Part 50 final burden spreadsheet

Part 50 Burden Spreadsheet.xlsx

10 CFR Part 50, Domestic Licensing of Production and Utilization Facilities

Part 50 final burden spreadsheet

OMB: 3150-0011

Document [xlsx]
Download: xlsx | pdf

Overview

Reporting
Recordkeeping
Third-Party Disclosure
Totals


Sheet 1: Reporting


ANNUAL REPORTING REQUIREMENTS
(Recurring Information Collection Requirements)
Supporting Statement Section Rule Section Description Number of Respondents Responses per Respondent Total Number of Responses Burden per Response Total Annual Burden Hours Total Cost @ $279/Hour
2 50.33(a)-(d), (g), (j) Early Site Permit application - general information - - - 360.0 - $-
50.33(a)-(d), (j) Standard Design Certification application - general information 1.0 0.3 0.3 450.0 148.5 $41,432
50.33(a)-(d), (g), (j) Combined OL application - general information - - - 2,700.0 - $-
50.33(a)-(d), (j) Standard Design Approval application - general information 1.0 0.3 0.3 450.0 148.5 $41,432
50.33(a)-(d), (j) Manfacturing License application - general information - - - 450.0 - $-
50.33(a)-(d), (h), (j) NPUF Construction Permit application - general information - - - 2,700.0 - $-
50.33(a)-(d), (h), (j) NPUF Operating License application - general information - - - 2,700.0 - $-
50.33(a)-(d), (h)-(j) Nuclear Power Plant Construction Permit application - general information - - - 2,700.0 - $-
50.33(a)-(d), (g)-(j) Nuclear Power Plant Operating License application - technical information - - - 2,700.0 - $-
50.33(f) Financial qualification information as requested by the Commission - - - 3,580.0 - $-
50.34 NPUF Construction Permit application - general information (PSAR) - - - 14,000.0 - $-
50.34 NPUF Operating License application - technical information (FSAR) - - - 7,000.0 - $-
50.34 Nuclear Power Plant Construction Permit application - general information (PSAR) - - - 90,000.0 - $-
50.34 Nuclear Power Plant Operating License application - technical information (FSAR) - - - 40,000.0 - $-
50.54(bb) Decommissioned plants submit program for managing and funding irradiated fuel following permanent cessation of operation of the reactor - - - 250.0 - $-
50.59(c), 50.90, 50.91(a), (b) License Amendments 164.0 6.0 984.0 313.0 307,992.0 $85,929,768
50.59(c), 50.90, 50.91(a), (b) License Amendments - Topical Reports 15.0 1.0 15.0 400.0 6,000.0 $1,674,000
50.74 Notification within 30 days of a change in status of a licensed reactor operator or senior operator. 201.0 1.0 201.0 1.0 201.0 $56,079
50.80(b) License Transfers 8.0 1.0 8.0 540.0 4,320.0 $1,205,280
50.36,50.36A, 50.36B & Appendix I Technical Specifications 164.0 5.0 820.0 168.0 137,760.0 $38,435,040
50.36,50.36A, 50.36B, 50.36C & Appendix I Technical Specifications - Risk Informed Completion Times (RICT) Program 5.0 1.0 5.0 60.0 300.0 $83,700
50.34(c) & (d) & 50.54(p) - Burden covered under 10 CFR 73.67 approved by OMB under Clearance No. 3150-0151 Physical security and safeguards contingency plans (operating power reactors) - 1.0 - 29.0 - $-
50.34(c) & (d) & 50.54(p) - Burden covered under 10 CFR 73.67 approved by OMB under Clearance No. 3150-0151 Physical security and safeguards contingency plans (decommissioned/shutdown power reactors) - - - 29.0 - $-
50.34(c) & (d) & 50.54(p) - Burden covered under 10 CFR 73.67 approved by OMB under Clearance No. 3150-0151 Physical security and safeguards contingency plans (nonpower reactors) - 1.0 - 29.0 - $-
50.35(b) Periodic reports of the progress and results of research and development programs designed to resolve safety questions - - - 100.0 - $-
50.54(w)(3) Annual report on the source of property and damage insurance 118.0 1.0 118.0 4.0 472.0 $131,688
10 CFR 50.54(w)(4) Cleanup plan outlining the steps and costs needed to complete decontamination and cleanup following an accident - - - 2,000.0 - $-









3 50.33(k) Contents of applications 1.0 1.0 1.0 200.0 200.0 $55,800
50.75 Decommissioning planning 89.0 1.0 89.0 5.0 445.0 $124,155
50.82 Termination of license 5.0 1.0 5.0 680.0 3,400.0 $948,600









4 50.71(b)& Appendix C Annual financial reporting 60.0 1.0 60.0 1.0 60.0 $16,740
50.76 Submission of financial qualifications information within 75 days prior to ceasing to be an electric utility - - - 33.0 - $-
50.71(e) Updated FSAR (operating reactors) 51.0 1.0 51.0 900.0 45,900.0 $12,806,100
50.71(e) Updated FSAR (power reactors that have ceased operating) 16.0 1.0 16.0 225.0 3,600.0 $1,004,400
50.72 & 50.54(z) Notification of Events 120.0 2.0 240.0 1.00 240.0 $66,960
10 CFR Part 50, Appendix E, Paragraph E.9.d Daily testing of the ENS system by the HOO, submission of voluntary reactor status and grid information 91.0 365.0 33,215.0 0.083 2,757.0 $769,203
Appendix E, VI.1 Periodic Testing Quarterly testing of Emergency Response Data System 120.0 4.0 480.0 2.0 960.0 $267,840
Appendix E, VI.3 a&b HW/SW changes affecting ERDS DPLs and communication 9.0 1.0 9.0 4.0 36.0 $10,044
50.72(a) Emergency Response Data System reports 7.0 1.0 7.0 4.0 28.0 $7,812
50.70 Team Inspections 51.0 1.0 51.0 160.0 8,160.0 $2,276,640
50.70 Other Inspections (e.g. Resident, Supplemental, Special and Infrequently Performed, Temporary Instructions, and Reactive) 51.0 1.0 51.0 45.0 2,295.0 $640,305
50.69(g) Submission of event report to submit a licensee event report for any event or condition that would have prevented RISC-1 and RISC-2 structures, systems, and components from performing a safety-significant function 10.0 1.0 10.0 600.0 6,000.0 $1,674,000









5 50.54(cc) Bankruptcy Notifications - - - 1.0 - $-
50.55(e) 48 hour notification (Design and Construction Deficiencies) 2.0 1.0 2.0 10.0 20.0 $5,580
50.55(e) 30-day reports (Design and Construction Deficiencies) 2.0 1.0 2.0 70.0 140.0 $39,060
50.55(f), Appendices A & B Quality Assurance reports (operating reactors) 89.0 1.0 89.0 160.0 14,240.0 $3,972,960
50.55(f), Appendices A & B Quality Assurance reports (reactors under construction) 2.0 1.0 2.0 160.0 320.0 $89,280
50.55(f), Appendices A & B Quality Assurance reports (Part 52 applicants) 2.0 1.0 2.0 667.0 1,334.0 $372,186
50.55a(z) Alternatives submitted by COLs 2.0 1.0 2.0 230.0 460.0 $128,340
50.55a(z) Alternatives submitted by Power Reactors 89.0 3.0 267.0 230.0 61,410.0 $17,133,390
50.55a(z) Alternatives submitted for I&C 0.0 0.0 - 230.0 - $-
50.55a(z)(1) and 50.55a(z)(2) - Burden covered under 50.55a(z)(1) and 50.55a(z)(2), approved by OMB under Clearance No. 3150-0244 Request for Alternatives (Online portal) 89.0 2.4 218.0 230.0 50,140.0 $13,989,060
50.55a(f)(5) and (g)(5) Relief requests 89.0 2.0 178.0 230.0 40,940.0 $11,422,260
50.55a Codes and Standards 89.0 2.0 178.0 58.0 10,324.0 $2,880,396
50.59(c) and d Power reactors - Reports changes in the facility, of changes in procedures, and of tests and experiments and to submit a report containing a brief description of any changes, tests, and experiments, including a summary of the evaluation of each 118.0 1.0 118.0 380.0 44,840.0 $12,510,360
50.59(c) and d Non-power reactors - Reports changes in the facility, of changes in procedures, and of tests and experiments and to submit a report containing a brief description of any changes, tests, and experiments, including a summary of the evaluation of each 31.0 1.0 31.0 120.0 3,720.0 $1,037,880
Appendices G & H, 50.60 Fracture Toughness 22.0 1.0 22.0 102.0 2,244.0 $626,076
50.61 Pressurized Thermal Shock 4.0 1.0 4.0 24.0 96.0 $26,784
50.64(c)(1) Unique purpose application for highly enriched uranium 2.0 1.0 2.0 10.0 20.0 $5,580
50.64(c)(2)(i) Highly enriched uranium - updated documentation 4.0 1.0 4.0 10.0 40.0 $11,160
50.64(c)(2)(ii) Highly enriched uranium - updated documentation 4.0 1.0 4.0 10.0 40.0 $11,160
50.64(c)(2)(iii) Highly enriched uranium, safety analyses 3.0 1.0 3.0 333.3 1,000.0 $279,000
50.66 Thermal Annealing - - - 6,400.0 -









6 50.12 Exemptions 30.0 1.0 30.0 360.0 10,800.0 $3,013,200









7 50.34(i) Part 50 applicants provide plans for implementing rule requirements in application - - - 300.0 - $-
50.44(c) Hydrogen Control Requirements - - - 203.0 - $-
50.46(a)(3)(ii) Annual report of changes to change evaluation model 104.0 1.0 104.0 20.0 2,080.0 580,320.0
50.46(a)(3)(ii) 30-day report of significant change or error to evaluation model 52.0 1.0 52.0 20.0 1,040.0 290,160.0
50.46, Appendix K Realistic evaluation model submittal 1.0 1.0 1.0 2,500.0 2,500.0 697,500.0
50.46, Appendix K Modified evaluation model submittal 0.6 1.0 0.6 1,750.0 1,050.0 292,950.0
50.46, Appendix K Schedule for completing actions associated with 10 CFR 50 Appendix K and 10 CFR 50.46(b) 1.6 1.0 1.6 16.0 25.6 7,142.4
Appendix K, 50.46 ECCS
2.0 - 40.0 - -
50.47, 50.54(q & t), Appendix E Emergency plans (operating power reactors) 57.0 25.0 1,425.0 81.0 115,425.0 $32,203,575
50.54(q)(4) Submission of proposed changes that would reduce the effective of approved emergency plans (operating power reactors) 12.0 1.0 12.0 40.0 480.0 $133,920
App. E.IV.F.2.a,b Participation Exercise – exercise scenario submission 28.5 1.0 28.5 40.0 1,140.0 $318,060
50.47, 50.54(q & t), Appendix E Emergency plans (operating non-power reactors) 31.0 10.0 310.0 2.0 620.0 $172,980
50.47, 50.54(q & t), Appendix E Emergency plans (power reactor sites being decommissioned) 29.0 15.0 435.0 34.0 14,790.0 $4,126,410
50.47, 50.54(q & t), Appendix E Emergency plans (non-power reactors being decommissioned and possession only) 4.0 5.0 20.0 1.0 20.0 $5,580
50.47, 50.54(q & t), Appendix E Emergency Planning 116.0 18.0 2,088.0 60.0 125,280.0 $34,953,120
Appendix S and 50.54(ff) Earthquake Engineering Criteria, DC applicants 1.0 1.0 1.0 155,000.0 155,000.0 $43,245,000
Appendix S and 50.54(ff) Earthquake Engineering Criteria, Operating Reactors 5.0 1.0 5.0 900.0 4,500.0 $1,255,500

Total
164
42,078
1,197,502 $334,102,946

Sheet 2: Recordkeeping


ANNUAL RECORDKEEPING REQUIREMENTS
(Recurring Information Collection Requirements)
Supporting Statement Section Section Description Number of Recordkeepers Hours per Recordkeeper Total Annual Burden Hours Annual Cost @ $279/hr
2 50.33(a)-(d), (g), (j) Early Site Permits (records) - 13.0 - $-
50.33(a)-(d), (j) Standard Design Certification (records) 1.0 16.5 16.5 $4,587
50.33(a)-(d), (g), (j) Combined OL (records) - 99.0 - $192,654
50.33(a)-(d), (j) Standard Design Approval (records) 1.0 16.5 16.5 $13,761
50.33(a)-(d), (j) Manfacturing License (records) - 16.5 - $-
50.33(a)-(d), (h), (j) NPUF Construction Permit (records) - 99.0 - $192,654
50.33(a)-(d), (h), (j) NPUF Operating License (records) - 99.0 - $27,522
50.33(a)-(d), (h)-(j) Nuclear Power Plant Construction Permit (records) - 99.0 - $137,610
50.33(a)-(d), (g)-(j) Nuclear Power Plant Operating License (records) - 99.0 - $27,522
50.59(c), 50.90, 50.91(a), (b) Records License Amendments 164.0 192.0 31,488.0 $8,785,152
50.74 - Burden covered under 10 CFR 55.22 approved by OMB under Clearance No. 3150-0024 Records of change in status of a licensed reactor operator or senior operator - - - $-
50.80(b) License Transfers 8.0 60.0 480.0 $133,920
50.36,50.36A, 50.36B & Appendix I Technical Specifications (Operating power reactor) 89.0 2080.0 185,120.0 $51,648,480
50.36,50.36A, 50.36B & Appendix I Technical Specifications (operating NPUFs) 31.0 80.0 2,480.0 $691,920
50.36,50.36A, 50.36B & Appendix I Technical Specifications (shutdown power reactor) 29.0 208.0 6,032.0 $1,682,928







3 50.75 Decommissioning planning 149.0 73.0 10,877.0 $3,034,683







4 50.71(b)& Appendix C Financial records 60.0 0.1 6.0 $1,674
50.71(e) Records for updated FSAR (operating reactors) 51.0 100.0 5,100.0 $1,422,900
50.71(e) Records for updated FSAR (power reactors that have ceased operating) 16.0 25.0 400.0 $111,600
50.72 & 50.54(z) Notification of Events 120.0 0.8 96.0 $26,784
Appendix E, VI.1 Periodic Testing Quarterly testing of Emergency Response Data System 120.0 0.2 24.0 $6,696
Appendix E, VI.3 a&b HW/SW changes affecting ERDS DPLs and communication 9.0 1.2 10.8 $3,013
50.72(a) Emergency Data Response System 7.0 0.4 2.8 $781
50.69 Maintain processes to control the inspection, testing, and corrective actions for structures, systems, and components, other SSC records 10.0 833.0 8,330.0 $2,324,070
50.69 (one-time implementation requirements) After approval of application, perform evaluations of the significance of SSC functions (implementation for the alternative requirements of 10 CFR 50.69 - voluntary) 16.0 920.0 14,720.0 $4,106,880







5 50.54(hh)(1) Procedures for aircraft threat 51.0 40.0 2,040.0 $569,160
50.55(e) Retention of evaluations, 50.55(e)(9)(ii) (Design and Construction Deficiencies) 25.0 2.0 50.0 $13,950
50.55(f), Appendices A & B Quality Assurance records (operating reactors, 4 reactors under construction, 1 ESP, 1 COL) 104.0 10,000.0 1,040,000.0 $290,160,000
50.55(f), Appendices A & B Quality Assurance records (shutdown reactors) 29.0 2,500.0 72,500.0 $20,227,500
50.55a Records related to Codes and Standards 104.0 2,310.0 240,240.0 $67,026,960
50.59(c) and (d) Power reactors - Records of changes in the facility, of changes in procedures, and of tests and experiments and to submit a report containing a brief description of any changes, tests, and experiments, including a summary of the evaluation of each 118.0 100.0 11,800.0 $3,292,200
50.59(c) and (d) Non-power reactors - Records of changes in the facility, of changes in procedures, and of tests and experiments and to submit a report containing a brief description of any changes, tests, and experiments, including a summary of the evaluation of each 31.0 480.0 14,880.0 $4,151,520
Appendices G & H, 50.60 Fracture Toughness 22.0 11.0 242.0 $67,518
50.61 Pressurized Thermal Shock 4.0 216.0 864.0 $241,056
50.65 Maintenance program records for operating plants 89.0 4,315.0 384,035.0 $107,145,765
50.65 Maintenance program records for shutdown plants 29.0 128.0 3,712.0 $1,035,648







6 50.12 Exemptions 30.0 40.0 1,200.0 $334,800







7 50.44(c) Hydrogen Control Requirements 89.0 1.0 89.0 $24,831
50.47, 50.54(q & t), Appendix E Emergency Planning Records for Operating Power Reactors 114.0 1,090.0 124,260.0 $34,668,540
50.47, 50.54(q & t), Appendix E Emergency Planning Records for Operating Non-Power Reactors 31.0 589.0 18,259.0 $5,094,261
50.47, 50.54(q & t), Appendix E Emergency Planning Records for Power Reactor Sites Being Decommissioned 29.0 256.0 7,424.0 $2,071,296
50.47, 50.54(q & t), Appendix E Emergency Planning Records for Non-Power Reactors Being Decommissioned and Possession Only 4.0 4.0 16.0 $4,464
50.48 (c) One-time transition of records for fire protection to NFPA 805 - - - $-
50.48, Appendix R Fire Protection plan records 118.0 84.0 9,912.0 $2,765,448
50.49(a),(d),(f)
One-time environmental qualification (program establishment, qualification of equipment), annualized 8.0 793.3 6,346.4 $1,770,646
50.49(d),(f),(j)
Environmental Qualification 89.0 2,080.0 185,120.0 $51,648,480
50.120(b) Training & Qualification Records for Operating Reactors 51.0 780.0 39,780.0 $11,098,620
50.120(b) Training & Qualification Records for Applicants - 1,440.0 - $-
50.155(a)(1) One-time Licensees review rule requirements and update procedures, programs, or plans 17.0 315.0 5,355.0 $1,494,045
50.155(f) Maintain documentation of changes in the implementation of requirements 51.0 100.0 5,100.0 $1,422,900
Appendix J Development and Ongoing Analyses & Maintenance of Performance Based Leakage Testing Program 164.0 60.0 9,840.0 $2,745,360
Appendix S and 50.54(ff) Earthquake Engineering Criteria, Operating Reactors 5.0 100.0 500.0 $139,500
Appendix S and 50.54(ff) Earthquake Engineering Criteria, DC applicants 1.0 100.0 100.0 $27,900
Appendix S IV(a)(3) Plant inspection and documentation of inspection following seismic event 5.0 320.0 1,600.0 $446,400

Total
164
2,450,464.0 $683,679,456.00

Sheet 3: Third-Party Disclosure


ANNUAL 3rd PARTY DISCLOSURES
(Recurring Information Collection Requirements)
Supporting Statement Section Section Description Number of Respondents Responses per Respondent Total Number of Responses Burden per Response Total Annual Burden Hours Cost @ $279/Hour (Notes)
5 50.55a Submission to ASME of Owner's certificate, AIA agreement (III/NCA-3230) 2.0 1.0 2.0 100.0 200.0 $55,800
TOTAL



2.0
200.0 $55,800

Sheet 4: Totals

Total Burden and Responses Section 2

Total Burden and Responses Section 3


Item #13, Other Costs Section




Hours Responses


Hours Responses
Section Costs



Reporting 457,342 2,152

Reporting 4,045 95
2 $25,181



Recordkeeping 225,633 164

Recordkeeping 10,877 149
3 $1,214



TOTAL 682,975 2,316

TOTAL 14,922 244
4 $3,202












5 $197,573












6 $134



Item #13, Other Costs Section 2


Item #13, Other Costs Section 3


7 $46,169



Recordkeeping $25,181


Recordkeeping $1,214

Total $273,472



TOTAL $25,181


TOTAL $1,214































Item #14, Costs to the Federal Government,


Item #14, Costs to the Federal Government, Section 2

Item #14, Costs to the Federal Government, Section 3
Section Staff Time Hours Cost @ $279/hr



Hours Cost @ $279/hr


Hours Cost @ $279/hr






Staff time 101953 $28,444,887

Staff time 1526 $425,754
2 101,953 $28,444,887











3 1,526 $425,754











4 41,295 $11,521,305


Total Burden and Responses Section 4





5 73,115 $20,399,085



Hours Responses

Total Burden and Responses Section 5


6 2,250 $627,750


Reporting 70,036 34,190


Hours Responses
7 20,275 $5,656,725


Recordkeeping 28,690 120

Reporting 231,328 1,128
Total 240,414 $67,075,506


TOTAL 98,726 34,310

Recordkeeping 1,770,363 118











Third Party Disclosure 200 2
Burden Hours





TOTAL 2,001,891 1,248
Section Reporting Recordkeeping 3rd Party Total Cost
Item #13, Other Costs Section 4













Recordkeeping $3,202






2 457,342 225,633
682,975 $190,550,025
TOTAL $3,202


Item #13, Other Costs Section 5


3 4,045 10,877
14,922 $4,163,238





Recordkeeping $197,573

4 70,036 28,690
98,726 $27,544,442





TOTAL $197,573

5 231,328 1,770,363 200 2,001,891 $558,527,589
Item #14, Costs to the Federal Government, Section 4







6 10,800 1,200
12,000 $3,348,000

Hours Cost @ $279/hr





7 423,951 413,701
837,652 $233,704,908
Staff time 41295 $11,521,305

Item #14, Costs to the Federal Government, Section 5
Total 1,197,502 2,450,464 200 3,648,166 $1,017,838,202






Hours Cost @ $279/hr
Previous total 1,148,086 2,562,696 100 3,710,881.7 $975,961,887





Staff time 73,115 $20,399,085
Deltas 49,416 -112,232 100 -62,716 -$17,497,792















Total Burden and Responses Section 6



Total Burden and Responses Section 7







Hours Responses


Hours Responses
Reponses
Reporting 10,800 30

Reporting 423,951 4,484
Section Reporting Recordkeeping 3rd Party TOTAL
Recordkeeping 1,200 30

Recordkeeping 413,701 164






TOTAL 12,000 60

TOTAL 837,652 4,648
2 2,152 164
2,316









3 95 149
244









4 34,190 120
34,310
Item #13, Other Costs Section 6



Item #13, Other Costs Section 7


5 1,128 118 2 1,248
Recordkeeping $134


Recordkeeping $46,169

6 30 30
60
TOTAL $134


TOTAL $46,169

7 4,484 164
4,648









2021 TOTAL 42,078 164 2 42,244









Previous total 43,467 149 1 43,617
Item #14, Costs to the Federal Government, Section 6



Item #14, Costs to the Federal Government, Section 7


Deltas -1,389 15 1 -1,373

Hours Cost @ $279/hr


Hours Cost @ $279/hr






Staff time 2,250 $627,750

Staff time 20,275 $5,656,725










































HOURS RESPONSES











2021 3,648,166 42,244











Previous 3,710,882 43,617











Delta -62,716 -1,373






File Typeapplication/vnd.openxmlformats-officedocument.spreadsheetml.sheet
File Modified0000-00-00
File Created0000-00-00

© 2024 OMB.report | Privacy Policy