GUIDANCE MANUAL FOR ENVIRONMENTAL REPORT PREPARATION VOLUME II
ICR 202610-1902-004 · OMB 1902-0062 · Object 174025400.
Document Viewer [pdf]
Status: Original and derived artifacts are available for this document.
Download: pdf
Loading document viewer…
Document Metadata
| File Type | application/pdf |
|---|---|
| File Title | GUIDANCE MANUAL FOR ENVIRONMENTAL REPORT PREPARATION VOLUME II |
| Subject | GUIDANCE MANUAL |
| Keywords | GUIDANCE MANUAL FOR ENVIRONMENTAL REPORT PREPARATION VOLUME II |
| Author | FERC |
| Last Modified By | Acrobat PDFMaker 11 for Word |
| File Modified | 2017-02-22 |
| File Created | 2017-02-09 |
| Conversion State | complete |
Extracted Text
FEDERAL ENERGY REGULATORY COMMISSION Office of Energy Projects GUIDANCE MANUAL FOR ENVIRONMENTAL REPORT PREPARATION For Applications Filed Under the Natural Gas Act Volume II Liquefied Natural Gas Project Resource Reports 11 & 13 Supplemental Guidance February 2017 BACKGROUND In 1999, the Federal Energy Regulatory Commission (FERC or Commission) referenced in its regulations the document National Bureau of Standards Information Report (NBSIR) 84-2833 Data Requirements for Seismic Review of LNG Facilities for seismic hazard evaluations and seismic design criteria for LNG facilities. However, this document was published in 1984 and its seismic requirements were based on the version of Title 49 of the Code of Federal Regulations (CFR), Part 193 (49 CFR Part 193) that existed and the edition of National Fire Protection Association (NFPA) Standard 59A that was referenced by 49 CFR Part 193 at that time. DOT regulations under 49 CFR 193 largely went unchanged from 1980 until 1999. After 1999, DOT changed substantial portions of their regulations. When the Commission received applications for liquefied natural gas (LNG) import terminals in the early- and middle-2000s, we therefore developed a series of guidance documents to assist project sponsors preparing applications to satisfy our regulations and needs to evaluate the safety of the proposed projects. On December 15, 2005, we issued Draft Guidance on Resource Report 11 and 13 to assist project sponsors in interpreting regulations under 18 CFR §380.12(m) and 18 CFR §380.12(o) for LNG applications. On April 12, 2006, we issued the Draft Preferred Format Submittal Guidance to recommend the format of submitted material to make our review more efficient. Finally, on January 23, 2007, we issued the Draft FERC Seismic Design Guidelines and Data Submittal Requirements for LNG Facilities in recognition that new U.S. Department of Transportation (DOT requirements in 2003 adopted the 2001 edition of National Fire Protection Association (NFPA) Standard 59A. The Draft Guidance on Resource Report 11 and 13 and Draft Preferred Format Submittal Guidance were based upon what was understood to be the requirements of Title 49 CFR Part 193, incorporated references (e.g., NFPA 59A), and practices of LNG facilities at the time. However, since then, a number of LNG project proposals have necessitated our evaluation of distinct hazards and potential safety impacts. In addition, we participated in a number of studies with the Fire Protection Research Foundation, Department of Energy, Coast Guard, and Department of Transportation to better address these hazards and potential safety impacts. In 2010, we assisted DOT in issuing additional interpretations on the requirements to meet the exclusion zones and siting requirements in 49 CFR Part 193 and in 2011 assisted DOT in evaluating and approving additional hazard modeling programs to demonstrate compliance with the 49 CFR Part 193 siting regulations. Accordingly, we have refined and clarifed the level of information needed for our evaluation of the hazards associated with proposed LNG facilities per 18 CFR §380.12(m) and 18 CFR §380.12(o). Commission Staff Guidance February 2017 Similarly, Draft FERC Seismic Design Guidelines and Data Submittal Requirements for LNG Facilities has benefited from years of application and were based on DOT requirements for seismic evaluations, which have since changed. The current seismic requirements for LNG facilities in DOT regulations under 49 CFR Part 193 incorporate by reference NFPA 59A-2006 and NFPA 59A-2001. NFPA 59A-2006 is only applicable to stationary LNG storage tanks to be seismically designed for the safe shutdown earthquake (SSE) and operating basis earthquake (OBE) design earthquake ground motions. NFPA 59A-2001 requires piping with cold contents (−20 °F or lower) to be designed dynamically for the OBE or statically 0.60 SDS (maximum spectral acceleration of the design earthquake which equals 2/3 of the maximum considered earthquake [MCE]) as specified in the National Earthquake Hazards Reduction Program (NEHRP) Recommended Provisions. NFPA 59A-2001, Appendix B.5.2, refers seismic design for the remainder of the LNG facilities to NEHRP Recommended Provisions, but these are in nonmandatory Appendix B. We also recognize the current FERC regulations under Title 18 CFR §380.12(h)(5) continues to incorporate NBSIR 84-2833. NBSIR 84-2833 provides guidance on classifying stationary storage containers and related safety equipment as Category I and classifying the remainder of the LNG project structures, systems, and components as either Category II or Category III, but does not provide specific guidance for the seismic design requirements for them. Absent any other regulatory requirements, this guidance recommends that other LNG project structures classified as Seismic Category II or Category III be seismically designed to satisfy the seismic requirement of the American Society of Civil Engineers (ASCE) 7-05 1 in order to demonstrate there is not a significant impact on the safety of the public. ASCE 7-05 is recommended as it is a complete American National Standards Institute (ANSI) consensus design standard, its seismic requirements are based directly on the NEHRP Recommended Provisions, and it is referenced directly by the International Building Code (IBC). Having a link directly to the IBC and ASCE 7 is important to accommodate seals by the engineer of record because the IBC is directly linked to state professional licensing laws while the NEHRP Recommended Provisions are not. Taken together, this Guidance Manual is based upon the regulatory requirements of 18 CFR §380.12, 49 CFR Part 193, and provisions in ASCE 7 and other best practices to demonstrate that the potential hazard to the public from failure of facility components resulting from natural catastrophes is addressed and that there would not be a significant impact on public safety from seismicity and other natural hazards at LNG facilities. 1 This guidance is based on the current version 49 CFR Part 193 that was applicable at the time of its writing and is therefore consistent with NFPA 59A – 2006 for determination of seismic design ground motions. The determination of seismic ground motions using the detailed procedures of ASCE 7-05 are consistent with the seismic design ground motions defined in NFPA 59A – 2006 and are therefore utilized in this document. This guidance does not supersede or alleviate an applicant of meeting 49 CFR Part 193 or any subsequent revisions made to 49 CFR Part 193. Commission Staff Guidance February 2017 GUIDANCE MANUAL FOR ENVIRONMENTAL REPORT PREPARATION For Applications Filed Under the Natural Gas Act TABLE OF CONTENTS PAGE VOLUME II ACRONYMS AND ABBREVIATIONS ........................................................................ ix 1 INTRODUCTION .................................................................................................. 1 11 RESOURCE REPORT 11 – RELIABILITY AND SAFETY ............................ 1 11.1 Regulatory Oversight .................................................................................... 1 11.1.1 Regulatory Oversight of Reliability and Safety .............................. 1 11.2 Hazard Identification ..................................................................................... 3 11.2.1 Hazardous Materials ........................................................................ 3 11.2.2 Process Hazards ............................................................................... 5 11.2.3 Marine Transportation Hazards ....................................................... 6 11.2.4 Other Transportation Hazards ......................................................... 6 11.2.5 Crane and Lifting Hazards............................................................... 7 11.2.6 Adjacent Hazards............................................................................. 7 11.2.7 Natural Hazards ............................................................................... 7 11.2.8 Security Threats and Vulnerabilities ............................................... 7 11.3 Hazard Analyses ............................................................................................ 8 11.3.1 Hazardous Releases ......................................................................... 8 11.3.2 Hot and Cold Fluid Temperature Hazard Analysis ......................... 9 11.3.3 Asphyxiant and Toxic Vapor Dispersion Hazards Analysis ......... 10 11.3.4 Flammable Vapor Dispersion Hazards Analysis........................... 12 11.3.5 Vapor Cloud Overpressure Hazards Analysis ............................... 13 11.3.6 Fire Hazards Analysis.................................................................... 14 11.3.7 Vessel Overpressure Analyses ...................................................... 16 11.3.8 Fog or Steam Hazard Analyses ..................................................... 17 11.3.9 Other Hazard Analyses .................................................................. 18 11.3.10 Hazardous Material Disposal ........................................................ 18 11.4 Layers of Protection .................................................................................... 19 11.4.1 Layers of Protection ...................................................................... 19 11.5 Reliability .................................................................................................... 26 11.5.1 Description of Reliability .............................................................. 26 Commission Staff Guidance i February 2017 GUIDANCE MANUAL FOR ENVIRONMENTAL REPORT PREPARATION For Applications Filed Under the Natural Gas Act TABLE OF CONTENTS PAGE 13 RESOURCE REPORT 13 – ENGINEERING AND DESIGN MATERIAL ............................................................................................................ 1 13.1 General Background and Project Management ............................................. 1 13.1.1 Project Facilities .............................................................................. 1 13.1.2 Location ........................................................................................... 2 13.1.3 Owner, Principal Contractors, and Operator ................................... 2 13.1.4 Feed and Sendout Product(s) ........................................................... 2 13.1.5 Project Schedule .............................................................................. 2 13.2 Site Information ............................................................................................. 3 13.2.1 Site Conditions ................................................................................ 3 13.2.2 Shipping Channel ............................................................................ 3 13.2.3 Climatic Conditions ......................................................................... 4 13.2.4 Geotechnical Conditions ................................................................. 4 13.3 Natural Hazard Design Conditions ............................................................... 5 13.3.1 Earthquakes ..................................................................................... 5 13.3.2 Tsunamis and Seiche ....................................................................... 6 13.3.3 Hurricanes and Other Meteorological Events ................................. 6 13.3.4 Tornados .......................................................................................... 7 13.3.5 Floods .............................................................................................. 7 13.3.6 Rain, Ice, Snow, and Related Events............................................... 7 13.3.7 Other Natural Hazards ..................................................................... 8 13.4 Marine Facilities ............................................................................................ 9 13.4.1 LNG Vessels .................................................................................... 9 13.4.2 Marine Platform Design ................................................................ 10 13.4.3 Marine Transfer Design ................................................................. 11 13.5 Feed Gas ...................................................................................................... 13 13.5.1 Feed Gas Design ............................................................................ 13 13.6 Feed Gas Pretreatment................................................................................. 15 13.6.1 Acid Gas Removal Design ............................................................ 15 13.6.2 Mercury Removal Design.............................................................. 17 13.6.3 Water Removal Design.................................................................. 18 13.7 Natural Gas Liquids (NGL) Removal, Storage, and Disposition................ 20 13.7.1 NGL Removal Design ................................................................... 20 13.7.2 NGL Storage Design ..................................................................... 22 13.7.3 NGL Disposition Design ............................................................... 23 Commission Staff Guidance ii February 2017 GUIDANCE MANUAL FOR ENVIRONMENTAL REPORT PREPARATION For Applications Filed Under the Natural Gas Act TABLE OF CONTENTS PAGE 13.8 Heavies/Condensates Removal, Storage, and Disposition .......................... 25 13.8.1 Heavies/Condensates Removal Design ......................................... 25 13.8.2 Heavies/Condensates Storage Design ........................................... 26 13.8.3 Heavies/Condensates Disposition Design ..................................... 27 13.9 Liquefaction System .................................................................................... 29 13.9.1 Refrigerant Trucking/Production Design ...................................... 29 13.9.2 Refrigerant Storage Design ........................................................... 30 13.9.3 Refrigerant Charge/Loading Pumps Design.................................. 31 13.9.4 Liquefaction Design ...................................................................... 32 13.9.5 Cooling System Design ................................................................. 34 13.10 LNG Product Transfer to Storage ............................................................... 35 13.10.1 LNG Transfer to Storage Design ................................................... 35 13.11 LNG Storage Tanks ..................................................................................... 37 13.11.1 LNG Storage Tank Design ............................................................ 37 13.12 Vapor Handling ........................................................................................... 39 13.12.1 Vapor Handling Design ................................................................. 39 13.12.2 Boil-off Gas (BOG) Re-Condensation Design .............................. 41 13.13 LNG Pumps ................................................................................................. 42 13.13.1 LNG Tank/Low Pressure (LP) Pump Design................................ 42 13.13.2 LNG Sendout/High Pressure (HP) System Design ....................... 43 13.14 LNG Trucking ............................................................................................. 45 13.14.1 LNG Trucking Design ................................................................... 45 13.15 LNG Vaporization ....................................................................................... 47 13.15.1 LNG Vaporizers Design ................................................................ 47 13.16 Heat Transfer Fluid (HTF) System(s) ......................................................... 49 13.16.1 HTF Storage Design ...................................................................... 49 13.16.2 HTF Heating System Design ......................................................... 50 13.17 Btu Adjustment............................................................................................ 52 13.17.1 Btu Adjustment System Design .................................................... 52 13.18 Sendout Metering System ........................................................................... 53 13.18.1 Sendout Metering Design .............................................................. 53 13.19 Fuel Gas ....................................................................................................... 54 13.19.1 Fuel Gas Design ............................................................................ 54 13.20 Nitrogen and Inert Gas ................................................................................ 55 13.20.1 Nitrogen Design............................................................................. 55 Commission Staff Guidance iii February 2017 GUIDANCE MANUAL FOR ENVIRONMENTAL REPORT PREPARATION For Applications Filed Under the Natural Gas Act TABLE OF CONTENTS PAGE 13.20.2 Inert Gas Design ............................................................................ 56 13.21 Instrument and Plant/Utility Air .................................................................. 58 13.21.1 Instrument Air Design ................................................................... 58 13.21.2 Plant/Utility Air Design................................................................. 59 13.22 Utility Water and Other Utilities ................................................................. 61 13.22.1 Utility Water Design...................................................................... 61 13.22.2 Other Utilities Design .................................................................... 62 13.23 Piping and Valves ........................................................................................ 63 13.23.1 Piping and Valve Design ............................................................... 63 13.24 Process Vessels............................................................................................ 65 13.24.1 Process Vessel Design ................................................................... 65 13.25 Rotating Equipment ..................................................................................... 66 13.25.1 Rotating Equipment Design* ........................................................ 66 13.26 Fired Equipment .......................................................................................... 67 13.26.1 Fired Equipment Design* .............................................................. 67 13.27 Buildings and Structures ............................................................................. 68 13.27.1 Buildings and Structures Design ................................................... 68 13.28 Electrical ...................................................................................................... 69 13.28.1 Electrical System Design............................................................... 69 13.29 Plans and Procedures ................................................................................... 71 13.29.1 Operation and Maintenance Plans ................................................. 71 13.30 Instrumentation and ControlS ..................................................................... 72 13.30.1 Basic Process Control System Design (BPCS) ............................. 72 13.31 Safety Instrumented Systems ...................................................................... 73 13.31.1 Safety Instrumented System (SIS) Design .................................... 73 13.32 Security Plans .............................................................................................. 74 13.32.1 Physical Security Plans.................................................................. 74 13.32.2 Cybersecurity Plans ....................................................................... 75 13.33 Relief Valve and Flare/Vent Systems ......................................................... 76 13.33.1 Relief Valves and Flare/Vent Systems Design.............................. 76 13.34 Spill Containment ........................................................................................ 78 13.34.1 Spill Containment System Design ................................................. 78 13.35 Passive Protection Systems ......................................................................... 79 13.35.1 Passive Protection Design ............................................................. 79 Commission Staff Guidance iv February 2017 GUIDANCE MANUAL FOR ENVIRONMENTAL REPORT PREPARATION For Applications Filed Under the Natural Gas Act TABLE OF CONTENTS PAGE 13.36 Hazard Detection Systems........................................................................... 80 13.36.1 Hazard Detection System Design .................................................. 80 13.37 Hazard Control Systems .............................................................................. 81 13.37.1 Hazard Control System Design ..................................................... 81 13.38 Fire Water System ....................................................................................... 82 13.38.1 Fire Water Design.......................................................................... 82 13.39 Emergency Response Plan .......................................................................... 85 13.39.1 Emergency Response Plan ............................................................ 85 RESOURCE REPORT 13 APPENDICES .................................................................... 87 13.A Appendix 13.A, Project Management ......................................................... 87 13.A.1 Site Location Maps and Drawing .................................................. 87 13.A.2 Owner Organizational Structure .................................................... 87 13.A.3 Construction Workforce Organizational Chart(s)* ....................... 87 13.A.4 Operation Workforce Organizational Chart(s)* ............................ 87 13.A.5 Gantt Chart .................................................................................... 88 13.B Appendix 13.B, Design Basis, Criteria, and Philosophies .......................... 91 13.B.1 Basis of Design and Criteria .......................................................... 91 13.B.2 Design and Control Philosophies .................................................. 92 13.C Appendix 13.C, Regulations and Permits ................................................... 93 13.C.1 Table of Regulatory Agencies, Permits, and Approvals ............... 93 13.C.2 Regulatory Agency Correspondence ............................................. 93 13.C.3 Regulatory Compliance Matrix ..................................................... 93 13.D Appendix 13.D, Codes and Standards ......................................................... 94 13.D.1 List of Codes and Standards .......................................................... 94 13.E Appendix 13.E, Engineering Design Information....................................... 95 13.E.1 Block Diagram of Facilities .......................................................... 95 13.E.2 Process Flow Diagrams ................................................................. 95 13.E.3 Utility Flow Diagrams ................................................................... 95 13.E.4 Heat and Material Balances ........................................................... 96 13.E.5 Piping and Instrumentation Drawings ........................................... 96 13.E.6 Plant and Equipment Layouts........................................................ 97 13.E.7 Plant Reliability, Availability, and Maintainability (RAM) Analyses* ...................................................................................... 98 Commission Staff Guidance v February 2017 GUIDANCE MANUAL FOR ENVIRONMENTAL REPORT PREPARATION For Applications Filed Under the Natural Gas Act TABLE OF CONTENTS PAGE 13.F Appendix 13.F, Specifications .................................................................... 99 13.F.1 Civil Specifications ....................................................................... 99 13.F.2 Mechanical Specifications ........................................................... 100 13.F.3 Electrical and Instrumentation Specifications ............................. 102 13.F.4 Security and Fire Safety Specifications....................................... 103 13.G Appendix 13.G, Hazard Identification ...................................................... 105 13.G.1 Process Hazard Analyses and Recommendations ....................... 105 13.G.2 Simultaneous Operation Studies ................................................. 105 13.G.3 Waterway Safety and Reliability Impact Studies ........................ 105 13.G.4 Road Safety and Reliability Impact studies ................................ 106 13.G.5 Rail Safety and Reliability Impact Studies.................................. 107 13.G.6 Air Safety and Reliability Impact studies.................................... 107 13.G.7 Crane and Lifting Impact studies ................................................ 108 13.G.8 Security Threat and Vulnerability Analyses ............................... 108 13.H Appendix 13.H, Hazard Analyses ............................................................. 109 13.H.1 Safety Data Sheets ....................................................................... 109 13.H.2 Hazardous Release List ............................................................... 109 13.H.3 Hazard Analysis Reports ............................................................. 110 13.H.4 Meteorological Data .................................................................... 111 13.I Appendix 13.I, Natural Hazard Design Investigations and Forces ........... 112 13.I.1 Earthquakes ................................................................................. 112 13.I.2 Tsunami and Seiche ..................................................................... 119 13.I.3 Hurricanes and Other Meteorological Events ............................. 120 13.I.4 Tornados ...................................................................................... 122 13.I.5 Floods .......................................................................................... 124 13.I.6 Rain, Ice, and Snow ..................................................................... 125 13.I.7 Other Natural Hazards ................................................................. 126 13.J Appendix 13.J, Site Investigation and Conditions, and Foundation Design ........................................................................................................ 127 13.J.1 Topographic Map ........................................................................ 127 13.J.2 Bathymetric Chart ....................................................................... 127 13.J.3 Climatic Data ............................................................................... 127 13.J.4 Geotechnical Investigation .......................................................... 127 13.J.5 Foundation Recommendations .................................................... 129 13.J.6 Structural Design Basis and Criteria ........................................... 130 Commission Staff Guidance vi February 2017 GUIDANCE MANUAL FOR ENVIRONMENTAL REPORT PREPARATION For Applications Filed Under the Natural Gas Act TABLE OF CONTENTS PAGE 13.J.7 Foundation and Support Drawings and Calculations .................. 131 13.K Appendix 13.K, Marine Systems .............................................................. 132 13.K.1 Marine Facility Drawings ............................................................ 132 13.L Appendix 13.L, LNG Tank Information ................................................... 133 13.L.1 LNG Tank Specifications ............................................................ 133 13.L.2 LNG Tank Drawings. .................................................................. 133 13.L.3 LNG Tank and Foundation Structural Design ............................ 133 13.M Appendix 13.M, Piping, Vessel, Equipment, and Buildings .................... 134 13.M.1 Piping and Valve List* ................................................................ 134 13.M.2 Tie-in List* .................................................................................. 134 13.M.3 Equipment List ............................................................................ 134 13.M.4 Equipment Process, Mechanical, and Thermal Data Sheets ....... 134 13.M.5 Manufacturer’s Data .................................................................... 134 13.M.6 List of Buildings and Structures .................................................. 134 13.M.7 Building Siting Analysis.............................................................. 135 13.M.8 Building Drawings....................................................................... 135 13.N Appendix 13.N, Electrical Design Information ........................................ 136 13.N.1 Electrical Load List ..................................................................... 136 13.N.2 Transformer List .......................................................................... 136 13.N.3 Single Line Drawings .................................................................. 136 13.N.4 UPS Drawings ............................................................................. 136 13.N.5 Electrical Area Classification Drawings ..................................... 136 13.N.6 Electrical Seal Drawings ............................................................. 136 13.O Appendix 13.O, Plans and Procedures ...................................................... 137 13.O.1 Management of Change Procedures and Forms* ........................ 137 13.O.2 QA/QC Plans and Procedures* ................................................... 137 13.O.3 Commissioning Plans* ................................................................ 137 13.O.4 Operating Plans and Procedures* ................................................ 138 13.O.5 Maintenance Plans and Procedures* ........................................... 138 13.O.6 Safety Procedures* ...................................................................... 138 13.P Appendix 13.P, Process Control and Instrumentation .............................. 139 13.P.1 Instrument Lists ........................................................................... 139 13.P.2 System Architecture drawings..................................................... 139 13.Q Appendix 13.Q, Safety Instrumented Systems and Shut-off Valves ........ 140 13.Q.1 Cause & Effect Matrices ............................................................. 140 Commission Staff Guidance vii February 2017 GUIDANCE MANUAL FOR ENVIRONMENTAL REPORT PREPARATION For Applications Filed Under the Natural Gas Act TABLE OF CONTENTS PAGE 13.Q.2 Block Diagrams ........................................................................... 140 13.Q.3 List of Shutoff Valves ................................................................. 140 13.Q.4 Drawing of ESD Manual Activation Devices ............................. 140 13.Q.5 Shutoff Valve Manufacturer’s Data ............................................ 140 13.R Appendix 13.R, Relief Valves and Flare/Vent Systems ........................... 141 13.R.1 List of Relief Valves* .................................................................. 141 13.R.2 Flaring Load and Venting Capacities and Sizing ........................ 141 13.S Appendix 13.S, Spill, Toxic, Fire, and Explosion Protection ................... 142 13.S.1 Preliminary Fire Protection Evaluation ....................................... 142 13.S.2 Spill Containment Matrix ............................................................ 142 13.S.3 Spill Containment Drawings and Calculations ........................... 143 13.S.4 Passive Protection Drawings ....................................................... 143 13.S.5 Hazard Detection Matrix ............................................................. 143 13.S.6 Hazard Detection Drawings ........................................................ 144 13.S.7 Hazard Control Matrix ................................................................ 144 13.S.8 Hazard Control Drawings ............................................................ 144 13.S.9 Fire Water Matrix ........................................................................ 145 13.S.10 Fire Water Drawings ................................................................... 145 13.T Appendix 13.T, Technology, Process, and Equipment Selection and Alternatives ............................................................................................... 146 13.T.1 Design Studies and Alternatives.................................................. 146 ATTACHMENTS .............................................................................................................. 1 Attachment 1 – Typical Cost-Influence Curve of a LNG Facility and FERC Review ........................................................................................................... 1 Attachment 2 – Equipment Data Table .................................................................... 2 Attachment 3 – Sample Seismic Ground Motion Hazard Evaluation Contents ...... 3 Attachment 4 – Sample Categorization of LNG Structures, Components, and Systems ........................................................................................................ 10 Attachment 5 – Sample Seismic Design Information Contents ............................. 14 Attachment 6 – Sample Geotechnical Report Contents ......................................... 19 Attachment 7 – Sample Foundation Design Criteria Contents .............................. 29 Commission Staff Guidance viii February 2017 ACRONYMS AND ABBREVIATIONS AEGL AFFF ALE ANSI API ASCE ASD ASTM BLEVE BOG BPCS Bscf Btu CBR CCTV CEII CFR CIDH Coast Guard Commission CPT DCS DE DoD DOT DTE EF EPA ESD °F FAA FAQ FAT FEED FEMA FERC FGS ft ft3 gal Acute Exposure Guideline Levels Aqueous Film-Forming Foam Aftershock Level Earthquake American National Standards Institute American Petroleum Institute American Society of Civil Engineers allowable stress design American Society for Testing and Materials boiling-liquid expanding-vapor explosion boil-off gas basic process control system billion standard cubic feet British thermal unit California Bearing Ratio closed circuit television Critical Energy Infrastructure Information Code of Federal Regulations cast-in drill hole U.S. Coast Guard Federal Energy Regulatory Commission cone penetration test distributed control system Design Earthquake U.S. Department of Defense U.S. Department of Transportation design tip elevation Enhanced Fujita U.S. Environmental Protection Agency emergency shutdown degrees Fahrenheit Federal Aviation Administration frequently asked questions factory acceptance test front-end engineering design Federal Emergency Management Agency Federal Energy Regulatory Commission fire and gas system foot cubic foot U.S. gallon Commission Staff Guidance ix February 2017 gpm hr HAZID HAZOP HHV HMI HP HTF HVAC IBC inH2O inHg ISA ISO kV kVA lb/hr LFL LHV LNG LOI LOPA LP m3 mbar MCE MCT mil mm MMBtu MMscfd MOC mph MSE MTPA MWt NAVD NBSIR NDE NEHRP NEPA NFPA NGA U.S. gallons per minute hour Hazard Identification Hazard and Operability higher heating value human-machine interface high pressure heat-transfer fluid heating, ventilation, and air conditioning International Building Code inches of water inches of mercury International Society of Automation International Organization for Standardization kilovolt kilovolt-ampere (one-thousand volt-amperes) pounds per hour lower flammability limit lower heating value liquefied natural gas Letter of Intent Layers of Protection Analysis low pressure cubic meter millibar Maximum Considered Earthquake Maximum Considered Tsunami thousandth of an inch millimeter million British thermal units million standard cubic feet per day management of change miles per hour mechanically stabilized earth million tons per annum megawatt-thermal North American Vertical Datum of 1988 National Bureau of Standards Information Report non-destructive examination National Earthquake Hazards Reduction Program National Environmental Policy Act National Fire Protection Association Natural Gas Act Commission Staff Guidance x February 2017 NGL NGVD NIST NOAA NOx NPSH NRC NTP NVIC OBE OECD P&C P&IDs PDA PFD PHA PHMSA ppm ppb-v %-vol psia psig PVB RAM RQD SAT scfm SDS SD1 SIL SIMOPS SIS SIT SMS SM1 SSE STE TER TL UFD UFL UPS USGS natural gas liquids National Geodetic Vertical Datum of 1929 National Institute of Standards and Technology National Oceanic and Atmospheric Administration nitrogen oxides net positive suction head U.S. Nuclear Regulatory Commission normal temperature and pressure Navigation and Vessel Inspection Circular Operating Basis Earthquake Organisation for Economic Co-operation and Development privileged and confidential piping and instrumentation drawings pile driving analyzer process flow diagrams process hazard analysis Pipeline and Hazardous Materials Administration parts per million parts per billion by volume percent by volume pounds per square inch absolute pounds per square inch gauge pressure vessel burst reliability, availability, and maintainability rock quality designation site acceptance test standard cubic feet per minute design earthquake spectral response acceleration at short periods design earthquake spectral response acceleration at 1-sec period Safety Integrity Level Simultaneous Operations safety instrumented system site integration test MCE spectral response acceleration at short periods MCE spectral response acceleration at 1-sec periods Safe Shutdown Earthquake specified tip elevation transcutaneous electrical resistance long-period transition period utility flow diagram upper flammability limit uninterruptible power supply U.S. Geological Survey Commission Staff Guidance xi February 2017 V VCE (ϕ) volt vapor cloud explosion angle of internal friction Commission Staff Guidance xii February 2017 1 INTRODUCTION We 2 provide this Guidance Manual to describe information in an application for a LNG project to evaluate and address potential safety and reliability impacts and include related engineering design information 3. This document combines, replaces, and updates the Guidance for Filing Resource Reports 11 & 13 for LNG Facility Applications (Dec. 2005), Resource Report 13 Draft Preferred Submittal Format Guidance (Apr. 2006), and the Draft Seismic Design Guidelines and Data Submittal Requirements for LNG Facilities (Jan. 2007). This manual does not substitute for, amend, or supersede the Commission’s regulations under the Natural Gas Act of 1938 (NGA) or the Commission’s and Council on Environmental Quality’s (CEQ) regulations under the National Environmental Policy Act of 1969 (NEPA). It imposes no new legal obligations and grants no additional rights. To the extent practicable, we use non-mandatory language such as “recommend,” “encourage,” and “may” to describe Commission staff’s recommendations. We use mandatory language such as “required,” “must,” and “must not” to describe controlling requirements under the terms of statutes and regulations. The manual discusses our preferred format for certain documents and data presentation. However, applicants can use an alternative approach if it satisfies the requirements of the applicable statutes and regulations. The purpose of Volume II is to facilitate our review and to assist applicants by identifying the specific information and level of detail and formatting recommended for Resource Report 11 and Resource Report 13 submitted in applications for LNG projects. These Resource Reports are required are required for proposals for new LNG facilities, expansions of existing LNG facilities, or re-commissioning of existing LNG facilities per Title 18 of the Code of Federal Regulations (CFR) Section 380.12 (18 CFR §380.12). The resource reports must contain the type of site-specific design information produced in the normal course of developing the design of an LNG project. The resource reports usually would not require abnormal details or special drawings generated solely for the Commission unless novel designs require additional detail or we request further detail. 2 3 “We,” “us,” and “our” refer to the environmental staff of the Federal Energy Regulatory Commission’s Office of Energy Projects. “You,” whether explicit or implied, refers to the applicant proposing a natural gas project or to the applicant’s agent(s) who prepares, uses, or reviews these types of environmental documents. See Title 18, Chapter I of the Code of Federal Regulations (CFR) §380.12(h)(5), 18 CFR §380.12(m), and 18 CFR §380.12(o) of the Commission’s regulations, which appear throughout this document. The Commission’s regulations in part 380 implement the National Environmental Policy Act of 1969, with section 380.12 specifically addressing Environmental Reports for applications under the Natural Gas Act. Similarly, other agencies’ regulations include a full citation, such as 49 CFR Part 193 issued by the Pipeline and Hazardous Materials Safety Administration within the U.S. Department of Transportation. Commission Staff Guidance 1-1 February 2017 Resource Report 11 addresses the potential hazard if facility components were to fail due to accidents or natural catastrophes, how these events would affect reliability and safety, and the procedures and design features that applicants would use to reduce potential hazards. Resource Report 11 should serve as a public summary that we can use to prepare our environmental document under NEPA. Resource Report 13 contains more detailed information that supports the summarized information in Resource Report 13, which we use to verify whether the engineering design ensures adequate reliability and safety. The level of detail to be submitted in Resource Report 13 varies based on the phase of project development. We intend to provide our input early enough in the design phase to influence the reliability and safety provisions considered in the design while minimizing associated costs with changes as shown in the relationship in Attachment 1. No matter the phase of the project development, the level of detail should include all features necessary to evaluate the design, construction, commissioning, start-up, operation, and maintenance of the facilities as identified in this guidance. The level of detail at the time of pre-filing is typically reflective of a front end engineering design (FEED) still in development. The level of detail at the time of application is typically reflective of a completed FEED. We do not expect details about the final design at the time of application, but note that this guidance also includes information that may become available during the final design phase, as indicated by an asterisk (*). The development of final design information should be discussed as identified in this guidance, but would not be expected to be developed at the time of application. Detailed information filed on the engineering design may qualify as Critical Energy Infrastructure Information (CEII) and privileged material. All filings must be made in compliance with the 18 CFR Part 388 of the Commission’s regulations concerning CEII and privileged material. If providing separate binders or electronic filings for public, CEII, and privileged versions, then the privileged version should be a complete resource report for review that includes all public and CEII information. Any CEII or privleged material should be filed as non-public and labeled “Contains Privileged Information – Do Not Release” (18 CFR §388.112) or “Contains Critical Energy Infrastructure Information – Do Not Release” (18 CFR §388.113) and should be filed separately from the remaining information which should be marked “Public.” Commission Staff Guidance 1-2 February 2017 Filings We issue this Guidance Manual to broadly address all types of LNG projects. Because each project is unique, some topics may not be appropriate for the scope of a proposed project or may not apply at all. Where a topic does not apply to the proposed facilities, applicants should note that the topic is “Not applicable” in the filing. If the applicant wishes to add to the list of topics, the applicant should make the addition at the end of the list and not as an insert. The filings should include a complete set of drawings in electronic and hard copy format to FERC LNG staff as part of the submitted application. Hard copies of drawings should be on 11”x17” paper in three-ring binders. The drawings must be legible (e.g., hard copies of colored drawings are to be printed in color, not black and white) with a title block and not folded. The drawings should be preceded by a master index on 8.5” x 11” paper that lists drawing number, drawing name, revision date, and revision number. Hard copies should be placed in separate binders in the format order recommended in this guidance and be separated for each Appendix. Each binder volume should be labeled, numbered, and ordered with a master index of the entire Resource Report contents. The spine of each volume should also be labeled, numbered, and ordered to reflect the contents. Electronic copies of drawings should be filed in .pdf or .docx formats. The drawings must be legible, and the textual content should be searchable. The drawings should be preceded by a master index that lists drawing number, drawing name, revision date, and revision number matching the hard copies. Electronic copies should be bookmarked and separated into distinct electronic documents for the main text of Resource Report 11, for the main text of Resource Report 13, and for each Appendix. Commission Staff Guidance 1-3 February 2017 11 RESOURCE REPORT 11 – RELIABILITY AND SAFETY 11.1 REGULATORY OVERSIGHT 4 11.1.1 Regulatory Oversight of Reliability and Safety PROVIDE a description of the regulatory oversight of reliability and safety for the proposed facilities. At a minimum, the description should describe the regulatory agencies that have oversight over the reliability and safety of the facilities, operations, and associated hazardous material transportation to and from the facilities as well as any agency coordination that has occurred. The description should reference Resource Report 13, Regulations and Permits in Appendix 13.C, and all other applicable appendices, and should describe: 11.1.1.1 U.S. Department of Transportation Pipeline and Hazardous Materials Administration For U.S. Department of Transportation (DOT) Pipeline and Hazardous Materials Administration (PHMSA) jurisdictional facilities, discuss and include consultation on any interpretations, special permits, equivalencies, and other issuances by DOT on the project. 11.1.1.2 U.S. Coast Guard For U.S. Coast Guard (Coast Guard) jurisdictional facilities, discuss and includeall Letter of Intent (LOI) submittals and any issuances by the Coast Guard on the project. 11.1.1.3 U.S. Environmental Protection Agency For U.S. Environmental Protection Agency (EPA) jurisdictional facilities, discuss and include all preliminary Risk Management Plans and any correspondence or issuances by the EPA on the project. 11.1.1.4 U.S. Occupational Safety and Health Administration For U.S. Occupational Safety and Health Administration (OSHA) jurisdictional facilities, discuss and include all Process Safety Management Plans and any correspondence or issuances by the OSHA on the project. 4 18 CFR §380.12(m)(1) and 18 CFR §380.12(o)(13). Commission Staff Guidance 11-1 February 2017 11.1.1.5 U.S. Department of Transportation Federal Aviation Administration For DOT Federal Aviation Administration (FAA) jurisdictional facilities with aeronautical operations and installations that may be impacted by the proposed facilities, or by construction (e.g., cranes) or operation of the project, or by transportation to or from the project site, discuss and include any related aeronautical studies and determinations from the DOT FAA on the project. 11.1.1.6 U.S. Department of Defense For Department of Defense (DoD) military operations and installations that may be impacted by the facilities, or by construction or operation of the project, or by transportation to or from the project site, discuss and include any correspondence and issuances by the DoD on the project. 11.1.1.7 U.S. Nuclear Regulatory Commission For U.S. Nuclear Regulatory Commission (NRC) jurisdictional nuclear plants that may be impacted by the proposed facilities, or by construction or operation of the project, or by transportation to or from the project site, discuss and include any related correspondence and issuances by the NRC. 11.1.1.8 State Agencies For all proposed facilities, discuss and include any communications or correspondence with the state and local safety agencies and fire marshals. Commission Staff Guidance 11-2 February 2017 11.2 HAZARD IDENTIFICATION 5 11.2.1 Hazardous Materials PROVIDE a description of all hazardous materials 6 that would be stored, processed, or handled onsite, including those arriving at or departing from the site by various transportation modes including pipelines. For materials whose compositions vary throughout the process, such as natural gas liquids, use the full range of properties. If any material composition would not be known until vendor selection, use conservative estimates that cover the full range of potential compositions. The description should reference any safety data sheets or calculations of mixed fluid properties submitted pursuant to Appendix 13.H, as well as any relevant details in all other applicable appendices, and should include: 11.2.1.1 11.2.1.1.1 Hazardous material stored (capacities, U.S. gallons [gal]; temperatures, degrees Fahrenheit [°F]; pressures, pounds per square inch gauge [psig]) 11.2.1.1.2 Hazardous materials processed or handled (concentration range, percent by volume (%-vol); temperature range, °F; pressure range, psig) 11.2.1.2 5 6 7 8 9 List of hazardous materials List of all physical properties 11.2.1.2.1 Freezing/melting temperature at normal 7 (14.7 pounds per square inch absolute [psia]) 8, °F pressure 11.2.1.2.2 Boiling/condensing (14.7 psia) 9, °F pressure temperature at normal 18 CFR §380.12(m)(1)-(3). Proprietary mixtures may be filed as privileged and confidential, but a summary or range of the properties as public information. National Institute of Standards and Technology (NIST) Handbook 44, 2016. Normal temperature and pressure (NTP) is defined as 21 °C (70 °F) and 101.325 kPa (14.696 psia). American Society for Testing and Materials (ASTM) D1015, Standard Test Method for Freezing Points of High Purity Hydrocarbons. NFPA 704, Standard System for the Identification of the Hazards of Materials for Emergency Response, defines boiling point as the temperature at which vapor pressure of liquid is equal to the surrounding atmospheric pressure. For mixes that do not have a constant boiling temperature, use the 20% evaporation point of a distillation performed in accordance with ASTM D86, Standard Test Method for Distillation of Petroleum Products at Atmospheric Pressure. Commission Staff Guidance 11-3 February 2017 11.2.1.2.3 Vapor and liquid densities at boiling/condensing temperature and normal pressure (14.7 psia), pounds per cubic foot (lb/ft3) 11.2.1.2.4 Vapor and liquid densities at normal temperature (70 °F) and normal pressure (14.7 psia) 10, lb/ft3 11.2.1.3 11.2.1.3.1 Maximum concentration of toxic component in process 11.2.1.3.2 Maximum amount of toxic component accumulated for disposal 11.2.1.3.3 Acute Exposure Guideline Levels (AEGL)-1, -2, -3 concentrations 11.2.1.4 10 11 12 13 List of all toxic properties List of all flammable and combustible properties 11.2.1.4.1 Flash points, 11 °F 11.2.1.4.2 Flammability ranges, upper flammability limit (UFL) and lower flammability limit (LFL), 12 %-vol 11.2.1.4.3 Stoichiometric concentrations, %-vol 11.2.1.4.4 Minimum ignition energies, millijoules (mJ) 11.2.1.4.5 Quenching distance, 13 millimeter (mm) 11.2.1.4.6 Maximum experimental safety gap, mm ASTM D1657, Standard Test Method for Density or Relative Density of Light Hydrocarbons by Pressure Hydrometer; ASTM D1298, Standard Test Method for Density, Relative Density, or API Gravity of Crude Petroleum and Liquid Petroleum Products by Hydrometer Method. ASTM D92, Standard Test Method for Flash and Fire Points by Cleveland Open Cup Tester; ASTM D1310, Standard Test Methods for Flash Point and Fire Point of Liquids by Tag Open Cup Tester; ASTM E502, Standard Test Method for Selection and Use of ASTM Standards for the Determination of Flash Point of Chemicals for by Closed Cup Methods; ASTMD56, Standard Test Method for Flash Point by Tag Closed Cup Tester; ASTM D93 Standard Test Methods for Flash Point by Pensky-Martens Closed Cup Tester; ASTM D3278 Standard Test Methods for Flash Point of Liquids by Small Scale Closed-Cup Apparatus; ASTM D3828, Standard Test Methods for Flash Point by Small Scale Closed Cup Tester. ASTM E681, Standard Test Method for Concentration Limits of Flammability of Chemicals; ASTM E918, Standard Test Method for Determining Limits of Flammability of Chemicals at Elevated Temperature and Pressure. ASTM E582, Standard Test Method for Minimum Ignition Energy and Quenching Distance in Gaseous Mixtures. Commission Staff Guidance 11-4 February 2017 11.2.1.4.7 Auto-ignition temperatures,14 °F 11.2.1.4.8 Heat of combustions, megajoules per kilogram (MJ/kg) 11.2.1.4.9 Laminar flame speed, meters per second (m/s) 11.2.1.5 11.2.1.5.1 Corrosivity of skin15 11.2.1.5.2 External and internal corrosion rate of metal surfaces, thousandths of an inch per year (mils/year) 11.2.1.5.3 Stress Corrosion Cracking sucetpibility or potential (e.g., active path dissolution SCC, chloride SCC, anhydrous ammonia SCC, hydrogen SCC, etc) 11.2.1.6 11.2.2 List of all corrosive properties List of all reactivity properties with other materials in process 11.2.1.6.1 Reactivity with water 11.2.1.6.2 Reactivity with mercury (e.g. aluminum) 11.2.1.6.3 Reactivity with other materials in process Process Hazards PROVIDE a description of process hazard identification and analyses conducted to date to identify potential hazardous events possible from the hazardous materials stored, processed, and handled onsite and analyze the safeguards necessary to mitigate such hazards. The description should reference the Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and Hazard Identification in Appendices 13.G.1 and 13.G.2, and all other applicable appendices. 14 15 ASTM E659, Standard Test Method for Autoignition Temperature of Liquid Chemicals. OECD 404, Acute Dermal Irritation/Corrosion; OECD TG 430, In Vitro Transcutaneous Electrical Resistance Test (TER); OECD 431, In Vitro Human Skin Model Test; OECD TG 435, In Vitro Membrane Barrier Test Method. Commission Staff Guidance 11-5 February 2017 11.2.3 Marine Transportation Hazards PROVIDE a description of marine transportation hazard identification and analyses conducted to date to identify the potential for hazardous events and analyze the safeguards and security necessary to mitigate such events along the transit route. The description should reference the Waterway Safety and Reliability Impact Studies 16 in Appendix 13.G.3, and all other applicable appendices, and should include: 11.2.4 11.2.3.1 Results of the ship simulation studies 11.2.3.2 Depictions of the marine hazard zones (accidental and intentional) 11.2.3.3 Areas impacted by the marine hazard zones (e.g., populated areas, transportation infrastructure, industrial facilities, public health and safety facilities, and military facilities) 11.2.3.4 Safeguards and security necessary to mitigate impacts Other Transportation Hazards PROVIDE a description of any potential hazards from transportation activities (e.g., road, rail, air) that may impact the proposed facilities. The description should reference Appendices 13.G.4, 13.G.5, and 13.G.6, and all other applicable appendices, and should include: 16 11.2.4.1 Transportation within the LNG plant boundaries 11.2.4.2 Transportation alongside or through the LNG plant 11.2.4.3 Safeguards that would mitigate impacts Waterway Suitability Assessments submitted to Coast Guard in accordance with 18 CFR §157.21(a)(1), 18 CFR §157.21(f)(13), 33 CFR §127.007, and Navigation and Vessel Inspection Circular (NVIC) 01-2011, Guidance Related to Waterfront Liquefied Natural Gas Facilities may satisfy Waterway Safety and Reliability Impact Studies in Appendix 13.G.3. This material may include Critical Energy Infrastructure Information (CEII), Security Sensitive Information (SSI), or Chemical-Terrorism Vulnerability Information (CVI) and must comply with all applicable regulations. Commission Staff Guidance 11-6 February 2017 11.2.5 Crane and Lifting Hazards PROVIDE a description of any potential hazards from crane and lifting activities that may impact the proposed facilities. The description should reference Appendices 13.G.7, and all other applicable appendices. 11.2.6 Adjacent Hazards PROVIDE a description of any potential hazards from facilities adjacent to the project site and describe any safeguards that would mitigate impacts. The description should reference Appendix 13.H.3 and all other applicable appendices. 11.2.7 Natural Hazards PROVIDE a description of natural hazard analyses conducted to date to identify the potential for hazardous events and the safeguards necessary to mitigate such events. The description should reference Appendices 13.I and 13.J, and all other applicable appendices. 11.2.8 Security Threats and Vulnerabilities 17 PROVIDE a description of the type of threat and vulnerability analyses that have been and will be conducted to identify potential hazardous events and the safeguards and security necessary to mitigate such events. At a minimum, the description should reference security threat and vulnerability assessments that have been or will be completed as part of the development of the facility or site security plan in Section 13.31 and Appendix 13.G.8 and all other applicable appendices. 17 Security Threat and Vulnerability Information prepared for or submitted to Coast Guard in accordance with 33 CFR §105.305 or prepared for or submitted to Department of Homeland Security (DHS) in accordance with 6 CFR §27.215 may satisfy Security Threat and Vulnerability Analyses in Appendix 13.G.8. This material may include Critical Energy Infrastructure Information (CEII), Security Sensitive Information (SSI), or ChemicalTerrorism Vulnerability Information (CVI) and should comply with all applicable regulations. Commission Staff Guidance 11-7 February 2017 11.3 HAZARD ANALYSES 18 11.3.1 Hazardous Releases PROVIDE a summary of the hazardous releases used for consequence modeling. The summary should demonstrate compliance with federal regulations 19 and should reference Appendix 13.H, and all other applicable appendices. The summary should tabulate: 18 19 11.3.1.1 Scenario number 11.3.1.2 Hazardous fluid 11.3.1.3 Size of hole/failure, in 11.3.1.4 Size of piping/equipment, in (piping), gal (vessels/tanks) 11.3.1.5 General location, plant area 11.3.1.6 Orientation, vertical, horizontal, other 11.3.1.7 Release height, ft 11.3.1.8 Release temperature, °F 11.3.1.9 Release pressure, psig (depressurization pressure, if applicable) 11.3.1.10 Release flow rate, lb/hr and gallons per minute (gpm) 11.3.1.11 Release duration, min or hr 11.3.1.12 Liquid rainout, %-vol 18 CFR §380.12(m)(2), 18 CFR §380.12(m)(3), 18 CFR §380.12(m)(5). This may include distinct hazards for DOT’s regulations at 49 CFR Part 193 and/or worst case and alternative scenarios for EPA’s regulations at 40 CFR Part 68, as applicable. Commission Staff Guidance 11-8 February 2017 11.3.2 Hot and Cold Fluid Temperature Hazard Analysis PROVIDE a summary of the of hot and cold temperature hazards from contact with liquid spills and jetting fluids or inadequately mitigated cascading events. The summary should demonstrate compliance with federal regulations 20 and should reference the complete Hazard Analysis Report(s) in Appendix 13.H, and relevant details in all other applicable appendices, and should summarize: 11.3.2.1 20 21 22 Models, assumptions, and uncertainties used to analyze hazards 11.3.2.1.1 Description of model used to analyze hazards and uncertainty in predictions based on scientific assessment, verification and validation results 11.3.2.1.2 Description of releases or inadequately mitigated cascading events used in modeling 11.3.2.1.3 Description of terrain and other surrounding features used in modeling 11.3.2.1.4 Description of structures, equipment, piping, and other plant components used in modeling 11.3.2.2 Description of grading, curbing, trenches, impoundments, and other hazard mitigation measures used in modeling 11.3.2.3 Drawing(s) with scale depicting grading, curbing, trenches, impoundments, and other hazard mitigation measures with directions of flow and other relevant descriptive features 11.3.2.4 Drawing(s) with scale depicting extent of potential contact burns (e.g., 160 °F 21) and thermal degradation for hot temperature hazards and potential freeze burns and embrittlement (e.g., –20 °F 22) for cold temperature hazards, relative to equipment, This may include design spills for DOT’s regulations at 49 CFR Part 193, worst case and alternative scenarios for EPA’s regulations at 40 CFR Part 68, and/or zones of concern for Coast Guard’s NVIC 01-2011, as applicable. ASTM C1055, Standard Guide for Heated System Surface Conditions that Produce Contact Burn Injuries; ASTM C680, Standard Practice for Estimate of the Heat Gain or Loss and the Surface temperatures of Insulated Flat, Cylindrical, and Spherical Systems by Use of Computer Programs. Based on minimum design metal temperatures (MDMT) in ASME Code for Pressure Piping, B31.3, Process Piping; ASME Boiler and Pressure Vessel Code Commission Staff Guidance 11-9 February 2017 occupied buildings, and property lines, taking into account any uncertainties of models and hazard mitigation measures 23 11.3.3 Asphyxiant and Toxic Vapor Dispersion Hazards Analysis PROVIDE a summary of the asphyxiant and toxic dispersion hazards from releases or inadequately mitigated cascading events. The summary should demonstrate compliance with federal regulations 24 and should reference the complete Hazard Analysis Report(s) in Appendix 13.H, and relevant details in all other applicable appendices, and should summarize: 11.3.3.1 23 24 25 Models, assumptions, and uncertainties used to analyze hazards 11.3.3.1.1 Description of model used to analyze hazards and uncertainty in predictions based on scientific assessment, verification and validation results 25 11.3.3.1.2 Description of releases or inadequately mitigated cascading events used in modeling 11.3.3.1.3 Description of the toxic endpoint concentration of AEGL-1, -2, and -3 and exposure duration 11.3.3.1.4 Description of wind direction, speed, stability, turbulence, temperature, relative humidity, ambient pressure, and other weather conditions used in modeling 11.3.3.1.5 Description of terrain and surface roughness, and other surrounding features used in modeling Hot and cold temperature hazards are typically limited by the heat transfer characteristics of the fluid. Direct contact with liquids, surfaces of equipment, or direct exposure to high momentum vapors at the release location tend to produce high enough heat transfer rates compared to vapors dispersing in low wind conditions. Referencing of properly designed spill containment and structural supports in Resource Report 13 is satisfactory to demonstrate these hot and cold temperature hazards from liquid spills will not impact the safety or reliability of the facilities. Referencing of properly designed piping and equipment thermal insulation in Resource Report 13 is satisfactory to demonstrate direct contact with surfaces of equipment would not pose a hazard. Referencing of properly done hazard modeling that shows hot and cold temperatures would not extend offsite or onto equipment or structural supports in Resource Report 13 is satisfactory to demonstrate hot and cold temperatures from vapor releases will not impact the safety or reliability of the facilities. The modeling should show this by tracking the temperature directly or by tracking the concentrations and correlating the concentrations with temperatures. This may include distinct hazards for DOT’s regulations at 49 CFR Part 193 and/or worst case and alternative scenarios for EPA’s regulations at 40 CFR Part 68, as applicable. Dispersion of a release with multiple toxins should discuss how all toxic components are accounted for in modeling when determining the toxic concentrations. Commission Staff Guidance 11-10 February 2017 26 27 28 11.3.3.1.6 Description of structures, equipment, piping, and other plant components used in modeling 11.3.3.1.7 Description of vapor barriers (material of construction, dimensions, locations, impermeability, maintenance requirements, etc.), fans, and other hazard mitigation measures used in modeling 26 11.3.3.2 Drawing(s) with scale depicting vapor barriers, fans, and other hazard mitigation measures with vapor barrier heights, fan capacities, and other descriptive information 11.3.3.3 Drawing(s) with scale depicting extent of 19.5 %-vol, 16 %-vol, and 12.5 %-vol oxygen concentrations 27 for asphyxiation hazards, relative to equipment, occupied buildings, and property lines taking into account any uncertainties of models and hazard mitigation measures 28 11.3.3.4 Drawing(s) with scale depicting extent of AEGL-1, -2, and -3 based on exposure time toxicity hazards, relative to equipment, occupied buildings, property lines, and offsite areas (e.g., populated areas, transportation infrastructure, industrial facilities, public health and safety facilities, and military facilities), taking into account any uncertainties of models (e.g., ½-AEGL-1, -2, -3) and hazard mitigation measures 11.3.3.5 Description of any mitigation measures to address the impacts that would exacerbate the initial hazard, including effects from intake of toxic or oxygen depriving vapors into occupied buildings. Active mitigation used in modeling should be supported with information on reliability of its operation and must be approved. ASNI Z88.2, American National Standard for Respiratory Protection, 1992. Hightower, M., Gritzo, L., Luketa-Hanlin, A., et al, Guidance on Risk Analysis and Safety Implications of a Large Liquefied Natural Gas (LNG) Spill Over Water, SAND2004-6258, December 2004. OSHA’s Respiratory Protection rule, 63 Fed. Reg. 1152, 1159 (Jan. 1998). Where flammable endpoint concentrations or toxic endpoint concentrations are less than asphyxiation endpoint concentrations and are modeled and shown to not impact the public, there does not need to be further demonstration that higher asphyxiation concentrations would also not impact the public as the dispersion distance of a lower concentration will encompass the dispersion distance of a higher concentration. Commission Staff Guidance 11-11 February 2017 11.3.4 Flammable Vapor Dispersion Hazards Analysis PROVIDE a summary of the flammable vapor dispersion hazards from releases or inadequately mitigated cascading events. The summary should demonstrate compliance with federal regulations 29 and should reference the complete Hazard Analysis Report(s) in Appendix 13.H, and relevant details in all other applicable appendices, and should summarize: 11.3.4.1 29 30 Models, assumptions, and uncertainties used to analyze hazards 11.3.4.1.1 Description of model used to analyze hazards and uncertainty in predictions based on scientific assessment, verification and validation results 11.3.4.1.2 Description of releases or inadequately mitigated cascading events used in modeling 11.3.4.1.3 Description of wind direction, speed, stability, turbulence, temperature, relative humidity, ambient pressure, and other weather conditions used in modeling 11.3.4.1.4 Description of terrain and surface roughness, and other surrounding features used in modeling 11.3.4.1.5 Description of structures, equipment, piping, and other plant components used in modeling 11.3.4.1.6 Description of vapor barriers, fans, and other hazard mitigation measures used in modeling 30 11.3.4.2 Drawing(s) with scale depicting vapor barriers, fans, and other hazard mitigation measures with vapor barrier heights, fan capacities, and other descriptive information 11.3.4.3 Drawing(s) with scale depicting extent of LFL and UFL concentrations for flammable vapor dispersion hazards, relative to equipment, occupied buildings, property lines, and offsite areas (e.g., populated areas, transportation infrastructure, industrial facilities, public health and safety facilities, and military facilities), This may include exclusion zones and other distinct hazardous zones for DOT’s regulations at 49 CFR Part 193, worst case and alternative scenarios for EPA’s regulations at 40 CFR Part 68, and/or zones of concern for Coast Guard’s NVIC 01-2011, as applicable. Active mitigation used in modeling should be supported with information about its operating reliability and must be approved to be used in modeling. Commission Staff Guidance 11-12 February 2017 taking into account any uncertainties of models (e.g., ½-LFL) and hazard mitigation measures 11.3.4.4 11.3.5 Description of any mitigation measures to address the impacts that would exacerbate the initial hazard, including cascading effects from ingestion into occupied buildings, and intake into fired equipment, dispersion to confined locations or congested areas. Vapor Cloud Overpressure Hazards Analysis PROVIDE a summary of the vapor cloud explosion (VCE) overpressure hazards that could result from releases or inadequately mitigated cascading events. The summary should demonstrate compliance with federal regulations 31 and should reference the complete Hazard Analysis Report(s) in Appendix 13.H, and relevant details in all other applicable appendices, and should summarize: 11.3.5.1 31 Models, assumptions, and uncertainties used to analyze hazards 11.3.5.1.1 Description of model used to analyze hazards and uncertainty in predictions based on scientific assessment, verification and validation results 11.3.5.1.2 Description of releases or inadequately mitigated cascading events used in modeling 11.3.5.1.3 Description of ignition source(s) and strength(s), if applicable to the model 11.3.5.1.4 Description of fluid 11.3.5.1.5 Description of vapor cloud concentration, homogeneity, size (e.g., dimensions and flammable mass), and location used in VCE modeling 11.3.5.1.6 Description of vapor cloud reactivity and laminar flame speed used in VCE modeling 11.3.5.1.7 Description of confinement from structures, equipment, piping, and other plant components used in VCE modeling 11.3.5.1.8 Description of congestion from equipment, piping, vegetation, and other plant components and surrounding features used in VCE modeling This may include distinct hazards for DOT’s regulations at 49 CFR Part 193 and/or worst case and alternative scenarios for EPA’s regulations at 40 CFR Part 68, as applicable. Commission Staff Guidance 11-13 February 2017 11.3.6 11.3.5.1.9 Description of structures, equipment, piping, and other plant components used in VCE modeling 11.3.5.1.10 Description of hardened structures, blast walls, and other hazard mitigation measures used in modeling 11.3.5.2 Drawing(s) with scale depicting hardened structures, blast walls, and other hazard mitigation measures with blast wall heights, ratings, and other descriptive information 11.3.5.3 Drawing(s) with scale depicting the extent of 1 psi, 3 psi, and 10 psi and projectiles (11 ft-lbf and higher) for overpressure hazards of vapor cloud explosions, relative to equipment, occupied buildings, property lines, and offsite areas (e.g., populated areas, transportation infrastructure, industrial facilities, public health and safety facilities, and military facilities), taking into account any uncertainties of models and any hazard mitigation measures 11.3.5.4 Description of any mitigation measures to address the impacts that would exacerbate the initial hazard, including cascading effects from failure of occupied buildings, more hazardous equipment, and safety related equipment. Fire Hazards Analysis PROVIDE a summary of the fireball, jet fire, and pool fire radiant heat hazards and impacts from releases or inadequately mitigated cascading events. The summary should demonstrate compliance with federal regulations 32 and should reference the complete Hazard Analysis Report(s) in Appendix 13.H, and relevant details in all other applicable appendices, and should summarize: 11.3.6.1 32 Models, assumptions, and uncertainties used to analyze hazards 11.3.6.1.1 Description of model used to analyze hazards and uncertainty in predictions based on scientific assessment, verification and validation results 11.3.6.1.2 Description of releases or inadequately mitigated cascading events used in modeling This may include exclusion zones and distinct hazards for DOT’s regulations at 49 CFR Part 193, worst-case and alternative scenarios for EPA’s regulations at 40 CFR Part 68, and/or zones of concern for Coast Guard’s NVIC 01-2011, as applicable. Commission Staff Guidance 11-14 February 2017 11.3.6.1.3 Description of wind direction, speed, stability, turbulence, temperature, relative humidity, ambient pressure, and other weather conditions used in modeling 11.3.6.1.4 Description of terrain and other surrounding features used in modeling 11.3.6.1.5 Description of structures, equipment, piping, and other plant components used in modeling 11.3.6.1.6 Description of fire walls, structural fire protection, and other hazard mitigation measures used in modeling 11.3.6.2 Drawing(s) with scale depicting fire walls, radiant heat shields, structural fire protection, mounding, and other hazard mitigation measures with fire wall heights, ratings, and other descriptive information 11.3.6.3 Drawing(s) with scale depicting the extent of equivalent 1,600 British thermal units (Btu)/ft2-hr and 40-second dose for radiant heat hazards of fireballs, relative to equipment, occupied buildings, property lines, and offsite areas (e.g., populated areas, transportation infrastructure, industrial facilities, public health and safety facilities, and military facilities), taking into account any uncertainties of models and any hazard mitigation measures 11.3.6.4 Drawing(s) with scale depicting the extent of 1,600 Btu/ft2-hr, 3,000 Btu/ft2-hr, and 10,000 Btu/ft2-hr for radiant heat hazards of jet fires, relative to equipment, occupied buildings, property lines, and offsite areas (e.g., populated areas, transportation infrastructure, industrial facilities, public health and safety facilities, and military facilities), taking into account any uncertainties of models and any hazard mitigation measures 11.3.6.5 Drawing(s) with scale depicting extent of 1,600 Btu/ft2-hr, 3,000 Btu/ft2-hr, and 10,000 Btu/ft2-hr for radiant heat hazards of pool fires, relative to equipment, occupied buildings, property lines, and offsite areas (e.g., populated areas, transportation infrastructure, industrial facilities, public health and safety facilities, and military facilities), taking into account any uncertainties of models and any hazard mitigation measures 11.3.6.6 Description of any mitigation measures to address the impacts that would exacerbate the initial hazard, including cascading effects from failure of occupied buildings, hazardous equipment, and safety related equipment. Commission Staff Guidance 11-15 February 2017 11.3.7 Vessel Overpressure Analyses PROVIDE a summary of the overpressure and projectile hazards from boiling-liquid expanding-vapor explosions (BLEVEs) and pressure vessel bursts (PVBs). Evaluate a two hour fire in impoundments, unless an impoundment could not receive that amount of flammable fluid, and also evaluate any jet fires that could be sustained. Also consider BLEVEs and PVBs of transportation vessels (e.g., trucks, railcars, etc.) at transfer stations. If any details about vessel design would not be known until a vendor is selected, use conservative estimates that cover the full range of potential values. Also, provide technical justifications for any design measures to mitigate the potential for vessel BLEVE and PVB events. The summary should reference relevant details in Appendix 13.H and all other applicable appendices and should summarize: 11.3.7.1 Models, assumptions, and uncertainties used to analyze hazards 11.3.7.1.1 Description of model used to analyze BLEVE and PVB hazards and uncertainty in predictions based on scientific assessment, verification and validation results 11.3.7.1.2 Description and amount of product in vessels used in BLEVE and PVB modeling 11.3.7.1.3 Description of structures, equipment, piping, and other plant components used in BLEVE and PVB modeling 11.3.7.1.4 Description of hardened structures, blast walls, and other hazard mitigation measures used in BLEVE and PVB modeling 11.3.7.2 Drawing(s) with scale depicting hardened structures, blast walls, and other hazard mitigation measures with blast walls’ heights, ratings, and other descriptive information 11.3.7.3 Drawing(s) with scale depicting extent of 1 psi, 3 psi, and 10 psi and projectiles (11 ft-lbf and higher) for overpressure hazards of BLEVEs and PVBs, relative to equipment, occupied buildings, property lines, and offsite areas (e.g., populated areas, transportation infrastructure, industrial facilities, public health and safety facilities, and military facilities) taking into account any uncertainties of models and any hazard mitigation measures 11.3.7.4 Drawing(s) with scale depicting the extent of equivalent 1,600 Btu/ft2-hr and 40 second dose for radiant heat hazards of fireballs, relative to equipment, occupied buildings, property lines, and offsite areas (e.g., populated areas, transportation infrastructure, industrial facilities, public health and safety Commission Staff Guidance 11-16 February 2017 facilities, and military facilities), taking into account any uncertainties of models and any hazard mitigation measures 11.3.7.5 11.3.8 Description of any mitigation measures to address impacts that would exacerbate the initial hazard, including cascading effects from failure of occupied buildings, more hazardous equipment, and safety related equipment. Fog or Steam Hazard Analyses PROVIDE a summary of visibility hazards due to water condensation (i.e., fog generation from ambient vaporizers or other cooling and heating systems or steam generation). The summary should demonstrate compliance with federal regulations and should reference the complete Hazard Analysis Report(s) in Appendix 13.H, and relevant details in all other applicable appendices, and should summarize: 11.3.8.1 33 Models, assumptions, and uncertainties used to analyze hazards 11.3.8.1.1 Description of model used to analyze dispersion hazards and uncertainty in predictions based on scientific assessment, verification and validation results 11.3.8.1.2 Description of fog and steam generation sources used in modeling 11.3.8.1.3 Description of wind direction, speed, stability, turbulence, temperature, relative humidity, ambient pressure, and other weather conditions used in modeling 11.3.8.1.4 Description of terrain and surface roughness, and other surrounding features used in modeling 11.3.8.1.5 Description of structures, equipment, piping, and other plant components used in modeling 11.3.8.1.6 Description of vapor barriers, fans, and other hazard mitigation measures used in modeling 33 11.3.8.2 Drawing(s) with scale depicting vapor barriers, fans, and other hazard mitigation measures with vapor barrier heights, fan capacities, and other descriptive information 11.3.8.3 Drawing(s) with scale depicting extent of visibility hazards, relative to equipment, occupied buildings, property lines, and Active mitigation used in modeling should be supported with information on reliability of its operation and must be approved to be used in modeling. Commission Staff Guidance 11-17 February 2017 offsite areas (e.g., populated areas, transportation infrastructure, industrial facilities, public health and safety facilities, and military facilities), taking into account any uncertainties of models and hazard mitigation measures 11.3.8.4 11.3.9 Description of any mitigation measures to address the impacts, including loss of visibility due to water condensation and other impacts that would exacerbate the initial hazard Other Hazard Analyses PROVIDE a summary of other hazards that may be unique to the installation and any related cascading events. The summary should demonstrate compliance with federal regulations 34 and should reference the complete Hazard Analysis Report(s) in Appendix 13.H, and relevant details in all other applicable appendices, and should summarize: 11.3.9.1 11.3.10 Models, assumptions, and uncertainties used to analyze hazards 11.3.9.1.1 Description of model used to analyze hazards and uncertainty in predictions based on scientific assessment, verification and validation results 11.3.9.1.2 Description of parameters used in modeling 11.3.9.2 Drawing(s) with scale depicting hazard mitigation measures with descriptive information 11.3.9.3 Drawing(s) with scale depicting the extent of hazard for reversible, irreversible, and fatal effects relative to equipment, occupied buildings, property lines, and offsite areas (e.g., populated areas, transportation infrastructure, industrial facilities, public health and safety facilities, and military facilities), taking into account any uncertainties of models and any hazard mitigation measures Hazardous Material Disposal PROVIDE a description of the disposal processes for hazardous materials, as well as the potential hazardous events that could occur and safeguards taken to prevent them. Reference all applicable appendices to Resource Report 13. 34 This may include exclusion zones and distinct hazards for DOT’s regulations at 49 CFR Part 193, worst case and alternative scenarios for EPA’s regulations at 40 CFR Part 68, and/or zones of concern for Coast Guard’s NVIC 01-2011, as applicable. Commission Staff Guidance 11-18 February 2017 11.4 LAYERS OF PROTECTION 35 11.4.1 Layers of Protection PROVIDE a summary of the basic design and various layers of protection and associated codes and standards to mitigate the risk of an incident impacting the safety or reliability of the plant’s design, construction, operation, maintenance, and management. At a minimum, the summary should describe: 11.4.1.1 11.4.1.1.1 Summary of basis of design used in structural design, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.1.2 Summary of regulatory requirements used in structural design, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.1.3 Summary of primary codes and standards used in structural design, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.1.4 Summary of design to withstand structural loads, including natural hazards, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.2 35 Structural design of the facilities and components Mechanical design of the facilities and components 11.4.1.2.1 Summary of basis of design used in mechanical design, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.2.2 Summary of regulatory requirements used in mechanical design, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.2.3 Summary of primary codes and standards used in mechanical design, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.2.4 Summary of provisions for (e.g. spare pump column without pump, equipment layout space for spare compressor, etc.) and installations of spare equipment and redundancies, and design to withstand internal and external pressures, temperatures, 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(1) thru (15). Commission Staff Guidance 11-19 February 2017 expansion/contraction, corrosion, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.3 Operations and maintenance plans 11.4.1.3.1 Summary of basis of design used in development of operation and maintenance plans and procedures, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.3.2 Summary of regulatory requirements used in development of operation and maintenance plans and procedures, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.3.3 Summary of primary codes and standards used in development of operation and maintenance plans and procedures, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.3.4 Summary of the development of operation and maintenance plans and procedures, including standard operation procedures, startup and shutdown procedures, abnormal operations, safety procedures, preventive maintenance plans, work order tracking, training, and management systems, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.4 Basic plant control systems (BPCS) 11.4.1.4.1 Summary of basis of design used in control system and operating modes, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.4.2 Summary of regulatory requirements used in control systems design, developing operational procedures, and training, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.4.3 Summary of primary codes and standards used in control systems design, developing operational procedures, and training, with reference to all applicable Resource Report 13 sections and Appendices for additional details Commission Staff Guidance 11-20 February 2017 11.4.1.4.4 11.4.1.5 Summary of the development of operating limits for flows, pressures, temperatures, and alarm management plans, with reference to all applicable Resource Report 13 sections and Appendices for additional details Safety instrumented systems (SIS) 11.4.1.5.1 Summary of basis of design used in safety instrumented systems, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.5.2 Summary of regulatory requirements used in safety instrumented systems design, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.5.3 Summary of primary codes and standards used in safety instrumented systems design, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.5.4 Summary of the current development of alarms and shutdowns (e.g. flows, pressures, temperatures) and plans for further development, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.6 Security systems and plans 11.4.1.6.1 Summary of basis of design used in security systems, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.6.2 Summary of regulatory requirements used in security systems design, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.6.3 Summary of primary codes and standards used in security systems design, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.6.4 Summary of lighting, fencing, access control, intrusion monitoring, intrusion detection, and security plans, with reference to all applicable Resource Report 13 sections and Appendices for additional details Commission Staff Guidance 11-21 February 2017 11.4.1.7 Physical protection devices 11.4.1.7.1 Summary of basis of design used in relief valve and flare/vent design, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.7.2 Summary of regulatory requirements used in relief valve and flare/vent design, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.7.3 Summary of primary codes and standards used in relief valve and flare/vent design, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.7.4 Summary of relief valve scenarios, set points, and capacities, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.8 Ignition controls 11.4.1.8.1 Summary of basis of design used in ignition controls, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.8.2 Summary of regulatory requirements used in ignition controls, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.8.3 Summary of primary codes and standards used in ignition controls, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.8.4 Summary of electrical area classification, hot work permits, equipment and building spacing and layouts, smoking restrictions, and static electricity (e.g., grounding/bonding, lightning protection) safeguards, with reference to all applicable Resource Report 13 sections and Appendices for additional details Commission Staff Guidance 11-22 February 2017 11.4.1.9 Spill containment systems 11.4.1.9.1 Summary of basis of design used in spill containment design, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.9.2 Summary of regulatory requirements used in spill containment design, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.9.3 Summary of primary codes and standards used in spill containment design, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.9.4 Summary of hazardous fluids contained by spill containment; spill containment dimensions, flow, and volumetric capacities; and spacing/location of spill containment systems, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.10 Passive protection for cryogenic fluids, overpressures, projectiles, and fire 11.4.1.10.1 Summary of basis of design used in passive protection, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.10.2 Summary of regulatory requirements used in passive protection, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.10.3 Summary of primary codes and standards used in passive protection, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.10.4 Summary of passive protection philosophy and performance requirements, with reference to all applicable Resource Report 13 sections and Appendices for additional details Commission Staff Guidance 11-23 February 2017 11.4.1.11 Hazard detection and notification systems 11.4.1.11.1 Summary of basis of design used in hazard detection, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.11.2 Summary of regulatory requirements used in hazard detection, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.11.3 Summary of primary codes and standards used in hazard detection, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.11.4 Summary of low temperature detection, flammable gas detection, fire detection, heat detection, smoke detection, oxygen deficiency detection, toxic detection, manual pushbuttons, and audible and/or visual alarms and notification, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.12 Hazard control equipment 11.4.1.12.1 Summary of basis of design used in hazard control, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.12.2 Summary of regulatory requirements used in hazard control, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.12.3 Summary of primary codes and standards used in hazard control, with reference to all applicable Resource Report 13 and Appendices for additional details 11.4.1.12.4 Summary of hand-held fire extinguishers, wheeled fire extinguishers, fire water systems, and hi-expansion foam systems, with reference to all applicable Resource Report 13 sections and Appendices for additional details Commission Staff Guidance 11-24 February 2017 11.4.1.13 Emergency response 11.4.1.13.1 Summary of emergency responders, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.13.2 Summary of regulatory requirements used in development of emergency response plans, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.13.3 Summary of primary codes and standards used in development of emergency response plans, with reference to all applicable Resource Report 13 sections and Appendices for additional details 11.4.1.13.4 Summarize and outline the development of onsite and offsite emergency response team/capabilities and procedures, cost sharing plans, and training, with reference to all applicable Resource Report 13 sections and Appendices for additional details Commission Staff Guidance 11-25 February 2017 11.5 RELIABILITY 36 11.5.1 Description of Reliability PROVIDE a description of the reliability of the proposed project facilities and equipment to minimize downtime and interruption of service, including a discussion of the following: 11.5.1.1 Equipment redundancies 11.5.1.2 Sparing philosophy 11.5.1.3 Warehouse philosophy 11.5.1.4 Anticipated plant reliability and availability 11.5.1.4.1 36 Plant reliability, availability, and maintainability (RAM) analyses with a reference to Appendix 13.E.6* 11.5.1.5 Contingency plans for failure of or impacts to major plant assets or operations due to accidental or natural disasters (e.g., cracked LNG storage tank, trucking incidents, etc.) 11.5.1.6 Design life of the facilities (e.g., 50 years) for purposes of determining time-dependent design conditions, such as fatigue cycling, corrosion allowances, sea-level rise, regional subsidence/gradual tectonic uplift or permafrost depths 18 CFR §380.12(m)(2) thru (5). Commission Staff Guidance 11-26 February 2017 13 RESOURCE REPORT 13 – ENGINEERING AND DESIGN MATERIAL 13.1 GENERAL BACKGROUND AND PROJECT MANAGEMENT 37 13.1.1 Project Facilities PROVIDE a description summarizing the proposed facilities. At a minimum, the description should include the following: 37 38 13.1.1.1 Number of marine docks, and with both rated and maximum export and import rates, million standard cubic feet per day (MMscfd) and million tons per annum (MTPA) 38 13.1.1.2 Number of LNG storage tanks, and with both net and gross storage capacity per tank, gal and cubic meter (m3) and equivalent billion standard cubic feet (Bscf) of natural gas 13.1.1.3 Number of liquefaction trains, and with both rated and anticipated maximum liquefaction capacity per train, MMscfd and MTPA 13.1.1.4 Number of LNG vaporizers, and with both sustained and anticipated maximum vaporization capacities, MMscfd 13.1.1.5 Number of feed gas pipelines and interconnects, and with both rated and anticipated maximum capacities, MMscfd, and pressures, psig 13.1.1.6 Number of sendout pipelines and interconnects, and with both rated and anticipated maximum sendout rates, MMscfd 13.1.1.7 Fractionation products, and with both rated and anticipated maximum capacity rates, gpm and MMscfd 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(8). Assumptions and supporting calculations used to determine export and import rates, including liquefaction rates, RAM studies, docking studies, and number of days assumed to be operational in a year, should be described, referenced, and included. Commission Staff Guidance 13-1 February 2017 13.1.2 Location PROVIDE a description of the site location of the facilities. At a minimum, the description should include: 13.1.2.1 13.1.3 Owned and leased property boundaries, options, easements, and rights of way with reference to Site Location Maps and Drawings in Appendix 13.A.1 Owner, Principal Contractors, and Operator PROVIDE a description of the owner, principal contractors, and operator of the facility. At a minimum, the description should discuss: 13.1.4 13.1.3.1 Owner of the facilities with reference to the Organizational Structure in Appendix 13.A.2 13.1.3.2 Principal Contractors identified for design, engineering, procurement, and construction of the facilities with reference to any preliminary Construction Workforce Organizational Chart or Work Breakdown Structure (if available) in Appendix 13.A.3* 13.1.3.3 Operating Company of the facilities with reference to a preliminary Operating Workforce Organizational Chart in Appendix 13.A.4* Feed and Sendout Product(s) PROVIDE a description summarizing the market for all products imported, exported, and sent out by the project. At a minimum, the description should include: 13.1.5 13.1.4.1 Natural gas pipeline(s) sending out to 13.1.4.2 Natural gas pipelines feeding from 13.1.4.3 Fractionation product pipelines sending out to Project Schedule PROVIDE a description of the project schedule, detailing project design, construction, commissioning, and in-service schedule with milestones. At a minimum, the project schedule description should reference the Gantt Chart in Appendix 13.A.5 and should provide sufficient detail to show the feasibility of the engineering, procurement, construction, commissioning, and startup of the facilities. Phased construction and operation, tie-ins, and future plans should also be summarized and included in the project schedule. Commission Staff Guidance 13-2 February 2017 13.2 SITE INFORMATION 39 13.2.1 Site Conditions PROVIDE a description of the site elevations. At a minimum, the description should reference the Topographic Map in Appendix 13.J.1 and should describe: 13.2.2 13.2.1.1 Elevation reference, North American Vertical Datum of 1988 (NAVD88) or National Geodetic Vertical Datum of 1929 (NGVD29) 13.2.1.2 Marine platform elevation, ft 13.2.1.3 LNG storage tank inner tank bottom elevation, ft 13.2.1.4 Process areas foundation elevation, ft 13.2.1.5 Impoundment floor elevation, ft 13.2.1.6 Utilities foundation elevation, ft 13.2.1.7 Buildings foundation elevation, ft 13.2.1.8 Roads elevation, ft Shipping Channel PROVIDE a description of the shipping channel. At a minimum, the description should reference the Bathymetric Chart in Appendix 13.J.2 and should describe: 39 13.2.2.1 Channel width, ft 13.2.2.2 Channel depth, ft 13.2.2.3 Berth depth, ft 13.2.2.4 Tidal range elevations, ft 13.2.2.5 Channel current (normal, maximum), knots 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14), 18 CFR §380.12(o)(15). Commission Staff Guidance 13-3 February 2017 13.2.3 Climatic Conditions PROVIDE a description of the climatic design conditions at the site and along the shipping channel. The description should reference the Climatic Data in Appendix 13.J.3, and all other applicable appendices, and should describe: 13.2.4 13.2.3.1 Temperature design basis (minimum, average, maximum), °F 13.2.3.2 Barometric pressure design basis (minimum, average, maximum), inches mercury (Hg) 13.2.3.3 Barometric pressure rate of increase design basis (minimum, average, maximum), inHg/h 13.2.3.4 Barometric pressure rate of decrease design basis (minimum, average, maximum), inHg/hr 13.2.3.5 Prevailing wind with seasonal wind rose or charts with 16 radial directions and wind speeds, mph 13.2.3.6 Rain fall rates design basis (100-year return period, 50-year return period, 10-year return period), inches per hour 13.2.3.7 Snow fall rates design basis (100-year return period, 50-year return period, 10-year period), inches per hour 13.2.3.8 Frost line depth, ft 13.2.3.9 Visibility frequency and distances, No. fog alerts per year, visibility ft 13.2.3.10 Lightning strike frequency, No. per year Geotechnical Conditions PROVIDE a description of the geotechnical conditions at the onshore and offshore permanently affixed facilities and structures as described below. The expected geotechnical testing is provided in the Appendix 13.J.4 guidance. 13.2.4.1 Groundwater conditions 13.2.4.2 Soil/rock layer description 13.2.4.3 Geotechnical cross-sections 13.2.4.4 Soil and rock parameters Commission Staff Guidance 13-4 February 2017 13.3 NATURAL HAZARD DESIGN CONDITIONS 40 13.3.1 Earthquakes PROVIDE a description of the design against earthquakes. The description should reference the Natural Hazard Design Investigations and Design Forces in Appendix 13.I.1, and all other applicable appendices, and should describe: 40 13.3.1.1 Seismic design basis and criteria for Seismic Category I, II, and III structures, systems and component 13.3.1.2 Identification of structures, systems and components classified as Seismic Category I, II, and III 13.3.1.3 Maximum considered earthquake (MCE) site-specific ground motion spectral values for 5% damping 13.3.1.4 Design earthquake (DE) site-specific ground motion spectral values for 5% damping and ground motion parameters, SDS, SD1, SMS, SM1, TL 13.3.1.5 Safety shutdown earthquake (SSE) site-specific ground motion spectral values for 5% damping 13.3.1.6 Operating basis earthquake (OBE) site-specific ground motion spectral values for 5% damping 13.3.1.7 Aftershock level earthquake (ALE) site-specific ground motion spectral values for 5% damping 13.3.1.8 At locations crossing active faults, design surface fault offsets (horizontal and vertical) and fault orientations 13.3.1.9 At locations where crossing growth faults, design offsets for growth faults: Provide design fault offsets for growth faults (horizontal and vertical) for the facility design life and fault orientations 13.3.1.10 Ground motions and frequencies of earthquakes at site location 13.3.1.11 Sloshing freeboard 13.3.1.12 Ground motion detection systems that alarm and shutdown 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14), 18 CFR §380.12(15). Commission Staff Guidance 13-5 February 2017 13.3.2 Tsunamis and Seiche PROVIDE a description of the design against tsunamis and seiche. The description should reference the Natural Hazard Design Investigations and Design Forces in Appendix 13.I.2, and all other applicable appendices, and should describe: 13.3.3 13.3.2.1 Tsunami and seiche design basis and criteria 13.3.2.2 Tsunami and seiche design inundation and run-up elevations and corresponding return periods for all structures, systems, and components 13.3.2.3 Maximum considered tsunami (MCT), MCT inundation and runup elevations for project site, including the MCE level ground motions at the site if the MCE is the triggering source of the MCT 13.3.2.4 Discussion of inundation and run up elevations and frequencies of tsunamis and other natural hazards at site location 13.3.2.5 Design sea level rise: elevation change to be used in design to account for sea level rise at project site for the facility design life 13.3.2.6 Design regional subsidence: elevation change to be used in design to account for regional subsidence at facility site for the facility design life 13.3.2.7 Discussion of co-seismic subsidence/uplift 13.3.2.8 Discussion of expected settlement over the design life of the facilities Hurricanes and Other Meteorological Events PROVIDE a description of the design against hurricanes and other meteorological events. The description should reference the Natural Hazard Design Investigations and Design Forces in Appendix 13.I.3, and all other applicable appendices, and should describe: 13.3.3.1 Wind and storm surge design basis and criteria 13.3.3.2 Identification of design wind speeds (sustained and 3-second gusts) and corresponding return periods, wind importance factors, and storm surge design elevations for all structures, systems, and components 13.3.3.3 Sea level rise: elevation change to be used to account for sea level rise at the site for the design life Commission Staff Guidance 13-6 February 2017 13.3.3.4 13.3.4 Regional subsidence: elevation change to be used to account for regional subsidence at the site for the design life Tornados PROVIDE a description of the design against tornados. The description should reference the Natural Hazard Design Investigation and Design Forces in Appendix 13.I.4, and all other applicable appendices, and should describe: 13.3.5 13.3.4.1 Wind speed design basis and criteria 13.3.4.2 Identification of design wind speeds (sustained and 3-second gusts) and corresponding return periods, and wind importance factors for all structures, systems, and components Floods PROVIDE a description of the design against floods. The description should reference the Natural Hazard Design Investigations and Design Forces in Appendix 13.I.5, and all other applicable appendices, and should describe: 13.3.6 13.3.5.1 Flood design basis and criteria 13.3.5.2 Identification of stream flows and flood design elevations and corresponding return periods for all structures, systems, and components 13.3.5.3 Discussion of streamflows, flood elevations, and frequencies of floods and other natural hazards at site location Rain, Ice, Snow, and Related Events PROVIDE a description of the design against blizzards. The description should reference the Natural Hazard Design Investigations and Design Forces in Appendix 13.I.6, and all other applicable appendices, and should describe: 13.3.6.1 Rainfall design basis and criteria 13.3.6.2 Ice load design basis and criteria 13.3.6.3 Snow load design basis and criteria 13.3.6.4 Identification of snow and ice loads and corresponding return periods for all structures, systems, and components, including snow removal for spill containment systems Commission Staff Guidance 13-7 February 2017 13.3.7 13.3.6.5 Identification of stormwater flows, outfalls, and stormwater management systems for all surfaces, including spill containment system sump pumps 13.3.6.6 Discussion of snow and ice formation and frequencies of blizzards and other snow and ice events at site location Other Natural Hazards PROVIDE a description of the design against landslides, wildfires, volcanic activity, geomagnetism, and other natural hazards. The description should reference the Natural Hazard Design Investigations and Design Forces in Appendix 13.I.7, and all other applicable appendices, and should describe: 13.3.7.1 Design basis and criteria 13.3.7.2 Identification of loads and corresponding return periods for all structures, systems, and components 13.3.7.3 Discussion of natural hazards and frequencies of natural hazards at site location Commission Staff Guidance 13-8 February 2017 13.4 MARINE FACILITIES 41 13.4.1 LNG Vessels PROVIDE a description of the LNG vessels (i.e., LNG carriers, LNG barges) that the facilities would be designed to accommodate. The description should reference the Waterway Safety and Reliability Impact Studies in Appendix 13.G.3 42, and all other applicable appendices, and should describe: 13.4.1.1 Shipping route within U.S. waters 13.4.1.2 Ship traffic 13.4.1.3 Ship simulations 13.4.1.4 Tug services, owned/leased 13.4.1.5 Tug services, full time/as required 13.4.1.6 Aids to navigation 13.4.1.7 LNG vessel size 13.4.1.8 LNG vessel draft 13.4.1.9 LNG vessel cargoes design and operating conditions and specifications for unloading and vapor recovery: 13.4.1.9.1 13.4.1.10 LNG vessel cargoes design and operating conditions and specifications for loading and vapor recovery: 13.4.1.10.1 41 42 Molecular weight, higher heating value (HHV), lower heating value (LHV), Wobbe, specific gravity, equilibrium temperature (°F) and cargo pressure (psig), composition Cargoes’ molecular weight, HHV, LHV, Wobbe, specific gravity, equilibrium temperature (°F) and cargo pressure (psig), composition 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(12) thru (14). Waterway Suitability Assessments submitted to Coast Guard in accordance with 18 CFR §157.21(a)(1), 18 CFR §157.21(f)(13), 33 CFR §127.007, and Navigation and Vessel Inspection Circular (NVIC) 01-2011, Guidance Related to Waterfront Liquefied Natural Gas Facilities may satisfy Waterway Safety and Reliability Impact Studies in Appendix 13.G.3. This material may include Critical Energy Infrastructure Information (CEII), Security Sensitive Information (SSI), or Chemical-Terrorism Vulnerability Information (CVI) and must comply with all applicable regulations. Commission Staff Guidance 13-9 February 2017 13.4.2 13.4.1.10.2 LNG vessel pump design pressure range, psig 13.4.1.10.3 LNG vessel pump design rates, gpm Marine Platform Design PROVIDE a description of the marine platform design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Project Specifications in Appendix 13.F, Marine Facility Drawings in Appendix 13.K, and all other applicable appendices, and should describe: 13.4.2.1 Wave crests and periods, ft 13.4.2.2 Prevailing currents (normal, maximum), knots 13.4.2.3 Tidal range elevations, ft 13.4.2.4 Water depth at berth and in approach channel, ft 13.4.2.5 LNG carrier capacity range, m3 13.4.2.6 LNG carrier approach velocity, knots 13.4.2.7 LNG carrier approach angle, degrees 13.4.2.8 LNG carrier unloading frequency, per year 13.4.2.9 LNG carrier unloading duration, hours 13.4.2.10 LNG carrier loading frequency, per year 13.4.2.11 LNG carrier loading duration, hours 13.4.2.12 LNG carrier port time, pilot on to pilot off, hours 13.4.2.13 Barge capacity range, m3 13.4.2.14 Barge approach velocity, knots 13.4.2.15 Barge approach angle, degrees 13.4.2.16 Barge unloading frequency, per year 13.4.2.17 Barge unloading duration, hours 13.4.2.18 Barge loading frequency, per year Commission Staff Guidance 13-10 February 2017 13.4.3 13.4.2.19 Barge loading duration, hours 13.4.2.20 Turning basin depth and radius, ft 13.4.2.21 Marine platform location/spacing 13.4.2.22 Jetty/trestle configuration 13.4.2.23 Number and design* of berths 13.4.2.24 Number and design* of hooks, quick release hooks 13.4.2.25 Number and design* of capstans 13.4.2.26 Number and design* of fenders 13.4.2.27 Number, arrangement, and design* of breasting dolphins 13.4.2.28 Number, arrangement, and design* of mooring dolphins 13.4.2.29 Current monitors 13.4.2.30 Vessel approach velocity monitors 13.4.2.31 Tension monitors 13.4.2.32 Marine platform other safety features Marine Transfer Design PROVIDE a description of the marine transfer design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 13.4.3.1 LNG arms or hoses and size per dock, No., in 13.4.3.2 Vapor arms or hoses and size per dock, No., in 13.4.3.3 Hybrid arms or hoses and size per dock, No., in 13.4.3.4 LNG arms or hoses operating and design flow rate capacities (minimum, normal, maximum), gpm 13.4.3.5 LNG arms or hoses operating (minimum, normal, maximum), psig Commission Staff Guidance 13-11 and design pressures February 2017 13.4.3.6 LNG arms or hoses operating and design temperatures at ship manifold (minimum, normal, maximum), °F 13.4.3.7 Vapor arms or hoses operating and design flow rate capacities (minimum, normal, maximum), lb/hr 13.4.3.8 Vapor arms or hoses operating and design pressures at ship manifold (minimum, normal, maximum), psig 13.4.3.9 Vapor arms or hoses operating and design temperatures at ship manifold (minimum, normal, maximum), °F 13.4.3.10 Marine transfer startup and operation 13.4.3.10.1 Marine transfer custody transfer 13.4.3.10.2 Marine transfer measurement and analysis 13.4.3.10.3 Unloading and/or loading 13.4.3.10.4 Recirculating system 13.4.3.10.5 Vapor return handling 13.4.3.10.6 Vapor return desuperheating 13.4.3.11 Marine transfer shutdown 13.4.3.12 Marine transfer piping, vessel, and equipment design and specifications 13.4.3.13 Marine transfer isolation valves, vents, and drains 13.4.3.14 Marine transfer basic process control systems 13.4.3.15 Marine transfer safety instrumented systems 13.4.3.16 Marine transfer relief valves and discharge 13.4.3.17 Marine transfer other safety features 13.4.3.17.1 Safe working envelope of transfer arms 13.4.3.17.2 Powered Emergency Release Coupling valves 13.4.3.17.3 Ship/shore communication and shutdown capability Commission Staff Guidance 13-12 February 2017 13.5 FEED GAS 43 13.5.1 Feed Gas Design PROVIDE a description of the feed gas design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 43 44 13.5.1.1 Feed gas battery limit operating and design flow rate capacities (minimum, normal, maximum), MMscfd 13.5.1.2 Feed gas battery limit operating (minimum, normal, maximum), psig 13.5.1.3 Feed gas battery limit operating and design temperatures (minimum, normal, maximum), °F 13.5.1.4 Feed gas operating and design inlet gas compositions (minimum/lean/light, normal/design/average, maximum/rich/heavy), %-vol and/or parts per million (ppm) 13.5.1.5 Feed gas filters 13.5.1.6 Feed gas booster compressor(s) type 44 13.5.1.7 Feed gas booster compressor(s), operating and spare 13.5.1.8 Feed gas booster compressor(s) flow (minimum, normal, maximum), MMscfd 13.5.1.9 Feed gas booster compressor(s) operating and design suction pressures (minimum, normal, maximum), psig 13.5.1.10 Feed gas booster compressor(s) operating and design suction temperatures (minimum, normal, maximum), °F 13.5.1.11 Feed gas booster compressor(s) operating and design discharge pressures (minimum, normal, maximum), psig and design pressures capacities each 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(12) thru (14). Applicants can supply data for sections 13.5.1.6 to 13.5.1.12 using Equipment Data Table in Attachment 2. Commission Staff Guidance 13-13 February 2017 13.5.1.12 Feed gas booster compressor(s) operating and design discharge temperatures (minimum, normal, maximum), °F 13.5.1.13 Feed gas startup and operation 13.5.1.13.1 Feed gas metering 13.5.1.13.2 Feed gas analysis and measurement 13.5.1.14 Feed gas shutdown 13.5.1.15 Feed gas piping, vessel, and equipment design and specifications 13.5.1.16 Feed gas isolation valves, drains, and vents 13.5.1.17 Feed gas basic process control systems 13.5.1.18 Feed gas high integrity pressure protection systems 13.5.1.19 Feed gas relief valves and discharge 13.5.1.20 Feed gas other safety features Commission Staff Guidance 13-14 February 2017 13.6 FEED GAS PRETREATMENT 45 13.6.1 Acid Gas Removal Design PROVIDE a description of the acid gas removal design. At a minimum, the description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 45 46 13.6.1.1 Acid gas removal system type 46 13.6.1.2 Acid gas removal operating and design inlet flow rate capacities (minimum, normal, maximum), MMscfd 13.6.1.3 Acid gas removal operating and design inlet gas compositions (minimum/lean/light, normal/design/average, maximum/rich/heavy), parts per million (ppm) 13.6.1.4 Acid gas removal operating and design inlet pressures (minimum, normal, maximum), psig 13.6.1.5 Acid gas removal operating and design inlet temperatures (minimum, normal, maximum), °F 13.6.1.6 Acid gas removal operating and design outlet flow rate capacities (minimum, normal, maximum), MMscfd 13.6.1.7 Acid gas removal operating and design outlet gas compositions (minimum/lean/light, normal/design/average, maximum/rich/heavy), ppm 13.6.1.8 Acid gas removal operating and design outlet pressures (minimum, normal, maximum), psig 13.6.1.9 Acid gas removal operating and design outlet temperatures (minimum, normal, maximum), °F 13.6.1.10 Acid gas disposal operating and design compositions, ppm 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(10), 18 CFR 380.12(o)(12) thru (14). Applicants can supply data for sections 13.6.1.1 to 13.6.1.9 using Equipment Data Table in Attachment 2. Commission Staff Guidance 13-15 February 2017 13.6.1.11 Acid gas disposal operating (minimum, normal, maximum), psig 13.6.1.12 Acid gas disposal operating and design outlet temperatures (minimum, normal, maximum), °F 13.6.1.13 Acid gas removal startup and operation 13.6.1.13.1 Normal startup and operation 13.6.1.13.2 Regeneration startup and operation and design pressures 13.6.1.14 Acid gas removal shutdown 13.6.1.15 Acid gas removal piping, vessel, and equipment design and specifications 13.6.1.16 Acid gas removal isolation valves, drains, and vents 13.6.1.16.1 Hydrogen sulfide removal/disposal 13.6.1.16.2 Carbon dioxide removal/disposal 13.6.1.17 Acid gas removal safety instrumented systems 13.6.1.18 Acid gas removal relief valves and discharge 13.6.1.19 Acid gas removal other safety features Commission Staff Guidance 13-16 February 2017 13.6.2 Mercury Removal Design PROVIDE a description of the mercury removal design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 13.6.2.1 Mercury specifications, ppm 13.6.2.2 Mercury removal type 47 13.6.2.3 Mercury removal operating and design inlet flow rate capacities (minimum, normal, maximum), lb/hr 13.6.2.4 Mercury removal operating and design inlet gas compositions (minimum/lean/light, normal/design/average, maximum/rich/heavy), ppm 13.6.2.5 Mercury removal operating and (minimum, normal, maximum), psig 13.6.2.6 Mercury removal operating and design inlet temperatures (minimum, normal, maximum), °F 13.6.2.7 Mercury removal operating and design outlet flow rate capacities (minimum, normal, maximum), lb/hr 13.6.2.8 Mercury removal operating and design outlet gas compositions (minimum/lean/light, normal/design/average, maximum/rich/heavy), ppm 13.6.2.9 Mercury removal operating and (minimum, normal, maximum), psig 13.6.2.10 Mercury removal operating and design outlet temperatures (minimum, normal, maximum), °F 13.6.2.11 Mercury removal startup and operation 13.6.2.12 Mercury removal isolation valves, drains, and vents 13.6.2.12.1 47 design design inlet outlet pressures pressures Mercury removal disposal Applicants can supply data for sections 13.6.2.2 to 13.6.2.10 using Equipment Data Table in Attachment 2. Commission Staff Guidance 13-17 February 2017 13.6.3 13.6.2.13 Mercury removal shutdown 13.6.2.14 Mercury removal piping, vessel, and equipment design and specifications 13.6.2.15 Mercury removal basic process control systems 13.6.2.16 Mercury removal safety instrumented systems 13.6.2.17 Mercury removal relief valves and discharge 13.6.2.18 Mercury removal other safety features Water Removal Design PROVIDE a description of the water removal design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 48 13.6.3.1 Water specifications, ppm 13.6.3.2 Dehydration system type 48 13.6.3.3 Dehydration operating and design (minimum, normal, maximum), lb/hr 13.6.3.4 Dehydration operating and design inlet compositions capacities (minimum, normal, maximum), ppm 13.6.3.5 Dehydration operating and design (minimum, normal, maximum), psig 13.6.3.6 Dehydration operating and design (minimum, normal, maximum), °F 13.6.3.7 Dehydration operating and design outlet flow rates (minimum, normal, maximum), lb/hr 13.6.3.8 Dehydration operating and design outlet gas compositions (minimum/lean/light, normal/design/average, maximum/rich/heavy), ppm inlet flow inlet inlet rates pressures temperatures Applicants can supply data for sections 13.6.3.2 to 13.6.3.10 using Equipment Data Table in Attachment 2. Commission Staff Guidance 13-18 February 2017 49 13.6.3.9 Dehydration operating and design (minimum, normal, maximum), psig 13.6.3.10 Dehydration operating and design (minimum, normal, maximum), °F outlet 13.6.3.11 Regeneration gas operating (minimum/lean/light, maximum/rich/heavy), lb/hr 49 design flow rates normal/design/average, 13.6.3.12 Regeneration gas operating and design temperatures to/from adsorber (minimum, normal, maximum), °F 13.6.3.13 Regeneration gas operating and design pressures to/from adsorber (minimum, normal, maximum), psig 13.6.3.14 Dehydration and regeneration startup and operation 13.6.3.15 Dehydration and regeneration isolation valves, drains, and vents 13.6.3.16 Dehydration and regeneration basic process control systems 13.6.3.17 Dehydration and regeneration safety instrumented systems 13.6.3.18 Dehydration and regeneration relief valves and discharge 13.6.3.19 Dehydration and regeneration other safety features and outlet pressures temperatures Applicants can supply data for sections 13.6.3.11 to 13.6.3.13 using Equipment Data Table in Attachment 2. Commission Staff Guidance 13-19 February 2017 13.7 NATURAL GAS LIQUIDS (NGL) REMOVAL, STORAGE, AND DISPOSITION 50 13.7.1 NGL Removal Design PROVIDE a description of the NGL removal design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 50 51 13.7.1.1 NGL removal type (Demethanizer, Deethanizer, Depropanizer, Debutanizer) 51 13.7.1.2 Number of NGL removal columns 13.7.1.3 NGL removal columns operating and design flow rate capacities (minimum, normal, maximum), gpm 13.7.1.4 NGL removal column operating and design inlet compositions (minimum/lean/light, normal/design/average, maximum/rich/heavy), %-vol 13.7.1.5 NGL removal columns operating and design pressures (minimum, normal, maximum), psig 13.7.1.6 NGL removal columns operating and design temperatures (minimum, normal, maximum), °F 13.7.1.7 NGL removal column operating and design products flow rates (minimum, normal, maximum), gpm 13.7.1.8 NGL removal column operating and design products compositions (minimum/lean/light, normal/design/average, maximum/rich/heavy), %-vol 13.7.1.9 NGL removal column operating and design products pressures (minimum, normal, maximum), psig 13.7.1.10 NGL removal column operating and design products temperatures (minimum, normal, maximum), °F 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(12) thru (14). Applicants can supply data for sections 13.7.1.1 to 13.7.1.10 using Equipment Data Table in Attachment 2. Commission Staff Guidance 13-20 February 2017 52 13.7.1.11 NGL removal reboilers operating and design flow rate capacities (minimum, normal, maximum), gpm 13.7.1.12 NGL removal reboilers operating and design duties (minimum, normal, maximum), MMBtu/hr 13.7.1.13 NGL removal reboilers operating and design pressures (minimum, normal, maximum), psig 13.7.1.14 NGL removal reboilers operating and design inlet temperatures (minimum, normal, maximum), °F 13.7.1.15 NGL removal reboilers operating and design outlet temperatures (minimum, normal, maximum), °F 13.7.1.16 NGL removal reflux pumps operating and design flow rate capacities (minimum, normal, maximum), gpm 52 13.7.1.17 NGL removal reflux pumps operating and design duties (minimum, normal, maximum), MMBtu/hr 13.7.1.18 NGL removal reflux pumps operating and design suction pressures (minimum, normal, maximum), psig 13.7.1.19 NGL removal reflux pumps operating and design inlet temperatures (minimum, normal, maximum), °F 13.7.1.20 NGL removal reflux pumps operating and design discharge pressures (minimum, normal, maximum), psig 13.7.1.21 NGL removal reflux pumps operating and design outlet temperatures (minimum, normal, maximum), °F 13.7.1.22 NGL removal columns startup and operation 13.7.1.23 NGL removal columns piping, vessel, and equipment design and specifications 13.7.1.24 NGL removal columns isolation valves, drains, and vents 13.7.1.25 NGL removal column basic process control systems 13.7.1.26 NGL removal columns safety instrumented systems Applicants can supply data for sections 13.7.1.16 to 13.7.1.21 using Equipment Data Table in Attachment 2. Commission Staff Guidance 13-21 February 2017 13.7.2 13.7.1.27 NGL removal columns relief valves and discharge 13.7.1.28 NGL columns other safety features NGL Storage Design PROVIDE a description of the NGL storage design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 13.7.2.1 NGL storage tank type 13.7.2.2 Number of NGL storage tanks 13.7.2.3 NGL storage tank foundation type 13.7.2.4 NGL storage tank operating (minimum, normal, maximum), gal 13.7.2.5 NGL storage tank operating and design levels (minimum, normal, maximum), ft 13.7.2.6 NGL storage tank operating and design vacuums and pressures (minimum, normal, maximum), inH2O (vacuum) and psig 13.7.2.7 NGL storage tank operating and design temperatures (minimum, normal, maximum), °F 13.7.2.8 NGL storage tank operating and design (minimum, normal, maximum), specific gravity 13.7.2.9 NGL storage startup and operation 13.7.2.10 NGL storage fill shutdown 13.7.2.11 NGL storage piping, vessel, and equipment design and specifications 13.7.2.12 NGL storage isolation valves, drains, and vents 13.7.2.13 NGL storage basic process control systems 13.7.2.14 NGL storage safety instrumented systems Commission Staff Guidance 13-22 and design capacities densities February 2017 13.7.3 13.7.2.15 NGL storage relief valves, discharge, and redundancy 13.7.2.16 NGL storage tank impoundment 13.7.2.17 NGL storage other safety features NGL Disposition Design PROVIDE a description of the NGL disposition design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 53 13.7.3.1 NGL final disposition (truck stations, sendout pipelines, reinjection, fuel gas, etc.) 13.7.3.2 Number of NGL truck stations or sendout pipelines 13.7.3.3 NGL truck scales or sendout metering 13.7.3.4 Number of NGL trucks, No. per year, truck capacity, gal 13.7.3.5 NGL pumps type 53 13.7.3.6 Number of NGL pumps, operating and spare 13.7.3.7 NGL truck fill/sendout/fuel gas operating and design flow rate capacities (minimum, normal, maximum), gpm or standard cubic feet per minute (scfm) 13.7.3.8 NGL trucking/sendout/fuel gas pumps operating and design suction pressures (minimum/net positive suction head [NPSH], normal/rated, maximum), psig 13.7.3.9 NGL pumps operating and design (minimum, normal, maximum), °F 13.7.3.10 NGL pumps operating and design discharge (minimum, normal/rated, maximum/shutoff), psig 13.7.3.11 NGL pumps operating and design discharge temperatures (minimum, normal/rated, maximum/shutoff), °F suction temperatures pressures Applicants can supply data for sections 13.7.3.5 to 13.7.3.12 using Equipment Data Table in Attachment 2. Commission Staff Guidance 13-23 February 2017 13.7.3.12 NGL pumps operating and design (minimum, normal, maximum), specific gravity 13.7.3.13 NGL truck/sendout startup and operation 13.7.3.14 NGL truck/sendout isolation valves, drains, and vents 13.7.3.15 NGL truck/sendout basic process control systems 13.7.3.16 NGL truck/sendout safety instrumented systems 13.7.3.17 NGL truck/sendout relief valves and discharge 13.7.3.18 NGL truck/sendout other safety features Commission Staff Guidance 13-24 densities February 2017 13.8 HEAVIES/CONDENSATES DISPOSITION 54 REMOVAL, 13.8.1 Heavies/Condensates Removal Design STORAGE, AND PROVIDE a description of the heavies/condensates removal design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 54 55 13.8.1.1 Heavies/condensates removal type 55 13.8.1.2 Heavies/condensates removal operating and design inlet flow rate capacities (minimum, normal, maximum), lb/hr 13.8.1.3 Heavies/condensates removal operating compositions (lean, normal, rich), %-vol 13.8.1.4 Heavies/condensates removal operating and design inlet pressures (minimum, normal, maximum), psig 13.8.1.5 Heavies/condensates removal operating and temperatures (minimum, normal, maximum), °F 13.8.1.6 Heavies/condensates removal operating and design outlet product flow rates (minimum, normal, maximum), lb/hr 13.8.1.7 Heavies/condensates removal operating and design outlet product compositions (lean, normal, rich), %-vol 13.8.1.8 Heavies/condensates removal outlet operating and design outlet pressures (minimum, normal, maximum), psig 13.8.1.9 Heavies/condensates removal outlet operating and design column temperatures (minimum, normal, maximum), °F 13.8.1.10 Heavies/condensates removal startup and operation 13.8.1.11 Heavies/condensates removal isolation valves, drains, and vents and design design inlet inlet 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(12) thru (14). Applicants can supply data for sections 13.8.1.1 to 13.8.1.9 using Equipment Data Table in Attachment 2. Commission Staff Guidance 13-25 February 2017 13.8.2 13.8.1.12 Heavies/condensates removal basic process control systems 13.8.1.13 Heavies/condensates removal safety instrumented systems 13.8.1.14 Heavies/condensates removal relief valves and discharge 13.8.1.15 Heavies/condensates removal other safety features Heavies/Condensates Storage Design PROVIDE a description of the heavies/condensates storage design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 13.8.2.1 Heavies/condensates storage tanks type 13.8.2.2 Number of heavies/condensates storage tanks 13.8.2.3 Heavies/condensates storage tanks foundation type 13.8.2.4 Heavies/condensates storage operating and design capacities (minimum, normal, maximum), gal 13.8.2.5 Heavies/condensates Storage operating and design liquid levels (minimum, normal, maximum), ft 13.8.2.6 Heavies/Condensates storage operating and design vacuums and pressures (minimum, normal, maximum), inH2O (vacuum) and psig 13.8.2.7 Heavies/condensates storage operating and design temperatures (minimum, normal, maximum), °F 13.8.2.8 Heavies/condensates storage operating and design densities (minimum, normal, maximum), specific gravity 13.8.2.9 Heavies/condensates storage startup and operation 13.8.2.10 Heavies/condensates storage isolation valves, drains, and vents 13.8.2.11 Heavies/condensates storage basic process control systems 13.8.2.12 Heavies/condensates storage safety instrumented systems Commission Staff Guidance 13-26 February 2017 13.8.3 13.8.2.13 Heavies/condensates redundancy storage relief valves, discharge, 13.8.2.14 Heavies/condensates storage impoundment 13.8.2.15 Heavies/condensates storage other safety features and Heavies/Condensates Disposition Design PROVIDE a description of the heavies/condensate disposition design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 56 13.8.3.1 Heavies/condensates final disposition (truck stations, sendout pipelines, reinjection, fuel gas, etc.) 13.8.3.2 Number of heavies/condensates truck stations or sendout pipelines 13.8.3.3 Heavies/condensates truck scales or sendout metering 13.8.3.4 Number of heavies/condensates truck capacity, gal 13.8.3.5 Heavies/condensates pumps type 56 13.8.3.6 Number of heavies/condensates pumps, operating and spare 13.8.3.7 Heavies/condensates truck fill/sendout/re-injection/fuel gas operating and design flow rate capacities (minimum, normal, maximum), gpm 13.8.3.8 Heavies/condensates trucking/sendout/fuel gas pumps operating and design suction pressures (minimum/ NPSH, normal/rated, maximum), psig 13.8.3.9 Heavies/condensates pumps operating and design suction temperatures (minimum, normal, maximum), °F 13.8.3.10 Heavies/condensates pumps operating and design discharge pressures (minimum, normal/rated, maximum/shutoff), psig trucks, No. per year, Applicants can supply data for sections 13.8.3.5 to 13.8.3.12 using Equipment Data Table in Attachment 2. Commission Staff Guidance 13-27 February 2017 13.8.3.11 Heavies/condensates pumps operating and design discharge temperatures (minimum, normal/rated, maximum/shutoff), °F 13.8.3.12 Heavies/condensates pumps operating and design densities (minimum, normal, maximum), specific gravity 13.8.3.13 Heavies/condensates truck/sendout startup and operation 13.8.3.14 Heavies/condensates truck/sendout isolation valves, drains, and vents 13.8.3.15 Heavies/condensates truck/sendout basic process control systems 13.8.3.16 Heavies/condensates truck/sendout safety instrumented systems 13.8.3.17 Heavies/condensates truck/sendout relief valves and discharge 13.8.3.18 Heavies/condensates truck/sendout other safety features Commission Staff Guidance 13-28 February 2017 13.9 LIQUEFACTION SYSTEM 57 13.9.1 Refrigerant Trucking/Production Design PROVIDE a description of the refrigerant trucking/production design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 57 13.9.1.1 Source 13.9.1.2 Number of refrigerant trucks during startup, truck capacity, gal 13.9.1.3 Number of refrigerant trucks, No. per year, truck capacity, gal 13.9.1.4 Refrigerant trucking/production operating and design compositions (minimum, normal, maximum), %-vol 13.9.1.5 Refrigerant trucking/production operating and design flow rate capacities (minimum, normal, maximum), gpm 13.9.1.6 Refrigerant trucking/production pumps operating and design suction pressures (minimum/NPSH, normal/rated, maximum), psig 13.9.1.7 Refrigerant trucking/production pumps operating and design suction temperatures (minimum, normal, maximum), °F 13.9.1.8 Refrigerant trucking/production pumps operating and design discharge pressures (minimum, normal/rated, maximum/shutoff), psig 13.9.1.9 Refrigerant trucking/production pumps operating and design discharge temperatures (minimum, normal/rated, maximum/shutoff), °F 13.9.1.10 Refrigerant trucking/production pumps operating and design densities (minimum, normal, maximum), specific gravity 13.9.1.11 Number of refrigerant truck stations 13.9.1.12 Refrigerant truck scales 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(12) thru (14). Commission Staff Guidance 13-29 February 2017 13.9.1.13 13.9.2 Refrigerant trucking/production startup and operation 13.9.1.13.1 Truck unloading system 13.9.1.13.2 Refrigerant pretreatment system 13.9.1.13.3 Vapor handling 13.9.1.13.4 Pumps 13.9.1.13.5 Refrigerant transfer/makeup system 13.9.1.14 Refrigerant trucking/production isolation valves, drains, and vents 13.9.1.15 Refrigerant trucking/production basic process control systems 13.9.1.16 Refrigerant trucking/production safety instrumented systems 13.9.1.17 Refrigerant trucking/production relief valves and discharge 13.9.1.18 Refrigerant trucking/production other safety features Refrigerant Storage Design PROVIDE a description of the refrigerant storage design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 13.9.2.1 Refrigerant storage tank type 13.9.2.2 Number of refrigerant storage tanks, operating and spare 13.9.2.3 Refrigerant storage tanks foundations type 13.9.2.4 Refrigerant storage operating (minimum, normal, maximum), gal 13.9.2.5 Refrigerant storage operating and design levels (minimum, normal, maximum), ft 13.9.2.6 Refrigerant storage operating and design pressures/vacuums (minimum, normal, maximum), inH2O (vacuum) and psig 13.9.2.7 Refrigerant storage operating and design temperatures (minimum, normal, maximum), °F Commission Staff Guidance 13-30 and design capacities February 2017 13.9.3 13.9.2.8 Refrigerant storage operating and design (minimum, normal, maximum), specific gravity densities 13.9.2.9 Refrigerant storage startup and operation 13.9.2.10 Refrigerant storage isolation valves, drains, and vents 13.9.2.11 Refrigerant storage basic process control systems 13.9.2.12 Refrigerant storage safety instrumented systems 13.9.2.13 Refrigerant storage relief valves, discharge, and redundancy 13.9.2.14 Refrigerant storage tanks impoundment 13.9.2.15 Refrigerant storage other safety features Refrigerant Charge/Loading Pumps Design PROVIDE a description of the refrigerant charge/loading pump design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 58 13.9.3.1 Refrigerant pumps type 58 13.9.3.2 Number of refrigerant pumps, operating and spare 13.9.3.3 Refrigerant pumps operating and design flow rate capacities (minimum, normal/rated, maximum), gpm 13.9.3.4 Refrigerant pumps operating and design suction pressures (minimum/NPSH, normal/rated, maximum), psig 13.9.3.5 Refrigerant pumps operating and design suction temperatures (minimum, normal, maximum), °F 13.9.3.6 Refrigerant pumps operating and design discharge pressures (minimum, normal/rated, maximum/shutoff), psig 13.9.3.7 Refrigerant pumps operating and design discharge temperatures (minimum, normal, maximum), °F Applicants can supply data for sections 13.9.3.1 to 13.9.3.8 using Equipment Data Table in Attachment 2. Commission Staff Guidance 13-31 February 2017 13.9.4 13.9.3.8 Refrigerant pumps operating and design (minimum, normal, maximum), specific gravity 13.9.3.9 Refrigerant pumps startup and operation 13.9.3.10 Refrigerant pumps isolation valves, drains, and vents 13.9.3.11 Refrigerant pumps basic process control systems 13.9.3.12 Refrigerant pumps safety instrumented systems 13.9.3.13 Refrigerant pumps relief valves and discharge 13.9.3.14 Refrigerant pumps other safety features densities Liquefaction Design PROVIDE a description of the liquefaction design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 13.9.4.1 Feed gas precooling system 13.9.4.2 Number of liquefaction trains 13.9.4.3 Liquefaction process type (mixed refrigerant, cascade, nitrogen, etc.) 13.9.4.4 Main refrigerant heat exchangers, cold box(es), etc. 13.9.4.5 Refrigerant compressors and drivers 13.9.4.6 Liquefaction operating and design flow rate capacities (minimum, normal, maximum), MMscfd 13.9.4.7 Liquefaction operating and design inlet compositions (minimum/lean/light, normal/design/average, maximum/rich/ heavy), %-vol 13.9.4.8 Liquefaction operating and design (minimum, normal, maximum), psig 13.9.4.9 Liquefaction operating and design (minimum, normal, maximum), °F Commission Staff Guidance 13-32 inlet inlet pressures temperatures February 2017 13.9.4.10 Liquefaction final exchanger operating and design outlet pressures (minimum, normal, maximum), psig 13.9.4.11 Liquefaction final exchanger operating and design outlet temperatures (minimum, normal, maximum), °F 13.9.4.12 Liquefaction condenser operating and design inlet temperatures (minimum, normal, maximum), °F 13.9.4.13 Liquefaction condenser operating and design outlet temperatures (minimum, normal, maximum), °F 13.9.4.14 Liquefaction cooling fluid operating and design inlet temperatures (minimum, normal, maximum), °F 13.9.4.15 Liquefaction cooling fluid operating and design outlet temperatures (minimum, normal, maximum), °F 13.9.4.16 Liquefaction operating and design (minimum, normal, maximum), °F 13.9.4.17 Refrigerant compressor operating and design flow rate capacities (minimum, normal, maximum), MMscfd 13.9.4.18 Refrigerant compressor operating and design suction pressures (minimum, normal, maximum), psig 13.9.4.19 Refrigerant operating and design discharge pressures (minimum, normal, maximum/shutoff), psig 13.9.4.20 Liquefaction system startup and operation 13.9.4.21 Liquefaction system isolation valves, drains, and vents 13.9.4.22 Liquefaction system basic process control systems 13.9.4.23 Liquefaction system safety instrumented systems 13.9.4.24 Liquefaction system relief valves and discharge 13.9.4.25 Liquefaction system other safety features Commission Staff Guidance 13-33 air temperatures February 2017 13.9.5 Cooling System Design PROVIDE a description of the cooling system design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 13.9.5.1 Cooling system source and type 13.9.5.2 Cooling system operating and (minimum, normal, maximum), gal 13.9.5.3 Cooling system operating and design flow rate capacities (minimum, normal, maximum), gpm 13.9.5.4 Cooling system operating and design delivery pressures (minimum, normal, maximum), psig 13.9.5.5 Cooling system operating and design delivery temperatures (minimum, normal, maximum), °F 13.9.5.6 Cooling system operating and (minimum, normal, maximum), psig 13.9.5.7 Cooling system operating and design return temperatures (minimum, normal, maximum), °F 13.9.5.8 Cooling system startup and operation 13.9.5.9 Cooling system isolation valves, drains, and vents 13.9.5.10 Cooling system basic process control systems 13.9.5.11 Cooling system safety instrumented systems 13.9.5.12 Cooling system relief valves and discharge 13.9.5.13 Cooling system other safety features Commission Staff Guidance 13-34 design design storage return capacities pressures February 2017 13.10 LNG PRODUCT TRANSFER TO STORAGE 59 13.10.1 LNG Transfer to Storage Design PROVIDE a description of the LNG transfer system design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 59 13.10.1.1 LNG Product transfer pumps type 13.10.1.2 Number of LNG Product transfer pumps, operating and spare 13.10.1.3 LNG Product transfer operating and design flow rate capacities (minimum, normal/rated, maximum), gpm 13.10.1.4 LNG Product transfer operating and design suction pressures (minimum/NPSH, normal/rated, maximum), psig 13.10.1.5 LNG Product transfer operating and design suction temperatures (minimum, normal, maximum), °F 13.10.1.6 LNG Product transfer operating and design discharge pressures (minimum, normal/rated, maximum/shutoff), psig 13.10.1.7 LNG Product transfer operating and design discharge temperatures (minimum, normal, maximum), °F 13.10.1.8 LNG Product transfer operating and design (minimum, normal/rated, maximum), specific gravity 13.10.1.9 LNG flash vessel operating and design inlet pressures (minimum, normal, maximum), psig 13.10.1.10 LNG flash vessel operating and design inlet temperatures (minimum, normal, maximum), °F 13.10.1.11 LNG flash vessel operating and design outlet pressures (minimum, normal, maximum), psig densities 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(12) thru (14). Commission Staff Guidance 13-35 February 2017 13.10.1.12 LNG flash vessel operating and design outlet temperatures (minimum, normal, maximum), °F 13.10.1.13 Flash gas compressor operating and design flow rate capacities (minimum, normal, maximum), MMscfd 60 13.10.1.14 Flash gas compressor operating and design suction pressures (minimum, normal, maximum), psig 13.10.1.15 Flash gas compressor operating and design suction temperatures (minimum, normal, maximum), °F 13.10.1.16 Flash gas compressor operating and design discharge pressures (minimum, normal, maximum/shutoff), psig 13.10.1.17 Flash gas compressor operating and design outlet temperatures (minimum, normal, maximum), °F 13.10.1.18 LNG Product transfer startup and operation 13.10.1.19 LNG Product transfer isolation valves, drains, and vents 13.10.1.20 LNG Product transfer basic process control systems 13.10.1.20.1 LNG product flow control 13.10.1.20.2 LNG flash drum pressure control 13.10.1.20.3 LNG flash vapor handling 60 13.10.1.21 LNG Product transfer safety instrumented systems 13.10.1.22 LNG Product transfer relief valves and discharge 13.10.1.23 LNG Product transfer other safety features Applicants can supply data for sections 13.10.1.13 to 13.10.1.17 using Equipment Data Table in Attachment 2. Commission Staff Guidance 13-36 February 2017 13.11 LNG STORAGE TANKS 61 13.11.1 LNG Storage Tank Design PROVIDE a description of the LNG storage tank design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, LNG Storage Tank Information in Appendix 13.L, and all other applicable appendices and should describe: 61 13.11.1.1 LNG storage tank type (above ground, below ground, single, double, full, membrane, etc.) 13.11.1.2 Number of LNG storage tanks 13.11.1.3 LNG storage tank foundation type 13.11.1.4 LNG storage tank insulation systems 13.11.1.5 LNG storage tanks operating and (minimum, normal, maximum), gal or m3 13.11.1.6 LNG storage tanks operating (minimum, normal, maximum), ft 13.11.1.7 LNG storage tanks operating and design pressures/vacuums (minimum, normal, maximum), inH2O (vacuum) and psig 13.11.1.8 LNG storage tanks operating and design temperatures (minimum, normal, maximum), °F 13.11.1.9 LNG storage tanks operating and design (minimum, normal, maximum), specific gravity 13.11.1.10 LNG storage tanks operating and design (minimum, normal, maximum), %-vol per day 13.11.1.11 LNG storage operating and design residence times, days/hours 13.11.1.12 Hydrotest water source and design design capacities liquid levels densities boil-off rate 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7) thru (10), 18 CFR §380.12(o)(12) thru (14). Commission Staff Guidance 13-37 February 2017 13.11.1.13 Hydrotest water specifications and concentrations, %-vol or ppmv 13.11.1.14 Hydrotest water available flow rate, gpm 13.11.1.15 Hydrotest water pressure, psig 13.11.1.16 Hydrotest water discharge/treatment 13.11.1.17 LNG storage tank startup and operation 13.11.1.18 LNG storage tank isolation valves, drains, and vents 13.11.1.19 LNG storage tank piping support system 13.11.1.20 LNG storage tank basic process control systems 13.11.1.20.1 LNG storage tank cooldown sensors 13.11.1.20.2 LNG storage tank level control 13.11.1.20.3 LNG storage tank pressure control 13.11.1.20.4 LNG storage tank density/rollover control 13.11.1.21 LNG storage tank safety instrumented systems 13.11.1.21.1 LNG storage tank overfill protection 13.11.1.21.2 LNG storage tank overpressure protection 13.11.1.22 LNG storage tank relief valves and discharge 13.11.1.22.1 Calculations for sizing pressure and vacuum relief valves 13.11.1.23 LNG storage tank Impoundment System 13.11.1.23.1 LNG storage tank containment 13.11.1.23.2 LNG storage tank roof spill containment and protection 13.11.1.24 LNG storage tank other safety features 13.11.1.24.1 LNG storage tank leak detection instrumentation 13.11.1.24.2 Foundation frost heave mitigation (heaters temperature detection) Commission Staff Guidance 13-38 February 2017 13.12 VAPOR HANDLING 62 13.12.1 Vapor Handling Design PROVIDE a description of the vapor handling design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 62 63 13.12.1.1 Vapor return blowers type 63 13.12.1.2 Number of vapor return blowers, operating and spare 13.12.1.3 Vapor return blowers operating and design flow rate capacities (minimum, normal/rated, maximum), lb/hr 13.12.1.4 Vapor return blowers operating and design suction pressures (minimum, normal/rated, maximum), psig 13.12.1.5 Vapor return blowers operating and design suction temperatures (minimum, normal, maximum), °F 13.12.1.6 Vapor return blowers operating and design discharge pressures (minimum, normal/rated, maximum/shutoff), psig 13.12.1.7 Vapor return blowers operating and design discharge temperatures (minimum, normal, maximum), °F 13.12.1.8 Boil-off gas (BOG) low pressure compressors type 13.12.1.9 Number of BOG low pressure compressors, operating and spare 13.12.1.10 BOG low pressure compressors operating and design flow rate capacities (minimum, normal/rated, maximum), lb/hr 13.12.1.11 BOG low pressure compressors operating and design suction pressures (minimum, normal/rated, maximum), psig 13.12.1.12 BOG low pressure compressors operating and design suction temperatures (minimum, normal, maximum), °F 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(12) thru (14). Applicants can supply data for sections 13.12.1.1 to 13.12.1.21 using Equipment Data Table in Attachment 2. Commission Staff Guidance 13-39 February 2017 13.12.1.13 BOG low pressure compressors operating and design discharge pressures (minimum, normal/rated, maximum/shutoff), psig 13.12.1.14 BOG low pressure compressors operating and design discharge temperatures (minimum, normal, maximum), °F 13.12.1.15 BOG high pressure compressors type 13.12.1.16 Number of BOG high pressure compressors, operating and spare 13.12.1.17 BOG high pressure compressors operating and design flow rate capacities (minimum, normal/rated, maximum), lb/hr 13.12.1.18 BOG high pressure compressors operating and design suction pressures (minimum, normal/rated, maximum), psig 13.12.1.19 BOG high pressure compressors operating and design suction temperatures (minimum, normal, maximum), °F 13.12.1.20 BOG high pressure compressors operating and design discharge pressures (minimum, normal/rated, maximum/shutoff), psig 13.12.1.21 BOG high pressure compressors operating and design discharge temperatures (minimum, normal, maximum), °F 13.12.1.22 Vapor handling startup and operation 13.12.1.22.1 Vapor return blowers to or from the LNG vessel 13.12.1.22.2 BOG low pressure compression 13.12.1.22.3 BOG high pressure compression, including BOG holding mode compression to pipeline 13.12.1.22.4 BOG utilization 13.12.1.23 Vapor handling isolation valves, drains, and vents 13.12.1.24 Vapor handling basic process control systems 13.12.1.25 Vapor handling safety instrumented systems 13.12.1.26 Vapor handling relief valves and discharge 13.12.1.27 Vapor handling other safety features Commission Staff Guidance 13-40 February 2017 13.12.2 Boil-off Gas (BOG) Re-Condensation Design PROVIDE a description of the BOG re-condensation design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 13.12.2.1 BOG recondenser type 13.12.2.2 Number of BOG recondensers, operating and spare 13.12.2.3 BOG recondensers operating and design inlet flow rate capacities (minimum, normal/rated, maximum), lb/hr 13.12.2.4 BOG recondensers operating and design inlet pressures (minimum, normal/rated, maximum), psig 13.12.2.5 BOG recondensers operating and design inlet temperatures (minimum, normal, maximum), °F 13.12.2.6 BOG recondensers operating and design outlet flow rate capacities (minimum, normal/rated, maximum), lb/hr 13.12.2.7 BOG recondensers operating and design outlet pressures (minimum, normal/rated, maximum), psig 13.12.2.8 BOG recondensers operating and design outlet temperatures (minimum, normal, maximum), °F 13.12.2.9 BOG recondenser startup and operation 13.12.2.9.1 Minimum sendout rate for recondensation 13.12.2.9.2 BOG recondensation 13.12.2.10 BOG recondenser isolation valves, drains, and vents 13.12.2.11 BOG recondenser basic process control systems 13.12.2.12 BOG recondenser safety instrumented systems 13.12.2.13 BOG recondenser relief valves and discharge 13.12.2.14 BOG recondenser other safety features Commission Staff Guidance 13-41 February 2017 13.13 LNG PUMPS 64 13.13.1 LNG Tank/Low Pressure (LP) Pump Design PROVIDE a description of the LNG LP pump design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 64 65 13.13.1.1 LNG tank/LP pumps type 65 13.13.1.2 Number of LNG tank/LP pumps, operating and spare 13.13.1.3 LNG tank/LP pumps operating and design flow rate capacities (minimum, normal/rated, maximum), gpm 13.13.1.4 LNG tank/LP pumps operating and design suction pressures (minimum/NPSH, normal/rated, maximum), psig 13.13.1.5 LNG tank/LP pumps operating and design suction temperatures (minimum, normal, maximum), °F 13.13.1.6 LNG tank/LP pumps operating and design discharge pressures (minimum, normal/rated, maximum/shutoff), psig 13.13.1.7 LNG tank/LP pumps operating and design discharge temperatures (minimum, normal, maximum), °F 13.13.1.8 LNG tank/LP pumps operating and design (minimum, normal/rated, maximum), specific gravity 13.13.1.9 LNG tank/LP pumps startup and operation densities 13.13.1.9.1 LNG pump to marine transfer (LNG carrier, LNG barge, etc.) 13.13.1.9.2 LNG pump to sendout for vaporization 13.13.1.9.3 LNG pump minimum flow recycle 13.13.1.9.4 LNG pump recirculation to marine transfer 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(12) thru (14). Applicants can supply data for sections 13.13.1.1 to 13.13.1.8 using Equipment Data Table in Attachment 2. Commission Staff Guidance 13-42 February 2017 13.13.1.9.5 LNG pump recirculation to sendout for vaporization 13.13.1.9.6 LNG pump inter tank transfer 13.13.1.10 LNG tank/LP pumps isolation valves, drains, and vents 13.13.1.11 LNG tank/LP pumps basic process control systems 13.13.1.11.1 LNG pump flow control 13.13.2 13.13.1.12 LNG tank/LP pumps safety instrumented systems 13.13.1.13 LNG tank/LP pumps relief valves and discharge 13.13.1.14 LNG tank/LP pumps other safety features LNG Sendout/High Pressure (HP) System Design PROVIDE a description of the LNG HP pump design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 66 13.13.2.1 LNG HP pumps type 66 13.13.2.2 Number of LNG HP pumps, operating and spare 13.13.2.3 LNG HP pumps operating and design flow rate capacities (minimum, normal/rated, maximum), gpm 13.13.2.4 LNG HP pumps operating and design suction pressures (minimum/NPSH, normal/rated, maximum), psig 13.13.2.5 LNG HP pumps operating and design suction temperatures (minimum, normal, maximum), °F 13.13.2.6 LNG HP pumps operating and design discharge pressures (minimum, normal/rated, maximum/shutoff), psig 13.13.2.7 LNG HP pumps operating and design discharge temperatures (minimum, normal, maximum), °F Applicants can supply data for sections 13.13.2.1 to 13.13.2.8 using Equipment Data Table in Attachment 2. Commission Staff Guidance 13-43 February 2017 13.13.2.8 LNG HP pumps operating and design (minimum, normal, maximum), specific gravity 13.13.2.9 LNG HP pumps startup and operation 13.13.2.9.1 LNG pump to vaporization 13.13.2.9.2 LNG pump minimum flow recycle 13.13.2.10 LNG HP pumps isolation valves, drains, and vents 13.13.2.11 LNG HP pumps basic process control systems densities 13.13.2.11.1 LNG pump flow control 13.13.2.12 LNG HP pumps safety instrumented systems 13.13.2.13 LNG HP pumps relief valves and discharge 13.13.2.14 LNG HP pumps other safety features Commission Staff Guidance 13-44 February 2017 13.14 LNG TRUCKING 67 13.14.1 LNG Trucking Design PROVIDE a description of the LNG trucking design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 67 68 13.14.1.1 Number of LNG trucks unloaded, No. per year 13.14.1.2 LNG truck unloaded capacities, gal 13.14.1.3 Number of LNG trucks loaded, No. per year 13.14.1.4 LNG truck loaded capacities, gal 13.14.1.5 Number of LNG truck stations 13.14.1.6 LNG truck scales 13.14.1.7 LNG truck unloading operating and design flow rate capacities (minimum, normal, maximum), gpm 13.14.1.8 LNG truck loading operating and design flow rate capacities (minimum, normal, maximum), gpm 13.14.1.9 LNG truck unloading operating (minimum, normal, maximum), psig and design pressures 13.14.1.10 LNG truck loading operating (minimum, normal, maximum), psig and design pressures 13.14.1.11 LNG truck unloading operating and design temperatures (minimum, normal, maximum), °F 13.14.1.12 LNG truck loading operating (minimum, normal, maximum), °F 13.14.1.13 LNG truck pumps type 68 and design temperatures 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(12) thru (14). Applicants can supply data for sections 13.14.1.11 to 13.14.1.16 using Equipment Data Table in Attachment 2. Commission Staff Guidance 13-45 February 2017 13.14.1.14 Number of LNG truck pumps, operating and spare 13.14.1.15 LNG truck pumps operating and design flow rate capacities (minimum, normal/rated, maximum), gpm 13.14.1.16 LNG truck pumps operating and design suction pressures (minimum/NPSH, normal/rated, maximum), psig 13.14.1.17 LNG truck pumps operating and design discharge pressures (minimum, normal/rated, maximum/shutoff), psig 13.14.1.18 LNG truck pumps operating and design (minimum, normal, maximum), specific gravity 13.14.1.19 LNG trucking startup and operation densities 13.14.1.19.1 LNG loading 13.14.1.19.2 LNG unloading 13.14.1.19.3 Vapor handling 13.14.1.20 LNG trucking piping, vessel, and equipment design and specifications 13.14.1.21 LNG trucking isolation valves, drains, and vents 13.14.1.22 LNG trucking basic process control systems 13.14.1.23 LNG trucking safety instrumented systems 13.14.1.24 LNG trucking relief valves and discharge 13.14.1.25 LNG trucking other safety features Commission Staff Guidance 13-46 February 2017 13.15 LNG VAPORIZATION 69 13.15.1 LNG Vaporizers Design PROVIDE a description of the LNG vaporizers design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 13.15.1.1 Emission design criteria 13.15.1.2 LNG vaporizers type 13.15.1.3 Number of LNG vaporizers, operating and spare 13.15.1.4 LNG vaporizers operating and design flow rate capacities (minimum, normal, maximum), MMscfd 13.15.1.5 LNG vaporizers operating and design heat duties each (minimum, rated, maximum), MMBtu/hr 13.15.1.6 LNG vaporizers operating and (minimum, normal, maximum), psig 13.15.1.7 LNG vaporizers operating and design inlet temperatures (minimum, normal, maximum), °F 13.15.1.8 LNG vaporizers operating and design outlet temperatures (minimum, normal, maximum), °F 13.15.1.9 LNG vaporizers startup and operation 13.15.1.9.1 LNG vaporizer heating system 13.15.1.9.2 LNG vaporization 13.15.1.10 design pressures LNG vaporizers isolation valves, drains, and vents 13.15.1.10.1 Generated water handling/disposal system 13.15.1.11 69 LNG vaporizers basic process control systems 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(12) thru (14). Commission Staff Guidance 13-47 February 2017 13.15.1.12 LNG vaporizers safety instrumented systems 13.15.1.13 LNG vaporizers relief valves and discharge 13.15.1.14 LNG vaporizers other safety features Commission Staff Guidance 13-48 February 2017 13.16 HEAT TRANSFER FLUID (HTF) SYSTEM(S) 70 13.16.1 HTF Storage Design PROVIDE a description of the HTF storage design. At a minimum, the description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 70 13.16.1.1 Number of HTF trucks, No. per year 13.16.1.2 HTF truck capacities, gal 13.16.1.3 Number of HTF storage tanks, operating and spare 13.16.1.4 HTF operating and design storage capacities, gal 13.16.1.5 HTF operating and design storage pressures (minimum, normal, maximum), psig 13.16.1.6 HTF operating and design (minimum, normal, maximum), °F 13.16.1.7 HTF operating and design residence times, minutes 13.16.1.8 HTF system startup and operation 13.16.1.9 HTF system isolation valves, drains, and vents 13.16.1.10 HTF system basic process control systems 13.16.1.11 HTF system safety instrumented systems 13.16.1.12 HTF system relief valves and discharge 13.16.1.13 HTF system other safety features storage temperatures 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(12) thru (14). Commission Staff Guidance 13-49 February 2017 13.16.2 HTF Heating System Design 71 PROVIDE a description of the HTF heating system design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 71 72 13.16.2.1 HTF distribution list and usage requirement by equipment, gpm 13.16.2.2 Heating source 13.16.2.3 HTF heaters type 13.16.2.4 Number of HTF heaters, operating and spare 13.16.2.5 HTF heaters operating and design (minimum, rated, maximum), MMBtu/hr 13.16.2.6 HTF heaters operating and design pressures (minimum, normal, maximum), psig 13.16.2.7 HTF heaters operating and design (minimum, normal, maximum), °F inlet temperatures 13.16.2.8 HTF heaters operating and design (minimum, normal, maximum), °F outlet temperatures 13.16.2.9 HTF pumps type 72 13.16.2.10 Number of HTF pumps, operating and spare 13.16.2.11 HTF pumps operating and design suction (minimum/NPSH, normal/rated, maximum), psig pressures 13.16.2.12 HTF pumps operating and design discharge (minimum, normal/rated, maximum/shutoff), psig pressures 13.16.2.13 HTF pumps operating and design flow (minimum, normal/rated, maximum), gpm capacities heat duty/rate rate each 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(12) thru (14). Applicants can supply data for sections 13.16.2.9 to 13.16.2.14 using Equipment Data Table in Attachment 2. Commission Staff Guidance 13-50 February 2017 13.16.2.14 HTF pumps operating and design (minimum, normal, maximum), specific gravity 13.16.2.15 HTF heating system startup and operation 13.16.2.16 HTF heating system isolation valves, drains, and vents 13.16.2.17 HTF heating system basic process control systems 13.16.2.18 HTF heating system safety instrumented systems 13.16.2.19 HTF heating system relief valves and discharge 13.16.2.20 HTF heating system other safety features Commission Staff Guidance 13-51 densities February 2017 13.17 BTU ADJUSTMENT 73 13.17.1 Btu Adjustment System Design PROVIDE a description of the Btu adjustment system design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 73 13.17.1.1 Btu adjustment system type 13.17.1.2 Btu adjustment system mixing location 13.17.1.3 Btu adjustment system composition specifications (minimum, normal, maximum), percent volume, Wobbe 13.17.1.4 Btu adjustment system operating and design flow rate capacities (minimum, normal, maximum), MMscfd or lb/hr 13.17.1.5 Btu adjustment system operating (minimum, normal, maximum), psig 13.17.1.6 Btu adjustment system operating and design temperatures (minimum, normal, maximum), °F 13.17.1.7 Btu adjustment system startup and operation 13.17.1.8 Btu adjustment system isolation valves, drains, and vents 13.17.1.9 Btu adjustment system basic process control systems 13.17.1.10 Btu adjustment system safety instrumented systems 13.17.1.11 Btu adjustment system relief valves and discharge 13.17.1.12 Btu adjustment system other safety features and design pressures 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(12) thru (14). Commission Staff Guidance 13-52 February 2017 13.18 SENDOUT METERING SYSTEM 74 13.18.1 Sendout Metering Design PROVIDE a description of the sendout metering system design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 74 13.18.1.1 Sendout operating and design flow rate capacities (minimum, normal, maximum), MMscfd 13.18.1.2 Sendout operating and design pressures (minimum, normal, maximum), psig 13.18.1.3 Sendout operating and design temperatures (minimum, normal, maximum), °F 13.18.1.4 Pipeline operating and design flow rate capacities (minimum, normal, maximum), MMscfd 13.18.1.5 Pipeline operating and design pressures (minimum, normal, maximum), psig 13.18.1.6 Pipeline operating and design temperatures (minimum, normal, maximum), °F 13.18.1.7 Sendout metering system startup and operation 13.18.1.8 Sendout metering system isolation valves, drains, and vents 13.18.1.9 Sendout metering system basic process control systems 13.18.1.10 Sendout metering system safety instrumented systems 13.18.1.11 Sendout metering system relief valves and discharge 13.18.1.12 Sendout metering system other safety features 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(12) thru (14). Commission Staff Guidance 13-53 February 2017 13.19 FUEL GAS 75 13.19.1 Fuel Gas Design PROVIDE a description of the fuel gas system design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 13.19.1.1 Fuel gas sources 13.19.1.2 Fuel gas specifications 13.19.1.3 Fuel gas distribution list and requirement by equipment, MMscfd 13.19.1.4 Fuel gas operating and design flow rate capacities (minimum, normal/rated, maximum), lb/hr 13.19.1.5 Fuel gas operating and design pressures (minimum, normal/rated, maximum), psig 13.19.1.6 Fuel gas operating and design temperatures (minimum, normal, maximum), °F 13.19.1.7 Fuel gas operating and design densities (minimum, normal, maximum), specific gravity 13.19.1.8 Fuel gas startup and operation 13.19.1.9 Fuel gas isolation valves, drains, and vents 13.19.1.10 Fuel gas basic process control systems 13.19.1.11 Fuel gas safety instrumented systems 13.19.1.12 Fuel gas relief valves and discharge 13.19.1.13 Fuel gas other safety features 13.19.1.13.1 Fuel gas odorant system 75 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(6) thru (8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(12) thru (14). Commission Staff Guidance 13-54 February 2017 13.20 NITROGEN AND INERT GAS 76 13.20.1 Nitrogen Design PROVIDE a description of the nitrogen system design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 13.20.1.1 76 Nitrogen source 13.20.1.1.1 Number of liquid nitrogen trucks and truck capacity, gal 13.20.1.1.2 Nitrogen production system and production rate, gpm 13.20.1.2 Nitrogen distribution list of continuous and intermittent users or usage factors, including leakage, and usage requirement by equipment, scfm 13.20.1.3 Number of liquid nitrogen storage tanks, operating and spare 13.20.1.4 Liquid nitrogen storage capacity, gal 13.20.1.5 Number of nitrogen vaporizers, operating and spare 13.20.1.6 Liquid nitrogen vaporizer type 13.20.1.7 Number of nitrogen receivers, operating and spare 13.20.1.8 Liquid nitrogen vaporizer operating and design flow rate capacities, scfm 13.20.1.9 Nitrogen receivers operating and design storage capacities, scf 13.20.1.10 Nitrogen receivers operating and design storage pressures (minimum, normal, maximum), psig 13.20.1.11 Nitrogen receivers residence times, minutes 13.20.1.12 Nitrogen system startup and operation 13.20.1.13 Nitrogen system shutdown 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(12) thru (14). Commission Staff Guidance 13-55 February 2017 13.20.2 13.20.1.14 Liquid nitrogen truck loading 13.20.1.15 Nitrogen system isolation valves, drains, and vents 13.20.1.16 Nitrogen system basic process control systems 13.20.1.17 Nitrogen system safety instrumented systems 13.20.1.18 Nitrogen system relief valves and discharge 13.20.1.19 Nitrogen system other safety features Inert Gas Design PROVIDE a description of the inert gas system design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 13.20.2.1 Inert gas distribution list of continuous and intermittent users or usage factors, including leakage, and usage requirement by equipment, scfm 13.20.2.2 Inert gas compressors type 13.20.2.3 Number of inert gas compressors, operating and spare 13.20.2.4 Number of inert gas receivers, operating and spare 13.20.2.5 Inert gas source 13.20.2.6 Inert gas specifications 13.20.2.7 Inert gas compressor operating and design flow rate capacities (minimum, normal/rated, maximum), scfm 13.20.2.8 Inert gas compressor operating and design discharge pressures (minimum, normal/rated, maximum), psig 13.20.2.9 Inert gas receivers operating and design storage capacities, scf 13.20.2.10 Inert gas receivers operating and design storage pressures (minimum, normal, maximum), psig 13.20.2.11 Inert gas receivers residence times, minutes Commission Staff Guidance 13-56 February 2017 13.20.2.12 Inert gas startup and operation 13.20.2.13 Inert gas isolation valves, drains, and vents 13.20.2.14 Inert gas basic process control systems 13.20.2.15 Inert gas safety instrumented systems 13.20.2.16 Inert gas relief valves and discharge 13.20.2.17 Inert gas other safety features Commission Staff Guidance 13-57 February 2017 13.21 INSTRUMENT AND PLANT/UTILITY AIR 77 13.21.1 Instrument Air Design PROVIDE a description of the instrument air system design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 77 13.21.1.1 Instrument air distribution list of continuous and intermittent users or usage factors, including leakage, and usage requirement by equipment, scfm 13.21.1.2 Instrument air specifications, dew point, particulates 13.21.1.3 Number of filters, operating and spare 13.21.1.4 Instrument air compressors type 13.21.1.5 Number of instrument air compressors, operating and spare 13.21.1.6 Instrument air compressor operating and design flow rate capacities (minimum, normal/rated, maximum), scfm 13.21.1.7 Instrument air compressor operating and design discharge pressures (minimum, normal/rated, maximum), psig 13.21.1.8 Instrument air drying system type 13.21.1.9 Number of instrument air dryers, operating and spare 13.21.1.10 Instrument air dryers operating and design dew point temperatures, °F 13.21.1.11 Number of air receivers, operating and spare 13.21.1.12 Air receiver operating and design storage capacities, scf 13.21.1.13 Instrument air receiver operating and design storage pressures (minimum, normal, maximum), psig 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(12) thru (14). Commission Staff Guidance 13-58 February 2017 13.21.2 13.21.1.14 Air receiver residence times, sec 13.21.1.15 Instrument air startup and operation 13.21.1.16 Instrument air isolation valves, drains, and vents 13.21.1.17 Instrument air basic process control systems 13.21.1.18 Instrument air safety instrumented systems 13.21.1.19 Instrument air relief valves and discharge 13.21.1.20 Instrument air other safety features Plant/Utility Air Design PROVIDE a description of the plant/utility air system design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 13.21.2.1 Plant/utility air compressors type 13.21.2.2 Number of plant/utility air compressors, operating and spare 13.21.2.3 Plant/utility air distribution list of continuous and intermittent users or usage factors, including leakage, and usage requirement by equipment, scfm 13.21.2.4 Plant/utility air specifications 13.21.2.5 Plant/utility air compressors operating and design flow rate capacities (minimum, normal/rated, maximum), scfm 13.21.2.6 Plant/utility air compressors operating and design discharge pressures (minimum, normal/rated, maximum), psig 13.21.2.7 Number of plant/utility air receivers, operating and spare 13.21.2.8 Plant/utility air receivers operating and design storage capacities, scf 13.21.2.9 Plant/utility air receivers operating and design storage pressures (minimum, normal, maximum), psig Commission Staff Guidance 13-59 February 2017 13.21.2.10 Plant/utility air receivers operating and design residence times, minutes 13.21.2.11 Plant/utility air startup and operation 13.21.2.12 Plant/utility air isolation valves, drains, and vents 13.21.2.13 Plant/utility air basic process control systems 13.21.2.14 Plant/utility air safety instrumented systems 13.21.2.15 Plant/utility air relief valves and discharge 13.21.2.16 Plant/utility air other safety features Commission Staff Guidance 13-60 February 2017 13.22 UTILITY WATER AND OTHER UTILITIES 78 13.22.1 Utility Water Design PROVIDE a description of the utility water system design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 78 13.22.1.1 Utility water type (service water, potable water, demineralized water, steam, chemical treatment. scavengers) 13.22.1.2 Utility water sources 13.22.1.3 Utility water distribution list and usage requirement by equipment, gpm 13.22.1.4 Utility water operating and design (minimum, normal, maximum), gal 13.22.1.5 Utility water operating and design flow rate capacities (minimum, normal, maximum), gpm 13.22.1.6 Utility water operating and design pressures (minimum, normal, maximum), psig 13.22.1.7 Utility water startup and operation 13.22.1.8 Utility water isolation valves, drains, and vents 13.22.1.9 Utility water basic process control systems 13.22.1.10 Utility water safety instrumented systems 13.22.1.11 Utility water relief valves and discharge 13.22.1.12 Utility water other safety features storage capacities 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(12) thru (14). Commission Staff Guidance 13-61 February 2017 13.22.2 Other Utilities Design 79 PROVIDE a description of other utility systems design. The description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, and all other applicable appendices, and should describe: 79 13.22.2.1 Other utilities type (amine solutions, water glycol solutions, aqueous ammonia, etc.) 13.22.2.2 Other utility distribution list and usage requirement by equipment, gpm 13.22.2.3 Other utility sources 13.22.2.4 Number of other utility truck stations 13.22.2.5 Other utility operating and design (minimum, normal, maximum), gal 13.22.2.6 Other utility operating and design flow rate capacities (minimum, normal, maximum), gpm 13.22.2.7 Other utility operating and design pressures (minimum, normal, maximum), psig 13.22.2.8 Utility truck scales 13.22.2.9 Utilities startup and operation 13.22.2.10 Utilities isolation valves, drains, and vents 13.22.2.11 Utilities basic process control systems 13.22.2.12 Utilities safety instrumented systems 13.22.2.13 Utilities relief valves and discharge 13.22.2.14 Utilities other safety features storage capacities 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(12) thru (14). Commission Staff Guidance 13-62 February 2017 13.23 PIPING AND VALVES 80 13.23.1 Piping and Valve Design PROVIDE a description of the piping and valve design. At a minimum, the description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, Piping, Vessel, Equipment, and Building Information in Appendix 13.M, and all other applicable appendices, and should describe: 13.23.1.1 Piping and valve list(s) 13.23.1.2 Tie-in list(s) 13.23.1.3 Isolation, vent and drain philosophies 13.23.1.4 Car seal and lock philosophy 13.23.1.5 Piping layout 13.23.1.6 Pipe supports and pipe racks 13.23.1.7 Piping, valve, flange, and insulation design and specifications 13.23.1.7.1 Conditions and loads (e.g. pressures, temperatures, vibration, internal and external corrosion, etc.) 13.23.1.7.2 Material of construction temperature limits 13.23.1.7.3 Material of construction allowable stress limits 13.23.1.7.4 Material of construction corrosivity potential and corrosion allowance 13.23.1.7.5 Cathodic protection 13.23.1.8 Positive Material Identification Requirements* 13.23.1.9 Post Weld Heat Treatment* 13.23.1.10 Non-destructive examination (NDE)* 13.23.1.10.1 Weld radiographic/ultrasonic testing 13.23.1.10.2 Magnetic particle or liquid penetrant examination 80 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-63 February 2017 13.23.1.10.3 Pneumatic/hydrostatic leak testing medium and pressure 13.23.1.10.4 Other 13.23.1.11 Piping and valve preventive maintenance* 13.23.1.11.1 Internal and external examination 13.23.1.11.2 Corrosion under insulation 13.23.1.11.3 Metal thickness tests Commission Staff Guidance 13-64 February 2017 13.24 PROCESS VESSELS 81 13.24.1 Process Vessel Design PROVIDE a description of the process vessel design. At a minimum, the description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, Piping, Vessel, Equipment, and Building Information in Appendix 13.M, and all other applicable appendices, and should describe: 13.24.1.1 Process vessel list 13.24.1.2 Process vessel layout 13.24.1.3 Process vessel support 13.24.1.4 Process vessel and insulation design and specifications 13.24.1.4.1 Conditions and loads (e.g. pressures, temperatures, vibration, internal and external corrosion, etc.) 13.24.1.4.2 Material of construction allowable stress limits 13.24.1.4.3 Material of construction temperature limits 13.24.1.4.4 Material of construction corrosivity potential and corrosion allowance 13.24.1.4.5 Cathodic protection 13.24.1.5 13.24.1.5.1 Magnetic particle or liquid penetrant examination 13.24.1.5.2 Full or spot radiographic or ultrasonic testing 13.24.1.5.3 Pneumatic or hydrostatic leak testing pressure 13.24.1.6 81 NDE Process vessel preventive maintenance 13.24.1.6.1 Internal and external examination 13.24.1.6.2 Corrosion under insulation 13.24.1.6.3 Metal thickness tests 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-65 February 2017 13.25 ROTATING EQUIPMENT 82 13.25.1 Rotating Equipment Design* PROVIDE a description of the rotating equipment design. At a minimum, the description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, Piping, Vessel, Equipment, and Building Information in Appendix 13.M, and all other applicable appendices, and should describe: 13.25.1.1 Rotating equipment and drivers list 13.25.1.2 Rotating equipment layout 13.25.1.3 Rotating equipment support 13.25.1.4 Rotating equipment design and specifications 13.25.1.4.1 Conditions and loads (e.g. pressures, temperatures, vibration, internal and external corrosion, etc.) 13.25.1.4.2 Performance curves 13.25.1.4.3 Material of construction allowable stress limits 13.25.1.4.4 Material of construction temperature limits 13.25.1.4.5 Material of construction corrosivity potential and corrosion allowance 13.25.1.4.6 Cathodic protection 13.25.1.5 Machinery Monitoring System 13.25.1.6 Rotating equipment preventive maintenance 13.25.1.6.1 82 Performance monitoring and tests 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-66 February 2017 13.26 FIRED EQUIPMENT 83 13.26.1 Fired Equipment Design* PROVIDE a description of the fired equipment design. At a minimum, the description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, Piping, Vessel, Equipment, and Building Information in Appendix 13.M, and all other applicable appendices, and should describe: 13.26.1.1 Fired equipment list 13.26.1.2 Fired equipment layout 13.26.1.3 Fired equipment support 13.26.1.4 Fired equipment design and specifications 13.26.1.4.1 Conditions and loads (e.g. pressures, temperatures, vibration, internal and external corrosion, etc.) 13.26.1.4.2 Duty 13.26.1.4.3 Material of construction allowable stress limits 13.26.1.4.4 Material of construction temperature limits 13.26.1.4.5 Material of construction corrosivity potential and corrosion allowance 13.26.1.4.6 Cathodic protection 13.26.1.5 Burner Management System 13.26.1.6 Fired equipment preventive maintenance 13.26.1.6.1 83 Performance monitoring and tests 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-67 February 2017 13.27 BUILDINGS AND STRUCTURES 84 13.27.1 Buildings and Structures Design PROVIDE a description of the building and structure design. At a minimum, the description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, Piping, Vessel, Equipment, and Building Information in Appendix 13.M, and all other applicable appendices, and should describe: 84 13.27.1.1 Buildings list with dimensions and purpose 13.27.1.2 Building and structure design and specifications 13.27.1.3 Building layout and siting 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-68 February 2017 13.28 ELECTRICAL 85 13.28.1 Electrical System Design PROVIDE a description of the electrical design. At a minimum, the description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, Electrical Design Information in Appendix 13.N, and all other applicable appendices, and should describe: 85 13.28.1.1 Power requirements 13.28.1.2 Main power supply, utility/generated 13.28.1.3 Electrical Equipment layout drawings* 13.28.1.4 Cable routing drawings* 13.28.1.5 Main power generators, type 13.28.1.6 Number of main power generators, including any black start generators 13.28.1.7 Main power supply voltage, kilovolt (kV) 13.28.1.8 Main power supply capacity, kilovolt ampere (kVA) 13.28.1.9 Emergency power supply, utility/generated 13.28.1.10 Emergency power generators, type 13.28.1.11 Number of emergency power generators, No. 13.28.1.12 Emergency power voltage, kV 13.28.1.13 Emergency power capacity, kVA 13.28.1.14 UPS services, voltage, size and capacity, V, kVA, hr 13.28.1.15 Transformer type, dry/oil 13.28.1.16 Number of transformers 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(11), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-69 February 2017 13.28.1.17 Electrical distribution system 13.28.1.18 Distribution and voltage levels 13.28.1.19 Uninterruptible power supply, battery backup system 13.28.1.20 Electrical cable schedule/list* 13.28.1.21 Electrical cable design and specification 13.28.1.22 Cathodic protection 13.28.1.23 Hazardous area classifications 13.28.1.24 Ignition control setbacks and separation 13.28.1.25 Electrical pass-through seals and vents to the atmosphere Commission Staff Guidance 13-70 February 2017 13.29 PLANS AND PROCEDURES 86 13.29.1 Operation and Maintenance Plans PROVIDE a description of the proposed operation and maintenance procedures. Sufficient information should be included to demonstrate that the facilities would be operated and maintained to meet the federal regulations and the level of safety is consistent with the design of the facilities. The description should reference the Organizational Chart in Appendix 13.A.4, Plans and Procedures in Appendix 13.O, and all other applicable appendices, and should describe: 86 13.29.1.1 Operation procedure development 13.29.1.2 Safety procedures (e.g., hot work and other work permit procedures, etc.) 13.29.1.3 Maintenance plan and procedure development 13.29.1.4 Operations and maintenance structure 13.29.1.5 Number of operation and maintenance personnel* 13.29.1.6 Location of operation and maintenance personnel* 13.29.1.7 Operation and maintenance personnel training* 13.29.1.8 Training plans and procedures* 13.29.1.9 Management procedures (e.g., alarm management, shift procedures/fatigue management, management of change procedures, etc.)* 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-71 February 2017 13.30 INSTRUMENTATION AND CONTROLS 87 13.30.1 Basic Process Control System Design (BPCS) PROVIDE a description of the BPCS design, including all PLCs and DCS. At a minimum, the description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, Process Control and Instrumentation Information in Appendix 13.P, and all other applicable appendices, and should describe: 87 13.30.1.1 Instrument list 13.30.1.2 Instrumentation design and specifications 13.30.1.3 BPCS philosophy 13.30.1.4 BPCS architecture 13.30.1.5 BPCS design and specifications 13.30.1.6 Number of servers, operating and backup 13.30.1.7 Number of historians, operating and backup 13.30.1.8 Distributed control systems (DCS) block diagrams 13.30.1.9 PLC and DCS software 13.30.1.10 Control communication types 13.30.1.11 Number of lines of communication to control room, operating and backup 13.30.1.12 Control power sources, operating and backup 13.30.1.13 Human machine interface (HMI) local and control room displays, type 13.30.1.14 Number of HMI control room displays 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-72 February 2017 13.31 SAFETY INSTRUMENTED SYSTEMS 88 13.31.1 Safety Instrumented System (SIS) Design PROVIDE a description of the SIS design, including emergency shutdown (ESD) and fire and gas system (FGS). At a minimum, the description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, Shutoff Valve Information in Appendix 13.Q, and all other applicable appendices, and should describe: 88 13.31.1.1 SIS, FGS, ESD and depressurization philosophies 13.31.1.2 SIS and FGS architecture 13.31.1.3 SIS, FGS, and ESD cause and effect matrices 13.31.1.4 SIS, FGS, and ESD design and specifications 13.31.1.5 Number of SIS and FGS servers, operating and backup* 13.31.1.6 Number of SIS and FGS historians, operating and backup* 13.31.1.7 SIS and FGS block diagrams 13.31.1.8 SIS and FGS software* 13.31.1.9 List of ESD valves 13.31.1.10 ESD valve spacing* 13.31.1.11 ESD closure times* 13.31.1.12 SIS, FGS, and ESD Safety Integrity Levels (SIL)* 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-73 February 2017 13.32 SECURITY PLANS 89 13.32.1 Physical Security Plans PROVIDE a general description of the proposed security that addresses the principal concerns for physical security. Identify who would be involved in the development of the physical security plan during the design phase of the project. Applicants should include sufficient information to demonstrate that the facilities would be designed, installed, and operated to meet federal regulations and that the level of security and safety is consistent with the security threats and vulnerabilities at the project location. At a minimum, the description should reference Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, the Security Threat and Vulnerability Analyses in Appendix 13.G.8 90, and all other applicable appendices, and should describe: 89 90 13.32.1.1 Security plan developments 13.32.1.2 Lighting 13.32.1.3 Physical barriers (e.g. fences, vehicle barriers, etc.) 13.32.1.4 Site and onsite access controls 13.32.1.5 Intrusion monitoring 13.32.1.6 Intrusion detection 13.32.1.7 Site security communication 13.32.1.8 Site security service and number of site security personnel 13.32.1.9 Site security use of force 13.32.1.10 Site security training 13.32.1.11 Setbacks, blast walls, hardened structures, and blast resistant designs 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14). Security Threat and Vulnerability Information prepared for or submitted to Coast Guard in accordance with 33 CFR §105.305 or prepared for or submitted to Department of Homeland Security (DHS) in accordance with 6 CFR §27.215 may satisfy Security Threat and Vulnerability Analyses in Appendix 13.G.8. This material may include Critical Energy Infrastructure Information (CEII), Security Sensitive Information (SSI), or ChemicalTerrorism Vulnerability Information (CVI) and must comply with all applicable regulations. Commission Staff Guidance 13-74 February 2017 13.32.2 Cybersecurity Plans PROVIDE a general description of the proposed security that addresses the principal concerns for cybersecurity. Identify who would be involved in the development of the cyber security plan during the design phase of the project. Applicants should describe their consideration of cybersecurity threats and vulnerabilities and compliance with federal regulations. At a minimum, the description should reference Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Project Specifications in Appendix 13.F, the Security Threat and Vulnerability Analyses in Appendix 13.G.8 91, and all other applicable appendices, and should describe: 91 13.32.2.1 Cybersecurity Plan developments 13.32.2.2 Physical access to control systems 13.32.2.3 Computer and network access controls 13.32.2.4 Intrusion monitoring 13.32.2.5 Intrusion detection 13.32.2.6 Cybersecurity personnel and response teams 13.32.2.7 Cybersecurity awareness and training 13.32.2.8 Air gaps, waterfalls, and firewalls Security Threat and Vulnerability Information prepared for or submitted to Coast Guard in accordance with 33 CFR §105.305 or prepared for or submitted to Department of Homeland Security (DHS) in accordance with 6 CFR §27.215 may satisfy Security Threat and Vulnerability Analyses in Appendix 13.G.8. This material may include Critical Energy Infrastructure Information (CEII), Security Sensitive Information (SSI), or ChemicalTerrorism Vulnerability Information (CVI) and must comply with all applicable regulations. Commission Staff Guidance 13-75 February 2017 13.33 RELIEF VALVE AND FLARE/VENT SYSTEMS 92 13.33.1 Relief Valves and Flare/Vent Systems Design PROVIDE a description of the relief valve and flare/vent design. At a minimum, the description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, Relief Valve and Flare/Vent System Information in Appendix 13.R, and all other applicable appendices, and should describe: 92 13.33.1.1 List of relief valves 13.33.1.2 Relief valve philosophy 13.33.1.3 Relief valve studies 13.33.1.4 Vent stack philosophy 13.33.1.5 Vent stack type 13.33.1.6 Number of vent stacks 13.33.1.7 Vent stack height and diameter 13.33.1.8 Vent stack studies 13.33.1.9 Vent sources 13.33.1.10 Vent stack operating and design flow rate capacities (minimum, normal/rated, maximum), MMscfd 13.33.1.11 Vent stack operating and normal/rated, maximum), psig 13.33.1.12 Vent stack operating and design temperatures (minimum, normal, maximum), °F 13.33.1.13 Vent stack operating and design densities (minimum, normal, maximum), specific gravity 13.33.1.14 Flare philosophy design pressures (minimum, 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-76 February 2017 13.33.1.15 Flare type 13.33.1.16 Number of flares 13.33.1.17 Flare height and diameter 13.33.1.18 Flare studies 13.33.1.19 Flare sources 13.33.1.20 Flare operating and design flow rate capacities (minimum, normal/rated, maximum), MMscfd 13.33.1.21 Flare operating and design pressures (minimum, normal/rated, maximum), psig 13.33.1.22 Flare operating and design temperatures (minimum, normal, maximum), °F 13.33.1.23 Flare operating and design (minimum, normal, maximum), specific gravity 13.33.1.24 Flare operating and design radiant heat (maximum), Btu/ft2-hr 13.33.1.25 Flare operating and design decibel (maximum), decibels on the A-weighted scale Commission Staff Guidance 13-77 densities February 2017 13.34 SPILL CONTAINMENT 93 13.34.1 Spill Containment System Design PROVIDE a description of the spill containment system design. Include a description of the spill locations and spill containment system, including curbing, grading, trenches, troughs downcomers, impoundments sub-impoundments, and dikes, for each hazardous fluid that could be spilled. The description should contain the location, design configuration, dimensions, capacity and materials of construction. The description should also include details of the water removal system, basis of design and flow rate required to be removed. Each spill containment system, trough, trench, sump and impoundment should be clearly referenced to the drawings At a minimum, the description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, Spill, Toxic, Fire, and Explosion Protection Information in Appendix 13.S, and all other applicable appendices, and should describe: 93 13.34.1.1 Spill containment philosophy 13.34.1.2 Spill locations and flows 13.34.1.3 Impoundment volumetric capacities 13.34.1.4 Trench and trough volumetric flow capacities 13.34.1.5 Downcomer volumetric flow capacities 13.34.1.6 Impoundment system water removal 13.34.1.7 Storm water flow design basis 13.34.1.8 Storm water drainage calculations 13.34.1.9 Impoundment system snow and ice removal 13.34.1.10 Snow and ice load basis of design and removal 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(4), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-78 February 2017 13.35 PASSIVE PROTECTION SYSTEMS 94 13.35.1 Passive Protection Design PROVIDE a description of the passive protection design. At a minimum, the description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, Spill, Toxic, Fire, and Explosion Protection Information in Appendix 13.S, and all other applicable appendices, and should describe: 94 13.35.1.1 Passive protection philosophy 13.35.1.2 Cryogenic structural protection 13.35.1.3 Vapor barriers 13.35.1.4 Equipment layout setbacks and separation 13.35.1.5 Blast walls, hardened structures, and blast resistant design 13.35.1.6 Fire-proofing, firewalls, and radiant heat shields design 13.35.1.7 Other passive protection (e.g. mounding, elevated heating, ventilation, and air conditioning [HVAC] intakes; foam glass blocks; etc.) 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-79 February 2017 13.36 HAZARD DETECTION SYSTEMS 95 13.36.1 Hazard Detection System Design PROVIDE a description of the hazard detection design. At a minimum, the description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, Spill, Toxic, Fire, and Explosion Protection Information in Appendix 13.S, and all other applicable appendices, and should describe: 95 13.36.1.1 Hazard detection philosophies (selection, layout, alarm, activation, and/or shutdown setpoints, voting logic, voting degradation logic) 13.36.1.2 Hazard detection design and performance criteria (e.g., minimum detector spacing, maximum detection time, etc.) 13.36.1.3 Low temperature detectors 13.36.1.4 Oxygen deficiency detectors 13.36.1.5 Toxic gas detectors 13.36.1.6 Flammable/combustible gas detectors 13.36.1.7 Flame detectors 13.36.1.8 Heat detectors 13.36.1.9 Smoke/products of combustion detectors 13.36.1.10 Manual pull stations 13.36.1.11 Audible and visual notification systems for field, control room, plant wide, and offsite 13.36.1.12 Other hazard detectors (e.g., rate of rise temperature detectors, acoustic leak detectors, closed-circuit television [CCTV] detectors, carbon monoxide, etc.) 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-80 February 2017 13.37 HAZARD CONTROL SYSTEMS 96 13.37.1 Hazard Control System Design PROVIDE a description of the hazard control design. At a minimum, the description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, Spill, Toxic, Fire, and Explosion Protection Information in Appendix 13.S, and all other applicable appendices, and should describe: 96 13.37.1.1 Hazard control philosophies (selection, layout, activation) 13.37.1.2 Performance criteria (e.g., minimum flow and capacity, maximum travel distance/spacing, etc.) 13.37.1.3 Portable fire extinguishers design and layout with reference to drawings in Appendix 13.S 13.37.1.4 Fixed dry chemical systems design and layout with reference to drawings in Appendix 13.S 13.37.1.5 Clean agent systems design and layout with reference to drawings in Appendix 13.S 13.37.1.6 Carbon dioxide systems design and layout with reference to drawings in Appendix 13.S 13.37.1.7 Other hazard control systems (e.g., nitrogen snuffing, dispersive fans, building ventilation, etc.) design and layout with reference to drawings in Appendix 13.S 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(2), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-81 February 2017 13.38 FIRE WATER SYSTEM 97 13.38.1 Fire Water Design PROVIDE a description of the fire water system design. At a minimum, the description should reference the Design Basis, Criteria, and Philosophies in Appendix 13.B, Regulations and Permits in Appendix 13.C, Codes and Standards in Appendix 13.D, Engineering Design Information in Appendix 13.E, Project Specifications in Appendix 13.F, Spill, Toxic, Fire, and Explosion Protection Information in Appendix 13.S, and all other applicable appendices, and should describe: 97 13.38.1.1 Fire water philosophy 13.38.1.2 Fire water system design cases, demands, calculations, and basis of sizing 13.38.1.3 Main fire water supply and back up supply (e.g., fire water tank, pond, ocean, wells, city, etc.) 13.38.1.4 Fire water supply pressure, psig 13.38.1.5 Fire water storage type and capacity, gal 13.38.1.6 Main fire water pumps and driver type 13.38.1.7 Number of main fire water pumps, operating and standby 13.38.1.8 Main fire water pumps operating and design flow rate capacities (minimum, rated, maximum), gpm 13.38.1.9 Main fire water pumps operating and design pressures (minimum, rated, maximum) 13.38.1.10 Jockey/make up water source 13.38.1.11 Jockey/make up water operating and design flow rate capacities (minimum, rated, maximum), gpm 13.38.1.12 Jockey/make up water operating and design pressures (minimum, rated, maximum), psig 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(2), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-82 February 2017 13.38.1.13 Fire water piping design and layout with reference to drawings in Appendix 13.S 13.38.1.13.1 Freeze protection (burial depth below frost depth, aboveground heat tracing, etc.) 13.38.1.14 Fire water hydrants design and layout with reference to drawings in Appendix 13.S 13.38.1.15 Fire water monitors design and layout with reference to drawings in Appendix 13.S 13.38.1.16 Hose reels design and layout with reference to drawings in Appendix 13.S 13.38.1.17 Water screens and deluge systems design and layout with reference to drawings in Appendix 13.S 13.38.1.18 Expansion foam philosophy 13.38.1.19 Expansion foam system design cases, demands, calculations, and basis of sizing 13.38.1.20 Expansion foam water supply 13.38.1.21 Expansion foam supply 13.38.1.22 Expansion foam type (e.g. low expansion Aqueous Film-Forming Foam [AFFF], high expansion foam, etc.) 13.38.1.23 Expansion foam concentration, percent volume 13.38.1.24 Expansion foam storage type and capacity, gal 13.38.1.25 Expansion foam pumps and driver type 13.38.1.26 Number of expansion foam pumps, operating and standby 13.38.1.27 Expansion foam pumps operating and design flow rate capacities (minimum, rated, maximum), gpm 13.38.1.28 Expansion foam pumps operating and design pressures (minimum, rated, maximum) Commission Staff Guidance 13-83 February 2017 13.38.1.29 Expansion foam piping design and layout with reference to drawings in Appendix 13.S 13.38.1.29.1 Freeze protection (burial depth below frost depth, aboveground heat tracing, etc.) 13.38.1.30 Expansion foam generators design and layout with reference to drawings in Appendix 13.S 13.38.1.31 Expansion foam hose reels design and layout with reference to drawings in Appendix 13.S 13.38.1.32 External impact protection (bollards) Commission Staff Guidance 13-84 February 2017 13.39 EMERGENCY RESPONSE PLAN 98 13.39.1 Emergency Response Plan PROVIDE a description of the Emergency Response Plan development, planned coordination, and a summary of utilization of onsite personnel and offsite personnel and equipment in response to fires. At a minimum, the description should include: 98 99 13.39.1.1 Incident Command System organizational chart for emergency response 13.39.1.2 Proximity of emergency response, fire brigades/departments, mutual aid, and local law enforcement 13.39.1.3 Number of emergency response personnel 13.39.1.4 Number and type of emergency response apparatus 13.39.1.5 Response to emergencies and deployment of resources 13.39.1.6 Public and onsite notification and communication 13.39.1.7 Multiple access and egress locations and roadways, internal and external to site 13.39.1.8 Preliminary evacuation routes within and adjacent to plant and LNG vessel route 13.39.1.9 Proposed frequency and type of security and emergency response training and drills for onsite personnel and emergency responders 13.39.1.10 Contact and communications with the Coast Guard, including LOI and submittal of preliminary Waterway Suitability Assessment (at time of pre-filing), and submittal of a Follow-on Waterway Suitability Assessment (at time of application) 99 13.39.1.11 Contact and communications with the State Fire Marshal 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14). Waterway Suitability Assessments submitted to Coast Guard in accordance with 18 CFR §157.21(a)(1), 18 CFR §157.21(f)(13), 33 CFR §127.007, and Navigation and Vessel Inspection Circular (NVIC) 01-2011, Guidance Related to Waterfront Liquefied Natural Gas Facilities may satisfy this provision and Waterway Safety and Reliability Impact Studies in Appendix 13.G.3. This material may include Critical Energy Infrastructure Information (CEII), Security Sensitive Information (SSI), or Chemical-Terrorism Vulnerability Information (CVI) and must comply with all applicable regulations. Commission Staff Guidance 13-85 February 2017 13.39.1.12 Contacts and communications with all other appropriate agencies 13.39.1.13 Preliminary Cost-Sharing Plans with any state and local agencies and responders to fund security, emergency management, and training costs 13.39.1.14 Schedule for any future actions, studies or meetings to develop the Emergency Response Plan and Cost-Sharing Plan Commission Staff Guidance 13-86 February 2017 RESOURCE REPORT 13 APPENDICES 13.A APPENDIX 13.A, PROJECT MANAGEMENT 100 13.A.1 Site Location Maps and Drawing PROVIDE area location maps and drawings detailing the plant and surrounding areas. The maps and drawings should show: owned and leased property boundaries, easements, and rights of ways; water bodies and sensitive resources, such as streams, ponds, marshes, and wetlands; existing site features that would be removed or demolished, including existing vegetation, structures, foundations, equipment, and containers; populated areas, such as residential communities, business districts, schools, day care centers, religious facilities, and recreational areas; transportation infrastructure, such as roads and highways, railroads and rail yards, waterlines, sewer lines, and storm culverts, hazardous pipelines, electric lines, marinas, and airports; industrial facilities, such as power plants, nuclear facilities, wastewater facilities, and petrochemical and processing facilities; public health and safety facilities, such as police and fire departments, hospitals, and mutual aid facilities; and military facilities, such as bases, test sites, restricted areas, and research areas. 13.A.2 Owner Organizational Structure PROVIDE an Organizational Chart detailing the structure of the ownership of the project. The structure should include the owner of the project, parent companies, and subsidiaries. 13.A.3 Construction Workforce Organizational Chart(s)* PROVIDE an organizational chart for the construction workforce. 13.A.4 Operation Workforce Organizational Chart(s)* PROVIDE an organizational chart for the operational plant. At a minimum, the organizational chart should include the structure and number of all staff for operations, maintenance, engineering, safety, security, health, environment, management, and administration. 100 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8). Commission Staff Guidance 13-87 February 2017 13.A.5 Gantt Chart PROVIDE a preliminary Gantt chart of the project schedule that should include general milestones for the following: 13.A.5.1 13.A.5.2 Front-end engineering design and reviews, including milestones for completed: 13.A.5.1.1 Hazard Identification (HAZID) or Preliminary Hazard and Operability (HAZOP) 13.A.5.1.2 Piping and Instrumentation Drawings (P&IDs) 13.A.5.1.3 Fire protection evaluation 13.A.5.1.4 FEED Regulatory Permits and Approvals, including milestones for submittals and authorizations/permits for: 13.A.5.2.1 13.A.5.2.2 13.A.5.2.3 13.A.5.2.4 13.A.5.2.5 13.A.5.3 Site Preparation, including milestones for starting and completing: 13.A.5.3.1 13.A.5.3.2 13.A.5.3.3 13.A.5.3.4 13.A.5.3.5 13.A.5.3.6 13.A.5.3.7 13.A.5.3.8 13.A.5.3.9 13.A.5.4 U.S. Army Corps of Engineers U.S. Environmental Protection Agency U.S. Department of Energy FERC State agencies Mobilization Soil stabilization Grading Electric Power Waterlines Underground piping and systems Access roads Laydown areas Dredging Detailed/Final Engineering, including milestones for starting and completing: 13.A.5.4.1 13.A.5.4.2 13.A.5.4.3 Commission Staff Guidance Process Hazard Analyses (PHA) (e.g., HAZOP, SIL verification, Layers of Protection Analysis [LOPA], etc.) Issued for construction P&IDs Structural design 13-88 February 2017 13.A.5.4.4 13.A.5.5 Procurement, including milestones for completing: 13.A.5.5.1 13.A.5.5.2 13.A.5.5.3 13.A.5.6 Procurement of long-lead equipment Transit/delivery of major equipment Receipt of bulk materials/fluids Construction, including milestones for starting and completing: 13.A.5.6.1 13.A.5.6.2 13.A.5.6.3 13.A.5.6.4 13.A.5.6.5 13.A.5.6.6 13.A.5.6.7 13.A.5.6.8 13.A.5.6.9 13.A.5.6.10 13.A.5.6.11 13.A.5.6.12 13.A.5.6.13 13.A.5.7 Fire protection evaluation Piling Foundations Fabrication/erection of structural steel Major pieces of equipment Storage tanks Vessels Piping Tie-ins Electrical and instrumentation Insulation Equipment tagging Labeling Signage Pre-Commissioning and Commissioning, including milestones for starting and completing: 13.A.5.7.1 13.A.5.7.2 13.A.5.7.3 13.A.5.7.4 13.A.5.7.5 13.A.5.7.6 13.A.5.7.7 13.A.5.7.8 13.A.5.7.9 13.A.5.7.10 13.A.5.7.11 13.A.5.7.12 13.A.5.7.13 13.A.5.7.14 13.A.5.7.15 13.A.5.7.16 13.A.5.7.17 Commission Staff Guidance Cleanout Purging Dryout Leak/pneumatic testing Hydrotests Equipment alignment checks Mechanical completion Loop checks Alarm/trip checks Commissioning plans and procedures Electrical tests Factory acceptance tests (FAT) Site acceptance tests (SAT) Site integration tests (SIT) Functional tests and commissioning demonstration tests Introduction of hazardous fluids Ready for Startup documentation 13-89 February 2017 13.A.5.8 Startup, including milestones for starting and completing: 13.A.5.8.1 13.A.5.8.2 13.A.5.9 Training of personnel Startup and cooldown procedures Commencement of operations, including milestones for starting and completing: 13.A.5.9.1 13.A.5.9.2 13.A.5.9.3 13.A.5.9.4 Commission Staff Guidance Operation procedures Maintenance plans Performance tests Turnover 13-90 February 2017 13.B APPENDIX 13.B, DESIGN BASIS, CRITERIA, AND PHILOSOPHIES 101 13.B.1 Basis of Design and Criteria PROVIDE the basis of the engineering design that justifies, explains, or clarifies the design criteria. Items to be considered should include, but are not limited to: feed gas pipeline conditions, LNG ship/import criteria, guarantee conditions, venting and flaring requirements, fire water, sendout pipeline criteria, LNG ship/export criteria. As applicable, the overall Design Basis and criteria should address: 13.B.1.1 13.B.1.2 13.B.1.3 13.B.1.4 13.B.1.5 13.B.1.6 13.B.1.7 13.B.1.8 13.B.1.9 13.B.1.10 13.B.1.11 13.B.1.12 13.B.1.13 13.B.1.14 13.B.1.15 13.B.1.16 13.B.1.17 13.B.1.18 13.B.1.19 13.B.1.20 13.B.1.21 13.B.1.22 13.B.1.23 13.B.1.24 13.B.1.25 13.B.1.26 13.B.1.27 13.B.1.28 13.B.1.29 13.B.1.30 13.B.1.31 101 Marine platform Marine transfer Feed gas system Acid gas removal Mercury removal Water removal Heavies/condensates removal, storage, and disposition NGL fractionation, storage, and disposition Refrigerant Liquefaction Cooling water LNG transfer LNG storage tank Vapor handling LNG trucking LNG vaporization HTF storage and heating Btu adjustment Sendout metering Electrical Fuel gas Nitrogen Inert gas Instrument air Plant/utility air Piping Process vessel Buildings and structures Basic process control system Safety Instrument System Relief valve and flare/vent systems 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-91 February 2017 13.B.1.32 13.B.1.33 13.B.1.34 13.B.1.35 13.B.1.36 Spill containment Passive protection Hazard detection Hazard control Fire water system 13.B.2 Design and Control Philosophies PROVIDE design and control philosophy of operation of all systems/facilities. At a minimum, the design and control philosophies should include the following systems: 13.B.2.1 13.B.2.2 13.B.2.3 13.B.2.4 13.B.2.5 13.B.2.6 13.B.2.7 13.B.2.8 13.B.2.9 13.B.2.10 13.B.2.11 13.B.2.12 13.B.2.13 13.B.2.14 13.B.2.15 13.B.2.16 13.B.2.17 13.B.2.18 13.B.2.19 13.B.2.20 13.B.2.21 13.B.2.22 13.B.2.23 13.B.2.24 13.B.2.25 13.B.2.26 13.B.2.27 13.B.2.28 Sparing philosophy Warehouse philosophy Marine transfer system philosophy Acid gas removal system philosophy Mercury removal system philosophy Dehydration and regeneration gas system philosophy Heavies/condensates removal, storage, and disposition systems philosophy NGL removal, storage, and disposition system philosophy Liquefaction system philosophy Cooling system philosophy LNG transfer system philosophy LNG storage tank system philosophy Vapor handling system philosophy LNG vaporization system philosophy Btu adjustment system philosophy Material selection philosophy Isolation, drain, and vent philosophies Car seal and lock philosophy BPCS philosophy SIS, FGS, ESD, and depressurization philosophies Relief valve philosophy Vent/Flare system philosophy Spill containment philosophy Passive protection philosophy Hazard detection philosophy Hazard control philosophy Fire water philosophy Expansion foam philosophy Commission Staff Guidance 13-92 February 2017 13.C APPENDIX 13.C, REGULATIONS AND PERMITS 102 13.C.1 Table of Regulatory Agencies, Permits, and Approvals PROVIDE a table of the government regulations and permits required for the design, construction, and operation of the facilities. At a minimum, the table should include all permits or approvals from local, state, Federal, or Native American groups or Indian agencies required prior to and during construction of the plant, and the status of each, including the date filed, the date issued, and any known obstacles to approval. This section may reference Resource Report 1. 13.C.2 Regulatory Agency Correspondence PROVIDE copies of all correspondence and submissions relating to all required safety and reliability related permits and approvals. Correspondence should resolve any potential safety impacts, including hazards to or from surrounding areas of the project site and shipping route. At a minimum, correspondence should be provided for the following agencies: 13.C.2.1 13.C.2.2 13.C.2.3 13.C.2.4 Coast Guard DOT FAA Other (e.g., EPA, OSHA, DoD, NRC, state, etc.)103 13.C.3 Regulatory Compliance Matrix PROVIDE a code compliance matrix that clearly describes how each applicable requirement in 49 CFR Part 193 and incorporated National Fire Protection Association (NFPA) 59A LNG Standards has been satisfied. The specific location of relevant supporting information contained in the application should also be provided. For new facilities, the siting requirements of 49 CFR Part 193, Subpart B, must be given special attention. Hazards for releases over water should also be presented to ensure compliance with the Coast Guard’s LNG regulations in 33 CFR Part 127, if applicable. 102 103 18 CFR §380.12(o)(13) and 18 CFR §380.12(o)(14). DoD should be consulted if the facilities, operations, or potential incidents could impact DoD military operations or facilities. NRC should be consulted if the facilities, operations, or potential incidents could impact NRC jurisdictional nuclear operations or facilities. State safety agencies should be consulted for any safety concerns expressed by the state. Commission Staff Guidance 13-93 February 2017 13.D APPENDIX 13.D, CODES AND STANDARDS 104 13.D.1 List of Codes and Standards PROVIDE a list of the codes, standards, and other recognized and general accepted good engineering practices with editions 105 under which the Project will be designed, constructed, and operated. The list should be ordered alphabetically by standard body and numerically for standards. Codes and Standards should include, but should not be limited to the following standard and code bodies/organizations: 13.D.1.1 13.D.1.2 13.D.1.3 13.D.1.4 13.D.1.5 13.D.1.6 13.D.1.7 13.D.1.8 13.D.1.9 13.D.1.10 13.D.1.11 13.D.1.12 13.D.1.13 13.D.1.14 13.D.1.15 13.D.1.16 13.D.1.17 13.D.1.18 13.D.1.19 13.D.1.20 13.D.1.21 104 105 106 American Concrete Institute (ACI) American Gas Association (AGA) American Institute of Steel Construction (AISC) American Petroleum Institute (API) American Society of Civil Engineers (ASCE) American Society of Mechanical Engineers (ASME) American Society for Testing and Materials (ASTM) American Welding Society (AWS) Gas Processors Association (GPA) International Code Council (ICC) International Electrotechnical Commission (IEC) Institute of Electrical and Electronics Engineers (IEEE) International Society of Automation (ISA) 106 National Association of Corrosion Engineers (NACE) National Electrical Manufacturers Association (NEMA) National Fire Protection Association (NFPA) Oil Companies International Marine Forum (OCIMF) Society of International Gas Tanker and Terminal Operators (SIGTTO) Steel Structures Painting Council (SSPC) Tubular Exchanger Manufacturers Association (TEMA) Underwriter Laboratories (UL) 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(12), 18 CFR §380.12(o)(14). For multiple codes and standards, applicants can summarize editions (e.g. latest edition at time of application unless otherwise noted). Previously, Instrumentation Systems and Automation Society. Commission Staff Guidance 13-94 February 2017 13.E APPENDIX 13.E, ENGINEERING DESIGN INFORMATION 107 13.E.1 Block Diagram of Facilities PROVIDE up-to-date overall schematics of the project facilities. Block Diagrams should show all major systems and should be legible. 13.E.2 Process Flow Diagrams PROVIDE up-to-date diagrams of the facilities. Process flow diagrams should show all major process equipment and conditions used as the basis for equipment design. The diagrams should be keyed to the material and energy balances. At a minimum, the process flow diagrams should show stream designations upstream and downstream of each major piece of process equipment, including but not limited to: 13.E.2.1 13.E.2.2 13.E.2.3 13.E.2.4 13.E.2.5 13.E.2.6 13.E.2.7 13.E.2.8 13.E.2.9 13.E.2.10 13.E.2.11 Pipelines Acid gas removal units Mercury removal units Dehydrators Distillation columns Fired heaters Compressors Pumps Heat exchangers Storage containers Transfer areas 13.E.3 Utility Flow Diagrams PROVIDE up-to-date diagrams of the facilities. Utility flow diagrams should show all major plant utility equipment and conditions used as the basis for equipment design. At a minimum, the utility flow diagrams should show stream designations upstream and downstream of each major piece of utility equipment including but not limited to: 13.E.3.1 13.E.3.2 13.E.3.3 13.E.3.4 13.E.3.5 13.E.3.6 107 Instrument air Plant air Nitrogen Service water Potable water Steam 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(1), 18 CFR §380.12(o)(6) thru (8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-95 February 2017 13.E.4 Heat and Material Balances PROVIDE up-to-date heat and material balances of the facilities. heat and material balances should be included for each operating mode (e.g., holding, loading, unloading, liquefying, vaporizing, etc.) and range of compositions and conditions that give the maximum and minimum operating parameters. The heat and material balances should include: 13.E.4.1 13.E.4.2 13.E.4.3 13.E.4.4 13.E.4.5 13.E.4.6 Design rating case Average composition, average ambient conditions Lean composition, cold ambient conditions Lean composition, warm ambient conditions Rich composition, cold ambient conditions Rich composition, warm ambient conditions 13.E.5 Piping and Instrumentation Drawings PROVIDE up-to-date drawings of the facilities. P&IDs should be included with a Master Drawing List, Legends and Symbols with Drawing Labeling Conventions, and Drawing Revision Number and Dates. The piping legend and symbol key should be in accordance with accepted practice (e.g., ISA 5.1). At a minimum, the P&IDs should include: 13.E.5.1 All equipment, including packaged equipment, labeled with tag number, name, size, duty, capacity and design conditions 13.E.5.2 All equipment power devices, controls, and monitoring, including motor type and local or remote operation and instrumentation 13.E.5.3 All equipment insulation and pipe connections and penetrations with size and pertinent interior arrangement (e.g. trays, weirs, demisters) and labeled nozzles or nozzle schedule 13.E.5.4 All piping, including vent, drain, cooldown and recycle piping, labeled with line number, piping class spec, size and insulation 13.E.5.5 All special notes indicating minimum or maximum slopes, distances, straight lengths, no pockets, and symmetrical arrangements 13.E.5.6 All reducers, including eccentric or concentric 13.E.5.7 All flanges, including isolation flanges, insulating flanges, and blinds Commission Staff Guidance 13-96 February 2017 13.E.5.8 All valves including control, isolation, check, vent, drain, and others for operation, start-up, and maintenance, labeled with tag number, type, valve operator type, normal position, and fail position 13.E.5.9 All car seals and locks 13.E.5.10 All instrumentation, including local, panel, and control room, with tag number, type, control loops, and software connections 13.E.5.11 All shutdown interlocks 13.E.5.12 All relief devices, including depressurization valves, vacuum relief valves, pressure relief valves, rupture discs, and rupture pins, labeled with tag number, set point, valve inlet and outlet piping size 13.E.5.13 All breaks and limits, including piping spec breaks and insulation limits, and battery limits between parties (e.g. contractor and vendor) 13.E.6 Plant and Equipment Layouts PROVIDE overall plot plans, unit plot plans, and elevation drawings. Overall project plot plans should show owned/leased property lines, the location of all major components to be installed, as listed below. Unit plot plans should be included for each process area or system and should show the locations of all equipment and piperacks. Each area and piece of equipment should be clearly labeled. The unit plot plans should be detailed enough to allow for measurement of distances between various components to verify the safe spacing of all equipment and buildings as required by federal regulations and other codes and standards. Specifically, the smallest scale used should be 1-inch to 100-feet (1:1200). Elevation drawing should be included for each process area and should show the elevations of all major process equipment and major pipe racks. Consideration should be given for allowing clearance above, below, and between equipment for planning access and maintenance, including access to manual valves; calibration of instrumentation and hazard detection; lifting arrangements for pumps, heavy valves, and other equipment; pulling heat exchanger tube bundles; and labeling, painting, and cleaning piping. 13.E.6.1 Overall project plot plans 13.E.6.1.1 13.E.6.1.2 13.E.6.1.3 13.E.6.1.4 13.E.6.1.5 13.E.6.1.6 Commission Staff Guidance Feed gas pipeline metering station Feed gas pretreatment equipment Heavies/condensates removal columns, storage, and sendout NGL fractionation columns, storage, and sendout Refrigerant systems and storage Liquefaction equipment 13-97 February 2017 13.E.6.1.7 13.E.6.1.8 13.E.6.1.9 13.E.6.1.10 13.E.6.1.11 13.E.6.1.12 13.E.6.1.13 13.E.6.1.14 13.E.6.1.15 13.E.6.1.16 13.E.6.1.17 13.E.6.1.18 13.E.6.1.19 13.E.6.1.20 13.E.6.1.21 13.E.6.1.22 13.E.6.1.23 13.E.6.1.24 13.E.6.1.25 13.E.6.1.26 13.E.6.1.27 13.E.6.1.28 Marine facilities Long transfer piping LNG storage Truck transfer areas Pumps LNG vaporizers Btu stabilization equipment Compressors and blowers Boil-off gas recondensation Vent stacks and flare stacks Sendout metering (gas and liquids) Buildings Power generation Major utility systems Auxiliary and appurtenant service facilities Emission control equipment Spill impoundments and dikes Fire water systems and storage Access and egress roads, access control, emergency routing Property and fence lines Tie-in points Any other significant equipment or features 13.E.6.2 Unit plot plans 13.E.6.3 Section and elevation drawings of major equipment, pipe racks, and typical piping support system 13.E.6.4 Three dimensional plant model* 13.E.7 Plant Reliability, Availability, and Maintainability (RAM) Analyses* PROVIDE copies of any conducted plant RAM analyses. At a minimum, the RAM analyses should support the guarantee conditions, if known, or design conditions and should justify the number of docks, liquefaction equipment, tanks, vaporizers, and sparing philosophy of rotating equipment, relief valves, and other critical equipment. Consideration should be given to the preventive and routine maintenance, storage/warehousing philosophy, and obsolescence plans for the life of the facilities. Commission Staff Guidance 13-98 February 2017 13.F APPENDIX 13.F, SPECIFICATIONS 108 13.F.1 Civil Specifications PROVIDE a list of the specifications that would be used to design, construct and test the facilities prior to initial operation. Specifications to clarify the proposed design should include: 13.F.1.1 Site preparation specifications 13.F.1.1.1 13.F.1.1.2 13.F.1.1.3 13.F.1.1.4 13.F.1.1.5 13.F.1.1.6 13.F.1.1.7 13.F.1.2 Design load specifications 13.F.1.2.1 13.F.1.2.2 13.F.1.2.3 13.F.1.2.4 13.F.1.2.5 13.F.1.2.6 13.F.1.2.7 13.F.1.2.8 13.F.1.2.9 13.F.1.2.10 13.F.1.2.11 13.F.1.2.12 13.F.1.2.13 13.F.1.2.14 13.F.1.2.15 108 109 Excavation Fill and backfill Stabilization Trenching Dewatering Stormwater and sewers Other site preparation specifications Live* Dead* Operational* Seismic 109 Wind Storm surge Tsunami Snow and ice Impact Blast Thermal* Transport* Erection/construction* Load combinations and factors Other design load specifications 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(5), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14), 18 CFR §380.12(o)(15). Provide seismic specifications for Seismic Category I, II, and III equipment items that are to be procured. Separate specifications can be provided for Seismic Category I, II, and III items and/or other subsets of equipment as deemed practicable. Seismic Category I seismic specifications should be in accordance with NBSIR 84-2833 and Seismic Category II and III equipment items should be in accordance with ASCE 7-05. Commission Staff Guidance 13-99 February 2017 13.F.1.3 Piling specifications 13.F.1.4 Foundation mat/slab specifications 13.F.1.5 Marine platform specifications 13.F.1.6 Structural steel specifications 13.F.1.7 Building specifications 13.F.1.7.1 13.F.1.7.2 13.F.1.7.3 13.F.1.7.4 13.F.1.7.5 13.F.1.7.6 13.F.1.7.7 13.F.1.8 Control buildings Electrical buildings Compressor buildings Storage buildings Pressurized buildings Ventilated buildings Blast resistant buildings Other civil specifications 13.F.2 Mechanical Specifications PROVIDE a list of the specifications that would be used to design, construct and test the facilities prior to initial operation. Specifications to clarify the proposed design should include: 13.F.2.1 Piping specifications 13.F.2.1.1 13.F.2.1.2 13.F.2.1.3 13.F.2.1.4 13.F.2.1.5 13.F.2.1.6 13.F.2.1.7 13.F.2.2 General piping Process piping Vacuum insulated piping Branch connections Flanged connections Pipe supports and pipe racks Other piping specifications Valve specifications 13.F.2.2.1 13.F.2.2.2 13.F.2.2.3 13.F.2.2.4 13.F.2.2.5 13.F.2.2.6 13.F.2.2.7 Commission Staff Guidance Control valves Pressure regulators Remotely actuated valves Emergency shutdown (ESD) valves On/Off or isolation valves Pressure relief valves Vacuum relief valves 13-100 February 2017 13.F.2.2.8 Check valves 13.F.2.2.9 Firesafe valves 13.F.2.2.10 Other valves 13.F.2.3 Insulation specifications 13.F.2.3.1 13.F.2.3.2 13.F.2.3.3 13.F.2.3.4 13.F.2.3.5 13.F.2.4 Rotating equipment specifications* 13.F.2.4.1 13.F.2.4.2 13.F.2.4.3 13.F.2.4.4 13.F.2.4.5 13.F.2.4.6 13.F.2.5 Submerged combustion exchangers Shell and tube exchangers Ambient air exchangers Fin-fan exchangers Plate exchangers Direct-fired heaters Distillation columns Other heat exchanger specifications Storage tank and vessel specifications 13.F.2.6.1 13.F.2.6.2 13.F.2.6.3 13.F.2.6.4 13.F.2.6.5 13.F.2.6.6 110 Canned pumps Centrifugal pumps Vertical turbine pumps Reciprocating compressors Centrifugal compressors Other rotating equipment specifications Heat exchanger specifications* 13.F.2.5.1 13.F.2.5.2 13.F.2.5.3 13.F.2.5.4 13.F.2.5.5 13.F.2.5.6 13.F.2.5.7 13.F.2.5.8 13.F.2.6 Hot insulation Cold insulation Cryogenic insulation Fireproofing insulation Other insulation specifications Non-LNG atmospheric storage tanks 110 Internal floating roof storage tanks External floating roof storage tanks Fixed roof storage tanks Pressure vessels Other storage tank and vessel specifications LNG atmospheric storage tank specifications should be provided in Appendix 13.L.1. Commission Staff Guidance 13-101 February 2017 13.F.2.7 Other specialized equipment specifications 13.F.2.7.1 13.F.2.7.2 13.F.2.7.3 13.F.2.7.4 13.F.2.7.5 13.F.2.7.6 13.F.2.7.7 Filters and coalescers Pig traps Vent stacks Flare stacks Flame arrestors Transfer arms/hoses Other specialized equipment specifications 13.F.3 Electrical and Instrumentation Specifications PROVIDE a list of the specifications that would be used to design, construct and test the facilities prior to initial operation. Specifications to clarify the proposed design should include: 13.F.3.1 Power system specifications 13.F.3.1.1 13.F.3.1.2 13.F.3.1.3 13.F.3.1.4 13.F.3.2 Switchgear Transformers Uninterruptible power supply (UPS) Other power system specifications Control system specifications 13.F.3.2.1 13.F.3.2.2 13.F.3.2.3 13.F.3.2.4 13.F.3.2.5 13.F.3.2.6 13.F.3.2.7 13.F.3.2.8 Basic process control system Flow measurement Level measurement Pressure measurement Temperature measurement Gas concentration measurement Human machine interface (HMI) Other control system specifications 13.F.3.3 Safety instrument system (SIS) specifications 13.F.3.4 Cable specifications 13.F.3.4.1 13.F.3.4.2 13.F.3.4.3 13.F.3.4.4 13.F.3.4.5 13.F.3.4.6 Commission Staff Guidance Power cables* Instrumentation cables* Cable tray specification* Fire resistant cable Electric and instrument cable seals Other cable specifications* 13-102 February 2017 13.F.3.5 Other electrical and instrumentation specifications 13.F.3.5.1 13.F.3.5.2 13.F.3.5.3 Electrical heat tracing Grounding and earthing Other electrical and instrumentation specifications 13.F.4 Security and Fire Safety Specifications PROVIDE a list of the specifications that would be used to design, construct and test the facilities prior to initial operation. Specifications to clarify the proposed design should include: 13.F.4.1 Security Specifications 13.F.4.1.1 13.F.4.1.2 13.F.4.1.3 13.F.4.1.4 13.F.4.1.5 13.F.4.1.6 13.F.4.1.7 13.F.4.2 Passive Protection Specifications 13.F.4.2.1 13.F.4.2.2 13.F.4.2.3 13.F.4.2.4 13.F.4.2.5 13.F.4.2.6 13.F.4.2.7 13.F.4.2.8 13.F.4.3 Lighting Fencing Access control Vehicular barriers Intrusion monitoring systems Intrusion detection systems Other security system specifications Spill containment Cryogenic structural protection Vapor barriers Blast walls and hardened structures Fireproofing/fire insulation Mounding Fire walls and radiant heat shields Other passive protection specifications Hazard Detection Specifications 13.F.4.3.1 13.F.4.3.2 13.F.4.3.3 13.F.4.3.4 13.F.4.3.5 13.F.4.3.6 13.F.4.3.7 13.F.4.3.8 13.F.4.3.9 Commission Staff Guidance Low temperature detectors Oxygen deficiency detectors Toxic gas detectors Flammable/combustible gas detectors Flame detectors Heat and high temperature detectors Smoke or products of combustion detectors Manual pull stations Audible and visual notification systems for field, control room, plant wide, and offsite 13-103 February 2017 13.F.4.3.10 Other hazard detector specifications 13.F.4.4 Hazard control specifications 13.F.4.4.1 13.F.4.4.2 13.F.4.4.3 13.F.4.4.4 13.F.4.4.5 13.F.4.5 Portable fire extinguishers Fixed dry chemical systems Clean agent systems Carbon dioxide systems Other hazard control system specifications Fire water specifications 13.F.4.5.1 13.F.4.5.2 13.F.4.5.3 13.F.4.5.4 13.F.4.5.5 13.F.4.5.6 13.F.4.5.7 13.F.4.5.8 13.F.4.5.9 13.F.4.5.10 Commission Staff Guidance Fire water piping Fire hydrants Fire monitors Fire hose Water curtains Deluge systems Sprinkler systems Mist systems Foam system Other fire water system specifications 13-104 February 2017 13.G APPENDIX 13.G, HAZARD IDENTIFICATION 111 13.G.1 Process Hazard Analyses and Recommendations PROVIDE copies of preliminary process hazard analysis (PHA) design reviews. The PHA should include lists of the recommendations and status of implementation. The design reviews should, at a minimum, include the requirements for siting, equipment layout and spacing, process controls, and ignition controls applicable during all phases of commissioning, startups, shutdowns, operation and maintenance. Recommendations resulting from the PHA (e.g., HAZID and/or preliminary HAZOP) reviews performed during the FEED phase of the project should be included in the design submitted with the application. The PHA should list the participants and years of relevant experience. 13.G.2 Simultaneous Operation Studies PROVIDE descriptions or plans to develop any Simultaneous Operations (SIMOPS) studies to be used during project construction near operational facilities or during phased startup of multiple project stages. 13.G.3 Waterway Safety and Reliability Impact Studies 112 PROVIDE an analysis that addresses potential safety and reliability impacts of proposed LNG vessels (i.e., LNG carriers, LNG barges, etc.) loaded or unloaded at the project facilities and from current commercial and recreational waterway traffic with reference to other Resource Reports (e.g. Resource Report 8). The safety and reliability analysis should include studies that take into account tides, currents, waves, winds, ice, visibility, day/night conditions, passing vessels direction, passing vessels sizes and speeds, and LNG vessel sizes and speeds. An evaluation of the LNG vessel transit route and berthing should be provided that includes local pilot participation and comments and that addresses: 13.G.3.1 Potential occurrence, potential effects, and mitigation of watercraft alliding and colliding with the transiting LNG vessel, moored LNG vessel, and marine facilities 13.G.3.2 Potential occurrence, potential effects, and mitigation for LNG vessel grounding, alliding, and colliding with ground, marine platform and coastal structures, and other watercraft based on LNG vessel route, 111 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14). 112 Waterway Suitability Assessments submitted to Coast Guard in accordance with 18 CFR §157.21(a)(1), 18 CFR §157.21(f)(13), 33 CFR §127.007, and Navigation and Vessel Inspection Circular (NVIC) 01-2011, Guidance Related to Waterfront Liquefied Natural Gas Facilities may satisfy Waterway Safety and Reliability Impact Studies in Appendix 13.G.3. This material may include Critical Energy Infrastructure Information (CEII), Security Sensitive Information (SSI), or Chemical-Terrorism Vulnerability Information (CVI) and must comply with all applicable regulations. Commission Staff Guidance 13-105 February 2017 shipping channel depths and harbor bottom type, widths, turning basins, and berthing arrangement 13.G.3.3 Tug requirements, security escorts, and speed limits to safely and securely transport, berth, and unberth LNG vessel 13.G.3.4 Maneuvers to berth and unberth LNG vessel 13.G.3.5 Hydrodynamic effect of slips on passing vessels 13.G.3.6 Hydrodynamic effect of passing ships on moored LNG vessels 13.G.3.7 Potential occurrence, potential effects, and mitigation for intentional acts involving LNG vessel during transit and marine transfer 13.G.4 Road Safety and Reliability Impact studies PROVIDE an analysis that addresses potential safety and reliability impacts from proposed tanker trucks loaded or unloaded at the project facilities and from commercial and recreational roadway traffic with reference to other Resource Reports (e.g. Resource Report 8). The safety and reliability analysis should include studies that take into account visibility, day/night conditions, passing vehicle direction, passing vehicle contents, sizes, and speeds, and tanker truck contents, sizes, and speeds. An evaluation of external and internal roadways at the project site should be included that addresses: 13.G.4.1 Potential occurrence, potential effects, and mitigation of vehicles and proposed tanker trucks’ impacts, such as collisions from vehicles on external roadways 13.G.4.2 Potential occurrence, potential effects, and mitigation for collisions of vehicle and tanker trucks with other vehicles and equipment based on entrances, routes, road grades, road widths, turn around areas, and exit ways within the plant 13.G.4.3 Vehicle and tanker trucks access control, vehicle barriers, bollards, clearance heights, and speed limits to safely and securely receive, load, and unload tanker trucks 13.G.4.4 Potential occurrence, potential effects, and mitigation for intentional acts involving tanker trucks during transit and truck transfer. Commission Staff Guidance 13-106 February 2017 13.G.5 Rail Safety and Reliability Impact Studies PROVIDE an analysis that addresses potential safety and reliability impacts from proposed rail cars loaded or unloaded at the project facilities and from current commercial and passenger rail traffic with reference to other Resource Reports (e.g. Resource Report 8). The safety and reliability analysis should include studies that take into account visibility, day/night conditions, frequency, passing rail car direction, contents, sizes, and speeds. An evaluation of external and internal railways at the project site should be provided that addresses: 13.G.5.1 Potential occurrence, potential effects, and mitigation of rail cars on railways outside the plant accidentally colliding with the facilities 13.G.5.2 Potential occurrence, potential effects, and mitigation of rail car derailments and collisions with equipment based on rail car entrances, routes, grades, switchyards, and exit ways within the plant 13.G.5.3 Rail car access control, barriers, clearance heights, and speed limits to safely and securely receive, load, and unload rail cars 13.G.5.4 Potential occurrence, potential effects, and mitigation for intentional acts involving rail cars during transit and rail transfer 13.G.6 Air Safety and Reliability Impact studies PROVIDE an analysis that addresses potential safety and reliability impacts from current commercial, military, and recreational air traffic near the facility and along the LNG vessel route. with reference to other Resource Reports (e.g. Resource Report 8). The safety and reliability analysis should include studies that take into account visibility, day/night conditions, flight paths, and aircraft sizes and speeds. An evaluation of facility equipment (including construction equipment) and LNG vessel heights should be included that addresses: 13.G.6.1 Potential occurrence, potential effects, and mitigation of an aircraft accidentally colliding with the facilities or LNG vessels. 13.G.6.2 Potential occurrence, potential effects, and mitigation for intentional acts involving aircraft during transit to airports. Commission Staff Guidance 13-107 February 2017 13.G.7 Crane and Lifting Impact studies PROVIDE an analysis that addresses potential safety and reliability impacts from cranes and lifting devices within the facility from construction and maintenance activities. The analysis should include the location, capacity, size, and lifting paths of all crane and other lifting devices and discuss the use of mobile lifting equipment and any procedures or provisions to minimize impact. The analysis should include the weight of equipment to be lifted, lifting path and height, and should address: 13.G.7.1 Potential occurrence, potential effects, and mitigation of slips and drops from a crane or lifting device impacting the facilities or LNG vessels. 13.G.7.2 Potential occurrence, potential effects, and mitigation of cranes accidentally colliding with the facilities or LNG vessels (e.g., extended bucket trucks colliding with overhead piperacks). 13.G.8 Security Threat and Vulnerability Analyses 113 PROVIDE security related drawings and any associated security threat and vulnerability analyses. At a minimum, the security threat and vulnerability analysis should cover the potential physical and cyber security threats and vulnerability of the facility and related transportation. At a minimum, drawings should include: 113 13.G.8.1 Security fencing, site and onsite access control, bollard, vehicle barrier, and other physical barrier layout and drawings 13.G.8.2 Lighting layout and drawings 13.G.8.3 Intrusion monitoring (e.g., camera) and intrusion detection layout and drawings Security Threat and Vulnerability Information prepared for or submitted to Coast Guard in accordance with 33 CFR §105.305 or prepared for or submitted to Department of Homeland Security (DHS) in accordance with 6 CFR §27.215 may satisfy Security Threat and Vulnerability Analyses in Appendix 13.G.8. This material may include Critical Energy Infrastructure Information (CEII), Security Sensitive Information (SSI), or ChemicalTerrorism Vulnerability Information (CVI) and must comply with all applicable regulations. Commission Staff Guidance 13-108 February 2017 13.H APPENDIX 13.H, HAZARD ANALYSES 114 13.H.1 Safety Data Sheets PROVIDE safety data sheets for hazardous materials that would be stored, processed, and handled at the facility and transported to or from the facility. 13.H.2 Hazardous Release List PROVIDE a full list of considered hazardous releases and the bounding scenarios for all hazardous fluids areas 115. A piping and equipment inventory table of LNG plant components in hazardous or flammable fluid service should be provided. The piping and equipment inventory table should be submitted in Excel (*.XL*) format. Separate tabs or lists should be used for each type of hazardous fluid, as well as a separate tab or list to present all of the final selections. At a minimum, the list should include: 13.H.2.1 Line segment or component number to identify potential releases 13.H.2.2 Hazardous fluid service (LNG, natural gas, refrigerants [such as ammonia, propane, ethane, mixed refrigerant]), natural gas liquids or gas condensate, hydrogen sulfide, benzene, etc.) for each component 13.H.2.3 General plant area or service (e.g. liquefaction train, refrigerant storage, marine area, etc.), unless the entire project is confined to one area 13.H.2.4 Unit plot plan drawing number reference(s) for each component 13.H.2.5 Beginning point location (e.g., exchanger outlet flange) for each line 13.H.2.6 Ending point location (e.g., pump suction nozzle) for each line 13.H.2.7 P&IDs and drawing number reference(s) for each component 13.H.2.8 Piping line designation or equipment tag number on P&ID 13.H.2.9 Pipe diameter or pipe size, volume of container, or size of equipment 13.H.2.10 Length of piping (feet and meters) or number of components (each) 13.H.2.11 Maximum connection diameter in the piping segment 114 115 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(14). Refer to PHMSA’s LNG Plant Requirements: Frequently Asked Questions http://primis.phmsa.dot.gov/lng/faqs.htm (visited September, 20, 2016) .. Commission Staff Guidance 13-109 February 2017 13.H.2.12 Failure type or mode selected from the failure rate table 13.H.2.13 Corresponding nominal failure rates per meter or unit 13.H.2.14 Calculated failure rate based on pipe length or number of units and failure rates per meter or unit listed in the failure rate table 13.H.2.15 Comparison of calculated failure rate to a failure rate criterion of 3x105 failures per year 13.H.2.16 Process or storage conditions (e.g., fluid phase [liquid or vapor], density [lb/ft3], pressure [psig], temperature [°F], flow rate, [lb/hr], compositions) 13.H.2.17 Process flow diagram and corresponding heat and material balance stream number 13.H.2.18 Heat and material design case (e.g., rich, lean, average, etc.) 13.H.2.19 Calculated equivalent hole size based on failure modes listed in the failure rate table 13.H.2.20 Calculated release flow rates 13.H.2.21 Scenarios selected with release duration, de-inventory duration, height, direction, orientation, rainout percentage, flashing and jetting vapor mass flow rate, pool vaporization mass flow rate, and total vapor mass flow rate 13.H.3 Hazard Analysis Reports PROVIDE hazard analysis report(s) detailing the governing release scenarios and sensitivity tests (e.g., hole size, wind speed, and site-specific conditions) to evaluate hot and cold temperature hazards, asphyxiant and toxic dispersion hazards, flammable vapor dispersion hazards, VCE, BLEVE, and pressure vessel burst (PVB) overpressure hazards, fireball, pool fire, jet fire, and fireball radiant heat hazards from releases and cascading events. 116 Input and Output files should accompany all modeling runs. The hazard analysis 116 Hazards that extend offsite should describe the impacts to: (1) populated areas, including number of people, residential communities, business districts, schools, day care centers, religious facilities, and recreational facilities; (2) transportation infrastructure, including roads and highways, railroads and rail yards, pipelines, electric lines, marinas, airports, space launch sites; (3) industrial facilities, including power plants, nuclear facilities, wastewater facilities, and other hazardous facilities; (4) public health and safety facilities, including police and fire departments, and hospitals; and (5) military facilities, including military bases, test sites, and research areas. Commission Staff Guidance 13-110 February 2017 report should also discuss whether the safety and reliability of the proposed LNG facilities could be impacted by adjacent facilities, operations, or potential hazardous releases. 13.H.4 Meteorological Data PROVIDE meteorological data supporting the wind speed, atmospheric temperature, and humidity used in all hazard analyses. At a minimum, the meteorological data should be representative of the site and should cite the source of the weather data. Commission Staff Guidance 13-111 February 2017 13.I APPENDIX 13.I, NATURAL HAZARD DESIGN INVESTIGATIONS AND FORCES 117 13.I.1 Earthquakes 13.I.1.1 Seismic evaluation PROVIDE a seismic hazard evaluation for the LNG project site. Include all supporting information and data for the seismic hazard evaluation of the site and seismic design of the proposed project as specified in NBSIR 84-2833, 49 CFR Part 193, and incorporated NFPA 59A and ASCE 7 Standards. At a minimum, the Seismic Hazard Evaluation should address geologic and seismic setting, seismic hazard investigation. The geologic and seismic setting should include the project site’s local geologic and seismic setting including faults and seismic sources. Both seismic and growth faults should be investigated and addressed including recommendations for design vertical and horizontal offset and fault orientations were facilities or pipelines cross faults. The seismic hazard evaluation should include site-specific determinations of the MCE, DE, SSE ,OBE, and the ALE. The SSE and OBE should be based on 49 CFR Part 193 and the incorporated NFPA 59A Standard. As such, the SSE is taken equivalent to the MCE as determined in accordance with the site-specific procedures of the incorporated ASCE 7 and the OBE is taken as the ground motion with a 10% probability of exceedance within a 50-year period (475-year return period). The seismic hazard evaluation should also include detailed assessments of surface rupture and fault offset displacements including recommended offset values to be considered for design. If present, the following should be addressed in detail with estimated settlements without and with proposed ground improvement: liquefaction potential, liquefaction-related settlement, potential for sand boils and other surface manifestation of liquefaction, lateral spreading, seismic slope stability, seismic compaction, and need for ground improvement to mitigate liquefaction hazard,. Recommended values to be considered for design after ground improvement should also be included. Seismic Categories should include detailed description, sizes, loads, and relative locations and designate the Seismic Category I, II, or III of major structures such as LNG tanks, containment systems, buildings, storage tanks, vaporizers, liquefaction trains, power plant structures, and other plant components including unloading and 117 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14), 18 CFR §380.12(o)(15). Commission Staff Guidance 13-112 February 2017 docking facilities. Reference should be made to the Geotechnical Investigation in Appendix 13.J. See Attachment 3 for more details. 13.I.1.2 13.I.1.1.1 Geologic and seismic setting 13.I.1.1.2 Development of design earthquakes 13.I.1.1.3 MCE site-specific ground motion spectral values for 5% damping 13.I.1.1.4 DE site-specific ground motion spectral values for 5% damping and ground motion parameters, SDS, SD1, SMS, SM1, TL 13.I.1.1.5 SSE site-specific ground motion spectral values for 5% damping 13.I.1.1.6 OBE site-specific ground motion spectral values for 5% damping 13.I.1.1.7 ALE site-specific ground motion spectral values for 5% damping 13.I.1.1.8 At locations crossing active faults, design surface fault offsets (horizontal and vertical) and fault orientations 13.I.1.1.9 At locations where crossing growth faults, design offsets for growth faults: Provide design fault offsets for growth faults (horizontal and vertical) for the design life of the facilities and fault orientations 13.I.1.1.10 Ground motions and frequencies of earthquakes at site location. 13.I.1.1.11 Sloshing freeboard 13.I.1.1.12 Ground motion detection systems that alarm and shutdown. Seismic Categories of LNG facility structures, components, equipment and systems PROVIDE the Seismic Category assignments for all LNG facility structures, components, equipment, and systems associated with the project. The seismic category assignments should be all-inclusive and should be in accordance with the definitions provided in NBSIR 84- Commission Staff Guidance 13-113 February 2017 2833. If only a portion of structures and systems are Category I or II, they should be listed and, where necessary for clarity, the boundaries of Category I and II portions should be shown on piping and instrumentation drawings. An example of a categorized list for an LNG project is included in Attachment 4. 13.I.1.3 13.I.1.2.1 List of structures, systems and components classified as Seismic Category I 13.I.1.2.2 List of structures, systems and components classified as Seismic Category II. 13.I.1.2.3 List of structures, systems and components classified as Seismic Category III. Seismic design basis and criteria of LNG facility structures, components, equipment and systems PROVIDE the Seismic Category design basis and criteria for all Seismic Categories. The seismic design basis and criteria for Seismic Category I, II, or III structures, components, equipment and systems should include information or references needed to perform a design including design response spectra, seismic design coefficients, load combinations, damping values, damping value reduction factors, ductility or inelastic reduction factors to be used with the OBE and SSE, the allowable stresses, strength capacities and φ-factors for each load combination, intended methods of analysis, building codes and material standards to be used and all other criteria necessary to perform the design of each structure, component, and system. The seismic design criteria should, at a minimum, satisfy 49 CFR Part 193 and the incorporated edition of NFPA 59A. Items to be considered in preparing the seismic design criteria documents are included in Attachment 5. The seismic design criteria should also include the incorporated ASCE 7 design earthquake seismic coefficients and seismic design parameters that should be used in the design of structures, systems and components that are assigned Seismic Category II and III. In addition, In addition, the criteria should consider the guidance included in NBSIR 84-2833 and the following: 13.I.1.3.1 Seismic Category I design basis and criteria, including 13.I.1.3.1.1 Commission Staff Guidance SSE and OBE response spectra 13-114 February 2017 13.I.1.3.2 Commission Staff Guidance 13.I.1.3.1.2 Damping values, ductility or inelastic reduction factors (if any), to be used with SSE and OBE 13.I.1.3.1.3 Load combinations, load factors, allowable stress or capacity increases (if any), and angle of internal friction (ϕ)factors for each load combination 13.I.1.3.1.4 Intended methods of analysis 13.I.1.3.1.5 Codes and standards and specifications that are intended to be used and all other criteria necessary to perform the seismic design of each Seismic Category I structure, component, equipment, and system. Seismic Category II design basis and criteria 13.I.1.3.2.1 MCE and DE response spectra 13.I.1.3.2.2 Ground motion parameters 13.I.1.3.2.3 Occupancy classification to individual structures and non-building structures 13.I.1.3.2.4 Seismic design category assigned to individual structures and non-building structures 13.I.1.3.2.5 The importance factors for structures, non-building structures and nonstructural components and systems 13.I.1.3.2.6 The inelastic seismic coefficients for structures, non-building structures and nonstructural components and systems 13.I.1.3.2.7 Load combinations, load factors, allowable stress or capacity increases (if any) and (ϕ)-factors for each load combination 13-115 seismic design February 2017 13.I.1.3.3 Commission Staff Guidance 13.I.1.3.2.8 Intended methods of analysis 13.I.1.3.2.9 Codes and standards and specifications that are intended to be used and all other criteria necessary to perform the seismic design of each Seismic Category II structure, component, equipment and system. Seismic Category III design basis and criteria 13.I.1.3.3.1 MCE and DE response spectra 13.I.1.3.3.2 Ground motion parameters 13.I.1.3.3.3 Occupancy classification to individual structures and non-building structures 13.I.1.3.3.4 Seismic design category assigned to individual structures and non-building structures 13.I.1.3.3.5 The importance factors for structures, non-building structures and nonstructural components and systems 13.I.1.3.3.6 The inelastic seismic coefficients for structures, non-building structures and nonstructural components and systems 13.I.1.3.3.7 Load combinations, load factors, allowable stress or capacity increases (if any) and (ϕ)-factors for each load combination 13.I.1.3.3.8 Intended methods of analysis 13.I.1.3.3.9 Codes and standards and specifications that are intended to be used and all other criteria necessary to perform the seismic design of each Seismic Category III structure, component, equipment and system. 13-116 seismic design February 2017 13.I.1.3.4 13.I.1.3.5 Commission Staff Guidance Hazardous fluid piping design basis and criteria 13.I.1.3.4.1 The OBE response spectra and seismic parameter SDS 13.I.1.3.4.2 Load combinations, load factors, allowable stress or capacity increases (if any) and (ϕ)-factors for each load combination 13.I.1.3.4.3 Intended methods of analysis 13.I.1.3.4.4 Codes and standards and specifications that are intended to be used and all other criteria necessary to perform the seismic design of each Seismic Category III structure, component, equipment, and system. Provide seismic criteria for small LNG containers with capacities less than 70,000 gallons. The criteria should satisfy the seismic requirements of federal regulations including 49 CFR Part 193 and any incorporations by reference. The criteria should include: 13.I.1.3.5.1 DE seismic design ground motion parameters occupancy classification to individual structures and non-building structures 13.I.1.3.5.2 Seismic Category containers 13.I.1.3.5.3 The importance factor assigned to the containers 13.I.1.3.5.4 The inelastic seismic assigned to the containers 13.I.1.3.5.5 Load combinations, load factors, allowable stress or capacity increases (if any) and (ϕ)-factors for each load combination 13.I.1.3.5.6 Intended methods of analysis 13-117 assigned to the coefficients February 2017 13.I.1.3.5.7 13.I.1.4 Codes and standards that are intended to be used and all other criteria necessary to perform the seismic design of the small containers. Seismic instrumentation: PROVIDE a description (make and model) of the proposed seismic instrumentation that will be installed at the LNG project site and the location of both the instrument and the sensors. The purpose of the instrumentation is to permit a comparison of measured responses of Seismic Category I structures and selected components against predetermined results of analyses that predict when damage might occur. This also permits plant operators to understand the possible extent of damage within the plant immediately following an earthquake and to be able to determine when an SSE event has occurred that would require the emptying of the tank(s) for inspection as specified in Section 4.1.3.6 (c) of NFPA 59A-2001. If the instrument already exists at the site, include a description of the existing equipment and location of the instrument and the sensors. The seismic instrumentation section should be in accordance with NBSIR 84-2833. Seismic recording instrumentation should be triaxial digital systems that record accelerations versus time accurately for periods between 0 and 10 seconds. Recorders should have rechargeable batteries such that if there is a loss of power, recording will still occur. The instrumentation should be housed in appropriate weather and creature-proofed enclosures. At all LNG facilities, at a minimum, one recorder should be located in the free field mounted on rock or competent ground generally representative of the site. In addition, at sites classified as Seismic Design Category D, E, or F in accordance with Chapter 11 of ASCE 705 (assuming Occupancy Category IV) recorders should be located and attached to the foundations and roofs of LNG tanks, and in the control room. The systems should have the capability to also produce response spectra for each recorded time history. At a minimum, the seismic instrumentation information should include: 13.I.1.4.1 Commission Staff Guidance Description and basis for selection and location of Seismic Instrumentation that will be installed to provide detection, alarms, emergency response, and post-event 13-118 February 2017 verification of structural integrity in selected Category I structures and on the selected Category I components 118. 13.I.1.4.1.1 13.I.1.4.1.2 13.I.1.4.1.3 13.I.1.4.2 Control room operator notification 13.I.1.4.2.1 13.I.1.4.3 Triaxial peak accelerographs Triaxial time history accelerographs Triaxial spectrum recorders. Emergency Response Plans for responding to seismic alarms and data, including reference to post-processed seismic instrumentation data (e.g., peak acceleration or spectral response data). Comparison of measured and predicted responses 13.I.1.4.3.1 Criteria and procedures that will be used to compare measured responses of Category I structures and of selected components in the event of an earthquake against the predetermined results of predictive analyses of the seismic system and subsystem 13.I.2 Tsunami and Seiche PROVIDE details on the facilities design being proposed to handle potential tsunamis, seiche, or other seismic hydrologic effects (e.g., site elevation, shoreline stabilization, jetty design and operation). Include information to confirm why and how the overall project (LNG storage tanks and critical equipment, cryogenic transfer piping; marine/cargo unloading platforms; primary and emergency electrical power; boil-off gas compression; and control systems) would adequately withstand conditions from potential tsunamis, seiche, or other seismic hydrologic events. Indicate the water-borne debris with their size and speed that the facilities will be designed to withstand. Indicate the procedures that will be used to evaluate whether the design of LNG facilities is adequate. In addition, describe the design water inundation elevations for the project site and their bases for both still water and with wind/wave effects considering site-specific studies. Include all project elevations for dikes, storm surge walls, piers, docks, unloading and loading arms and other pier and dock facilities, and other elevated features of the project, their design basis and demonstrate how they would conform to industry and Federal standards and would protect critical equipment or ensure minimal consequences. Include the historical or scientific 118 For example, see NRC Regulatory Guide 1.12: Nuclear Power Plant Instrumentation for Earthquakes Commission Staff Guidance 13-119 February 2017 basis for wind and storm surge conditions used as design criteria. Compare with 100- and 500-, 1,000-, 2,500- and 10,000-year return period elevations. Include in these elevations the effects of sea level rise and regional subsidence considering the design life of project facilities for time dependent severe natural hazards. 13.I.2.1 Tsunami and seiche design basis and criteria 13.I.2.2 Identification of tsunami and seiche design inundation and run-up elevations and corresponding return periods for all structures, systems, and components 13.I.2.3 Maximum considered tsunami (MCT) inundation and run-up elevations for project site, including the MCE level ground motions at the site if the MCE is the triggering source of the MCT 13.I.2.4 Comparison of design tsunami and seiche water inundation elevations with inundation elevations corresponding to: 13.I.2.4.1 13.I.2.4.2 13.I.2.4.3 13.I.2.4.4 10,000-year return period 1,000-year return period 500-year return period 100-year return period 13.I.2.5 Discussion of inundation and run up elevations and frequencies of tsunamis and other natural hazards at site location 13.I.2.6 Design sea level rise: elevation change to be used in design to account for sea level rise at project site for the design life of the facilities 13.I.2.7 Design regional subsidence: elevation change to be used in design to account for regional subsidence at project site for the design life of the facilities 13.I.2.8 Discussion of co-seismic subsidence/uplift 13.I.2.9 Discussion of expected settlement over the design life of the facilities 13.I.3 Hurricanes and Other Meteorological Events PROVIDE details on the facilities design that are being proposed to handle potential regional hurricane activity or other storm effects (e.g., site elevation, shoreline stabilization, jetty design and operation, stormwater management and spill retention). Include information to confirm why and how the overall project (LNG storage tanks and critical equipment, cryogenic transfer piping; marine/cargo unloading platforms; primary and emergency electrical power; boil-off gas compression; and control systems) would Commission Staff Guidance 13-120 February 2017 adequately withstand conditions from potential wind and storm surge of hurricanes and similar meteorological events. Describe the design wind speeds (both sustained and 3-second gust) and their basis for all LNG facilities, including LNG containers, LNG containers with capacities less than 70,000 gallons, and all other equipment as required per 49 CFR §193.2067. Supply an all-inclusive list of facilities (structures, systems, equipment and components) that need to be designed for these wind speeds consistent with the PHMSA LNG frequently asked questions (FAQ). Include the codes or standards that were used to convert the design wind speeds into design forces for each wind speed situation. In addition, for each wind speed and situation, include the wind importance factor, allowable stress design (ASD) and Strength Load Combinations, Load Factors and permitted allowable stress increase factors consistent with the codes and standards to be used for design. Indicate the wind-borne debris and their wind speed that will be design per the requirements of 49 CFR §193.2067 and the procedures that will be used to evaluate whether the design of LNG facilities is adequate. In addition, describe the design storm surge elevations for the project site and their basis for both still water and with wind/wave effects conditions considering site-specific studies. Include all project elevations for dikes, storm surge walls, piers, docks, unloading and loading arms and other pier and dock facilities, and other elevated features of the project, their design basis, and demonstrate how they will conform to industry and Federal standards and protect critical equipment or ensure minimal consequences. Include the historical or scientific basis for wind and storm surge conditions used as design criteria. Compare with 100- and 500-, 1,000-, and 10,000year return period elevations and NOAA storm surge elevations for hurricane prone areas at the site for Category 1, 2, 3, 4 and 5 hurricanes. Include in these elevations the effects of sea level rise and regional subsidence considering the design life of the facilities for time dependent severe natural hazards. 13.I.3.1 Wind and storm surge design basis and criteria 13.I.3.2 Identification of design wind speeds (sustained and 3-second gusts) and corresponding return periods, wind importance factors, and storm surge design elevations for all structures, systems, and components 13.I.3.3 Comparison of design wind speeds (sustained and 3-second gusts) and storm surge (still water, wind/wave run-up effects, crest elevations) with hurricane and other meteorological event wind speeds corresponding to: 13.I.3.3.1 13.I.3.3.2 13.I.3.3.3 13.I.3.3.4 13.I.3.4 10,000-year return period 1,000-year return period 500-year return period 100-year return period Discussion of wind speeds (sustained and 3-second gusts) and storm surge elevations (still water, wind/wave run-up effects, crest elevations) Commission Staff Guidance 13-121 February 2017 and frequencies of hurricanes, and other meteorological events at site location: 13.I.3.4.1 Hurricane Saffir-Simpson Category 5 (>156 mph sustained, >195 mph 3-second gust) 13.I.3.4.2 Hurricane Saffir-Simpson Category 4 (130-156 mph sustained, 166-195 mph 3-second gust) 13.I.3.4.3 Hurricane Saffir-Simpson Category 3 (111-129 mph sustained, 141-165 mph 3-second gust) 13.I.3.4.4 Hurricane Saffir-Simpson Category 2 (96-110 mph sustained, 117-140 mph 3-second gust) 13.I.3.4.5 Hurricane Saffir-Simpson Category 1 (74-95 mph sustained, 91-116 mph 3-second gust) 13.I.3.5 Design sea level rise: elevation change to be used in design to account for sea level rise at project site for the design life of the facilities 13.I.3.6 Design regional subsidence: elevation change to be used in design to account for regional subsidence at project site for the design life of the facilities 13.I.3.7 Discussion of expected settlement over the design life of the facilities 13.I.4 Tornados PROVIDE details on the facilities design being proposed to handle potential tornados. Include information to confirm why and how the overall project (LNG storage tanks and critical equipment, cryogenic transfer piping; primary and emergency electrical power; boil-off gas compression; and control systems) would adequately withstand conditions from potential tornados. Describe the design wind speeds (both sustained and 3-second gust) with their design basis for all LNG facilities, including LNG containers, LNG containers with capacities less than 70,000 gallons, and all other equipment. Supply an all-inclusive list of facilities (structures, systems, equipment and components) that would be designed for these wind speeds. Include the codes or standards that were used to convert the design wind speeds into design forces for each wind speed situation. In addition, for each wind speed and situation, include the wind importance factor, allowable stress design (ASD) and Strength Load Combinations, Load Factors and permitted allowable stress increase factors consistent with the codes and standards to be used for design. Indicate the wind-borne debris with their wind speed that would be designed against. Indicate the procedures that will be used to evaluate whether the design of LNG facilities is adequate. Include the historical or scientific basis for wind conditions used as Commission Staff Guidance 13-122 February 2017 design criteria. Compare with 100- and 500-, 1,000-, and 10,000-year return period elevations and wind speeds for Enhanced Fujita (EF) Categories 0, 1, 2, 3, 4 and 5 tornados. 13.I.4.1 Wind speed design basis and criteria 13.I.4.2 Identification of design wind speeds (sustained and 3-second gusts) and corresponding return periods, and wind importance factors for all structures, systems, and components 13.I.4.3 Comparision of design tornado wind speeds (sustained and 3-second gusts) with tornado wind speeds corresponding to: 13.I.4.3.1 13.I.4.3.2 13.I.4.3.3 13.I.4.3.4 13.I.4.4 10,000-year return period 1,000-year return period 500-year return period 100-year return period Discussion of wind speeds (sustained and 3-second gusts) and frequencies of tornados at site location: 13.I.4.4.1 Tornados Category Enhanced Fujita (EF) Category 5 EF5 (>134 mph sustained, >200 mph 3-second gust), 13.I.4.4.2 Tornados Category EF4 (111-134 mph sustained, 166-200 mph 3-second gust), 13.I.4.4.3 Tornados Category EF3 (91-111 mph sustained, 136-166 mph 3-second gust), 13.I.4.4.4 Tornados Category EF2 (75-91 111-135 mph 3-second gust), mph sustained, 13.I.4.4.5 Tornados Category EF1 86-110 mph 3-second gust), (58-74 mph sustained, 13.I.4.4.6 Tornados Category EF0 65-85 mph 3-second gust). (44-57 mph sustained, Commission Staff Guidance 13-123 February 2017 13.I.5 Floods PROVIDE details on the facilities design being proposed to handle potential regional flooding (e.g., site elevation, shoreline stabilization, jetty design and operation, stormwater management and spill retention). Include information to confirm why and how the overall project (LNG storage tanks and critical equipment, cryogenic transfer piping; marine/cargo unloading platforms; primary and emergency electrical power; boil-off gas compression; and control systems) would adequately withstand conditions from potential flooding. Describe the streamflows and flood elevations for the project site with their bases considering Federal Emergency Management Agency (FEMA) flood hazard maps and any conducted site-specific studies. Include all project elevations for dikes, storm surge walls, piers, docks, unloading and loading arms and other pier and dock facilities, and other elevated features of the project, their design basis, and demonstrate how they would conform to industry and Federal standards and would protect critical equipment or ensure minimal consequences. Include the historical or scientific basis for flooding conditions used as design criteria. Compare with 100- and 500-, 1,000-, and 10,000-year return period. Include in these elevations the effects of sea level rise, regional subsidence, and other timedependent severe natural hazards considering the design life of the facilities. 13.I.5.1 Flood design basis and criteria 13.I.5.2 Identification of stream flows and flood design elevations and corresponding return periods for all structures, systems, and components 13.I.5.3 Comparison of design stream flows and flood elevations with stream flows and flood elevations corresponding to: 13.I.5.3.1 13.I.5.3.2 13.I.5.3.3 13.I.5.3.4 10,000-year return period 1,000-year return period 500-year return period 100-year return period 13.I.5.4 Discussion of streamflows and flood elevations and frequencies of floods and other natural hazards at site location 13.I.5.5 Design sea level rise: Provide elevation change to be used in design to account for sea level rise at project site for the design life of the facilities 13.I.5.6 Design regional subsidence: Provide elevation change to be used in design to account for regional subsidence at project site for the design life of the facilities 13.I.5.7 Discussion of expected settlement over the design life of the facilities Commission Staff Guidance 13-124 February 2017 13.I.6 Rain, Ice, and Snow PROVIDE details on the facilities design being proposed to handle potential rain, ice, and snow (e.g., site elevation, tank and equipment design loads, jetty design and operation, stormwater management and spill retention). Include information to confirm why and how the overall project (LNG storage tanks and critical equipment, cryogenic transfer piping; marine/cargo unloading platforms; primary and emergency electrical power; boil-off gas compression; and control systems) would adequately withstand rain, freezing rain, ice, and snow. Describe the design loads and stormwater and snowfall management for the project site with their design basis, considering hazard maps and any conducted site-specific studies. Include all project elevations for dikes, storm surge walls, piers, docks, unloading and loading arms and other pier and dock facilities, and other elevated features of the project, their design basis, and demonstrate how they would conform to industry and Federal standards, including 49 CFR Part 193 for rainfall removal for impoundments, and would protect critical equipment or ensure minimal consequences. Include the historical or scientific basis for rain, ice, and snow conditions used as design criteria. Compare with 100- and 500-, 1,000-, and 10,000-year return periods. 13.I.6.1 Rain, ice, and snow design basis and criteria 13.I.6.2 Identification of stormwater flows, outfalls, and stormwater management systems for all surfaces, including spill containment system sump pumps 13.I.6.3 Identification of snow and ice loads and corresponding return periods for all structures, systems, and components, including snow removal for spill containment systems 13.I.6.4 Comparision of design rain, ice, and snow events with rainfall rates, snow, and ice loads corresponding to: 13.I.6.4.1 13.I.6.4.2 13.I.6.4.3 13.I.6.4.4 13.I.6.5 10,000-year return period 1,000-year return period 500-year return period 100-year return period Discussion of ice and snow and frequencies of blizzards and other ice and snow events at site location. Commission Staff Guidance 13-125 February 2017 13.I.7 Other Natural Hazards PROVIDE details on the facilities design being proposed to handle other potential natural hazards (e.g., site elevation, tank and equipment design loads, jetty design and operation, stormwater management and spill retention). Include information to confirm why and how the overall project would adequately withstand other natural hazards, such as landslides, wildfires, volcanic activity, and geomagnetism. Describe the design loads (e.g. landslides, volcanic ash, etc.) and management for the project site with their design basis, considering hazard maps and any conducted site-specific studies. Include all project elevations for dikes, storm surge walls, piers, docks, unloading and loading arms and other pier and dock facilities, and other elevated features of the project, their design basis, and demonstrate how they would conform to industry and Federal standards and would protect critical equipment or ensure minimal consequences. Include the historical or scientific basis used as design criteria. Compare with 100- and 500-, 1,000-, and 10,000-year return period. 13.I.7.1 Design basis and criteria 13.I.7.2 Identification of loads and corresponding return periods for all structures, systems, and components 13.I.7.3 Comparison of design loads with loads corresponding to: 13.I.7.3.1 13.I.7.3.2 13.I.7.3.3 13.I.7.3.4 13.I.7.4 10,000-year return period 1,000-year return period 500-year return period 100-year return period Discussion of natural hazards and frequencies of natural hazards at site location. Commission Staff Guidance 13-126 February 2017 13.J APPENDIX 13.J, SITE INVESTIGATION AND CONDITIONS, AND FOUNDATION DESIGN 119 13.J.1 Topographic Map PROVIDE a topographic map with 1- to 2-foot contours showing the current and proposed elevations of the site location. 13.J.2 Bathymetric Chart PROVIDE a bathymetric chart showing the current and proposed bathymetry of the shipping channel and berthing area and also indicate the type of harbor bottom. 13.J.3 Climatic Data PROVIDE the data and analysis used to support the climatic conditions for the site and along the shipping channel. 13.J.4 Geotechnical Investigation PROVIDE a geotechnical investigation and foundation recommendation report. The scope of field investigation should be developed so that it is adequate for FEED-level design. Pre-FEED investigations may not be adequate for the geotechnical report. The boring/cone penetration test (CPT)/testing in the following sections are provided as guidelines for typical LNG projects. Depending on the site conditions or soils encountered, some type of investigations, such as CPTs in dense gravelly soils or rock coring at soil sites, may not be needed Typically a minimum of 5 borings/CPTs should be performed at each LNG tank location. In each Liquefaction Train area and other process areas the borings/CPTs should be spaced at a minimum of 200 to 300 foot spacing. It is suggested that a proposed boring/CPT plan be submitted to FERC for review prior to undertaking the field investigation. Geotechnical information should be supplied that is needed to establish the Site Class in accordance with Chapters 11 and 20 of ASCE 7-05. Evaluations should also be supplied that predict how the geotechnical information will change for any ground improvement options that are recommended in the report. Site Classes should be determined and supplied for all Seismic Category II and III structures at the site based on Chapters 11 and 20 of ASCE 7-05 for the various ground improvement options that are included in the report. Subsidence due to earthquake, ground water, and oil withdrawal should also be evaluated. Presence of poor or unusual soil conditions, such as highly compressible or highly expansive soils, corrosive soils, collapsible soils, erodible soils, liquefaction-susceptible soils, frost-heave susceptible soils, frozen soils, or sanitary landfill 119 18 CFR §380.12(m), 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14), 18 CFR §380.12(o)(15). Commission Staff Guidance 13-127 February 2017 etc. should be identified and remedial measures including ground improvement methods should be recommended, if such soils are present. See Attachment 6 for more details. The geotechnical investigation should include the applicable tests conducted and results for the following: 13.J.4.1 Geotechnical data 13.J.4.1.1 13.J.4.1.2 13.J.4.1.3 13.J.4.1.4 13.J.4.1.5 13.J.4.1.6 13.J.4.1.7 13.J.4.1.8 13.J.4.2 Soil identification tests 13.J.4.2.1 13.J.4.2.2 13.J.4.2.3 13.J.4.2.4 13.J.4.2.5 13.J.4.3 Direct shear Unconfined compression Pocket penetrometer Torvane Triaxial Compressibility tests 13.J.4.4.1 13.J.4.4.2 13.J.4.4.3 13.J.4.5 Moisture content Dry density Gradation Plasticity index Specific gravity Strength tests 13.J.4.3.1 13.J.4.3.2 13.J.4.3.3 13.J.4.3.4 13.J.4.3.5 13.J.4.4 Soil borings Standard penetration tests Rock coring Test pits Cone penetration tests Seismic refraction Downhole/crosshole seismic velocity measurements Other in-situ measurements. Consolidation Expansion index Collapse potential Corrosivity tests 13.J.4.5.1 13.J.4.5.2 13.J.4.5.3 13.J.4.5.4 13.J.4.5.5 Commission Staff Guidance pH Electrical resistivity Stray electrical ground currents Sulfates Chlorides 13-128 February 2017 13.J.4.5.6 Recommended mitigation for corrosive soils 13.J.4.6 California Bearing Ratio (CBR)/ R-value. 13.J.4.7 Site surface conditions 13.J.4.7.1 13.J.4.7.2 13.J.4.7.3 13.J.4.7.4 13.J.4.8 Site elevations Overall relief Topography Drainage Site subsurface conditions 13.J.4.8.1 13.J.4.8.2 13.J.4.8.3 13.J.4.8.4 Groundwater conditions Soils/rock layer description Geotechnical cross-sections Representative soil parameters. 13.J.5 Foundation Recommendations PROVIDE a foundation recommendations report for each major foundation type, including foundation recommendations for buildings, tanks, re-gasification facilities, liquefaction facilities, containment berms, flood protection walls / berms, power generation equipment, walls including mechanically stabilized earth (MSE) walls, pipe supports, and other foundations and foundation loading. Provide a summary of anticipated range of foundation sizes for major equipment and structures along with cross sections and plan views of proposed project protective berms and walls. The foundation recommendation report should discuss and provide recommendations for ground improvement. Recommendations should be provided for pavement design for both asphalt and Portland cement concrete pavements for the plant. Effects of ground improvements on soil properties, liquefaction and lateral spreading, and seismic ground motions should be addressed. Structures where total liquefaction settlement is greater than 3 inches should be supported on piles designed for down-drag due to settlement; or be designed to mitigate the liquefaction hazard by ground improvement; or a combination of both. Evaluations of both static and seismic stability, including effects of dredged slopes should be provided for the stability of the tanks, storm surge walls and berms, and other safety related structures. The foundation recommendations should address the applicable items for the following: 13.J.5.1 Shallow foundation 13.J.5.1.1 13.J.5.1.2 13.J.5.1.3 13.J.5.1.4 13.J.5.1.5 Commission Staff Guidance Ultimate bearing capacity Factor of safety Allowable bearing capacity Settlement criteria Mat foundations 13-129 February 2017 13.J.5.1.6 13.J.5.1.7 13.J.5.1.8 13.J.5.1.9 13.J.5.2 Deep foundation 13.J.5.2.1 13.J.5.2.2 13.J.5.2.3 13.J.5.2.4 13.J.5.2.5 13.J.5.2.6 13.J.5.2.7 13.J.5.2.8 13.J.5.2.9 13.J.5.3 Axial pile capacity Lateral pile capacity Group effects Settlement of pile groups Lateral movement of pile groups Pile installation Load tests Dynamic pile testing Indicator pile and load test programs Details of applicable ground improvement options being considered, such as: 13.J.5.3.1 13.J.5.3.2 13.J.5.3.3 13.J.5.3.4 13.J.5.3.5 13.J.5.3.6 13.J.5.4 Total and differential settlements Liquefaction settlements Settlement monitoring Lateral resistance Surcharge Stone columns Vibroflotation Soil-cement columns Dynamic compaction Other types of ground improvement Slope stability 13.J.5.4.1 13.J.5.4.2 Calculation of static and seismic stability Safety factor 13.J.6 Structural Design Basis and Criteria PROVIDE a structural design basis and criteria document that compiles and summarizes the structural design criteria to be used in the design of structures (including non-building structures) and their foundations. The structural design basis and criteria document should include the severe natural hazard loading parameters to be used, the ASD and strength load combinations, load factors and permitted ASD allowable increases. The document should also include the acceptance criteria to be used to determine an acceptable design. Reference should be made to other design basis documents in Appendix 13.B and natural hazard design criteria documents in Appendix 13.I. Commission Staff Guidance 13-130 February 2017 13.J.7 Foundation and Support Drawings and Calculations PROVIDE a foundation and support drawings. Preliminary design drawings and structural calculations should be provided for the LNG tanks, containment structures and their proposed foundations. Particular attention should be given to providing a physical description of the storage tanks and impounding systems, including plan and section views in sufficient detail to define the primary structural aspects. If the bottom of the tank is steel and the surface is not continuous, the method of anchorage of the steel shell walls to the concrete base slab should be described. Other major structural attachments should also be described. At a minimum, the foundation and support drawings and calculations should include: 13.J.7.1 13.J.7.2 13.J.7.3 13.J.7.4 13.J.7.5 Typical foundation drawings Equipment support drawings Static stability calculations Seismic stability calculations Settlement calculations Commission Staff Guidance 13-131 February 2017 13.K APPENDIX 13.K, MARINE SYSTEMS 120 13.K.1 Marine Facility Drawings PROVIDE marine facility drawings. At a minimum, the marine facility drawings should include: 13.K.1.1 13.K.1.2 13.K.1.3 13.K.1.4 13.K.1.5 13.K.1.6 13.K.1.7 13.K.1.8 120 Marine platform layout Berthing layout Mooring arrangements Jetty to marine platform layout Jetty to marine platform elevations showing high and low water levels Platform piling plan and section Trestle piping plan Pipe trestle sections and details 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(5), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-132 February 2017 13.L APPENDIX 13.L, LNG TANK INFORMATION 121 13.L.1 LNG Tank Specifications PROVIDE a complete specification of the proposed LNG tank and foundation system. In the event that the LNG tank supplier has not been selected, the LNG tank specifications should include all details of the design that the selected tank supplier would be required to incorporate. 13.L.2 LNG Tank Drawings. PROVIDE preliminary LNG tank drawings with dimensions. At a minimum, the LNG tank drawings should include: 13.L.2.1 13.L.2.2 13.L.2.3 13.L.2.4 13.L.2.5 13.L.2.6 13.L.2.7 13.L.2.8 13.L.2.9 13.L.2.10 13.L.2.11 13.L.2.12 13.L.2.13 13.L.2.14 13.L.2.15 13.L.2.16 13.L.2.17 Overall tank drawing with dimensions and design data Foundations and piles Elevation section Insulation systems Corner thermal protection Piping penetrations and schedule of openings Piping support structure Tank roof spill containment and protection Tank base spill protection Top and bottom fill piping In-tank pump column and support arrangement Relief valve and discharge orientation Temperature sensors and locations Foundation heating system Inclinometer Cathodic protection LNG level and density instruments 13.L.3 LNG Tank and Foundation Structural Design PROVIDE preliminary structural design drawings and calculation for the LNG tank and foundation system considering both wind and seismic loadings. 121 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(9), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-133 February 2017 13.M APPENDIX 13.M, PIPING, VESSEL, EQUIPMENT, AND BUILDINGS 122 13.M.1 Piping and Valve List* PROVIDE a list of piping and valves with design conditions. Design conditions should include; P&ID reference, line connection (from and to), diameter, fluid service, fluid phase, design density, flow, pressure, and temperature conditions, insulation, material of construction, corrosion allowance, leak test pressure and medium, and whether the line would be designed to withstand full vacuum, and any special notes or features (e.g. pipe in pipe, PWHT). 13.M.2 Tie-in List* PROVIDE a list of all tie-in points to existing piping. 13.M.3 Equipment List PROVIDE a list of equipment with anticipated design conditions. Design conditions should be appropriate for the type of equipment and should include as applicable: design pressure and temperature conditions, equipment dimensions, corrosion allowance, rated and normal flow capacity, rated and normal heating capacity, heat transfer area, and motor horsepower or voltage. 13.M.4 Equipment Process, Mechanical, and Thermal Data Sheets PROVIDE equipment process, mechanical, and thermal data sheets for each equipment item. 13.M.5 Manufacturer’s Data PROVIDE typical manufacturer’s information for major process equipment items. Where more than one manufacturer is under consideration and meets specifications, the equipment specifications and design data need not be repeated. 13.M.6 List of Buildings and Structures PROVIDE a list of buildings and structures. At a minimum, include a description of the building or structure, dimensions, occupancy, and any special features, such as HVAC shutdowns, pressurization, blast resistance, or fire resistance. 122 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(7), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-134 February 2017 13.M.7 Building Siting Analysis PROVIDE an analysis of the location of occupied buildings and housing relative to hazards. At a minimum, the analysis should evaluate permanent and temporary/construction buildings and structures (e.g., API 752 and API 753). 13.M.8 Building Drawings PROVIDE preliminary plans for the proposed buildings and structures. At a minimum, the drawings should include: 13.M.8.1 Preliminary building plan and elevation drawings Commission Staff Guidance 13-135 February 2017 13.N APPENDIX 13.N, ELECTRICAL DESIGN INFORMATION 123 13.N.1 Electrical Load List PROVIDE a list of anticipated power requirements for equipment for each operating mode. 13.N.2 Transformer List PROVIDE list of transformers with tag number, size, and location 13.N.3 Single Line Drawings PROVIDE single line drawings for power distribution and emergency load supply and distribution 13.N.3.1 13.N.3.2 Single line drawings power distribution Single line drawings of emergency load supply and distribution 13.N.4 UPS Drawings PROVIDE a UPS distribution block diagram. 13.N.4.1 UPS distribution block diagram 13.N.5 Electrical Area Classification Drawings PROVIDE overall plan drawings, area plan drawings, and elevation drawings depicting the electrical area classifications for Class 1, Division 1 and Class 1, Division 2. Elevation drawings should be provided for pipe racks, flammable fluid storage tanks, major pieces of equipment, and impoundments. 13.N.5.1 13.N.5.2 13.N.5.3 Electrical area classification overall plan drawing Electrical area classification area plan drawings Electrical area classification elevation drawings 13.N.6 Electrical Seal Drawings PROVIDE typical drawings of the electrical pass through seal and vents for services such as pumps/expanders and instrumentation. 13.N.6.1 123 Electrical pass-through seal drawings 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(11), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-136 February 2017 13.O APPENDIX 13.O, PLANS AND PROCEDURES 124 13.O.1 Management of Change Procedures and Forms* PROVIDE a description of the management of change (MOC) system, review process, and sample forms used during final design and construction. PROVIDE MOC procedures and sample forms for changes after operation of the project has commenced.* 13.O.2 QA/QC Plans and Procedures* PROVIDE a description of the quality assurance and quality control (QA/QC) system used during construction* 13.O.3 Commissioning Plans* PROVIDE a description of the plans and procedures to achieve a safe and successful startup. These procedures should reference the schedule in Appendix 13.A.5.7. At a minimum, the plans should detail key activities such as: 124 13.O.3.1 Roles and responsibilities of commissioning teams 13.O.3.2 Production of documentation (e.g., operating manuals, maintenance manuals, training manuals, testing procedures, etc.) 13.O.3.3 Testing the integrity of on-site mechanical installation (e.g., tightness, pressure testings, leak tests, etc.) 13.O.3.4 Functional tests for hazard detectors, instrumentation, ESD systems, DCS, SIS, etc. 13.O.3.5 Pre-startup safety reviews 13.O.3.6 Approval for introduction of hazardous fluids following purging/cleanout, dry out, inerting of process systems, and cooldown plans 13.O.3.7 Demonstration/performance tests 13.O.3.8 Placing facilities into service 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-137 February 2017 13.O.4 Operating Plans and Procedures* PROVIDE the operating plans and procedures that include a description of each system, startup procedures, details control and operation of each system, safe shutdown, emergency shutdown, abnormal operations, etc. These plans should reference applicable drawings and plant documents. 13.O.5 Maintenance Plans and Procedures* PROVIDE a description of the maintenance plans that includes procedures for corrective, preventive, predictive maintenance, and mechanical integrity to ensure equipment is installed and maintained to design specifications and is consistent with manufacturer’s instructions. The maintenance plans and procedures should include isolation procedures, deinventorying, purging practices and procedures, cold and hot tap procedures, and other associated plans, practices, and procedures. 13.O.6 Safety Procedures* PROVIDE a description of the applicable safety procedures at the plant such as safe work permits, hot work permits, lockout/tagout, car seal philosophy, near misses, Incident investigations, etc. The plans should include details on how the plant would monitor contractor access and activities. Commission Staff Guidance 13-138 February 2017 13.P APPENDIX 13.P, PROCESS CONTROL AND INSTRUMENTATION 125 13.P.1 Instrument Lists PROVIDE an instrument index for all facilities. At a minimum, the instrument list should include: 13.P.1.1 13.P.1.2 13.P.1.3 13.P.1.4 13.P.1.5 13.P.1.6 13.P.1.7 13.P.1.8 13.P.1.9 13.P.1.10 13.P.1.11 13.P.1.12 13.P.1.13 13.P.1.14 13.P.1.15 P&ID reference Instrument tag number Measurement (e.g., flow, temperature, pressure, composition, etc.) Location (e.g., local, PLC, DCS, SIS, etc.) I/O Type (e.g., AI, DO, etc.)* Signal range (e.g., 4-20mA, 0-100 ohm, etc.)* Loop Fluid Service Instrument Range* Calibration* Alarm set points* Shutdown set points* Voting logic Voting degradation logic* Safety Integrity Level (SIL)* Notes 13.P.2 System Architecture drawings PROVIDE system architecture drawings of all facilities. At a minimum, the system architecture drawings should include: 13.P.2.1 13.P.2.2 13.P.2.3 13.P.2.4 125 HMIs CPUs RIEs JBs 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(5), 18 CFR §380.12(8), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-139 February 2017 13.Q APPENDIX 13.Q, SAFETY INSTRUMENTED SYSTEMS AND SHUT-OFF VALVES 126 13.Q.1 Cause & Effect Matrices PROVIDE cause and effect matrices. The cause and effect matrices should indicate all alarm, shutdown, and hazard control activations with set points and voting logic: 13.Q.1.1 13.Q.1.2 ESD cause and effect matrices FGS cause and effect matrices 13.Q.2 Block Diagrams PROVIDE block diagrams for the DCS, SIS, and FGS: 13.Q.2.1 13.Q.2.2 13.Q.2.3 DCS block diagrams SIS block diagram FGS block diagram 13.Q.3 List of Shutoff Valves PROVIDE a list of the emergency shutdown (ESD) valves. At a minimum, the list should include: 13.Q.3.1 13.Q.3.2 13.Q.3.3 13.Q.3.4 13.Q.3.5 13.Q.3.6 13.Q.3.7 13.Q.3.8 13.Q.3.9 P&ID reference Interlock tag and/or ESD designation Shutoff valve tag number Shutoff valve type Shutoff valve actuator type Shutoff valve fail position Shutoff valve leakage class Shutoff valve actuation/closure time* Special features required (e.g., fire safe) 13.Q.4 Drawing of ESD Manual Activation Devices PROVIDE a layout showing the locations of ESD manual activation devices. 13.Q.5 Shutoff Valve Manufacturer’s Data PROVIDE typical manufacturer's specifications, drawings, and literature on the fail-safe shut-off valves and actuators. 126 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(5), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-140 February 2017 13.R APPENDIX 13.R, RELIEF VALVES AND FLARE/VENT SYSTEMS 127 13.R.1 Relief Valves Capacities and Sizing PROVIDE a list and calculation sheets* of the vacuum and pressure relief valves. At a minimum, the list and calculation sheets should include: 13.R.1.1 13.R.1.2 13.R.1.3 13.R.1.4 13.R.1.5 13.R.1.6 13.R.1.7 13.R.1.8 13.R.1.9 13.R.1.10 P&ID reference Relief valve tag number Relief valve service Relief valve type* Relief valve size Relief valve capacity Relief valve set point Relief valve discharge location* Relief valve leakage class* Special features required (e.g., fire safe) 13.R.2 Flaring Load and Venting Capacities and Sizing PROVIDE a list and calculation sheets of the flares and vents. At a minimum, the list and calculation sheets should detail: 13.R.2.1 13.R.2.2 13.R.2.3 13.R.2.4 13.R.2.5 13.R.2.6 13.R.2.7 13.R.2.8 13.R.2.9 127 Criteria for sizing Capacity case description Capacity case load Capacity calculations Sizing case description Sizing case load Sizing calculations Flare radiant heats and sound at ground level and nearby structures, Vent concentrations at ground level and nearby elevated ignition sources 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(3), 18 CFR §380.12(o)(8), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-141 February 2017 13.S APPENDIX 13.S, PROTECTION 128 SPILL, TOXIC, FIRE, AND EXPLOSION 13.S.1 Preliminary Fire Protection Evaluation PROVIDE the preliminary fire protection evaluation according to incorporated editions of NFPA 59A Standards. This evaluation should support the design of the hazard detection and control systems. 13.S.2 Spill Containment Matrix PROVIDE a matrix of all spill containment impoundments with sizing spill and volumetric capacity. The sizing spill should demonstrate the ability to contain the largest vessel serving the impoundment and the largest flow from any single pipe for 10 minutes and should account for pump runout and piping deinventory. Fire water used to cool adjacent equipment should also be accounted for if it can discharge into the same impoundment. At a minimum, the spill containment matrix should include: 13.S.2.1 13.S.2.2 13.S.2.3 13.S.2.4 13.S.2.5 13.S.2.6 13.S.2.7 13.S.2.8 13.S.2.9 13.S.2.10 13.S.2.11 13.S.2.12 13.S.2.13 13.S.2.14 13.S.2.15 13.S.2.16 13.S.2.17 128 LNG marine transfer equipment and piping Pretreatment equipment and piping (Amine) Heavies/Condensates removal equipment and piping Heavies/Condensates storage, equipment, and piping NGL fractionation equipment and piping NGL storage, equipment and piping NGL truck transfer equipment and piping HTF storage, equipment and piping Refrigerant truck transfer equipment and piping Refrigerant storage, equipment, and piping Liquefaction process equipment and piping LNG storage, equipment, and piping LNG truck transfer equipment and piping LNG pumps and piping Liquid nitrogen storage, equipment, and piping Diesel storage, equipment and piping Other hazardous fluid storage and piping 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(2) thru (4), 18 CFR §380.12(o)(10), 18 CFR §380.12(o)(14). Commission Staff Guidance 13-142 February 2017 13.S.3 Spill Containment Drawings and Calculations PROVIDE drawings clearly showing the location of each spill containment system, direction of flow, material of construction, and the equipment served by each system. At a minimum, the drawings should show all curbing, grading, trenches, troughs, down comers, impoundments, sumps, dikes, water removal systems. It may be necessary to provide separate drawings for each process area and show underground to aboveground transitions of piping. 13.S.3.1 Spill containment plan drawings 13.S.3.2 Spill containment cross sections and details 13.S.3.3 Impoundment usable volumetric capacity calculations, including volume of largest containers contained by impoundment and largest flow rates and durations for piping (inventory and runout) contained by impoundment 13.S.3.4 Trench/trough volumetric flow capacity calculations 13.S.3.5 Downcomers volumetric flow capacity calculations 13.S.3.6 Storm water drainage calculations 13.S.4 Passive Protection Drawings PROVIDE unit plot plan drawings clearly showing the location of each passive protection system. At a minimum, the passive protection drawings should include: 13.S.4.1 Passive cryogenic structural protection drawings 13.S.4.2 Passive fire structural protection drawings 13.S.4.3 Passive blast structural protection drawings 13.S.4.4 Other passive protection drawings (e.g. vapor barriers, firewalls, and radiant heat shields) 13.S.5 Hazard Detection Matrix PROVIDE a matrix of all detection equipment with tag number, location, elevation*, detector type, calibration gas*, set points for alarms, shutdowns, and automatic activations of hazard control or fire water equipment. At a minimum, the matrix should include: 13.S.5.1 Hazard zones Commission Staff Guidance 13-143 February 2017 13.S.5.2 13.S.5.3 13.S.5.4 13.S.5.5 13.S.5.6 13.S.5.7 13.S.5.8 13.S.5.9 Low temperature detectors Oxygen deficiency detectors Toxic detectors Flammable and combustible gas detectors High temperature and heat detectors Smoke/products of combustion detectors Fire detectors Other hazard detectors (e.g., acoustic leak detectors, CCTV detectors, carbon monoxide, etc.) 13.S.6 Hazard Detection Drawings PROVIDE a layout of the hazard detection system showing the location of low temperature detectors, toxic gas detectors, oxygen deficiency detectors, combustible-gas detectors, fire detectors, heat detectors, smoke or products of combustion detectors, and manual pull stations. Separate plot plans should be created where necessary to provide clarity. In addition, PROVIDE a drawing showing all combustion/ventilation air intake equipment, the detectors covering the air intake and the distances to any possible hydrocarbon release (LNG, flammable refrigerants, flammable liquids and flammable gases). 13.S.6.1 13.S.6.2 13.S.6.3 13.S.6.4 Zones Hazard detector layout plans Manual pull stations Combustion/ventilation air intake locations 13.S.7 Hazard Control Matrix PROVIDE a matrix of hazard control equipment. At a minimum, the matrix should include tag number, location and area covered, type, size, discharge flow rates, activation, or remote control capabilities and manufacturer/model* for all dry chemical equipment. The matrix should provide similar information for other types of hazard control systems used at the site. 13.S.8 Hazard Control Drawings PROVIDE a detailed layout of the hazard control system showing the type of unit and the area of coverage. The legend should indicate the type of each unit and the quantity of suppressant. 13.S.8.1 13.S.8.2 Dry chemical equipment and other systems location plans Dry chemical equipment and other systems coverage plans Commission Staff Guidance 13-144 February 2017 13.S.9 Fire Water Matrix PROVIDE tag number, location and area covered, type, size, discharge conditions, activation, or remote control capabilities and manufacturer/model* for all fire water equipment including deluge systems, sprinklers, high expansion foam systems, monitors, hydrants, and hose stations. 13.S.10 Fire Water Drawings and Calculations PROVIDE drawings and calculations of the fire water system. Drawings should include P&IDs, system and equipment layouts, and coverage plans. Calculations should include firewater demand calculations based on the most demanding scenarios using minimum water densities that mitigate the hazard and hydraulic calculations for the most hydraulically demanding scenarios*. The layout of the fire protection system should show the location of fire water pumps, piping, hydrants, hose reels, high and low expansion foam systems, deluge systems, sprinkler systems, water mist systems, water screens, and other fire water-based systems and auxiliary or appurtenant service facilities. The plan drawings should show the fire water supply, the sizing of the fire water mains, and how they are arranged in either a loop or grid system throughout the site. Isolation valves to allow water flow in case a portion of the system is damaged should be shown. They should also show monitors, hydrants, hose stations and post indicator valves. Coverage areas for each system should be clearly depicted showing the coverage circle. Where buildings, or equipment block the line of sight of the monitor the non-covered area should be indicated. 13.S.10.1 13.S.10.2 13.S.10.3 Fire water P&IDs Fire water piping and equipment layout Fire water coverage plans Commission Staff Guidance 13-145 February 2017 13.T APPENDIX 13.T, TECHNOLOGY, PROCESS, SELECTION AND ALTERNATIVES 129 AND EQUIPMENT 13.T.1 Design Studies and Alternatives PROVIDE copies of company, engineering firm, or consultant studies that show the engineering planning or design approach to the construction of new facilities or plants. Include studies that support a design decision such as selecting a specific type of equipment where other alternatives were available. Studies that were used to develop unique design features that differ from currently operating facilities should also be supported. Alternative processes, technologies, and equipment that should be considered and evaluated include, but are not limited to, the following: 129 130 13.T.1.1 LNG Storage Tanks: Single, membrane, double, and full containment above-ground or below-ground LNG storage tank designs, including any LNG Storage Tank Risk Assessment Studies (e.g., API 625), Security Vulnerability Assessments 130, or other studies that led to the proposed selection 13.T.1.2 Vents/Flares: Derrick mounted or guy-wired elevated or vent stacks or flares, and ground flare designs, including any visual impact analyses, flare radiation analyses, maintainability studies, or other studies that led to the proposed selection 13.T.1.3 Vaporization: Ambient air vaporizers, shell and tube, or submerged combustion vaporizer designs, including any emission studies, fog dispersion studies, reliability studies, or other studies that led to the proposed selection 13.T.1.4 Liquefaction: Pre-cooled single mixed refrigerant, cascade, single mixed refrigerant, nitrogen expansion cycle, or other liquefaction systems, including any efficiency studies, or other studies that led to the proposed selection 13.T.1.5 Inherently safer refrigerants and intermediate heat transfer fluids, such as ethane versus ethylene in mixed refrigerant cycle, anhydrous ammonia versus propane as a pre-cooler refrigerant, or water ethylene glycol versus water propylene glycol mixtures for an intermediate heat 18 CFR §380.12(m)(1), 18 CFR §380.12(m)(3) thru (5), 18 CFR §380.12(o)(7). Security Threat and Vulnerability Information prepared for or submitted to Coast Guard in accordance with 33 CFR §105.305 or prepared for or submitted to Department of Homeland Security (DHS) in accordance with 6 CFR §27.215 may satisfy Security Threat and Vulnerability Analyses in Appendix 13.G.8. This material may include Critical Energy Infrastructure Information (CEII), Security Sensitive Information (SSI), or ChemicalTerrorism Vulnerability Information (CVI) and must comply with all applicable regulations. Commission Staff Guidance 13-146 February 2017 transfer fluid, including any hazard analyses, efficiency studies, or other studies that led to the proposed selection 13.T.1.6 Transformers: Dry type transformers versus liquid insulated transformers, including hazard analyses, or other studies that led to the proposed selection 13.T.1.7 Motors: Electric motor driven equipment and associated power lines and offsite power generation versus combustion engines or turbines with various emission control technologies and/or onsite power generation, including emission studies, reliability studies, or other studies that led to the proposed selection 13.T.1.8 Water Supply: Water storage/supply and use for potable, utility, firefighting water, including reliability studies, or other studies that led to the proposed selection Commission Staff Guidance 13-147 February 2017 ATTACHMENTS ATTACHMENT 1 – TYPICAL COST-INFLUENCE CURVE OF A LNG FACILITY AND FERC REVIEW Cost-Influence Curve Influence Influence Conceptual/Business Development FERC Prefiling and Application Review FERC Final/Detailed Design and Construction Review FERC Commissioning Cooldown/ Startup Review FERC Operational Review FEED Detailed Design Construction Operation Project Phase Commission Staff Guidance A-1 Februrary 2017 Cost Cost ATTACHMENT 2 – EQUIPMENT DATA TABLE A. Process Pumps 1. Type 2. Number, operating and spare 3. Operating and design flow rate capacities (minimum, normal/rated, maximum), gpm 4. Operating and design duties (minimum, normal, maximum), MMBtu/h 5. Operating and design suction pressures (minimum/net positive suction head [NPSH], normal/rated, maximum), psig 6. Operating and design suction temperatures (minimum, normal, maximum), °F 7. Operating and design discharge pressures (minimum, normal/rated, maximum/shutoff), psig 8. Operating and design discharge temperatures (minimum, normal, maximum/shutoff), °F 9. Operating and design densities (minimum, normal, maximum), specific gravity B. Compressors and Blowers 1. Type 2. Number, operating and spare 3. Operating and design flow rate capacities (minimum, normal/rated, maximum), MMscfd 4. Operating and design suction pressures (minimum/net positive suction head [NPSH], normal/rated, maximum), psig 5. Operating and design suction temperatures (minimum, normal, maximum), °F 6. Operating and design discharge pressures (minimum, normal/rated, maximum/shutoff), psig 7. Operating and design discharge temperatures (minimum, normal, maximum/shutoff), °F 8. Operating and design densities (minimum, normal/rated, maximum), specific gravity C. Gas Purification Systems 1. Type 2. Operating and design inlet flow rate capacities (minimum, normal, maximum), MMscfd or lb/hr 3. Operating and design inlet compositions (minimum/lean/light, normal/design/average, maximum/rich/heavy), %-vol or ppm 4. Operating and design inlet pressures (minimum, normal, maximum), psig 5. Operating and design inlet temperatures (minimum, normal, maximum), °F 6. Operating and design outlet product flow rates (minimum, normal, maximum), MMscfd or lb/hr (gpm for NGLs and Condensates) 7. Operating and design outlet compositions (minimum/lean/light, normal/design/average, maximum/rich/heavy), %-vol or ppm 8. Operating and design outlet pressures (minimum, normal, maximum), psig 9. Operating and design outlet temperatures (minimum, normal, maximum), °F Commission Staff Guidance A-2 Februrary 2017 ATTACHMENT 3 – SAMPLE SEISMIC GROUND MOTION HAZARD EVALUATION CONTENTS 1. General A seismic ground motion hazard analysis study should be performed to determine the site-specific OBE and SSE ground motions in accordance with 49 CFR Part 193 and the incorporated NFPA 59A requirements and to determine the MCE and DE ground motions in accordance with the incorporated ASCE 7 requirements. In addition to the specific data needed to support and justify the site-specific ground motion recommendations, the study should include geologic and seismic data requested in this Attachment and a discussion of other seismic hazards such as fault rupture, tsunamis, and seiche. The geotechnical report should address in detail the following hazards, if present, and the need for ground improvement to mitigate them: liquefaction potential, liquefactionrelated settlement, potential for sand boils and other surface manifestation of liquefaction, lateral spreading, seismic slope stability, and seismic compaction. Follow the outline in Attachment 6. 2. Geology In addition to standard geotechnical information needed to develop foundation recommendations, the additional geologic information requested herein should be provided in the seismic ground motion hazard study report. Information obtained from published reports, maps, private communications, or other sources should be referenced. Information from surveys, geophysical investigations, borings, trenches, or other investigations should be adequately documented by descriptions of techniques, graphic logs, photographs, laboratory results, identification of principal investigators, and other data necessary to assess the adequacy of the information. 2.1 Regional Geology Discuss all geologic, seismic, and manmade hazards within the site region and relate them to the regional physiography, tectonic structures and tectonic provinces, geomorphology, stratigraphy, lithology, and geologic and structural history and geochronology. This information should be discussed and shown on maps needed to illustrate actual or potential hazards such as landslides, subsidence, uplift, or collapse resulting from natural features such as tectonic depressions and cavernous or karst terrains that are significant to the site. Identify and describe tectonic structures such as folds, faults, basins, and domes underlying the region surrounding the site, and include a discussion of their geologic history. A regional tectonic map showing the structures of significance to the site should Commission Staff Guidance A-3 Februrary 2017 be provided. The detailed analyses of faults to determine their capacity for generating ground motions at the site and to determine the potential for surface faulting should be included. Refer to Section 3 of this Attachment for additional detail. Provide geologic profiles showing the relationship of the regional and local geology to the site location. The geologic province within which the site is located and the relation to other geologic provinces within 100 miles of the site should be indicated. Regional geologic maps indicating the site location and showing both surface and bedrock geology should also be included. 2.2 Site Geology A site topographic map showing the locations of the principal plant facilities should be included. Regional hazard identified in Section 2.1, e.g., landslides, should be evaluated for the site. The thicknesses, physical characteristics, origin, and degree of consolidation of each lithologic unit should also be described for the site, including a local stratigraphic column. Furnish summary logs of borings and excavations such as trenches used in the geologic evaluation. Boring logs included in Attachment 6, Section 2.1, may be referenced. A detailed discussion of the structural geology in the vicinity of the site should be provided with particular attention to specific structural units of significance to the site such as folds, faults, synclines, anticlines, domes, and basins. Provide a large-scale structural geology map (1:5,000) of the site showing bedrock surface contours and including the locations of Seismic Category I structures. A large-scale geologic map (1:24,000) of the region within 5 miles of the site that shows surface geology and that includes the locations of major structures of the LNG plant, including all Seismic Category I structures, embankments, and pipelines should be described in detail. Areas of bedrock outcrop from which geologic interpretation has been extrapolated should be distinguished from areas in which bedrock is not exposed at the surface. When the interpretation differs substantially from the published geologic literature on the area, the differences should be noted and documentation for the new conclusions presented. Include an evaluation from an engineering-geology standpoint of the local geologic features that affect the plant structures. Deformational zones such as shears, joints, fractures, and folds, or combinations of these features should be identified and evaluated relative to structural foundations. Describe and evaluate zones of alteration or irregular weathering profiles, zones of structural weakness, unrelieved residual stresses in bedrock, and all rocks or soils that might be unstable because of their mineralogy or unstable physical or chemical properties. The effects of man's activities in the area of the site should be evaluated; for example, withdrawal or addition of subsurface fluids or mineral extraction. Site groundwater conditions should be described. Commission Staff Guidance A-4 February 2017 3. Faulting 3.1 Investigation of Quaternary Faults Identified faults, any part of which is within 5 miles of the site, should be investigated in sufficient detail, using geological and geophysical techniques of sufficient sensitivity that demonstrate the age of the most recent movement on each. The type and extent of investigation varies from one geologic province to another and depends on sitespecific conditions. For Quaternary faults, any part of which is within 5 miles of the site, determine the following: 1) 2) 3) 4) 3.2 length of the fault; relationship to regional tectonic structures; nature, amount, and geologic displacement along the fault; and outer limits of the fault zone. Determination of Active Faults Determine the geologic evidence of fault offset at or near the ground surface at or near the site. Any lineaments identified on topographic maps, aerial photos, or satellite imagery linears identified as part of this study should be discussed. List all historically reported earthquakes that can be reasonably associated with faults, any part of which is within 5 miles of the site. A plot of earthquake epicenters superimposed on a map showing the local tectonic structures should be provided. The structure and genetic relationship between the site area faulting and regional tectonic framework should be discussed. In tectonically active regions, any detailed geologic and geophysical investigations conducted to demonstrate the structural relationships of site area faults with regional faults known to be seismically active should be discussed. 3.3 Fault Rupture Investigation A detailed faulting investigation should be conducted within one mile of the storage tank(s) foundation(s) and, as necessary, along any active faults identified under Section 3.2 of this Attachment that reasonably have a potential for affecting faulting on the site or provide significant information concerning such faulting. This investigation should be in sufficient detail to determine the potential for faulting and the magnitude of possible displacement impacting the safety-related facilities of the plant. The report of the faulting investigation should be coordinated with the investigation and report under Sections 3.1 and 3.2 of this Attachment and should include information in the form of boring logs, Commission Staff Guidance A-5 February 2017 detailed geologic maps, geophysical data, maps and logs of trenches, remote sensing data, and seismic refraction and reflection data. If faulting exists, it should be defined as to its attitudes, orientations, width of shear zone, amount and sense of movement, and age of movements. Site surface and subsurface investigations conducted to determine the absence of faulting should be reported, including information on the detail and areal extent of the investigation. The geologic studies included in a Fault Rupture Investigation should conform to established guidelines such as California Division of Mines and Geology, Note 49 (Ref. 22). Based on geologic studies, if it is determined that there is a potential for fault rupture hazard, and the structure is to be located either within 500 feet of a known fault or the possibility of a fault rupture passing through the proposed structure cannot be excluded, then seismic fault rupture analysis should be performed. This may include, but not be limited to magnitude, slip rates and recurrence models, type of fault (e.g., strike slip, normal), horizontal and vertical components of offset, and style of faulting. 4. Ground Motions 4.1 Historic Seismicity A complete list of all historically reported earthquakes affecting the region surrounding the site should be provided. The listing should include, as a minimum, all earthquakes of Modified Mercalli Intensity greater than IV or magnitude greater than 3.0. A map should also be provided that shows all listed earthquake epicenters. The following information describing each earthquake should be provided whenever it is available: 1) epicenter coordinates, 2) depth of focus, 3) origin time, 4) highest intensity, 5) magnitude (including moment magnitude), 6) source mechanism, 7) source dimensions, 8) stress drop, 9) any strong motion recordings relevant to a determination of the ground motion or design response spectra, and 10) references from which the specified information was obtained. Commission Staff Guidance A-6 February 2017 In addition, any earthquake-induced geologic hazards (e.g., liquefaction, landsliding, land spreading, or lurching) that have been reported on or within 5 miles of the site should be described in detail, including the level of strong motion that induced failure and the properties of the materials involved. This discussion should include identification of the methods used to locate the earthquake epicenters and an estimate of their accuracy. 4.2 Geologic Structures and Tectonic Activity Identify the regional geologic structures and tectonic activity that are significant in determining regional earthquake potential. All tectonic provinces any part of which could govern the design ground motions at the site should be identified. The identification should include a description of those characteristics of geologic structure, tectonic history, present and past stress regimes, and seismicity that distinguish the various tectonic provinces and particular areas within those provinces where historical earthquakes have occurred. Alternative models of regional tectonic activity from available literature sources should be discussed. The discussion in this section should be augmented by a regional-scale map showing the tectonic provinces, earthquake epicenters, the locations of geologic structures and other features that characterize the provinces, and the locations of any Quaternary faults. When an earthquake epicenter cannot be reasonably correlated with geologic structures, the epicenter should be discussed in relation to tectonic provinces. Subdivision of tectonic provinces should be supported on the basis of evaluations that consider, but should not be limited to, detailed seismicity studies, differences in geologic history, and differences in stress regime. 4.3 Maximum Earthquake Potential The largest earthquake or earthquakes associated with each geologic structure or tectonic province should be identified. Where the earthquakes are associated with a geologic structure, the largest earthquake that could occur on that structure should be evaluated based on considerations such as the nature of faulting, fault length, fault displacement, and earthquake history. The largest historical earthquakes within the province should be identified and, whenever reasonable, the return period for the earthquakes should be estimated. A table of faults with fault length, type of fault, distance at closest point to the site, maximum earthquake, etc. should be provided. 4.4 Near-Fault Effects For each set of conditions describing the occurrence of the maximum potential earthquakes, determined in Section 5.3 above, the types of seismic waves (such as Commission Staff Guidance A-7 February 2017 directivity, fault normal, and fault parallel) producing the maximum ground motion and the significant frequencies at the site should be determined. 4.5 Determination of Site Class Site Class definitions are provided in ACSE 7-05 (Chapter 20) or IBC 2006 (Table 1613.5.2). Site classes range from Class A for hard rock to Class F for liquefiable or other very poor soil conditions. Site Class should be determined by seismic velocity data and other geotechnical data provided in the geotechnical report in accordance with the procedure in Sections 1613.5.5 and 1613.5.5.1 of IBC 2006 or Chapter 20 of ASCE 7-05. 4.6 Deterministic Seismic Hazard Analysis A deterministic seismic hazard analysis should be performed which computes the peak ground horizontal acceleration and spectral response accelerations for periods of at least 0.2s and 1.0s from the maximum earthquake on each of the faults found within 100 miles from the site. The computation of the peak acceleration and spectral accelerations is based on the closest distance between the site and each fault and the selected attenuation relationships. In general, a minimum of three attenuation relationships should be used consistent with the geologic and seismic setting of the site and type of faulting. The closest active fault and the fault generating the maximum acceleration at the site should be identified. Differences between the selected attenuations and the attenuations used in the latest USGS National Seismic Hazard Maps should be discussed. 4.7 Probabilistic Hazard Analysis Probabilistic seismic hazard evaluation involves obtaining, through a formal mathematical process, the level of ground motion parameters that have a selected probability of being exceeded during a specified time interval. The probabilistic approach incorporates the contributions from historical seismicity and all faults and considers the likelihood of the occurrence of earthquakes at any point on the fault. It also incorporates the contributions from various magnitude earthquakes up to and including the maximum earthquake. This approach is described in a number of sources such as Cornell, 1968 (Ref. 25), Algermissen et al, 1976 (Ref. 27) and Frankel, 1996, 2002 (Ref. 26). A probabilistic seismic hazard analysis should be performed using at least three attenuation relationships consistent with the geologic and seismic setting of the site. Differences between the selected attenuations and the attenuations used in the latest USGS National Seismic Hazard Maps should be discussed. Based on the site-specific probabilistic analyses, two levels of site ground motions, the OBE and SSE ground motions should be developed in accordance with the guidelines provided in Section 5.2 of Part I of this document. Commission Staff Guidance A-8 February 2017 4.8 Code Values of Ground Motions The code values of ground motions should be determined using either ASCE 7-05 or IBC since both of these yield identical results. Two levels of shaking are identified as follows: Maximum Considered Earthquake (MCE) Ground Motion MCE ground motions have a 2 percent probability of exceedance within a 50-year period (2475-year return period) with deterministic limits. These ground motions may be read from the published maps in ASCE 7-05 or IBC adjusted for site class. These ground motions may also be obtained using a ground motion calculator that is available at the USGS web site (http://earthquake.usgs.gov/research/hazmaps/design/). A site-specific MCE may be developed in accordance with Chapter 21 of ASCE 7-05 including the 80% limits. Design Earthquake (DE) Ground Motion DE ground motions are 2/3 of the MCE motions as defined above adjusted for Site Class. Commission Staff Guidance A-9 February 2017 ATTACHMENT 4 – SAMPLE CATEGORIZATION OF LNG STRUCTURES, COMPONENTS, AND SYSTEMS 1. Seismic Categorization For purposes of design, all structures, components and systems important to normal operation of the LNG project operations should be classified into one of the three Seismic Categories that are defined below. 1.1 Seismic Category I NBSIR 84-2833 defines Category I as all structures, components, and systems which perform a vital safety related function such as containment of LNG and fire control. Title 49 CFR Part 193 incorporates NFPA 59A 2001 edition with the exception of NFPA 59A 2006 edition for seismic design of field fabricated LNG storage tanks. Section 4.1.3.3 of NFPA 59A (2001) and Section 7.2.2.5 of NFPA 59A (2006) indicate the following structures should be designed to withstand an OBE and SSE: (1) LNG storage containers and their impounding systems; (2) System components required to isolate the LNG container and maintain it in a safe shutdown condition; and (3) Structures and systems, including fire protection systems, the failure of which could affect the integrity of (1) or (2) above. This would include: LNG storage tanks, foundations, and containment dikes Emergency Power Generator(s) and Fuel Supply Emergency Lighting Fire protection systems: Sprinkler Systems Clean Agent Systems Fixed Dry Chemical Units Expansion Foam Units Fire Water Piping Fire Water Intakes Fire Water Tanks Fire Water Pump Structure Fire Water Pumps Fire Hydrants Fire Water velocity cap Interconnecting wiring Hazard detection systems: Low Temperature Detectors Flammable/Combustible Gas Detectors Oxygen Deficiency Detectors Toxic Gas Detectors Heat Detectors Commission Staff Guidance A-10 Februrary 2017 Fire Detectors Smoke Detectors Fire Alarm Boxes Hazard Detection Panels in control room Interconnecting wiring Radio Communications System All permanent mounted wireless radios Shutdown Systems: Emergency Shutdown Valves Safety Instrumented Systems Related SIS Panels Interconnecting wiring Uninterruptible Power System (U.P.S.) Batteries (in rack) Battery Charger U.P.S. Inverter Vent and relief system All liquid and vapor relief valves in natural gas service Vent and Flare Stacks 1.2 Seismic Category II NBSIR 84-2833 defines Category II as all structures, components, and systems other than those in Category I, which are required to maintain safe plant operation. This would include: LNG sendout system controls Liquefaction trains Vaporizers Fuel gas system for fired equipment Instrumentation Interconnecting piping systems Metering system Odorizing system Hazardous Liquid pumps Trim heater Vapor absorber LNG unloading and transfer system controls Instrumentation LNG recirculation system Offshore piping from dock to abutment Onshore piping systems from abutment to storage tanks Unloading and Loading arms Control Building Electrical distribution systems fire station/warehouse Commission Staff Guidance A-11 February 2017 Instrument & utility air system After Filter Air Receiver Compressors Controls Dryer Instrumentation Piping systems Main control panel and components Marine trestle and dock (includes structures such as unloading and loading platform, service platform, trestle, dock operator's building and control tower on dock) Nitrogen systems Power generation system controls Fuel gas heater Fuel gas system Instrumentation Power generation building Standby power generators Seawater supply and return system controls instrumentation Piping to vaporizers Seawater pumps Seawater return line screening equipment Standby plant lighting Substation buildings Vapor compression system Compressor suction drum controls instrumentation Interconnecting piping systems Unloading compressors 1.3 Seismic Category III NBSIR 84-2833 defines Category III as facilities which are essential operational support facilities not required for operation, shutdown, or maintenance of a safe shutdown condition. This would include all other facilities not in Category I or II, including: Administration Building Bunker Fuel System Diesel Fuel System except as needed for Category I or II equipment Dock Service Equipment Incoming Electrical Power Systems including switchyard normal plant lighting system Waste Treatment Building Commission Staff Guidance A-12 February 2017 2. Supporting Elements and Enclosures A structure, component, or system of a given Seismic Category may be supported or enclosed by a structure classified in a different category, provided it is demonstrated that the supported item can maintain its functional requirements specified by its Seismic Category. 3. Seismic Performance Goals by Category The following are the seismic performance goals for each category: 3.1 Seismic Category I At a minimum and in accordance with 49 CFR Part 193 and incorporated NFPA 59A, these structures, components and systems should be designed to remain operable during and after the OBE design ground motion (NFPA 59A, 2006 edition, Section 7.2.2.5 A). The design should provide for no loss of containment capability of the primary container and it should be possible to isolate and maintain the LNG container during and after the SSE design ground motion (NFPA 59A, 2006 edition, Section 7.2.2.6 D). At a minimum and in accordance with 49 CFR Part 193 and incorporated NFPA 59A, the impounding system should be designed to withstand an SSE while empty and an OBE while holding maximum operating volume of the LNG container (NFPA 59A, [2001 edition], Section 4.1.3.2 and NFPA 59A, [2006 edition], Section 7.2.2.6). After an OBE or SSE, there should be no loss of containment capability (NFPA 59A, 2001 edition, Section 4.1.3.4 and NFPA 59A, 2006 edition, Section 7.2.2.7). 3.2 Seismic Category II At a minimum and in accordance with 49 CFR Part 193 and incorporated NFPA 59A, piping systems and components for flammable liquids and gases and service temperatures below −20 °F should be designed to withstand an OBE (NFPA 59A, [2001 edition], Section 6.1.1 and 6.1.2). These systems and components should be designed to meet the seismic performance goals of the IBC for “hazardous” facilities. For hazardous facilities, it is expected that the damage from the DE ground motion defined in the incorporated ASCE 7 would not be so severe as to preclude continued occupancy and function of the project facilities. 3.3 Seismic Category III These structures, components and systems should be designed to meet the seismic performance goals of the IBC and ASCE 7 for normal “non-essential” facilities. For normal facilities, it is expected that structures designed and constructed according to ASCE 7, would sustain repairable damage when subjected to DE ground motions although it may not be economical to do so. Commission Staff Guidance A-13 February 2017 ATTACHMENT 5 – SAMPLE SEISMIC DESIGN INFORMATION CONTENTS 1. General A seismic design criteria document (also called design basis document) that specifies in detail the seismic criteria to be used in the design of Category I, II and III structures, components and systems should be provided. It should include all seismic design coefficients and inelastic reduction factors, load combinations and allowable stress/strength factors and φ-factors permitted for each load combination. The additional information requested in this Attachment should be included in the document. 2. Seismic Design 2.1 Design Response Spectra Design response spectra for the OBE, SSE, MCE, and DE should be provided. The response spectra applied at the finished grade in the free field or at the various foundation locations of Category I structures should be provided. The ASCE 7-05 seismic design parameters that should be used at the various locations of Category II and III structures should also be provided. 2.2 Design Time History For the time history analyses, the response spectra derived from the actual or synthetic earthquake time-motion records should be provided. A comparison of the response spectra obtained in the free field at the finished grade level and the foundation level (obtained from an appropriate time history at the base of the soil/structure interaction system) with the design response spectra should be submitted for each of the damping values to be used in the design of structures, systems, and components. Alternatively, if the design response spectra for the OBE and SSE are applied at the foundation levels of Category I structures in the free field, a comparison of the free-field response spectra at the foundation level (derived from an actual or synthetic time history) with the design response spectra should be provided for each of the damping values to be used in the design. The period intervals at which the spectral values were calculated should be identified. 2.3 Critical Damping Values The specific percentage of critical damping values used for Category I structures, systems, and components and soil should be provided for both the OBE and SSE (e.g., damping values for the type of construction or fabrication such as prestressed concrete and welded pipe). The basis for any proposed damping values should be included. Commission Staff Guidance A-14 Februrary 2017 2.4 Supporting Media for Category I Structures A description of the supporting media for each Category I structure should be provided. Include in this description foundation embedment depth, depth of soil over bedrock, soil layering characteristics, width of the structural foundation, total structural height, and soil properties such as shear wave velocity, shear modulus, and density. This information is needed to permit evaluation of the suitability of using either a finite difference or lumped spring approach for soil/structure interaction analysis, if necessary. 3. Seismic System Analysis for Category I Structures 3.1 Seismic Analysis Methods The applicable methods of seismic analysis (e.g., modal analysis response spectra, modal analysis time history, equivalent static load) should be identified and described. Descriptions (sketches) of typical mathematical models used to determine the response should be provided. Indicate how the dynamic system analysis method includes in the model consideration of foundation torsion, rocking, and translation. The method chosen for selection of significant modes and adequate number of masses or degrees of freedom should be specified. The manner in which consideration is given in the seismic dynamic analysis to maximum relative displacement among supports should be indicated. In addition, other significant effects that are accounted for in the seismic analysis (e.g., hydrodynamic effects and nonlinear response) should be indicated. If tests or empirical methods are used in lieu of analysis, the testing procedure, load levels, and acceptance bases should also be provided. 3.2 Natural Frequencies and Response Modes The significant natural frequencies and response modes determined by seismic system analyses should be provided for Category I structures. In addition, the response spectra at critical Category I elevations and points of support should be specified. 3.3 Procedure Used for Modeling The criteria and procedures used for modeling in the seismic system analyses should be provided. Include the criteria and bases used to determine whether a component or structure should be analyzed as part of a system analysis or independently as a subsystem. Commission Staff Guidance A-15 February 2017 3.4 Soil/Structure Interaction As applicable, the methods of soil/structure interaction analysis used in the seismic system analysis and their bases should be provided. The following information should be included: a) b) c) the extent of embedment the depth of soil over rock, and layering of the soil strata. If the finite difference approach is used, the criteria for determining the location of the bottom boundary and side boundary should be specified. The procedure by which strain dependent soil properties (e.g., damping and shear modulus) are incorporated in the analysis should also be specified. The material given in Section 2.4 of this Attachment may be referenced in this section. If lumped spring methods are used, the parameters used in the analysis should be discussed. Describe the procedures by which strain-dependent soil properties, layering, and variation of soil properties are incorporated into the analysis. The suitability of a lumped spring method used for the particular site conditions should also be discussed. Any other methods used for soil/structure interaction analysis or the basis for not using soil/structure interaction analysis should be provided. The procedures used to consider effects of adjacent structures on structural response in soil/structure interaction analysis should be provided. 3.5 Development of Floor Response Spectra The procedures for developing floor response spectra considering the three components of earthquake motion should be described. If a modal response spectrum method of analysis is used to develop floor response spectra, the basis for its conservatism and equivalence to a time history method should be provided. 3.6 Three Components of Earthquake Motion Identify the procedures for considering the three components of earthquake motion in determining the seismic response of structures, systems, and components. 3.7 Combination of Modal Responses When a response spectra method is used, a description of the procedure for combining modal responses (shears, moments, stresses, deflections, and accelerations) should be provided. Commission Staff Guidance A-16 February 2017 3.8 Interaction of Non-Category I Structures with Category I Structures Provide the design criteria used to account for the seismic motion of non-Category I structures or portions thereof in the seismic design of Category I structures or portions thereof. In addition, describe the design criteria that will be applied to ensure protection of Category I structures from the structural failure of non-Category I structures due to seismic effects. 3.9 Effects of Parameter Variations on Floor Response Spectra The procedures that will be used to consider the effects of expected variations of structural properties, damping, soil properties, and soil/structure interaction on floor response spectra (e.g., peak width and period coordinates) and time histories should be described. 3.10 Use of Constant Vertical Static Factors Where applicable, identify and justify the application of constant static factors as vertical response loads for the seismic design of Category I structures, systems, and components in lieu of a vertical seismic system dynamic analysis method. 3.11 Method Used to Account for Torsional Effects The method used to consider the torsional effects in the seismic analysis of the Category I structures should be described. Where applicable, discuss and justify the use of static factors or any other approximate method in lieu of a combined vertical, horizontal, and torsional system dynamic analysis to account for torsional accelerations in the seismic design of Category I structures. 3.12 Comparison of Responses Where both modal response and time history methods are applied, the responses obtained from both methods at selected points in major Category I structures should be provided, together with a discussion of the comparative responses. 3.13 Determination of Category I Structure Overturning Moments A description of the dynamic methods and procedures used to determine Category I structure overturning moments should be provided. 3.14 Analysis Procedure for Damping The analysis procedure used to account for the damping in different elements of the model of a coupled system should be described. Commission Staff Guidance A-17 February 2017 4. Design and Analysis Procedures The procedures that will be used in the design and analysis of all internal Category I structures should be described, including the assumptions made and the identification of boundary conditions. The expected behavior under load and the mechanisms for load transfer to these structures and then to the foundations should be provided. Computer programs that are used should be referenced to permit identification with published programs. Proprietary computer programs should be described to the maximum extent practical to establish the applicability of the program and the measures taken to validate the programs with solutions derived from other acceptable programs or with solutions of classical problems. 5. Structural Acceptance Criteria The acceptance criteria relating stresses, strains, gross deformations, and other parameters that identify quantitatively the margins of safety should be specified. The information provided should address the containment as an entire structure, and it should also address the margins of safety related to the major important local areas of the Category I structures important to the safety function. For each applicable loading condition listed below, the allowable limits should be provided, as appropriate for stresses, strains, deformation, and factors of safety against structural failure. The extent of compliance with the various applicable codes should be presented. The load conditions to consider include but are not limited to: a) Loads encountered during seasonal plant startup, including dead loads, live loads, thermal loads due to operating temperature, and hydrostatic loads. b) Loads that would be sustained in the event of severe environmental conditions, including those induced by the OBE. c) Loads that would be sustained in the event of extreme environmental conditions, including those that would be induced by the SSE. Commission Staff Guidance A-18 February 2017 ATTACHMENT 6 – SAMPLE GEOTECHNICAL REPORT CONTENTS 1. Contents of Report 1.1 Plant Description The general arrangement of major structures and equipment should be indicated by the use of plan and elevation drawings in sufficient number and detail to provide a reasonable understanding of the general layout of the plant. The sizes and loading of the critical structures should be provided. 1.2 Summary of Site Investigation and Project Status The current status of the site evaluation study should be documented and additional planned investigations should also be described. The current design status of the project should include whether the phase of design, such as conceptual design or final design, and should identify what level of computations have been performed to arrive at the current design stage and what studies, data gathering, calculations and documentation remains to be done. Such items as unusual site characteristics, solutions to particularly difficult engineering problems, and significant extrapolation in technology represented by the design should be highlighted. 2. Exploration Discuss the type, quantity, extent, and purpose of all explorations. Provide plot plans that graphically show the location of all site explorations such as borings, trenches, borrow pits, seismic lines, cone penetration tests, piezometers, wells, geologic profiles, and the limits of required construction excavations. The locations of the Seismic Category I, II, and III facilities should be superimposed on the plot plan. Also, furnish selected geologic cross-sections and profiles that indicate the location of borings and other site exploration features, groundwater elevations, and final foundation grades. The location of safetyrelated foundations should be superimposed on these sections and profiles. Logs of all borings and test pits should be provided. Furnish logs and maps of exploratory trenches and geologic maps and photographs of the excavations for the facilities of the LNG plant. 2.1 Logs of Borings/Cone Penetration Tests (CPT) Present the logs of borings, CPTs, test pits and trenches that were completed for the evaluation of foundations, slopes, and borrow materials to be used for slopes. Logs should indicate elevations, depths, soil and rock classification information, groundwater levels, exploration and sampling methods, recovery, rock quality designation Commission Staff Guidance A-19 Februrary 2017 (RQD), and blow counts from standard penetration tests. Provide specific details of how the Standard Penetration Test was performed. Discuss drilling and sampling procedures and indicate where samples were taken on the logs. In areas where liquefaction potential is high, borings should be performed by rotary drilling method in accordance with the requirements for obtaining standard penetration blow count N-values outlined by Youd, et al., 2001 (Ref.11) and Martin & Lew, 1999 (Ref. 21). Cone penetration tests should be performed to define the soil profile accurately and to use both N-values and CPT data for evaluation of liquefaction potential and settlements due to liquefaction. Typically a minimum of five (5) explorations (borings / CPTs) should be performed under each LNG tank and the depth of the exploration should be 20 feet deeper than deepest anticipated foundations. The borings and CPTs should also be sufficiently deep to sample the zone of influence for settlements and liquefaction potential (at least 100 feet if bedrock is not encountered). For large tanks more than 5 explorations may be necessary to adequately characterize the sub-surface conditions. All local, state, and Federal environmental regulations regarding obtaining permits for the geotechnical borings and wells, clearing of underground utilities, disposal of cuttings and drilling mud should be followed. Where groundwater is present at depths which could affect the foundations or liquefaction potential, selected borings should be converted into wells to define stabilized groundwater. Historic high groundwater should be determined from published literature for liquefaction evaluation. 2.2 Geophysical Surveys Results of compressional and shear wave velocity surveys performed to evaluate the occurrence and characteristics of the foundation soils and rocks should be provided in tables and profiles. Discuss other geophysical methods used to define foundation conditions. The depth of explorations for performing downhole or cross-hole shear wave velocity measurements should be at least 100 feet. 3. Laboratory Testing 3.1 General Laboratory testing should include the following tests. Actual tests should depend on the type of soil encountered. All testing should be performed in accordance with the most recent ASTM standards (Ref. 30), where applicable. Adequate number and type of tests should be performed on representative samples in order to characterize the subsurface soils and to develop representative strength, compressibility, and corrosivity properties of the soils as indicated in this specification. Commission Staff Guidance A-20 February 2017 3.2 Identification Tests Moisture Content (ASTM D2216) Unit Weight Specific Gravity (ASTM D854) Sieve Analysis (AS TM D422) Atterberg Limits (ASTM D4318) 3.3 Engineering Property Characterization Tests Compaction (ASTM D1557, or D698) California Bearing Ratio (ASTM D1883) R-value (ASTM D2844) Unconfined Compression Test of Cohesive Soils (ASTM D2166) Unconsolidated-Undrained Triaxial Compression Test (ASTM D2850) Consolidation Test with time readings (ASTM D2435) Swell Test (ASTM D4546) Expansion Index Test (ASTM D4829) Collapse test (ASTM D 5333) Consolidated-Drained Triaxial Compression Test Consolidated-Undrained Triaxial Compression Test with Pore Pressure Measurements (ASTM D4767) Direct Shear Test (ASTM D3080) Soil Permeability (ASTM D5084 and D2434) Corrosivity (Chloride, Sulfate, Electrical Resistivity) pH Value for Soil Corrosivity (ASTM G51) 4. Geologic and Seismic Setting This section of the report should discuss general geologic and seismic information relevant to foundation design such as geologic setting, regional geology, site geology, faulting. Specific geologic features that may affect site stability and foundation design such as the following should be discussed. 1) Areas of actual or potential surface or subsurface subsidence, uplift, or collapse and the causes of these conditions; 2) Previous loading history of the foundation materials, i.e., history of deposition and erosion, groundwater levels, and glacial or other preloading influences on the soil; 3) Rock bedding and jointing pattern and distribution, depth of weathering, zones of alteration or irregular weathering, and zones of structural weakness composed of crushed or disturbed materials such as slickensides, shears, Commission Staff Guidance A-21 February 2017 joints, fractures, faults, folds, or a combination of these features. Especially note seams and lenses of weak materials such as clays and weathered shales; 4) Unrelieved residual stresses in bedrock; 5) Rocks or soils that may be hazardous, or may become hazardous, to the plant because of their lack of consolidation or induration, inhomogeneity, variability, high water content, solubility, or undesirable response to natural or induced site conditions; and 6) Requirements of the detailed site geology, seismicity, and faulting as they relate to site Ground Motion Study are provided in Attachment 3. 5. Site Conditions 5.1 Surface Conditions The surface conditions at the site should be described. Presence of any unusual site features should be identified. Site topography including existing contours should be provided. Site drainage should be discussed. Include a current aerial photograph of the site, and if available, provide historic aerial photographs of the site that demonstrate any past conditions or uses of the site relevant to the proposed project design. 5.2 Subsurface Soil Conditions Site subsurface conditions should be described in detail. Generalized subsurface profiles including various soil strata should be presented in various cross-sections across the site specifically through the LNG tank area. Soil properties assigned to each strata should be tabulated for bearing capacity, settlement, pile capacity, and slope stability calculations. The basis for selected soil parameters (laboratory testing, blow counts, CPT data, experience) should be stated. A discussion on the selection of engineering parameters is required. When published correlation relationships are used to determine the engineering parameters, references should be given. A conversion ratio between blow counts from penetration tests not performed per ASTM D 1586 (standard penetration test) should be discussed and provided, if applicable. This includes nonstandard samplers, nonstandard hammer energy delivery systems, and considerations of hammer efficiency. 5.3 Groundwater Conditions The analysis of groundwater at the site should include the following points: 1) A discussion of groundwater conditions relative to the stability of Seismic Category I safety-related facilities; Commission Staff Guidance A-22 February 2017 6. 2) A discussion of design criteria for the control of groundwater levels or collection and control of seepage; 3) Requirements for dewatering during construction and a discussion of how dewatering will be accomplished; 4) Records of field and laboratory permeability tests; 5) History of groundwater fluctuations, including those due to flooding and recommended design groundwater level for the plant and for liquefaction analyses; 6) Information related to the periodic monitoring of local wells and piezometers; 7) Direction of groundwater flow, gradients, and velocities; and 8) Discussion of or reference to the groundwater monitoring program during the life of the plant to assess the potential for subsidence. Seismic Hazards Seismic hazards include fault rupture, ground motions, liquefaction, lateral spreading, seismic slope stability, seismic compaction, tsunamis and seiche. Details of fault rupture, ground motions, tsunamis, and seiche, should be provided in the site-specific seismic ground motion report. These items should be summarized in the geotechnical report. Liquefaction potential, liquefaction-related settlement, potential for sand boils and other surface manifestation of liquefaction, lateral spreading, seismic slope stability, seismic compaction, and need for ground improvement to mitigate these hazards, if present, should be addressed in detail in the geotechnical report. 6.1 Fault Rupture Distances from significant faults should be identified and potential for fault rupture should be discussed in the geotechnical report. The site-specific ground motion report should be referenced for more details. 6.2 Site Class Site Class should be identified per ASCE 7 or IBC. Commission Staff Guidance A-23 February 2017 6.3 Ground Motions A seismic hazard study should be performed to establish ground motions for the site for four levels of shaking, the OBE, the SSE, the MCE, and the DE. Details of the requirements for the determination of the ground motions are presented in Attachment 3. 6.4 Seismic Slope Stability The LNG tanks should have a minimum calculated static factor of safety of 1.5 for slope stability with respect to any nearby slopes of berthing slips or other existing or future slopes. Pseudo-static screening analyses may be used to determine seismic slope stability, provided the soils are not liquefiable or expected to lose shear strength significantly during deformation. Detailed deformation analyses should be performed where pseudo-static screening analyses indicate that factor of safety is less than 1.0. 6.5 Liquefaction Evaluation When the field investigation reveals that potentially liquefiable soils and conditions including lateral spreading exist and they pose a hazard to the project site, a quantitative geotechnical evaluation of such a potential should be conducted. In-situ testing, soil sampling, and laboratory testing on potentially liquefiable soils must be properly planned and conducted to obtain reliable data for the geotechnical evaluation. If liquefaction is likely to occur, its consequences should be assessed, its impact on foundations should be addressed, and mitigation measures should be specified. Elevations of the liquefiable layer(s) should be presented in the Foundation Report. Assumptions, analytical or empirical methods used, and conclusions for liquefaction evaluation should be stated with relevant data and analysis attached in Appendices. Potential for surface manifestation of liquefaction in form of sand boils and surface displacement should be identified. Total and differential settlements due to liquefaction should be estimated and provided. If liquefaction settlements are beyond the tolerance of the proposed structures, remedial measures to mitigate liquefaction potential should be provided. All liquefaction evaluations should be performed in accordance with latest published guidelines (e.g., Youd, T. L., et. al., 2001 (Ref. 11), and Martin, G. R., and Lew, M., 1999 (Ref. 21)). 6.6 Lateral Spreading If liquefaction potential exists, potential for lateral spreading should be evaluated and calculations of lateral movements made by Newmark simplified approach (Makdisi, F. I., and Seed H.B, 1978 and by Bartlett & Youd (1995)) method. The effects of calculated Commission Staff Guidance A-24 February 2017 lateral spreading movements on the stability of the plant structures should be evaluated and remedial measures proposed, if the movements exceed the design criteria. 6.7 Subsidence Subsidence due to earthquakes, groundwater or oil withdrawal is a significant geologic/seismic risk. Areal movements due to these effects should be evaluated and their effects on the differential settlement of the plant structures, or general effects on the site (e.g., should be evaluated. 7. Poor Soil Conditions Presence of poor or unusual soil conditions, such as highly compressible or highly expansive soils, corrosive soils, collapsible soils, erodible soils, liquefaction-susceptible soils, frost heave susceptible soils, frozen soils, or sanitary landfill etc. should be identified and remedial measures including ground improvement methods should be recommended, if such soils are present. 8. Foundation Recommendations Complete, concise, and definite foundation recommendations should be provided for various categories (Seismic Categories I, II, and II) structures. The selection of a specific foundation type depends on factors such as surface and subsurface conditions at the site, geotechnical capacity, dynamic and static demands, environmental concerns, economics, and construction issues. The recommended foundation type should be costeffective, performance-proven, and constructible. Alternative foundation types should be discussed and the reasons why those alternatives are not recommended should be stated. Solutions to potential construction problems should be discussed. A sufficient and adequate geotechnical evaluation for the recommended foundation should be performed. In general, any foundation design should meet four essential requirements: (1) adequate geotechnical capacity of soil/rock surrounding the foundation with a specified safety against ultimate failure; (2) acceptable total or differential settlements under static and dynamic loads; (3) adequate overall stability of slopes in the vicinity of a footing/mat; and (4) constructability with solutions for anticipated problems. 8.1 LNG Tanks 8.1.1 Tank Loading and Settlement Criteria For LNG tanks the loading from the tanks and criteria for adequate factor of safety against bearing capacity failure and settlement should be discussed. Commission Staff Guidance A-25 February 2017 8.1.2 Shallow Foundations LNG tanks supported on shallow foundations are generally supported on a mat. Ultimate bearing capacity of the mat should be calculated and should provide a minimum factor of safety of 3.0 for the applied tank loading during hydrotest. Effects of adjacent slopes, if present, on the bearing capacity should be evaluated. The reduction of the factor of safety due to liquefaction or other effects should be evaluated and addressed. Total and differential settlement of the mat foundation should be calculated under various applied loads such as during hydrotest, operation, and seismic conditions including liquefaction, if present. Recommendations for monitoring of the settlements during hydrotest should be provided. Lateral stability of the tanks under seismic and wind loads should be calculated and it should be demonstrated that an adequate factor of safety is present. If lateral spreading is a seismic issue, lateral stability of the tanks due to lateral spreading movements should be demonstrated. Overall lateral stability of the foundation for static and seismic conditions including any adjacent slopes, if present, should be evaluated. 8.1.3 Deep Foundations For Deep Foundations, the report should address, but not be limited to, the following when applicable: 1. Pile Types, Axial Compressive and Tensile, and Settlement a. Recommended pile types should be identified as driven Precast Prestressed Reinforced Concrete piles, Steel H or Pipe piles, cast-in drilled hole (CIDH) piles, Auger Cast Piles or others. Alternatives should be discussed and the reasons why those alternatives are not recommended should be stated. b. Whether compressive and/or tensional geotechnical capacities are derived from skin friction, end bearing, or a combination of both for a single or group pile(s) should be discussed. c. Pile design tip elevations (DTE) may be controlled by demands from compression, tension, lateral loads, scour potential, or liquefaction. The pile Specified Tip Elevation (STE) equals the lowest pile DTE as estimated above. d. The portion of the axial capacities for pile foundations in and above liquefiable soils should be neglected. e. Negative skin friction (down-drag) on pile shaft due to settlements of new fills or compressible soil layers should be eliminated by use of Commission Staff Guidance A-26 February 2017 preloading/surcharge with or without wick drains prior to pile installation or piles should be designed for downdrag associated with these settlements. Downdrag from settlements due to liquefaction should also be calculated. 2. 3. f. When a situation such as liquefaction potential exists that does not allow for mitigation and elimination of negative skin friction, the magnitude of the downdrag forces should be estimated and provided to the structural designer for him/her to incorporate those forces into Design Loading. The magnitude of estimated settlement should also be provided to the structural engineer. g. Lateral pile capacity should be estimated using the p-y method or equivalent. Group reduction factors depending on soil types, pile spacing, and anticipated lateral movement should be considered when evaluating lateral capacity for a group of piles. Formulation of p-y curves for liquefiable soils and weak rocks, effects of pile diameters on lateral soil modulus and soil strain parameters, evaluation of liquefaction or lateral spreading forces imposed on pile, and reduced moment of inertia for concrete piles should be addressed. h. The single and/or group pile settlement should not exceed the tolerable amount as established by the structural designer. Special Considerations for Cast-In Drilled Hole (CIDH) Piles a. When battered piles are required, CIDH piles should not be used because of the increased risk of caving and the difficulty of placing concrete in a sloping hole. b. If pile tips are below the groundwater table or wet construction method is used, CIDH piles should be designed at a diameter equal to or greater than 24 in. c. When CIDH piles are used under water, no end bearing should be used unless positive measures to verify the end bearing are recommended. Installation of Driven Piles Pile drivability should be evaluated by wave equation analyses. An indicator pile program including pile driving analyzer (PDA) measurements should be planned to verify the pile drivability and the estimated capacity. A load test program should be developed to verify the capacity of selected piles both under axial and lateral conditions. Commission Staff Guidance A-27 February 2017 4. Installation of Drilled or Auger Cast Piles Gamma-Gamma testing should be performed on CIDH piles installed underwater by the wet method to verify the integrity of the piles. An axial and lateral load test program should be implemented to verify the axial and lateral capacity of the piles. Pile Load Test can be used for determining pile capacity at failure (ultimate capacity), and for establishing field acceptance criteria. A load test remains the definitive way to determine whether the professional's estimate of capacity and specified tip elevations is appropriate in design and to determine whether the production piles meet the specifications during construction. The equipment and procedures for conducting pile axial compressive load tests can be found in literature such as ASTM D 1143. Static axial tension tests should be performed per ASTM D 3689. Static lateral load tests should be performed per ASTM D 3966. 8.1.4 Ground Improvement Ground Improvement should discuss the need for ground improvement, type(s) of ground improvement, surcharge, stone columns, vibroflotation, soil-cement columns, dynamic compaction, and other types of ground improvement. The discussion should address the effects of ground improvements on soil properties and seismic ground motions. 9. Corrosion An assessment of the corrosiveness of a site based on the review of relevant corrosion test data should be made. Corrosion test data should include pH, electrical resistivity, stray electrical ground currents, water soluble sulfates and chlorides. Sufficient information regarding the number and location of soil borings for corrosion testing should be included to allow a thorough review of the recommendations. Recommendations regarding concrete and metals in contact with onsite soils should be provided. 10. Pavement Design Recommendations for design of asphalt and Portland cement concrete pavements for the plant area should be provided based on the onsite soil R-value or CBR. Commission Staff Guidance A-28 February 2017 ATTACHMENT 7 – SAMPLE FOUNDATION DESIGN CRITERIA CONTENTS 1. General A foundation design criteria document should be provided that states how Seismic Category I, II and III structures will be designed. This document will be consistent with recommendations provided in the geotechnical report. In addition, the foundation criteria document should include the items requested in this attachment. 2. Foundation Design All Seismic Category I and II structures constructed of materials other than soil for the purpose of transferring loads and forces to the basic supporting media should be addressed in more detail. In particular, the information described below should be provided. 2.1 Description of the Foundations This section should provide descriptive information, including plan and section views of each foundation, to define the primary structural aspects and elements relied upon to perform the foundation function. The relationship between adjacent foundations, including any separation provided and the reasons for such separation, should be described. In particular, the type of foundation and its structural characteristics should be discussed. The general arrangement of each foundation should be provided with emphasis on the methods of transferring horizontal shears, such as those seismically induced, to the foundation media. If shear keys are used for such purposes, the general arrangement of the keys should be included. If waterproofing membranes are used, their effect on the capability of the foundation to transfer shears should be discussed. Information should be provided to adequately describe other types of foundation structures such as pile foundations, caisson foundations, retaining walls, abutments, and rock and soil anchorage systems. 2.2 Applicable Codes, Standards, and Specifications This section should provide information on the applicable codes, standards and specifications used in the design foundations of all Seismic Category I, II, and III structures. 2.3 Loads and Load Combinations This section should provide information, as applicable, on the load combinations that should be used in conjunction with the foundation recommendations for all Category I, II, and III structures. Commission Staff Guidance A-29 Februrary 2017 2.4 Design and Analysis Procedures This section should provide information, as applicable, on the foundations of all Category I , II, and III structures. In particular, the assumptions made on boundary conditions and the methods by which lateral loads and forces and overturning moments, thereof, are transmitted from the structure to the foundation media should be discussed, along with the methods by which the effects of settlement are taken into consideration. 2.5 Structural Acceptance Criteria This section should provide information applicable to foundations of all Category I, II, and III structures. In particular, the design limits imposed on the various parameters that serve to define the structural stability of each structure and its foundations should be indicated, including differential settlements and factors of safety against overturning and sliding. 2.6 Materials, Quality Control, and Special Construction Techniques This section should provide materials, quality control, and special construction techniques for the foundations of all Category I, II, and III structures. Commission Staff Guidance A-30 February 2017