.55(e) | 48 hour notification (Design and Construction Deficiencies) | 2.0 | 1.0 | 2.0 | 10.0 | 20.0 | $5,580 | |
50.55(e) | 30-day reports (Design and Construction Deficiencies) | 2.0 | 1.0 | 2.0 | 70.0 | 140.0 | $39,060 | |
50.55(f), Appendices A & B | Quality Assurance reports (operating reactors) | 89.0 | 1.0 | 89.0 | 160.0 | 14,240.0 | $3,972,960 | |
50.55(f), Appendices A & B | Quality Assurance reports (reactors under construction) | 2.0 | 1.0 | 2.0 | 160.0 | 320.0 | $89,280 | |
50.55(f), Appendices A & B | Quality Assurance reports (Part 52 applicants) | 2.0 | 1.0 | 2.0 | 667.0 | 1,334.0 | $372,186 | |
50.55a(z) | Alternatives submitted by COLs | 2.0 | 1.0 | 2.0 | 230.0 | 460.0 | $128,340 | |
50.55a(z) | Alternatives submitted by Power Reactors | 89.0 | 3.0 | 267.0 | 230.0 | 61,410.0 | $17,133,390 | |
50.55a(z) | Alternatives submitted for I&C | 0.0 | 0.0 | - | 230.0 | - | $- | |
50.55a(z)(1) and 50.55a(z)(2) - Burden covered under 50.55a(z)(1) and 50.55a(z)(2), approved by OMB under Clearance No. 3150-0244 | Request for Alternatives (Online portal) | 89.0 | 2.4 | 218.0 | 230.0 | 50,140.0 | $13,989,060 | |
50.55a(f)(5) and (g)(5) | Relief requests | 89.0 | 2.0 | 178.0 | 230.0 | 40,940.0 | $11,422,260 | |
50.55a | Codes and Standards | 89.0 | 2.0 | 178.0 | 58.0 | 10,324.0 | $2,880,396 | |
50.59(c) and d | Power reactors - Reports changes in the facility, of changes in procedures, and of tests and experiments and to submit a report containing a brief description of any changes, tests, and experiments, including a summary of the evaluation of each | 118.0 | 1.0 | 118.0 | 380.0 | 44,840.0 | $12,510,360 | |
50.59(c) and d | Non-power reactors - Reports changes in the facility, of changes in procedures, and of tests and experiments and to submit a report containing a brief description of any changes, tests, and experiments, including a summary of the evaluation of each | 31.0 | 1.0 | 31.0 | 120.0 | 3,720.0 | $1,037,880 | |
Appendices G & H, 50.60 | Fracture Toughness | 22.0 | 1.0 | 22.0 | 102.0 | 2,244.0 | $626,076 | |
50.61 | Pressurized Thermal Shock | 4.0 | 1.0 | 4.0 | 24.0 | 96.0 | $26,784 | |
50.64(c)(1) | Unique purpose application for highly enriched uranium | 2.0 | 1.0 | 2.0 | 10.0 | 20.0 | $5,580 | |
50.64(c)(2)(i) | Highly enriched uranium - updated documentation | 4.0 | 1.0 | 4.0 | 10.0 | 40.0 | $11,160 | |
50.64(c)(2)(ii) | Highly enriched uranium - updated documentation | 4.0 | 1.0 | 4.0 | 10.0 | 40.0 | $11,160 | |
50.64(c)(2)(iii) | Highly enriched uranium, safety analyses | 3.0 | 1.0 | 3.0 | 333.3 | 1,000.0 | $279,000 | |
50.66 | Thermal Annealing | - | - | - | 6,400.0 | - | ||
6 | 50.12 | Exemptions | 30.0 | 1.0 | 30.0 | 360.0 | 10,800.0 | $3,013,200 |
7 | 50.34(i) | Part 50 applicants provide plans for implementing rule requirements in application | - | - | - | 300.0 | - | $- |
50.44(c) | Hydrogen Control Requirements | - | - | - | 203.0 | - | $- | |
50.46(a)(3)(ii) | Annual report of changes to change evaluation model | 104.0 | 1.0 | 104.0 | 20.0 | 2,080.0 | 580,320.0 | |
50.46(a)(3)(ii) | 30-day report of significant change or error to evaluation model | 52.0 | 1.0 | 52.0 | 20.0 | 1,040.0 | 290,160.0 | |
50.46, Appendix K | Realistic evaluation model submittal | 1.0 | 1.0 | 1.0 | 2,500.0 | 2,500.0 | 697,500.0 | |
50.46, Appendix K | Modified evaluation model submittal | 0.6 | 1.0 | 0.6 | 1,750.0 | 1,050.0 | 292,950.0 | |
50.46, Appendix K | Schedule for completing actions associated with 10 CFR 50 Appendix K and 10 CFR 50.46(b) | 1.6 | 1.0 | 1.6 | 16.0 | 25.6 | 7,142.4 | |
Appendix K, 50.46 | ECCS | 2.0 | - | 40.0 | - | - | ||
50.47, 50.54(q & t), Appendix E | Emergency plans (operating power reactors) | 57.0 | 25.0 | 1,425.0 | 81.0 | 115,425.0 | $32,203,575 | |
50.54(q)(4) | Submission of proposed changes that would reduce the effective of approved emergency plans (operating power reactors) | 12.0 | 1.0 | 12.0 | 40.0 | 480.0 | $133,920 | |
App. E.IV.F.2.a,b | Participation Exercise – exercise scenario submission | 28.5 | 1.0 | 28.5 | 40.0 | 1,140.0 | $318,060 | |
50.47, 50.54(q & t), Appendix E | Emergency plans (operating non-power reactors) | 31.0 | 10.0 | 310.0 | 2.0 | 620.0 | $172,980 | |
50.47, 50.54(q & t), Appendix E | Emergency plans (power reactor sites being decommissioned) | 29.0 | 15.0 | 435.0 | 34.0 | 14,790.0 | $4,126,410 | |
50.47, 50.54(q & t), Appendix E | Emergency plans (non-power reactors being decommissioned and possession only) | 4.0 | 5.0 | 20.0 | 1.0 | 20.0 | $5,580 | |
50.47, 50.54(q & t), Appendix E | Emergency Planning | 116.0 | 18.0 | 2,088.0 | 60.0 | 125,280.0 | $34,953,120 | |
Appendix S and 50.54(ff) | Earthquake Engineering Criteria, DC applicants | 1.0 | 1.0 | 1.0 | 155,000.0 | 155,000.0 | $43,245,000 | |
Appendix S and 50.54(ff) | Earthquake Engineering Criteria, Operating Reactors | 5.0 | 1.0 | 5.0 | 900.0 | 4,500.0 | $1,255,500 | |
Total | 164 | 42,078 | 1,197,502 | $334,102,946 |
ANNUAL RECORDKEEPING REQUIREMENTS (Recurring Information Collection Requirements) |
||||||
Supporting Statement Section | Section | Description | Number of Recordkeepers | Hours per Recordkeeper | Total Annual Burden Hours | Annual Cost @ $279/hr |
2 | 50.33(a)-(d), (g), (j) | Early Site Permits (records) | - | 13.0 | - | $- |
50.33(a)-(d), (j) | Standard Design Certification (records) | 1.0 | 16.5 | 16.5 | $4,587 | |
50.33(a)-(d), (g), (j) | Combined OL (records) | - | 99.0 | - | $192,654 | |
50.33(a)-(d), (j) | Standard Design Approval (records) | 1.0 | 16.5 | 16.5 | $13,761 | |
50.33(a)-(d), (j) | Manfacturing License (records) | - | 16.5 | - | $- | |
50.33(a)-(d), (h), (j) | NPUF Construction Permit (records) | - | 99.0 | - | $192,654 | |
50.33(a)-(d), (h), (j) | NPUF Operating License (records) | - | 99.0 | - | $27,522 | |
50.33(a)-(d), (h)-(j) | Nuclear Power Plant Construction Permit (records) | - | 99.0 | - | $137,610 | |
50.33(a)-(d), (g)-(j) | Nuclear Power Plant Operating License (records) | - | 99.0 | - | $27,522 | |
50.59(c), 50.90, 50.91(a), (b) | Records License Amendments | 164.0 | 192.0 | 31,488.0 | $8,785,152 | |
50.74 - Burden covered under 10 CFR 55.22 approved by OMB under Clearance No. 3150-0024 | Records of change in status of a licensed reactor operator or senior operator | - | - | - | $- | |
50.80(b) | License Transfers | 8.0 | 60.0 | 480.0 | $133,920 | |
50.36,50.36A, 50.36B & Appendix I | Technical Specifications (Operating power reactor) | 89.0 | 2080.0 | 185,120.0 | $51,648,480 | |
50.36,50.36A, 50.36B & Appendix I | Technical Specifications (operating NPUFs) | 31.0 | 80.0 | 2,480.0 | $691,920 | |
50.36,50.36A, 50.36B & Appendix I | Technical Specifications (shutdown power reactor) | 29.0 | 208.0 | 6,032.0 | $1,682,928 | |
3 | 50.75 | Decommissioning planning | 149.0 | 73.0 | 10,877.0 | $3,034,683 |
4 | 50.71(b)& Appendix C | Financial records | 60.0 | 0.1 | 6.0 | $1,674 |
50.71(e) | Records for updated FSAR (operating reactors) | 51.0 | 100.0 | 5,100.0 | $1,422,900 | |
50.71(e) | Records for updated FSAR (power reactors that have ceased operating) | 16.0 | 25.0 | 400.0 | $111,600 | |
50.72 & 50.54(z) | Notification of Events | 120.0 | 0.8 | 96.0 | $26,784 | |
Appendix E, VI.1 Periodic Testing | Quarterly testing of Emergency Response Data System | 120.0 | 0.2 | 24.0 | $6,696 | |
Appendix E, VI.3 a&b | HW/SW changes affecting ERDS DPLs and communication | 9.0 | 1.2 | 10.8 | $3,013 | |
50.72(a) | Emergency Data Response System | 7.0 | 0.4 | 2.8 | $781 | |
50.69 | Maintain processes to control the inspection, testing, and corrective actions for structures, systems, and components, other SSC records | 10.0 | 833.0 | 8,330.0 | $2,324,070 | |
50.69 (one-time implementation requirements) | After approval of application, perform evaluations of the significance of SSC functions (implementation for the alternative requirements of 10 CFR 50.69 - voluntary) | 16.0 | 920.0 | 14,720.0 | $4,106,880 | |
5 | 50.54(hh)(1) | Procedures for aircraft threat | 51.0 | 40.0 | 2,040.0 | $569,160 |
50.55(e) | Retention of evaluations, 50.55(e)(9)(ii) (Design and Construction Deficiencies) | 25.0 | 2.0 | 50.0 | $13,950 | |
50.55(f), Appendices A & B | Quality Assurance records (operating reactors, 4 reactors under construction, 1 ESP, 1 COL) | 104.0 | 10,000.0 | 1,040,000.0 | $290,160,000 | |
50.55(f), Appendices A & B | Quality Assurance records (shutdown reactors) | 29.0 | 2,500.0 | 72,500.0 | $20,227,500 | |
50.55a | Records related to Codes and Standards | 104.0 | 2,310.0 | 240,240.0 | $67,026,960 | |
50.59(c) and (d) | Power reactors - Records of changes in the facility, of changes in procedures, and of tests and experiments and to submit a report containing a brief description of any changes, tests, and experiments, including a summary of the evaluation of each | 118.0 | 100.0 | 11,800.0 | $3,292,200 | |
50.59(c) and (d) | Non-power reactors - Records of changes in the facility, of changes in procedures, and of tests and experiments and to submit a report containing a brief description of any changes, tests, and experiments, including a summary of the evaluation of each | 31.0 | 480.0 | 14,880.0 | $4,151,520 | |
Appendices G & H, 50.60 | Fracture Toughness | 22.0 | 11.0 | 242.0 | $67,518 | |
50.61 | Pressurized Thermal Shock | 4.0 | 216.0 | 864.0 | $241,056 | |
50.65 | Maintenance program records for operating plants | 89.0 | 4,315.0 | 384,035.0 | $107,145,765 | |
50.65 | Maintenance program records for shutdown plants | 29.0 | 128.0 | 3,712.0 | $1,035,648 | |
6 | 50.12 | Exemptions | 30.0 | 40.0 | 1,200.0 | $334,800 |
7 | 50.44(c) | Hydrogen Control Requirements | 89.0 | 1.0 | 89.0 | $24,831 |
50.47, 50.54(q & t), Appendix E | Emergency Planning Records for Operating Power Reactors | 114.0 | 1,090.0 | 124,260.0 | $34,668,540 | |
50.47, 50.54(q & t), Appendix E | Emergency Planning Records for Operating Non-Power Reactors | 31.0 | 589.0 | 18,259.0 | $5,094,261 | |
50.47, 50.54(q & t), Appendix E | Emergency Planning Records for Power Reactor Sites Being Decommissioned | 29.0 | 256.0 | 7,424.0 | $2,071,296 | |
50.47, 50.54(q & t), Appendix E | Emergency Planning Records for Non-Power Reactors Being Decommissioned and Possession Only | 4.0 | 4.0 | 16.0 | $4,464 | |
50.48 (c) | One-time transition of records for fire protection to NFPA 805 | - | - | - | $- | |
50.48, Appendix R | Fire Protection plan records | 118.0 | 84.0 | 9,912.0 | $2,765,448 | |
50.49(a),(d),(f) |
One-time environmental qualification (program establishment, qualification of equipment), annualized | 8.0 | 793.3 | 6,346.4 | $1,770,646 | |
50.49(d),(f),(j) |
Environmental Qualification | 89.0 | 2,080.0 | 185,120.0 | $51,648,480 | |
50.120(b) | Training & Qualification Records for Operating Reactors | 51.0 | 780.0 | 39,780.0 | $11,098,620 | |
50.120(b) | Training & Qualification Records for Applicants | - | 1,440.0 | - | $- | |
50.155(a)(1) | One-time Licensees review rule requirements and update procedures, programs, or plans | 17.0 | 315.0 | 5,355.0 | $1,494,045 | |
50.155(f) | Maintain documentation of changes in the implementation of requirements | 51.0 | 100.0 | 5,100.0 | $1,422,900 | |
Appendix J | Development and Ongoing Analyses & Maintenance of Performance Based Leakage Testing Program | 164.0 | 60.0 | 9,840.0 | $2,745,360 | |
Appendix S and 50.54(ff) | Earthquake Engineering Criteria, Operating Reactors | 5.0 | 100.0 | 500.0 | $139,500 | |
Appendix S and 50.54(ff) | Earthquake Engineering Criteria, DC applicants | 1.0 | 100.0 | 100.0 | $27,900 | |
Appendix S IV(a)(3) | Plant inspection and documentation of inspection following seismic event | 5.0 | 320.0 | 1,600.0 | $446,400 | |
Total | 164 | 2,450,464.0 | $683,679,456.00 |
ANNUAL 3rd PARTY DISCLOSURES (Recurring Information Collection Requirements) |
|||||||||
Supporting Statement Section | Section | Description | Number of Respondents | Responses per Respondent | Total Number of Responses | Burden per Response | Total Annual Burden Hours | Cost @ $279/Hour | (Notes) |
5 | 50.55a | Submission to ASME of Owner's certificate, AIA agreement (III/NCA-3230) | 2.0 | 1.0 | 2.0 | 100.0 | 200.0 | $55,800 | |
TOTAL | 2.0 | 200.0 | $55,800 |
Total Burden and Responses Section 2 | Total Burden and Responses Section 3 | Item #13, Other Costs Section | ||||||||||||
Hours | Responses | Hours | Responses | Section | Costs | |||||||||
Reporting | 457,342 | 2,152 | Reporting | 4,045 | 95 | 2 | $25,181 | |||||||
Recordkeeping | 225,633 | 164 | Recordkeeping | 10,877 | 149 | 3 | $1,214 | |||||||
TOTAL | 682,975 | 2,316 | TOTAL | 14,922 | 244 | 4 | $3,202 | |||||||
5 | $197,573 | |||||||||||||
6 | $134 | |||||||||||||
Item #13, Other Costs Section 2 | Item #13, Other Costs Section 3 | 7 | $46,169 | |||||||||||
Recordkeeping | $25,181 | Recordkeeping | $1,214 | Total | $273,472 | |||||||||
TOTAL | $25,181 | TOTAL | $1,214 | |||||||||||
Item #14, Costs to the Federal Government, | ||||||||||||||
Item #14, Costs to the Federal Government, Section 2 | Item #14, Costs to the Federal Government, Section 3 | Section | Staff Time Hours | Cost @ $279/hr | ||||||||||
Hours | Cost @ $279/hr | Hours | Cost @ $279/hr | |||||||||||
Staff time | 101953 | $28,444,887 | Staff time | 1526 | $425,754 | 2 | 101,953 | $28,444,887 | ||||||
3 | 1,526 | $425,754 | ||||||||||||
4 | 41,295 | $11,521,305 | ||||||||||||
Total Burden and Responses Section 4 | 5 | 73,115 | $20,399,085 | |||||||||||
Hours | Responses | Total Burden and Responses Section 5 | 6 | 2,250 | $627,750 | |||||||||
Reporting | 70,036 | 34,190 | Hours | Responses | 7 | 20,275 | $5,656,725 | |||||||
Recordkeeping | 28,690 | 120 | Reporting | 231,328 | 1,128 | Total | 240,414 | $67,075,506 | ||||||
TOTAL | 98,726 | 34,310 | Recordkeeping | 1,770,363 | 118 | |||||||||
Third Party Disclosure | 200 | 2 | Burden Hours | |||||||||||
TOTAL | 2,001,891 | 1,248 | Section | Reporting | Recordkeeping | 3rd Party | Total | Cost | ||||||
Item #13, Other Costs Section 4 | ||||||||||||||
Recordkeeping | $3,202 | 2 | 457,342 | 225,633 | 682,975 | $190,550,025 | ||||||||
TOTAL | $3,202 | Item #13, Other Costs Section 5 | 3 | 4,045 | 10,877 | 14,922 | $4,163,238 | |||||||
Recordkeeping | $197,573 | 4 | 70,036 | 28,690 | 98,726 | $27,544,442 | ||||||||
TOTAL | $197,573 | 5 | 231,328 | 1,770,363 | 200 | 2,001,891 | $558,527,589 | |||||||
Item #14, Costs to the Federal Government, Section 4 | 6 | 10,800 | 1,200 | 12,000 | $3,348,000 | |||||||||
Hours | Cost @ $279/hr | 7 | 423,951 | 413,701 | 837,652 | $233,704,908 | ||||||||
Staff time | 41295 | $11,521,305 | Item #14, Costs to the Federal Government, Section 5 | Total | 1,197,502 | 2,450,464 | 200 | 3,648,166 | $1,017,838,202 | |||||
Hours | Cost @ $279/hr | Previous total | 1,148,086 | 2,562,696 | 100 | 3,710,881.7 | $975,961,887 | |||||||
Staff time | 73,115 | $20,399,085 | Deltas | 49,416 | -112,232 | 100 | -62,716 | -$17,497,792 | ||||||
Total Burden and Responses Section 6 | Total Burden and Responses Section 7 | |||||||||||||
Hours | Responses | Hours | Responses | Reponses | ||||||||||
Reporting | 10,800 | 30 | Reporting | 423,951 | 4,484 | Section | Reporting | Recordkeeping | 3rd Party | TOTAL | ||||
Recordkeeping | 1,200 | 30 | Recordkeeping | 413,701 | 164 | |||||||||
TOTAL | 12,000 | 60 | TOTAL | 837,652 | 4,648 | 2 | 2,152 | 164 | 2,316 | |||||
3 | 95 | 149 | 244 | |||||||||||
4 | 34,190 | 120 | 34,310 | |||||||||||
Item #13, Other Costs Section 6 | Item #13, Other Costs Section 7 | 5 | 1,128 | 118 | 2 | 1,248 | ||||||||
Recordkeeping | $134 | Recordkeeping | $46,169 | 6 | 30 | 30 | 60 | |||||||
TOTAL | $134 | TOTAL | $46,169 | 7 | 4,484 | 164 | 4,648 | |||||||
2021 TOTAL | 42,078 | 164 | 2 | 42,244 | ||||||||||
Previous total | 43,467 | 149 | 1 | 43,617 | ||||||||||
Item #14, Costs to the Federal Government, Section 6 | Item #14, Costs to the Federal Government, Section 7 | Deltas | -1,389 | 15 | 1 | -1,373 | ||||||||
Hours | Cost @ $279/hr | Hours | Cost @ $279/hr | |||||||||||
Staff time | 2,250 | $627,750 | Staff time | 20,275 | $5,656,725 | |||||||||
HOURS | RESPONSES | |||||||||||||
2021 | 3,648,166 | 42,244 | ||||||||||||
Previous | 3,710,882 | 43,617 | ||||||||||||
Delta | -62,716 | -1,373 |
File Type | application/vnd.openxmlformats-officedocument.spreadsheetml.sheet |
File Modified | 0000-00-00 |
File Created | 0000-00-00 |