Construction-Manager-as-Constructor Contracting; GSAR Section Affected: 552.236-72

ICR 202504-3090-008

OMB: 3090-0308

Federal Form Document

Forms and Documents
Document
Name
Status
Supporting Statement A
2025-07-30
IC Document Collections
IC ID
Document
Title
Status
221429
Modified
ICR Details
3090-0308 202504-3090-008
Received in OIRA 202207-3090-001
GSA
Construction-Manager-as-Constructor Contracting; GSAR Section Affected: 552.236-72
Revision of a currently approved collection   No
Regular 07/30/2025
  Requested Previously Approved
36 Months From Approved 08/31/2025
4,975 4,450
2,488 1,113
158,603 65,353

The collected information is required by GSAR clause 552.236-72, Submittals. The GSAR clause requires the Contractor to prepare and submit all submittals as specified in the contract or requested by the Contracting Officer in solicitations and contracts if construction, dismantling, demolition, or removal of improvements is contemplated. Alternate I of the clause will be used when a design-build project delivery method will be followed. ● Submittals. Submittals may include safety plans, schedules, shop drawings, coordination drawings, samples, calculations, product information, or mockups. ● Shop Drawings. Shop drawings may include fabrication, erection and setting drawings, manufacturers' scale drawings, wiring and control diagrams, cuts or entire catalogs, pamphlets, descriptive literature, and performance and test data. ● Additional information. Unless otherwise provided in this contract, or otherwise directed by the Contracting Officer, submittals shall be submitted to the Contracting Officer: (i) The Contractor shall be entitled to receive notice of action on submittals within a reasonable time, given the volume or complexity of the submittals and the criticality of the affected activities to substantial completion as may be indicated in the project schedule (ii) The Contractor shall not proceed with construction work or procure products or materials described or shown in submittals until the submittal is reviewed. Any work or activity undertaken prior to review shall be at the Contractor's risk. Should the Contracting Officer subsequently determine that the work or activity does not comply with the contract, the Contractor shall be responsible for all cost and time required to comply with the Contracting Officer's determination. The Contracting Officer shall have the right to order the Contractor to cease execution of work for which submittals have not been reviewed. The Government shall not be liable for any cost or delay incurred by the Contractor attributable to the proper exercise of this right. See Item 6 below for the consequences if the information collection is not conducted or conducted less frequently.

None
None

Not associated with rulemaking

  90 FR 21931 05/22/2025
90 FR 35303 07/25/2025
No

1
IC Title Form No. Form Name
Construction-Manager-as-Constructor Contracting

  Total Request Previously Approved Change Due to New Statute Change Due to Agency Discretion Change Due to Adjustment in Estimate Change Due to Potential Violation of the PRA
Annual Number of Responses 4,975 4,450 0 525 0 0
Annual Time Burden (Hours) 2,488 1,113 0 1,375 0 0
Annual Cost Burden (Dollars) 158,603 65,353 0 93,250 0 0
Yes
Miscellaneous Actions
No
● The hourly rate was updated to reflect the rates effective January 2025, as opposed to January 2022. ● The estimated hours to complete the submission was adjusted upward from 15 minutes to 30 minutes to be in alignment with current estimates. ● The estimated hours for review was adjusted upward from 15 minutes to 30 minutes to be in alignment with current estimates. ● The estimated number of construction contracts reflected in FPDS data was updated to reflect FY2024 data, as opposed to FY2021 data. ● Previous reference to the GSA Form 2437 has been removed as this form is not directly covered by this ICR and it does not impact the burden estimate.

$158,610
No
    No
    No
No
No
No
No
Amy Lara 816 926-7172 [email protected]

  No

On behalf of this Federal agency, I certify that the collection of information encompassed by this request complies with 5 CFR 1320.9 and the related provisions of 5 CFR 1320.8(b)(3).
The following is a summary of the topics, regarding the proposed collection of information, that the certification covers:
 
 
 
 
 
 
 
    (i) Why the information is being collected;
    (ii) Use of information;
    (iii) Burden estimate;
    (iv) Nature of response (voluntary, required for a benefit, or mandatory);
    (v) Nature and extent of confidentiality; and
    (vi) Need to display currently valid OMB control number;
 
 
 
If you are unable to certify compliance with any of these provisions, identify the item by leaving the box unchecked and explain the reason in the Supporting Statement.
07/30/2025


© 2025 OMB.report | Privacy Policy