Version 5 Critical Infrastructure Protection Docket No. RM13-5-000
Reliability Standards
ERRATA NOTICE
(May 3, 2013)
On April 18, 2013, the Commission issued an “Notice of Proposed Rulemaking” in the above-captioned proceeding, Version 5 Critical Infrastructure Protection Reliability Standards, 143 FERC ¶ 61,055 (2013).
This errata notice serves to correct P 119 and the table in P 124. Specifically, in P 119, the reference to “CIP version 4” in the fifth line is changed to “CIP version 5.” In addition, in the table in P 124, the “Total Burden Hours in Year 2” estimate is changed to “1,162,788 hrs” and the “Total Burden Hours in Year 3” estimate is changed to “757,948 hrs.”