Burden Calculations Table

1927t09.xlsx

Emission Guidelines for Existing Commerce and Industrial Solid Waste Incineration Units (40 CFR part 60, subpart DDDD) (Renewal)

Burden Calculations Table

OMB: 2060-0451

Document [xlsx]
Download: xlsx | pdf

Overview

Summary
Table 1
Table 2
Capital O&M
Responses
Respondents


Sheet 1: Summary

ICR Summary Information
Hours per Response 136
Number of Respondents 74
Total Estimated Burden Hours 16,100
Total Estimated Costs $3,110,000
Annualized Capital O&M $1,170,000
Total Annual Responses 118
Form Number Not applicable

Sheet 2: Table 1

Table 1: Annual Respondent Burden and Cost – Emission Guidelines for Existing Commercial and Industrial Solid Waste Incineration Units (40 CFR Part 60, Subpart DDDD) (Renewal)














Burden Item (A) (B) (C) (D) (E) (F) (G) (H)


Technical person-hours per occurrence No. of occurrences per respondent per year Technical person-hours per respondent per year Respondents per year a Technical hours per year (E=CxD) Management hours per year Clerical hours per year Total cost per year ($) b




(C=AxB)

(F=Ex0.05) (G=Ex0.10)



1. Applications N/A







Labor Rates
2. Survey and Studies N/A







Management $157.61
3. Reporting Requirements








Technical $123.94
A. Familiarize with regulatory requirements c, d 16 1 16 74 1,184 59.2 118 $163,477.84
Clerical $62.52
B. Required Activities










1) Initial requirements e










a) Initial stack test and report 16 1 16 0 0 0 0 $0


b) Establish and teach operator qualification course 64 1 64 0 0 0 0 $0


c) Obtain operator qualification 72 1 72 0 0 0 0 $0


d) Establish operating parameters (maximum and minimum) 160 1 160 0 0 0 0 $0


e) Continuous parameter monitoring initial costs (including by-pass stack) f 9 1 9 0 0 0 0 $0


2) Periodic requirements










a) Annual stack test and test report (PM, HCl, and opacity) 12 1 12 74 888 44.4 88.8 $122,608.38


b) Annual refresher operator training course 12 1 12 74 888 44.4 88.8 $122,608.38


c) Annual review of site-specific information 8 1 8 74 592 29.6 59.2 $81,738.92


d) Continuous parameter monitoring (including by-pass stack) annual costs g 83 1 83 74 6,142 307 614 $848,041.30


C. Create Information See 3B









D. Gather Information See 3E









E. Report Preparation










1) Control plan 40 1 40 0 0 0 0 $0


2) Notification of final compliance 4 1 4 0 0 0 0 $0


3) Report of initial performance test 8 2 16 0 0 0 0 $0


4) Siting analysis for new units only (establishes values for site-specific operating parameters) 8 1 8 0 0 0 0 $0


5) Waste management plan 160 1 160 0 0 0 0 $0


6) Annual Report h










a) Site-specific operating parameters 8 1 8 74 592 29.6 59.2 $81,738.92


b) Emissions/parameter exceedances and malfunctions See 3E.10









c) Results of stack tests conducted during the year See 3B









d) Statement of no exceedances i 8 1 8 66.6 533 26.6 53.3 $73,565.03


e) Documentation of use of by-pass stack See 3B









f) Documentation for periods when all qualified operators were unavailable for more than 8 hours 8 1 8 74 592 29.6 59.2 $81,738.92


7) Status report for operators that are off-site for more than 2 weeks j 8 1 8 7.4 59 2.96 5.92 $8,173.89


8) Corrective action summary for operators that are off-site for more than 2 weeks j 8 2 16 7.4 118 5.92 11.8 $16,347.78


9) Qualified operator deviation
notification of resumed operation
8 1 8 7.4 59.2 2.96 5.92 $8,173.89


10) Semiannual report of emissions/parameter exceedances i 12 2 24 7.4 178 8.88 17.8 $24,521.68


Subtotal for Reporting Requirements



13,599 $1,632,735


4. Recordkeeping Requirements










A. Familiarize with regulatory requirements c, d See 3A









B. Plan Activities See 3B









C. Implement Activities See 3B









D. Develop Record System N/A









E. Record Information










1) Records of operating parameters See 3B









2) Records of periods for which minimum amount of data on operating parameters were not obtained 0.5 52 26 7.4 192 9.62 19.2 $26,565.15


3) Records of malfunction of the unit 1.5 1 1.5 7.4 11.1 0.56 1.11 $1,532.60


4) Records of exceedances of operating parameters 1.5 1 1.5 7.4 11.1 0.56 1.11 $1,532.60


5) Records of stack tests See 3E









6) Records of persons who have reviewed operating procedures 1 1 1 74 74 3.7 7.4 $10,217.37


7) Records of persons who have completed operator training 1 1 1 74 74 3.7 7.4 $10,217.37


8) Records of persons who meet operator qualification criteria 1 1 1 74 74 3.7 7.4 $10,217.37


9) Records of monitoring device calibration See 3B









10) Records of site-specific documentation 24 1 24 74 1,776 88.8 178 $245,216.76


F. Personnel Training See 3B









G. Time for Audits N/A









Subtotal for Recordkeeping Requirements



2,544 $305,499


Total Labor Burden and Costs (rounded) k



16,100 $1,940,000


Total Capital and O&M Cost (rounded) k






$1,170,000


Grand Total (rounded) k






$3,110,000














Assumptions:










a We estimate that an average of 74 existing respondents and zero new respondents per year will be subject to the rule over the three-year period of this ICR.


b This ICR uses the following labor rates for privately-owned sources: $157.61 for managerial, $123.94 for technical, and $62.52 for clerical labor. These rates are from the United States Department of Labor, Bureau of Labor Statistics, September 2021, “Table 2. Civilian Workers, by occupational and industry group.” The rates are from column 1, “Total compensation.” The rates have been increased by 110 percent to account for varying industry wage rates and the additional overhead business costs of employing workers beyond their wages and benefits, including business expenses associated with hiring, training, and equipping their employees.


c We assume that all respondents will have to familiarize themselves with the regulatory requirements each year.


d Cost is incurred by a facility regardless of the number of affected units at the plant.


e This activity is based on a one-time cost only.


f Based on the “Revised Testing and Monitoring Options and Costs for Medical Waste Incinerators (MWIs) - Methodology and Assumptions (A-91-61,IV-B-66)," we assume 9 hours (($300 for planning + $500 for selection)/$89.94 per hour = 9 hours).


g Based on the "Revised Testing and Monitoring Options and Costs for Medical Waste Incinerators (MWIs) - Methodology and Assumptions (A-91-61, IV-B-66)," respondents spend 83 hours for reporting.


h Respondents make one combined annual report per year.


i We assume that 10 percent of the facilities will have an exceedance during the year. The remaining 90% of facilities would submit a statement of no exceedance.


j Assume that 10 percent of facilities will not have a qualified operator available for more than two weeks at least once a year, and that two corrective action summaries will be required.


k Totals have been rounded to 3 significant figures. Figures may not add exactly due to rounding.



Sheet 3: Table 2

Table 2: Average Annual EPA Burden and Cost – Emission Guidelines for Existing Commercial and Industrial Solid Waste Incineration Units (40 CFR Part 60, Subpart DDDD) (Renewal)















Burden Item (A) (B) (C) (D) (E) (F) (G) (H)


EPA Hours per Occurrence Number of Occurrences Per Respondent Per Year EPA Hours Per Respondent Per Year
(C=AxB)
Number of Respondents Per Year a Technical Hours Per Year
(E=CXD)
Management Hours Per Year
(F=Ex0.05)
Clerical Hours Per Year
(G=Ex0.1)
Total Costs, $ b


1. Applications N/A







Labor Rates
2. Familiarize with regulatory requirements 16 1 16 0 0 0 0 $0
Management $70.56
3. Required Activities








Technical $52.37
Report Reviews








Clerical $28.34
1) Review control plan 8 1 8 0 0 0 0 $0


2) Review notification of final compliance 8 1 8 0 0 0 0 $0


3) Review waste management plan 8 1 8 0 0 0 0 $0


4) Review initial stack test report 40 1 40 0 0 0 0 $0


5) Review annual compliance report 8 1 8 74 592 29.6 59.2 $34,769


6) Review semi-annual excess emission and parameter exceedance report c 8 2 16 7.4 118.4 5.92 11.84 $6,954


7) Review status report for operators that are off-site for more than 2 weeks d 2 1 2 7.4 14.8 0.74 1.48 $869


8) Corrective action summary for operators that are off-site for more than 2 weeks d 2 2 4 7.4 29.6 1.48 2.96 $1,738


9) Qualified operator deviation
notification of resumed operation
2 1 2 7.4 14.8 0.74 1.48 $869


TOTAL (rounded) e



885 $45,200














Assumptions:










a We estimate that an average of 74 existing respondents and zero new respondents per year will be subject to the rule over the three-year period of this ICR.


b This ICR uses the following labor rates: $70.56 for managerial, $52.37 for technical, and $28.34 for clerical labor. These rates are from the Office of Personnel Management (OPM), 2022 General Schedule, which excludes locality rates of pay. The rates have been increased by 60 percent to account for the benefit packages available to government employees.


c We assume that 10 percent of the facilities will have exceedance reports.


d Assume that 10 percent of facilities will not have a qualified operator available for more than two weeks at least once a year, and that two corrective action summaries will be required.


e Totals have been rounded to 3 significant figures. Figures may not add exactly due to rounding.



Sheet 4: Capital O&M

Capital/Startup vs. Operation and Maintenance (O&M) Costs
(A) (B) (C) (D) (E) (F) (G)
Continuous Monitoring Device Capital/Startup Cost for One Respondent Number of New Respondents Total Capital/Startup Cost, (B X C) Annual O&M Costs for One Respondent Number of Respondents with O&M Total O&M,
(E X F)
Wet scrubber a $3,423 0 $0 $0 0 $0
Annual stack testing b $0 0 $0 $15,493 74 $1,146,445
Continuous parameter monitoring (including bypass stack) c $0 0 $0 $322 74 $23,828


Total $0
Total d $1,170,000
a Total capital cost of parameter monitoring for wet scrubbers minus planning and equipment selecting cost equals: $18,786 - $800 = $17,986. Based on 0.11746 capital recovery factor, 10 percent interest rate, and 20 year lifetime of the units = $2,113 (1994 dollars); Costs have been increased from 1994 to 2020 $ using the CEPCI Equipment Cost Index: $2,113 x 1.62 cost adjustment = $3,423.
b Assume 125 contractor hours per respondent and an average contractor labor rate of $123.94 per hour. The labor rate is based on the United States Department of Labor, Bureau of Labor Statistics, Sept 2021, “Table 2. Civilian Workers, by occupational and industry group.” The rates are from column 1, “Total compensation.” The rates have been increased by 110 percent to account for varying industry wage rates and the additional overhead business costs of employing workers beyond their wages and benefits, including business expenses associated with hiring, training, and equipping their employees.
c Based on the memorandum titled "Revised Testing and Monitoring Options and Costs for Medical Waste Incinerators (MWIs) - Methodology and Assumptions (A-91-61,IV-B-66)," O&M cost = $1,693 x 0.11746 = $199 (1994 dollars); Costs have been increased from 1994 to 2020 $ using the CEPCI Equipment Cost Index. $199 x 1.62 cost adjustment = $322.
d Totals have been rounded to 3 significant figures. Figures may not add exactly due to rounding.

Sheet 5: Responses

Total Annual Responses
(A) (B) (C) (D) (E)
Information Collection Activity Number of Respondents Number of Responses Number of Existing Respondents That Keep Records but Do Not Submit Reports Total Annual Responses
E=(BxC)+D
State plans 0 1 0 0
Construction/reconstruction notification 0 1 0 0
Startup notification 0 1 0 0
Demonstration date of continuous monitoring system performance notification 0 1 0 0
Anticipated date for conducting opacity observations notification 0 1 0 0
Use of continuous opacity monitoring system data notification 0 1 0 0
Final control plan notification 0 1 0 0
Final compliance notification 0 1 0 0
Waste management plan 0 1 0 0
Initial performance test report 0 1 0 0
Annual report a 74 1 0 74
Semiannual report of emissions/parameter exceedances b 7.4 2 0 14.8
Status report for operators that are off-site for more than 2 weeks c 7.4 1 0 7.4
Corrective action summary for operators that are off-site for more than 2 weeks c 7.4 2 0 14.8
Qualified operator deviation notification of resumed operation c 7.4 1 0 7.4



Total (rounded) d 118
a Annual reports are not required until the second year that units are in operation; therefore, annual reports will only apply to existing sources (i.e., 74 respondents).
b We assume that 10 percent of the facilities will have an exceedance during the year.
c We assume that 10 percent of facilities will not have a qualified operator available for more than two weeks at least once a year, and that two corrective action summaries will be required.
d Totals have been rounded to 3 significant figures. Figures may not add exactly due to rounding.

Sheet 6: Respondents

Number of Respondents

Respondents That Submit Reports Respondents That Do Not Submit Any Reports

(A) (B) (C) (D) (E)
Year Number of New Respondents 1 Number of Existing Respondents Number of Existing Respondents that keep records but do not submit reports Number of Existing Respondents That Are Also New Respondents Number of Respondents (E=A+B+C-D)
1 0 74 0 0 74
2 0 74 0 0 74
3 0 74 0 0 74
Average 0 74 0 0 74
1 New respondents include sources with constructed, reconstructed and modified affected facilities.




File Typeapplication/vnd.openxmlformats-officedocument.spreadsheetml.sheet
File Modified0000-00-00
File Created0000-00-00

© 2024 OMB.report | Privacy Policy