4-1 Introduction and Applicability. A Reserve Fund for
Replacements exists for most projects with HUD-insured,
formerly coinsured, and HUD-held mortgages. This Chapter
applies to these projects as well as to Section 202 and
Section 162 Direct Loan Program projects and Section 801
and 811 Capital Advance Program projects. The Reserve
Fund is generally used to help defray the costs of
replacing a project's capital items. Title 24 of the Code
of Federal Regulations provides, at Section
207.19(f)(3)(i), "In all projects, except those involving
rehabilitation where the mortgage does not exceed
$200,000, a fund for replacements shall be established and
maintained with the mortgagee. The amount and type of
such fund and the conditions under which it shall be
accumulated, replenished, and used, shall be specified in
the charter, trust agreement, or regulatory agreement."
4-2 Regulatory Agreements for projects generally contain the
following typical language pertaining to the Reserve Fund
for Replacements to the effect that owners shall establish
or continue to maintain a reserve fund for replacements by
the allocation to such reserve fund in a separate account
with the mortgagee or in a safe and responsible depository
designated by the mortgagee, concurrently with the
beginning of payments towards amortization of principal of
the mortgage insured or held by the Federal Housing
Commissioner of an amount equal to $_____ per month unless
a different date or amount is approved in writing by the
Commissioner. Such fund, whether in the form of a cash
deposit or invested in obligations of, or fully guaranteed
as to principal by, the United States of America shall at
all times be under the control of the mortgagee.
Disbursements from such fund, whether for the purpose of
effecting replacement of structural elements and
mechanical equipment of the project, for the cure of
mortgage defaults, or for any other purpose, may be made
only after receiving the consent in writing of the
Commissioner. In the case of Section 202, 162, 801, or
811 projects, where HUD serves as the mortgagee, the
project owner escrows the funds but may not withdraw them
from the Reserve for Replacements Account without the
Asset Management Branch Chief's written permission. For
HUD-Held mortgages, HUD shall exercise control over the
Reserve Fund for Replacements by acting pursuant to its
own authority as well as in the stead of the mortgagee.
This authority may be exercised only by HUD Headquarters.
______________________________________________________________________
4-1 3/95
_____________________________________________________________________
4350.1 REV-1
______________________________________________________________________
4-3 Mortgagee's Certificates generally contain the following
typical language that pertains to the Reserve Fund for
Replacements: "Beginning on the date on which the first
payment toward amortization is required to be made by the
terms of the insured mortgage or at such later date as may
be agreed to by you [the Federal Housing Commissioner], we
[the Mortgagee] shall require a monthly deposit with us or
in a depository satisfactory to us of one-twelfth (1/12)
of the sum set forth in your Commitment for Insurance
constituting a 'Reserve Fund for Replacements' which fund
shall be subject to our order and from which fund
withdrawals may be made only upon the receipt of your
written permission. These funds will be deposited with us
by the Mortgagor in cash or in the form of obligations of
or guaranteed as to principal by the United States of
America. We will, upon appropriate request by the
Mortgagor, permit the conversion of the whole or a
substantial part of such cash deposits into the form of
obligations of, or fully guaranteed as to principal by,
the United States of America. . . ."
4-4 Remaining Economic Life of Building Improvements.
Economic life is the period over which improvements to
real property contribute to property value. Because
buildings are subject to physical deterioration and
functional or economic obsolescence, their periods of
usefulness are limited. For purposes of this Chapter 4,
"buildings" includes building structures themselves, major
movable equipment, and other on-site improvements such as
water mains, sewer laterals, swimming pools, parking lots,
etc. As buildings deteriorate or become obsolete, their
ability to serve useful purposes decreases and eventually
disappears. This decline and ultimate disappearance of
utility may occur gradually or rapidly.
______________________________________________________________________
3/95 4-2
_____________________________________________________________________
4350.1 REV-1
______________________________________________________________________
4-5 Economic Life vs. Physical Life. The period between the
time of completion of the building and the time when it is
no longer fit or safe for use, or when it is no longer
practicable to maintain it in a safe and usable condition,
is its total physical life. The total economic life of a
structure is the period of time between the completion of
the building and the disappearance of its ability to
produce the service of providing housing for its intended
occupants (in the case of non-profit mortgagors) or net
returns over and above a return on the land value (in the
case of profit motivated and limited dividend mortgagors),
notwithstanding that it is structurally sound, in good
condition, and usable (though not functionally or
profitably).
A. Estimates are made of both physical life and remaining
economic life, but the estimate of physical life sets
the maximum for the estimate of economic life.
NOTE: Judicious use of the Reserve Fund for
Replacements is expected to extend the physical life
of the building.
B. Economic life can never be greater than physical life
but it may be and frequently is less. A structure may
be sound and in good physical condition with a number
of years of physical life remaining and yet have
reached the end of its economic life if its remaining
years of physical usefulness will not deliver a
positive cash flow or provide the service of supplying
housing on a cost-effective basis.
4-6 Estimates of Remaining Economic Life. In predicting the
remaining economic life of a building, six types of
factors are considered:
A. Economic background of the community or region and the
need for accommodations of the type represented.
B. Relationship between the property and the immediate
environment.
C. Architectural design, style, and utility from the
functional point of view and the likelihood of
obsolescence attributable to new inventions, new
materials, changes in building codes, and changes in
tastes.
D. Trend and rate of changes of characteristics of the
neighborhood and their effect upon land values.
______________________________________________________________________
4-3 9/92
_____________________________________________________________________
4350.1 REV-1
______________________________________________________________________
E. Workmanship and durability of construction and the
rapidity with which natural forces cause physical
deterioration.
F. Physical condition and probable cost of maintenance
and repair, the practices of owners and occupants with
respect to maintenance, and the use or abuse to which
structures are subjected.
4-7 End of Useful Life of Building Improvements. The useful
life of a building has come to an end when the building is
incapable of producing an annual income sufficient to
offset the expense of operation and maintenance,
insurance, and taxes, and to produce returns upon the
value of the land or provide the service of shelter for
the intended occupants in the case of non-profit owners.
The improvements upon the land at that time possess no
more value than the amount which can be obtained from a
purchaser who will buy them and remove them from the site.
At this point the value of the building has dwindled to
"Shell" value less demolition costs. The last years of
economic life are more difficult to predict than the first
years, so caution must be exercised to avoid
over-estimation of the remaining economic life for older
buildings in older, declining neighborhoods.
4-8 Many projects with HUD-insured or HUD-held mortgages were
underwritten with forty year mortgages and with estimated
economic lives of fifty-five years. The Reserve Fund for
Replacements was established to help ensure that the
physical live of the buildings and structures would extend
to the assumed 55-year economic lives. It was not the
original purpose of this Reserve Fund to provide for a
complete, dollar for dollar, capability of replacing all
the building structural components and equipment as these
wear out but rather to provide a readily available source
of capital that will help defray these costs in the latter
years of amortization of the mortgage note.
______________________________________________________________________
9/92 4-4
_____________________________________________________________________
4350.1 REV-1
______________________________________________________________________
4-9 Building components generally tend to fall into two
categories: 1. Those items that are usually considered
to be capital items and eligible for reimbursement from
the Reserve Fund for Replacements to the extent of the
availability of money in that account; and, 2. Those
items that are usually considered to be routine
maintenance items. As a guideline, repair/replacement
expenditures that are generally capitalized may often be
eligible for payment from a project's Reserve Fund, while
those expenditures that are expensed are only occasionally
eligible for payment from the Reserve Fund.
NOTE: As items, equipment, etc. that fall into either of
these classifications are obtained for a project, HUD
expects that mortgagors will be mindful of energy and
environmental considerations and will be sensitive to
issues involving handicapped/disabled persons.
A. Items traditionally contemplated as eligible for draws
from this Fund include capital items such as (but not
limited to):
1. Replacement of refrigerators, ranges, and other
major appliances in the dwelling units.
2. Extensive replacement of kitchen and bathroom
sinks and counter tops, bathroom tubs, water
closets, and doors (exterior and interior).
3. Major roof repairs, including major replacements
of gutters, downspouts, and related eaves or
soffits.
NOTE: When replacing an entire roofing system,
HUD encourages owners to seek energy efficient
roofs and bonded roofs.
4. Major plumbing and sanitary system repairs.
5. Replacement or major overhaul of central air
conditioning and heating systems, including
cooling towers, water chilling units, furnaces,
stokers, boilers, and fuel storage tanks.
6. Overhaul of elevator systems.
7. Major repaving/resurfacing/sealcoating (sidewalks,
parking lots, and driveways).
______________________________________________________________________
4-5 9/92
_____________________________________________________________________
4350.1 REV-1
______________________________________________________________________
8. Repainting of the entire building exterior.
9. Extensive replacement of siding.
10. Extensive replacement of exterior (lawn) sprinkler
systems.
11. Replacement of or major repairs to a swimming
pool.
12. For certain projects, requests for capital
improvements or enhancements to the property could
be considered. For examples, a personal computer
and some associated software could be purchased,
or perhaps individual air conditioning units could
be added to a project that was not air conditioned
when it was built, or perhaps gutters and
downspouts could be added where necessary. Some
improvements may be eligible if in HUD's opinion
such items:
a. Would result in enhancing the mortgage
security.
b. Would upgrade the property and place the
property in a more favorable competitive
position in the rental market.
c. Would be necessary to comply with changes in
local, state, or federal laws.
d. Would not inordinately deplete the Reserve
Fund, i.e., the improvement must be
affordable.
B. Items traditionally contemplated as ineligible for
draws from this Fund include maintenance items such as
(but not limited to):
1. Repainting of interior areas of projects.
Note: A separate interior painting reserve for
this kind of work may be established by mutual
agreement and consent of the concerned parties.
______________________________________________________________________
9/92 4-6
_____________________________________________________________________
4350.1 REV-1
______________________________________________________________________
2. Replacement of range burners, bibs, oven elements,
controls, valves, wiring, etc.
3. Replacement of dwelling unit air conditioning
components such as fan motors and window unit
compressors.
4. Minor repairs to central air conditioning and
heating systems such as valve replacements and the
cleaning of boiler interiors.
5. Minor roof repairs, including minor repairs to
gutters and downspouts.
6. Minor paving repairs.
7. Caulking and sealing.
8. Window and screen repairs.
9. Purchase of maintenance tools and equipment such
as lawn mowers or snow blowers.
10. Purchase of minor office equipment.
11. Inspection/recharging/replacement of fire
extinguishers.
12. Other items generally considered to be routine
maintenance.
4-10 Adequacy of Reserve Fund for Replacements. Owners should
analyze periodically the amounts in their Reserve Fund in
the light of anticipated replacement needs. Owners should
rely on their own personal knowledge of the physical
condition of the project, evaluations made by their
managing agents, and physical inspection reports furnished
by their mortgagee and by HUD. After reviewing this
information, owners should project how much money needs to
be on deposit in the Reserve Fund at what points in the
future. Owners should then calculate what amounts need to
be deposited and when these amounts need to be deposited
in order to accommodate the projected future demands on
the Reserve Fund. If the owners' analyses indicate a need
to increase the rate of deposits into the Reserve Fund,
the owners should contact the Loan Management Branch Chief
of their HUD Field Office and request HUD to authorize an
increase in the deposits. These requests would usually be
made in conjunction with requests for increases in rental
rates so that enough revenue would exist to make the
______________________________________________________________________
4-7 9/92
____________________________________________________________________
4350.1 REV-1
______________________________________________________________________
increased deposits.
4-11 Recommended Minimum Threshold. HUD Handbook 4465.1 REV-2,
Valuation Analysis for Project Mortgage Insurance, gives
details on how the initial monthly deposit to the Reserve
Fund is established. All owners should strive to reach
some minimum threshold for the Reserve Fund for
Replacements. The main purpose of having a recommended
minimum threshold is to have funds available for an
emergency or unforeseen contingency, such as a major roof
failure or a water or sewer main break, so that funds
could be drawn below the customary threshold. Assuming
that a project is in very good physical condition and that
no major replacements are needed in the near future (e.g.,
five years), HUD strongly recommends, but does not
mandate, that owners target a minimum amount to be held in
the Reserve Fund that would equal or exceed the greater of
the following two amounts:
A. The initially established monthly deposit times 144
(12 years); or
B. At least $1,000 per unit.
4-12 Adjustments to a Recommended Minimum Threshold. The
dollar amount calculated above may need to be increased
for the following variables:
A. Physical Condition of the Project. Projects in less
than very good condition would almost certainly need
larger balances.
B. Geographical Location. Exposure to severe or unusual
weather conditions as well as widely varying costs of
replacements may have important consequences.
C. Immediate Replacement Needs. A property may be in
good physical condition and yet might have large
capital needs in the relatively near (five year)
future.
D. Changes in Replacement Items. If non-traditional
items, such as routine carpet replacement, are to
become eligible Reserve Fund items, the minimum to be
held in the fund would certainly need to be increased.
E. Unit composition. Projects with more units of larger
size typically need larger amounts in the Reserve Fund
than projects with smaller units. For example, a
______________________________________________________________________
9/92 4-8
_____________________________________________________________________
4350.1 REV-1
______________________________________________________________________
project designed for large families consisting
entirely of three and four bedroom units would almost
always need more reserves than a project of the same
number of units that consists of efficiencies and one
bedroom units because the former project usually
experiences greater wear.
F. Project Size. Larger projects typically need larger
reserves than smaller projects.
G. Urban vs. Rural. Urban projects often need larger
reserves than rural projects.
4-13 Suspension of Deposits to the Reserve Fund for
Replacements. In older projects where the mortgage is
seasoned and the owner has demonstrated the will and the
ability to stay with the property, the Loan Management
Branch Chief may, upon the owner's request and if deemed
appropriate, suspend further payments to the project's
Reserve Fund for Replacements by signing a Form HUD-9250,
"Reserve Fund for Replacements Authorization (Appendix
1)," authorizing a suspension. (Note: If rental rates
are predicated upon a certain rate of deposits being made
into the Reserve Fund, the rental rates may need to be
reexamined if the deposits are suspended.) This suspension
is considered by HUD to be a privilege that may be granted
to an owner for providing competent management and for
keeping the project in good physical condition as
determined by HUD. HUD's approval of suspending future
deposits is subject to the following conditions:
A. A mutually acceptable minimum threshold as calculated
above and revised as necessary is kept in the Fund.
B. The owner has asked the mortgagee to invest a
substantial portion of the Reserve Fund.
C. All interest earned by investments of the Reserve Fund
accrue to the Fund and is kept in the Fund (unless
released by HUD for repairs/replacements).
D. The property continues to be maintained in good
physical condition.
E. If the balance in the Fund should fall below the
recommended minimum threshold, monthly deposits would
resume at no less than the previous dollar amount
until a mutually acceptable minimum balance is
restored.
______________________________________________________________________
4-9 9/92
_____________________________________________________________________
4350.1 REV-1
______________________________________________________________________
F. The project remains under the effective control of the
same owners and the owners continue in good standing
with HUD.
G. Projects receiving Section 8 assistance generally may
not suspend deposits to the Reserve Fund for
Replacements except for:
1. Projects that are not subject to Section 8
Automatic Annual Adjustment Factors (AAFs), i.e.,
rental rates are established by HUD under the
budgeted rent increase procedures, and the Reserve
for Replacement line item is deleted as an
allowable cost in the rent determination; or,
2. The projects' rents are adjusted automatically by
application of the AAF and immediate, temporary
financial relief is needed. However, in this
case, the project owner would not be eligible to
take its distribution as long as the suspension is
in effect.
4-14 Earliest Withdrawals. Projects which were newly built or
substantially rehabilitated normally should not need
withdrawals from the Reserve Fund during the early years
of occupancy for repairs to or replacement of capital
items. For example, many building components may be
covered by a latent defects bond, roofs should be
guaranteed, and most appliances should be under warranty.
Projects insured under Section 223(f) are an exception to
this general statement; these projects may need and be
eligible for withdrawals from the Reserve Fund at any time
following Final Endorsement. Owners of Section 223(f)
projects should be urged to make and submit to the Field
Office an early analysis of their Reserve Fund
requirements in accordance with the procedures described
above.
______________________________________________________________________
9/92 4-10
_____________________________________________________________________
4350.1 REV-1
______________________________________________________________________
4-15 General Requirements for Requesting Withdrawals From the
Reserve Fund for Replacements.
A. Mortgagors shall make all requests in writing and
shall provide a detailed description of the work done
or to be done; the description should identify the
specific location including the dwelling unit (if
applicable) in order to permit an inspection of the
work without needing additional information about the
work.
B. Owners should be invited to discuss proposed large
withdrawals ($20,000 or more than twenty per cent of
the existing balance in the Fund) with the Loan
Management staff of the HUD Field Office before making
the written request to agree upon plans for
replenishing the Fund.
C. If the withdrawal request is a reimbursement for work
that has been done, a copy of the paid invoice(s)
normally should accompany the request unless the
Optional Procedures see below are being used.
D. If the withdrawal request is for work that is to be
done (an advance from the Fund), at least three formal
or informal bids together with a copy of the bid
specifications generally should accompany the request.
If the lowest bidder was not selected the owners
should explain their selection of a higher bidder.
For example, consideration may be given to the
bidder's reputation for quality workmanship,
materials, and timely performance and to the urgency
of the repairs. Owners also should explain why an
advance is needed. Approval of owners' requests may,
at the discretion of the Field Office Loan Management
Branch Chief, be granted on an installment basis
depending largely upon the scope of work done and
remaining to be done and upon the availability of
funds in the project's operating account.
E. Timing. Owners should not make requests for
withdrawals more often than quarterly unless an
emergency exists. Owners should make reimbursement
requests during the same (project) fiscal year in
which the expenditure occurred, preferably at least
sixty days prior to the close of the project's fiscal
year.
______________________________________________________________________
4-11 9/92
_____________________________________________________________________
4350.1 REV-1
______________________________________________________________________
4-16 HUD Actions. Unless the amount of the release is for a
large amount ($20,000 or 20% of the Fund balance,
whichever is greater), an inspection of the work generally
should not be necessary in order to act upon the request;
inspections should be made during subsequent visits to the
property. Inspection of a sample of the replacements
generally would be adequate if the mortgagor is submitting
acceptable annual audited financial statements and if the
project is generally untroubled. The Loan Management
Branch Chief will make reasonable effort to review and act
upon the mortgagor's request within thirty days (whenever
possible) from receipt and, if approved, prepare, sign,
and mail the Form HUD-9250 to the mortgagee of record.
4-17 Optional Procedures. HUD has developed optional
procedures in an effort to respond to industry requests
for expediting the procedures for requesting withdrawals
from the Reserve Fund for Replacements. Loan Management
Branch Chiefs may invite project owners to use these
optional procedures at their discretion. If the mortgage
is current, if there are no known major, uncured
violations of the Regulatory Agreement, and if there are
no major, unresolved findings from management reviews,
analyses of annual financial statements, or other known
and documented reasons that would tend to preclude use of
these optional procedures, HUD Field Offices may avail
themselves of the following optional procedures. If these
optional procedures are followed, the HUD Field Office
will make every effort to act on the mortgagor's request
within ten (10) business days from receipt. If a
mortgagor develops a pattern of errors when using these
optional procedures (such as continuing to request
ineligible items) or if the mortgage goes into default,
the project becomes troubled or potentially troubled,
etc., the mortgagor can expect the HUD Field Office to
suspend temporarily or deny the use of these optional
procedures.
A. A narrative request for the release of funds is to be
made by the mortgagor/managing agent.
B. A Mortgagor Certification is required; it should be as
follows:
______________________________________________________________________
9/92 4-12
_____________________________________________________________________
4350.1 REV-1
______________________________________________________________________
"I (Mortgagor) certify that:
1. "Funds expended or to be expended have been or
will be used for the work indicated in this
request;
2. "I have inspected/will inspect the work and have
determined/will determine that the damaged area(s)
or equipment have been restored to as good or
better condition;
3. "No mechanic's or materialman's liens will be or
have been attached to the property as a result of
the repair;
4. "The repairs have been or will be completed in
accordance with all applicable building codes and
ordinances;
5. "All contract materials, supplies, and services as
applicable have been obtained at the most
reasonable cost and on terms most advantageous to
the property;
6. "All discounts, rebates, or commissions have been
credited to the property;
7. "Any expenditures that are determined by HUD to be
ineligible, as a result of an inspection, will be
repaid to the property's Reserve Fund;
8. "All goods and services purchased from individuals
or companies with which the Owner or Managing
Agent has an identity-of-interest were or will be
purchased at costs not in excess of those that
would be incurred in making arms-length purchases
on the open market;
9. "Under the penalties and provisions of Title 18,
United States Code, Chapter 47, Section 1001, the
statements contained in this request have been
examined by me and to the best of my knowledge and
belief are true, correct, and complete."
C. Requests, except for emergencies, should be made no
more often than quarterly and at least annually (if
applicable) at least sixty days before the close of
the project's fiscal year.
______________________________________________________________________
4-13 9/92
_____________________________________________________________________
4350.1 REV-1
______________________________________________________________________
D. Copies of invoices are not required to be submitted to
HUD if the description of the work done or items
replaced is sufficiently detailed to permit an
inspection and verification; however, the mortgagor
must keep copies of the invoices on file for at least
three years and have the invoices available for HUD
staff to review.
E. The mortgagor/management agent is to prepare the Form
HUD-9250 for signature by the Field Office Loan
Management Branch Chief, who also can provide further
guidance on information that should be shown on the
Form. NOTE: Many mortgagees appreciate showing their
loan number on the Form HUD-9250 next to the HUD
Project Number and find that this makes their
processing of the form quicker and easier.
Owners/agents would be well advised to check with
their own lenders for their preferences in this
regard. NOTE: Mortgagors must never submit a Form
HUD-9250 directly to their mortgagees (other than
HUD).
F. If funds are to be released based upon bids alone,
three bids and a brief statement about why an advance
is necessary should accompany the request. The bid
selected should be identified in the narrative; if the
selected bid is not the lowest bid, a brief statement
about the reason for selecting a higher bidder should
be made. If a (selected) bid for items being
purchased is for more than $10,000, copies of all the
bids should accompany the request. The mortgagor must
keep copies of all the bids on file for at least three
years and have them available for HUD staff to review.
G. A supply of the Forms HUD-9250 may be obtained from
the HUD Field Office.
4-18 Mortgagor and Mortgagee Records. Since appliances and
similar items such as office equipment constitute security
under the mortgage, project owners should keep their
mortgagees fully informed when appliances and items that
are normally identified by make, model, and serial number
are replaced. Mortgagors are expected to provide their
mortgagees with this identifying information as it
changes; mortgagors also should provide HUD with copies of
the documentation they furnish their mortgagees.
Additionally, mortgagors should keep their insurer(s)
informed of changes or additions to the property.
______________________________________________________________________
9/92 4-14
4350.1 REV-1
CHG-9
4-19 Field Office Records. HUD Field Offices are encouraged to establish a
Reserve Fund for Replacements File for each project. Forms HUD-9250
authorizing releases of funds are to be kept on file for the present
fiscal year and for the previous three fiscal years of the project.
Except in unusual circumstances, such as defaults or major findings from
various project reviews or audits, copies of invoices that are on file
and more than a year old may be discarded if the required audited
financial statement covering the time period of the expenditure has been
submitted and if a management review or a physical inspection has been
conducted during that time period. Forms HUD-9250 that change
(increase, decrease, or suspend) the monthly Reserve deposits are to be
maintained on file until the mortgage matures or is prepaid in full or
until mortgage insurance is terminated.
4-20 Investment Requirements for Reserve for Replacement funds in Section 8
projects. Investment of the Reserve Funds in interest-bearing
* accounts is required for certain projects receiving Section 8
assistance:
A. The revised Section 8 regulations apply to all owners of older
Section 8 projects where the owners voluntarily opted to be bound
thy those regulations.
B. Except for owners of previously HUD-owned projects sold pursuant to
24 CFR Section 886 (Subpart C), partially assisted projects, and
Section 202/8 projects, the revised Section 8 regulations apply to
projects for which:
1. Agreements to Enter Into Housing Assistance Payments Contracts
(AHAPs) were executed on or after November 5, 1979, for New
Construction projects.
2. AHAPS were executed on or after February 20, 1980, for
Substantial Rehabilitation projects.
C. For these projects, earned interest is to remain in the Reserve
Fund until its release is authorized by HUD.
4-15 12/95
4350.1 REV-1
CHG-9
4-21 Liquidity Requirements. HUD recognizes that most property owners and
managing agents can make fairly good estimates of the amount and timing
of future replacement needs. Mortgagors should use prudence when
selecting the durations of investments and make their selections
according to anticipated and projected needs, including contingencies.
Therefore, HUD is not establishing specific liquidity requirements for
the Reserve Fund for Replacements. The mortgagor, not the mortgagee, is
responsible for deciding the liquidity requirements of funds held in the
Reserve Fund. The mortgagor should maintain some portion of its
reserves in the form of very liquid assets such as passbook savings
accounts. As a guideline only and depending on the specific project,
$50/unit or three or four month's required deposits to the Reserve Fund
should be enough to meet minimum liquidity requirements for some
projects. HUD does not encourage project owners to commit too large a
portion of Reserve Funds to excessively long term investments in order
to achieve a marginal increase in the net return on the investment.
Preservation of principal is of utmost importance when owners evaluate
various investments and formulate their investment strategies.
NOTE:- ALL MORTGAGORS SHOULD BE CAUTIONED. If any principal is lost as
a result of an early or premature liquidation of an investment that is
caused by an owner's requested withdrawal from the Reserve Fund for
Replacements, the lost principal must be repaid to the project. This
repayment must be repaid to the project (mortgagor entity) by the owning
persons, by persons with a controlling interest in the project, or by
such affiliated/related parties as the project's sponsors. This caution
is particularly important for non-profit mortgagors. Accordingly, the
terms and durations of investments should be selected prudently and with
great care.
9/92 4-16
4350.1 REV-1
CHG-9
4-22 Investment of Reserve for Replacements Funds. Consistent with program
* regulations and the Regulatory Agreement, the reserve for replacement
funds must be maintained by the mortgagee. Investment options should be
determined jointly by the mortgagor and mortgagee. The Regulatory
Agreement requires, ".. such fund, whether in the form of a cash
deposit, or invested in obligations of, or fully guaranteed by the
United States of America, shall at all times be under the control of the
mortgagee."
A. This paragraph suspends this provision by authorizing the mortgagee
to invest funds in excess of $100,000 in U. S. government-backed
securities and to hold funds in excess of $100,000 in institutions
under the control of, and whose deposits are insured by, the
Federal Deposit Insurance Corporation, National Credit Union
Association, or other U.S. government insurance corporations under
the following conditions:
1. Mortgagees must determine that the institution has a rating
consistent at all times with current minimally acceptable
ratings as established and published by Government National
Mortgage Association (GNMA).
2. Mortgagees must monitor the institution's ratings no less than
on a quarterly basis, and change institutions when necessary.
The mortgagee must document the ratings of the institutions
where the funds are deposited and maintain the documentation
in the administrative record for three years, including the
current year.
3. If the mortgagee does not perform the required quarterly
review of the institutions where there are deposits in excess
of $100,000 and does not maintain the funds in an institution
with a rating consistent with current minimally acceptable
ratings as established and published by GNMA, and the
institution fails, the mortgagee is held responsible for
replacing any lost funds. In addition, the mortgagee shall be
subject to sanctions. In the event the mortgagee fails to
replace the lost funds, HUD will seek all available remedies
to recover whatever funds are lost as a result of the failed
institution.
4-17 12/95
4350.1 REV-1
CHG- 9
B. The above language is not deemed a modification of the Regulatory
Agreement. Therefore, HUD reserves the right to invoke this
Regulatory Agreement provision and make it operational in the
future through notice or handbook change, if it is determined that
such a policy is necessary or desirable.
4-23 Interest on Investments. HUD encourages and in some cases requires that
interest earned on Reserve Fund investments remain in the Reserve
Account. Interest must remain in the Reserve Account for those Section
8 projects listed in paragraph 4-20 of this Chapter 4. When this earned
interest remains in the account, this interest will not be considered by
HUD when processing requests for increases in rental rates if this
interest is clearly and separately identified on the project's Form HUD-
92410. In other words, HUD will not offset newly computed gross
potential rents by the amount of interest that accrues to and remains in
the Reserve Account.
NOTE: Interest may never be disbursed directly to the owners of a
project or directly to any individuals associated with the owners. All
interest earned must flow through the accounts of the project and must
be disclosed on the project's accounting records.
A. With the issuance of this Chapter 4, owners of any of the following
types of projects are instructed to ask their mortgagees to invest
all or a substantial portion of their Reserve Fund for
Replacements; all interest on Reserve Fund investments must remain
a part of the Reserve Account. This
12/95 4-18
4350.1 REV-1
procedure applies if the project's mortgage is insured or held by
HUD under any of the following Sections of the National Housing
Act:
1. Section 236, a "Special Risk Insurance Fund."
2. Section 221(d) (3) BMIR [Section 221(d) (5)].
3. Section 221(d) (3) if the project receives Rent Supplement or
Section 8 Assistance.
4. Section 223(e), a "Special Risk Insurance Fund."
5. Section 223(f).
6. Any project that has an Operating Loss Loan or a Supplemental
Loan that is insured or held by HUD must keep all Reserve Fund
interest earned by any of its Replacement Reserve Funds in the
respective Funds.
B. With the issuance of this Chapter 4, owners of Section 202, 162,
801, and 811 projects are instructed to invest all or a substantial
portion of their Reserve Fund for Replacements.
C. HUD strongly encourages owners of all other projects to ask their
mortgagees, including HUD when the mortgage is HUD-held, to invest
a significant portion of the money held in the Reserve Fund for
Replacements. When making these investment requests, owners should
specify the desired form(s) of investment.
4-24 Insured Mortgagee Charges for Handling Investments of the Reserve Fund.
Reference is made to HUD Handbook 4350.4 for additional information on
this topic. If a mortgagee proposes to assess charges for investing the
Reserve Fund, the Field Office Loan Management staff are reminded to
examine the Mortgagees Certificate for the project to see if any fees or
charges for making or accepting investments were disclosed or stated.
Any fees so collected by the insured or coinsured mortgagee may only be
collected according to an agreement between the mortgagee and the
mortgagor.
4-19 7/93
4350.1 REV-1
CHG-9
4-25 Other Fees. HUD does not recognize special fees or charges that might
be paid by project mortgagors to investment brokers or other parties
(other than HUD) such as managing agents for providing investment advice
or for making or brokering investments except where the nature of the
investment itself requires that it be brokered, i.e., obligations of
federal agencies such as GNMA. Such fees, other than those involving
the above exception, are not considered to be necessary expenses, should
not be paid from project funds, and are not considered by HUD when
calculating rental rates.
4-26 Combined Investments. For HUD-insured mortgages, monies held in the
Reserve Fund for Replacements and the Residual Receipts Account (if
* such an account exists) may be combined to purchase a single investment
or combination of investments.
A. Earned interest and the return of principal when the investment is
liquidated must be prorated to the respective bookkeeping accounts.
B. The mortgagor must take care to preserve sufficient liquidity in
these accounts. Some forms of investment, such as passbook savings
accounts, are very liquid. Others are increasingly less liquid,
such as Thirty, Sixty, or Ninety Day Certificates of Deposit (CDs),
then U.S. Treasury Bills, U.S. Treasury Notes, etc.
4-27* HUD recognizes and appreciates the cooperation exhibited by many
mortgagees when facilitating investments of the Reserve Accounts on
behalf of mortgagors and acting on the mortgagors' requests. HUD
considers the ability to invest a project's Reserve for Replacement
Funds to be a right that accrues to the mortgagor. The mortgagor
and mortgagee are encouraged to jointly decide on the investment
vehicle for funds in the Reserve Accounts.
12/95 4-20
4350.1 REV-1
4-28 "Borrowing" from the Reserve Fund, other than advances from the Reserve
Fund for curing a delinquency or a default. (The uses of a project's
Reserve Fund for Replacements in curing mortgage delinquencies is
covered in Chapter 5 of this Handbook.) The Asset Management Branch
Chief may authorize the mortgagor to make brief, temporary uses of some
portion of the Reserve Fund for Replacements for purposes other than
those normally contemplated by the establishment of the Fund if:
A. There are no funds in a Residual Receipts account that could be
used first.
B. An immediate crisis exists.
C. The mortgagor agrees in writing to repay the advance from the Fund
over a reasonable period of time.
4-29 The Asset Management Branch Chief should exercise customary good
business judgement when making a decision to permit the mortgagor to
"borrow" from the Reserve Fund.
A. The purpose of such an advance is not merely to forestall an
assignment of the mortgage but it may be related to a condition or
circumstance beyond the normal course of business. Examples of
these kinds of events include but are not limited to:
1. An unexpected increase in taxes or a special assessment.
2. An unanticipated increase in the costs of insurance,
utilities, or like items.
3. Damage caused by unusually adverse weather conditions, whether
or not such damage may be covered by hazard insurance.
4. Other uses of the fund not normally contemplated, such as for
repairs and maintenance not usually eligible for reimbursement
from the Reserve Fund.
B. Overall management of the project is at least satisfactory and the
mortgagor has been cooperative in complying with requests from HUD
and the mortgagee.
C. There is a formal agreement with the mortgagor to repay the advance
on specified terms.
4-21 9/92
4350.1 REV-1
4-30 The Reserve Fund for Replacements will not always be adequate to meet
the future capital needs of a project nor is it expected to do so.
There are other sources of capital available to projects. Depending on
the project, these include:
A. Residual Receipts Accounts.
B. General Operating Reserves.
C. Debt Service Reserves.
D. Owner Contributions in the form of equity.
E. Owner contributions in the form of unsecured debt (loans). These
loans may, on a case-by-case basis, be allowed to carry a nominal
interest rate that normally should not exceed the interest rate
that the project owner or sponsor could earn elsewhere in a
reasonably safe security, such as a Certificate of Deposit of the
same duration as the loan to the project. The right to earn this
interest must be pre-approved by the Loan Management Branch Chief
and the terms and conditions of repayment should be formally
negotiated and committed to writing.
F. Capital contributions from Transfers of Physical Assets (TPAs).
G. Supplemental Loans (under Section 241).
H. Flexible Subsidy, both Operating Assistance and Capital Improvement
Loans.
I. Loans from the National Cooperative Bank for some projects.
J. Energy Loans.
K. Funds from private foundations.
L. Loans or grants from other governmental agencies or private
foundations.
M. Cash flows from operations.
9/92 4-22
_____________________________________________________________________
4350.1 REV-1
______________________________________________________________________
F. Capital contributions from Transfers of Physical
Assets (TPAs)
G. Supplemental Loans (under Section 241).
H. Flexible Subsidy, both Operating Assistance and
Capital Improvement Loans.
I. Loans from the National Cooperative Bank for some
projects.
J. Energy Loans.
K. Funds from private foundations.
L. Loans or grants from other governmental agencies or
private foundations.
M. Cash flows from operations.
______________________________________________________________________
4-23 9/92
_____________________________________________________________________
4350.1 REV-1
Appendix 1
__________________________________________________________________________
Reserve Fund for
Replacements
Authorizations
********************************************************************
* *
* *
* *
* *
* *
* *
* *
* *
* *
* GRAPHICS MATERIAL IN ORIGINAL DOCUMENT OMITTED *
* *
* *
* *
* *
* *
* *
* *
* *
* *
********************************************************************
__________________________________________________________________________
9/92 4-24
File Type | application/vnd.openxmlformats-officedocument.wordprocessingml.document |
File Title | 4350 |
Author | BPS |
File Modified | 0000-00-00 |
File Created | 2021-01-29 |