RUS Form 187 Certificate of Completion - Contract Construction

7 CFR 1726, Electric System Construction Policies and Procedures- Electric

Form RUS 187

7 CFR 1726, Electric System Construction Policies and Procedures- Electric

OMB: 0572-0107

Document [docx]
Download: docx | pdf

According to the Paperwork Reduction Act of 1995, an agency may not conduct or sponsor, and a person is not required to respond to a collection of information unless it displays a valid OMB control number. The valid OMB control number for this information collection is 0572-0107, which expires on XXXX. The time required to complete this information collection is estimated to average 1 minute per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection information. All responses to this collection of information are voluntary. Any questions on this burden can be sent to [email protected].


U.S. Department of Agriculture Rural Utilities Service

CERTIFICATE OF COMPLETION

  • CONTRACT CONSTRUCTION



I, the undersigned Architect or Engineer of the following Rural Utilities Service project, do hereby certify that:


    1. The construction provided for pursuant to Construction Contract No. ,


dated , 20 , including all approved amendments, between


, RUS designation (''Owner'') and (''Contractor'')

has been completed as of , 20 , and is in compliance with the

provisions of the Construction Contract, including all plans, specifications, maps, and drawings and all modifications thereof.


    1. Payment in full has been made to all persons who have furnished labor for the Project.

    2. The Contractor has obtained valid releases of lien from all manufacturers, material suppliers, and subcontractors furnishing services or materials which were employed by the Contractor in the performance of the Construction Contract, and that such releases have been delivered by the Contractor to the Owner.


    1. If applicable, the Final Inventory attached hereto and made a part hereof is a complete and accurate summary of all units of construction in the project and of all work performed in accordance with the Construction Contract.

    2. If applicable, the staking sheets and tabulation of staking sheets upon which the Final Inventory is based show the accurate location, number, and kind of all units of construction of the project and show all work performed in accordance with the Construction Contract.


    1. All defects in workmanship and materials reported during the period of construction of the project have been corrected.

    2. The total cost of the project as completed is dollars ($ ).


Dated this

day of ,20 .



Name of Architect or Engineer


By

Date


Title









RUS FORM 187 (Rev. 2-04)

CERTIFICATE OF COMPLETION CONTRACT CONSTRUCTION

(continued)



We. the undersigned Owner and Contractor, do hereby certify that:


  1. The Project has been completed in accordance with the provisions of the Construction Contract, dated


, 20 , provided, however, that acceptance of the project by the Owner shall not be deemed to relieve the Contractor of its obligations contained in the Construction Contract with respect to defective workmanship or, materials discovered within one year after the date of completion.

  1. If applicable. the Final Inventory attached hereto and made a part hereof is a complete and accurate summary of all units of construction in the Project and of work performed in accordance with the Construction Contract.


Shape4

Owner



Date

By

Shape5 President


Shape6

Name of Contractor



Shape7 Date

By


Shape8

Title





















RUS Form 187 (Rev. 2-04)

File Typeapplication/vnd.openxmlformats-officedocument.wordprocessingml.document
File TitleCertificate of Complettion Contract Construction
AuthorChester Davis
File Modified0000-00-00
File Created2025-01-23

© 2025 OMB.report | Privacy Policy