pdfSchedule Highlights- 2010 CCM Activities - Diagram 2, 7/1/2009
1. Create CCM Block Clusters
Oct 2008 - Feb 2009
MAF/TIGER
Benchmark
(for Address Canvass)
Previously Completed
- Independent Listing to begin August 28, 2009 (on-time).
- Puerto Rico to start listing 3 weeks later-- Sept 18, 2009.
- DSSD delivered the listing sample clusters to TMO, NPC,
FDCA and FLD (on time).
- ILBs being printed and shipped on a flow (on time).
- Finalized field training materials, translations, adaptations
- FLD Managers Conference on Listing (6/30-7/1, 2009)
- FLD will conduct 2010 IL Coverage Measurement Opera-
2. Select CCM Block Clusters
Feb 2009 - Apr 2009
3. CCM Independent HU Listing & QC
Aug 28, 2009 - Dec 12, 2009
tions Control System training for managers in July 2009.
- Military map spots will not be collected; Map Spot Numbers
assigned to structure as an identifier on ILB.
UC&M
(Preliminary
Census Address
List - assumes
GQV updates)
- Maps-- Large format already printed; Maps-- Small format
4. Subsample CCM Small Block Clusters
Jan 2010 - Feb 2010
to be printed by 7/31/09 at RCCs- on time.
- Training-- FOS-- starts 7/29/09; Listers 8/24/09-8/27/09
- PR Training --FOS 8/18/09; Listers 9/14/09-9/17/09
5. CCM Initial HU Computer Matching
Jan 2010 - Mar 2010
-Completed UAT (on-time)
6. CCM Initial HU Before Followup Clerical Matching
Feb 2010 - Mar 2010
NRFU &
RI
*
7. CCM Initial HU Followup & QC
Mar 2010 - Apr 2010
May -Jul
2010
In Development-- on schedule
- The DSSD began the test of the 2010 Housing Unit
Matching Review and Coding System in June 09.
8. CCM Initial HU After Followup Clerical Matching
Mar 2010 - May 2010
*
Detailed specifications completed. (on-time)
9. Relisting dropped.
10. Identify CCM Person Interview Sample
May 2010 - Jul 2010
CFU Complete
Aug 2010
11. CCM Person Interview & RI
Aug 2010- Oct 2010
Census Unedited
File (CUF)
Nov 2010
12. Identify CCM E Sample
Dec 2010
13. CCM Person Computer Matching
Dec 2010 - Jan 2011
14. CCM Person Before Followup Clerical Matching & Residence Status Coding
Oct 2010 - Feb 2011
15. CCM Person Followup & QC
Jan 2011 - Mar 2011
*
Draft Software Requirement Specification issued. (ontime)
- Working on draft PI and PIRI instrument specifications.
- Completed PI and PIRI 2010 requirements.
- TMO JAD for 2010 PI/RI CMOCS conducted 6/24-25.
#12-- Started drafting 2010 E-Sample Software
Requirement Specification (on time)
Updating requirements & specs due to 2006 and DR
testing experience.
Completed 2010 requirements (on time); working on
specs
16. CCM Person After Followup Clerical Matching *
Feb 2011 - Apr 2011
Updating requirements & specs due to 2006 and DR
testing experience.
17. CCM Final HU Computer Processing *
Mar 2011 - Apr 2011
New for 2010 but rather straightforward & was done
for 2000. Started requirements development.
18. CCM Final HU Before Followup Clerical Matching *
Apr 2011 - May 2011
* Not conducted for
DR & not fully tested.
19. CCM Final HU Followup & QC *
May 2011 - Jun 2011
Updating requirements due to TMO involvement; based
on IHU operations.
20. CCM Final HU After Followup Clerical Matching *
May 2011 - Jul 2011
Final Census
Final
Census
File
(CEF)
File
(CEF)
Feb
2011
Feb 2011
21. CCM Estimation *
May 2011 - June 2012
Net-April 30,2012, Components June 30, 2012
Reports: Net- July 31, 2012: Components- Sept. 30, 2012
CCM PMR 7/01/09, Ramos & Cantwell, DSSD
CCM PMR 7/01/09, Ramos & Cantwell, DSSD
Initial drafts of estimation specs completed. (on-time)