48C Appendix Files Checklist

Qualifying Advanced Energy Project Credit - Notice 2023-18

48C Appendix Files Checklist

OMB: 1545-2151

Document [docx]
Download: docx | pdf

48C Appendix Checklists

This non-exhaustive checklist is meant to support applicants in organizing their 48C appendix submissions and is not a required part of the application process. Note, not all deliverables listed below are required. Please refer to Appendix B of IRS Notice 2023-44 for a complete list of application content requirements.

Clean Energy Manufacturing and Recycling

Section

Submitted (Y/N)?

Project overview


Process diagrams, schematics, and/ or images



Letter of significant change in plan

only needed if there is a significant change in plan from the concept paper submission


Project plan


Documentation to support project schedule



Operations and maintenance agreement or letters of intent



EPC agreement



Site plan with evidence that applicant owns or controls a site



Information supporting site selection



Lists of all federal, state, and local permits, including environmental authorizations or reviews, necessary to commence construction, including the status of each


Business Plan


Cash flow model

The model should quantify the projected financial parameters including operating costs, operating revenues, financing cash flows, EBITDA, tax credits/liabilities, and ROI over the project lifespan. The model should also include a list of key economic/financial assumptions as a separate tab. See data sheet for further instructions.



Equity commitments or expressions of interest



Debt commitments or expressions of interest



Sales forecast



Offtake or sales agreements



Equipment sources (if available)


Management Expertise & Track Record (Referred to as “Management Plan” in IRS Notice 2023-44)


Resumes of key personnel



Audited company financial statements for the most recently ended three (3) fiscal years (if available)



Unaudited quarterly interim financial statements for the current fiscal year



Shareholders agreement (listed under “Project plan” in IRS Notice 2023-44)


Greenhouse gas emissions impacts


Product specifications to verify GHG emissions claims



Product warranty to substantiate product performance claims



Analysis or engineering studies to substantiate assessments of process improvements at the facility


Workforce and community engagement


Collective bargaining agreement, labor-management agreement, or similar agreement



Good Neighbor Agreements/Community Benefits Agreements, Collective Bargaining Agreements, Project Labor Agreements or Community Workforce Agreements






GHG Emission Reduction

Please refer to Appendix B of IRS Notice 2023-44 for a complete list of application content requirements.

Section

Submitted (Y/N)?

Project overview


Process diagrams, schematics, and/ or images



Letter of significant change in plan

only needed if there is a significant change in plan from the concept paper submission


Project plan


Documentation to support project schedule



Operations and maintenance agreement or letters of intent



EPC agreement



Site plan with evidence that applicant owns or controls a site



Information supporting site selection



Lists of all federal, state, and local permits, including environmental authorizations or reviews, necessary to commence construction, including the status of each


Business Plan


Cash flow model

The model should quantify the projected financial parameters including operating costs, operating revenues, financing cash flows, EBITDA, tax credits/liabilities, and ROI over the project lifespan. The model should also include a list of key economic/financial assumptions as a separate tab. See data sheet for further instructions.



Equity commitments or expressions of interest



Debt commitments or expressions of interest



Sales forecast



Offtake, sales agreements, environmental product declarations, low-and/or carbon materials certifications



Equipment sources (if available)


Management Expertise & Track Record (Referred to as “Management Plan” in IRS Notice 2023-44)


Resumes of key personnel



Audited company financial statements for the most recently ended three (3) fiscal years (if available)



Unaudited quarterly interim financial statements for the current fiscal year



Shareholders agreement (listed under “Project plan” in IRS Notice 2023-44)


Greenhouse gas emissions impacts


Analysis or engineering studies to substantiate assessments of process improvements at the facility


Workforce and community engagement


Collective bargaining agreement, labor-management agreement, or similar agreement



Good Neighbor Agreements/Community Benefits Agreements, Collective Bargaining Agreements, Project Labor Agreements or Community Workforce Agreements












Critical Materials and Recycling

Please refer to Appendix B of IRS Notice 2023-44 for a complete list of application content requirements.

Section

Submitted (Y/N)?

Project overview


Process diagrams, schematics, and/ or images



Letter of significant change in plan

only needed if there is a significant change in plan from the concept paper submission


Project plan


Documentation to support project schedule



Operations and maintenance agreement or letters of intent



Shareholders agreement



EPC agreement



Site plan with evidence that applicant owns or controls a site



Information supporting site selection



Lists of all federal, state, and local permits, including environmental authorizations or reviews, necessary to commence construction, including the status of each


Business Plan


Cash flow model

The model should quantify the projected financial parameters including operating costs, operating revenues, financing cash flows, EBITDA, tax credits/liabilities, and ROI over the project lifespan. The model should also include a list of key economic/financial assumptions as a separate tab. See data sheet for further instructions.



Equity commitments or expressions of interest



Debt commitments or expressions of interest



Sales forecast



Offtake or sales agreements



Equipment sources (if available)


Management Expertise & Track Record (Referred to as “Management Plan” in IRS Notice 2023-44)


Resumes of key personnel



Audited company financial statements for the most recently ended three (3) fiscal years (if available)



Unaudited quarterly interim financial statements for the current fiscal year



Shareholders agreement (listed under “Project plan” in IRS Notice 2023-44)


Greenhouse gas emissions impacts


Internal or external analysis to substantiate indirect emissions benefits of the end product



Analysis or engineering studies to substantiate assessments of process improvements at the facility


Workforce and community engagement


Collective bargaining agreement, labor-management agreement, or similar agreement



Good Neighbor Agreements/Community Benefits Agreements, Collective Bargaining Agreements, Project Labor Agreements or Community Workforce Agreements