SUPPLEMENTARY DOCUMENT
State Highway-Rail Grade Crossing Action Plans
OMB No. 2130-NEW
TABLE – Paperwork Requirements and Corresponding Estimates (Program Changes)
CFR Section |
Respondent Universe |
Total Annual Responses |
Average Time per Response |
Total Annual Burden Hours |
234.11 – State Highway-Rail Grade Crossing Action Plans – Development and Submission of Plans - Disapproval of State Highway-Rail Grade Crossing Action Plan and Submission of Revised Plan |
10 States
10 States |
10 plans
5 revised plans |
600 hours
80 hours |
6,000 hours
400 hours |
Note: Total estimated responses above amount to 15 and total estimated burden amounts to 6,400 hours. Since this is a new collection of information, these are all program changes (by definition).
File Type | application/msword |
Author | USDOT User |
Last Modified By | USDOT User |
File Modified | 2010-06-11 |
File Created | 2010-06-11 |