NRC Form 366, 366A, and 366B, "Licensee Event Report"
Extension without change of a currently approved collection
No
Regular
Approved without change
04/01/2024
08/22/2023
In accordance with 5 CFR 1320, the information collection is approved for three years.
table that charts list comparision
Inventory as of this Action
Requested
Previously Approved
04/30/2027
36 Months From Approved
03/31/2024
250
0
542
20,000
0
35,360
464
0
779
Part of the NRC's function is to license and regulate the operation of commercial nuclear power plants to ensure protection of public health and safety and the environment in accordance with the Atomic Energy Act of 1954 as amended. In order for the NRC to carry out these responsibilities, licensees must report significant events in accordance with 10 CFR 50.73, so that the NRC can evaluate the events to determine what actions, if any, are warranted to ensure protection of public health and safety or the environment. Section 50.73 requires reporting on NRC Forms 366, 366A, and 366B.
NRC Form 366B, NRC Form 366A, NRC FORMS 366, NRC Form 366
,
,
table that charts list of burden
Total Approved
Previously Approved
Change Due to New Statute
Change Due to Agency Discretion
Change Due to Adjustment in Estimate
Change Due to Potential Violation of the PRA
Annual Number of Responses
250
542
0
0
-292
0
Annual Time Burden (Hours)
20,000
35,360
0
0
-15,360
0
Annual Cost Burden (Dollars)
464
779
0
0
-315
0
No
No
The estimated burden has decreased from 35,360 hours to 20,000 hours, a decrease of 15,360 hours. The NRC reviewed the number of LERs submitted over the past two clearance cycles and estimates the annual average has decreased and will remain consistently lower than previous clearance periods for the licensees reporting using NRC Forms 366, 366A and 366B in the future. It is expected that a new lower threshold has been established. The number of estimated LERs has decreased from 542 to 250, a decrease of 292 responses. Additionally, the number of total licensees has decreased from prior clearance cycles; therefore, lower estimates for total number of units and reports per nuclear unit were used.
There was an increase in the fee rate from $275/hr to $290/hr used for this OMB clearance cycle.
On behalf of this Federal agency, I certify that the collection of information encompassed by this request complies with 5 CFR 1320.9 and the related provisions of 5 CFR 1320.8(b)(3).
The following is a summary of the topics, regarding the proposed collection of information, that the certification covers:
(i) Why the information is being collected;
(ii) Use of information;
(iii) Burden estimate;
(iv) Nature of response (voluntary, required for a benefit, or mandatory);
(v) Nature and extent of confidentiality; and
(vi) Need to display currently valid OMB control number;
If you are unable to certify compliance with any of these provisions, identify the item by leaving the box unchecked and explain the reason in the Supporting Statement.