Spreadsheet

grid1924a.xls

7 CFR 1924-A,

Spreadsheet

OMB: 0575-0042

Document [xlsx]
Download: xlsx | pdf
CFR 1924-A, PLANNING AND PERFORMING CONSTRUCTION AND OTHER DEVELOPMENT April 2006




























Section of Title Form No. Estimated Reports Total Est. No. Estimated Wage Total
Regulations
(if any) No. of Filed Annual Man-hrs/ Total Class Cost



Respondents Annually Responses Response Manhours
(H) x (I)





(D) x (E)
(F) x (G)

(A) (B) (C) (D) (E) (F) (G) (H) (I) (J)

REPORTING REQUIREMENTS - FORMS







1924.5(b) Development Plan 1924-1 7,500 on 7,500 0.25 1,875 $10 $18,750
1924.5(g)(1)


occasion




1924.5(f)(2)(iv) Description of 1924-2 4,910 on 4,910 0.25 1,228 $10 $12,280

Materials

occasion




1924.5(f)(2)(iv) Service Building 1924-3 2,500 on 2,500 0.25 625 $10 $6,250

Specifications

occasion




1924.6(a)(10)(v) Invitation for Bid 1924-5 4,500 on 4,500 0.25 1,125 $10 $11,250

(Construction Contract)

occasion




1924.10(a)(4) Contract Change Order 1924-7 8,500 on 8,500 0.25 2,125 $10 $21,250




occasion




1924.6(a)(1) Construction Contract 1924-6 16,500 on 16,500 0.25 4,125 $10 $41,250




occasion




1924.6(a)(12)(vi)(B) Certificate of 1924-9 14,000 on 14,000 0.25 3,500 $10 $35,000

Contractor's Release

occasion




1924.6(a)(12)(vi)(B) Release by Claimants 1924-10 14,000 on 14,000 0.5 7,000 $10 $70,000




occasion




1924.6(b)(3)(i) Statement of Labor 1924-11 370 on 370 0.5 185 $10 $1,850

Performed

occasion




1924.6(a)(12)(v)(A) Inspection Report 1924-12 19,300 on 77,200 0.25 19,300 $10 $193,000




occasion




1924.6(e)(1)(iv) Estimate and Certificate 1924-13 760 on 1,520 2 3,040 $20 $60,800

of Actual Cost

occasion




1924.13(e)(1)(vi) Partial Payment 1924-18 15,000 on 45,000 0.5 22,500 $10 $225,000
1924.13(e)(1)(ix) Estimate

occasion




1924.6(a)(1) Builder's Warranty 1924-19 13,880 on 13,880 0.25 3,470 $10 $34,700




occasion
























Section of Title Form No. Estimated Reports Total Est. No. Estimated Wage Total
Regulations
(if any) No. of Filed Annual Man-hrs/ Total Class Cost



Respondents Annually Responses Response Manhours
(H) x (I)





(D) x (E)
(F) x (G)

(A) (B) (C) (D) (E) (F) (G) (H) (I) (J)

REPORTING REQUIREMENTS - FORMS







1924.13(e)(1)(ii) Monthly Employment CC-257 14,000 on 42,000 0.5 21,000 $15 $315,000
XVII Utilization Report

occasion




1924.5(f)(a)(iii)(F) Plan Certification 1924-25 5,150 on 5,150 0.167 860 $40 $34,400




occasion





REPORTING REQUIREMENTS - NON FORMS







1924.5(d)(2) Drawings and
9,600 on 9,600 0.5 4,800 $10 $48,000
1924.5(e)(1) Specifications







1924.5(f)(1)(ii)


occasion




1924.5(d)(2) Cost Estimate
15,000 on 15,000 0.5 7,500 $10 $75,000
1924.13(e)(1)(iv)


occasion




1924.5(f)(1)(ii) Narrative Description
4,600 on 4,600 0.5 2,300 $10 $23,000

of Work Items

occasion




1924.5(f)(1)(iii) Certification of Drawings
9,600 on 9,600 0.25 2,400 $10 $24,000

and Specifications

occasion




1924.5(g)(3) Written Consent of Prior
615 on 615 0.25 154 $10 $1,540

Lien Holders

occasion




1924.5(i) Agreement to Pay with
250 on 250 0.25 63 $10 $630

Personal Funds

occasion




1924.6(a)(1),(2)&(7) Agreement between Borrower
210 on 210 0.25 53 $10 $530

and Builder

occasion




1924.6(a)(3)(i)(C) Request for Surety Bond
870 on 870 0.25 218 $10 $2,180




occasion




1924.6(a)(3)(ii) Payment Bond
870 on 870 0.5 435 $20 $8,700
Exhibit F


occasion




1924.6(a)(3)(ii) Performance Bond
870 on 870 0.5 435 $20 $8,700
Exhibit G


occasion




1924.6(a)(3)(iii)(A) Letter of Credit
40 on 40 1 40 $35 $1,400




occasion














Section of Title Form No. Estimated Reports Total Est. No. Estimated Wage Total
Regulations
(if any) No. of Filed Annual Man-hrs/ Total Class Cost



Respondents Annually Responses Response Manhours
(H) x (I)





(D) x (E)
(F) x (G)

(A) (B) (C) (D) (E) (F) (G) (H) (I) (J)

REPORTING REQUIREMENTS - NON FORMS







1924.6(a)(3)(iii)&(iv) Documents for Exception
500 on 500 0.5 250 $10 $2,500
1924.6(e)(1)(iii)&(B) to Surety Requirements

occasion




1924.6(a)(10)(ii) Construction Contract
60 on 60 0.25 15 $10 $150

Bidding Documents

occasion




1924.6(a)(12)(iv)&(v) Application for Payment
120 on 120 0.25 30 $10 $300
1924.6(e)(2)(ix)(B)


occasion




1924.6(a)(12)(vi)(B) Notification of Delays
840 on 840 0.25 210 $20 $4,200

in Construction

occasion




1924.6(b)(1)(ii) Lump-sum Agreements for
500 on 500 0.5 250 $10 $2,500

Labor or Material

occasion




1924.8(c) Manufacturer's and
620 on 620 0.5 310 $10 $3,100
Exhibit B, atch. 5 Builder's Certification

occasion




1924.6(b)(3)(i)&(ii) Documents for 10 Year
620 on 620 0.5 310 $20 $6,200
1924.9(d) Warranty

occasion




Exhibit L








1924.9(b)(5) Complaints of
50 on 50 0.25 13 $10 $130
1924.9(b)(4) Construction Defects

occasion




1924.9(b)(7) Irrigation System
45 on 45 0.5 23 $20 $460

Inspection Report

occasion




1924.10(a)(4) Contract Change Order
370 on 740 0.25 185 $10 $1,850




occasion




1924.13(a)(4)&(5) Agreement Between
240 on 240 0.25 60 $10 $600

Borrower & Architect

occasion




1924.13(b)(2) Project Representative's
15 on 15 0.25 4 $10 $40

Resume

occasion




1924.13(b)(2)(v) Project Representative's
15 on 15 0.25 4 $10 $40

Diary

occasion




1924.13(e)(1)(v) Audit Report
120 on 120 1 120 $20 $2,400
1924.13(e)(1)(viii)


occasion














Section of Title Form No. Estimated Reports Total Est. No. Estimated Wage Total
Regulations
(if any) No. of Filed Annual Man-hrs/ Total Class Cost



Respondents Annually Responses Response Manhours
(H) x (I)





(D) x (E)
(F) x (G)

(A) (B) (C) (D) (E) (F) (G) (H) (I) (J)

REPORTING REQUIREMENTS - NON FORMS







1924.13(e)(1)(vii) Documents for Exception
60 on 60 0.25 15 $10 $150
(A)(B)&(C) to Competitive Bidding

occasion




1924.13(e)(1)(viii)(C) Documents for Exception
5 on 5 4 20 $10 $200

to Contract Method

occasion




1924.6(e)(2)(i) Owner-Builder
10 on 10 4 40 $10 $400

Construction Proposal

occasion




Exhibit B,V,D,1,2 & 3 Prerequisites for
20 on 20 0.5 10 $20 $200
Exhibit B, atch. 1 Modular/Panelized

occasion





Housing Unit Mfrs.







Exhibit B,V,E Letter of Conditions
20 on 20 0.25 5 $20 $100
Exhibit B, atch. 2


occasion




Exhibit B,V,E Approval of Modular/
80 on 80 0.25 20 $20 $400
Exhibit B, atch. 3 Panelized Housing Units

occasion




Exhibit B, V, G Evidence of a HUD
80 on 160 0.5 80 $20 $1,600
Exhibit B, atch. 4 Review Process

occasion




Exhibit B, V, G Notification of
40 on 40 0.25 10 $20 $200
Exhibit B, atch. 4 Manufacturer

occasion




Exhibit B, XI, B HUD Bulletins
40 on 40 0.25 10 $20 $200




occasion




Exhibit B, XI, C Installation
40 on 40 0.25 10 $20 $200

Instructions

occasion




Exhibit C, V, A Individual Water Sewer
500 on 500 0.5 250 $10 $2,500

System Proposal Docs.

occasion




Exhibit E, 12 Notification for an
19,300 on 57,900 0.08 4,632 $20 $92,640

Inspection

occasion
































































Section of Title Form No. Estimated Reports Total Est. No. Estimated Wage Total
Regulations
(if any) No. of Filed Annual Man-hrs/ Total Class Cost



Respondents Annually Responses Response Manhours
(H) x (I)





(D) x (E)
(F) x (G)

(A) (B) (C) (D) (E) (F) (G) (H) (I) (J)

REPORTING REQUIREMENTS - RECORDKEEPING







1924.5(f)(1)(ii) Retain copy of approved


5,150 0.08 412 $10 $4,120

drawing & specs.







1924.6(c)(2)&(4) TA Grantee Bookkeeping


30 0.5 15 $10 $150

System







1924.13(a)(5)(v)&(C) Keep Construction


250 0.5 125 $40 $5,000
1924.13(e)(1)(ii)(C) Accounts







1924.13(b)(2) Maintain Construction


15 0.25 4 $20 $80

Diary







1924.13(e)(1)(v)(C) Construction Accounting


120 0.5 60 $20 $1,200





















REPORTING TOTALS


363,415
117,242
$1,397,720











RECORDKEEPING TOTALS




616
$10,550











DOCKET TOTALS


363,415
117,858
$1,408,270
File Typeapplication/vnd.ms-excel