10 CFR Part 52- Supporting Statement Burden Excel Tables 2

Copy of Copy of Final_Part_52_SS_Burden_Tables_051214.xlsx

10 CFR Part 52, Licenses, Certifications and Approvals for Nuclear Power Plants

10 CFR Part 52- Supporting Statement Burden Excel Tables 2

OMB: 3150-0151

Document [xlsx]
Download: xlsx | pdf

Overview

Sheet1
Sheet2


Sheet 1: Sheet1

TABLE 1

ANNUAL REPORTING BURDEN

10 CFR PART 52










GENERAL PROVISIONS










Section Number of Respondents Annually Responses per Respondent Annually Total Responses Annually Burden per Response Total Annual Burden Hours Estimate Annual Cost @ $274/hr

52.7 (Respondent is same as in Subpart C below. Only one exemption is expected to be requested annually) 1 1 1 360 360 $98,640



Subtotal: General Provisions 1
1
360 $98,640










SUBPART A: EARLY SITE PERMITS (ESPs)

NRC expects 0 ESP applications over the next 3 years.










52.15(b) – Burden covered under 10 CFR 50.30(a), (b), and (f), approved by OMB under Clearance No. 3150-0011. n/a n/a n/a n/a n/a n/a

52.16 – Burden covered under 10 CFR 50.33(a) – (d) and 50.33(j), approved by OMB under Clearance No. 3150-0011 n/a n/a n/a n/a n/a n/a

52.17(a)(1) JLD4: applies to ESP applicants (anticipate none)-assume application for Blue Castle comes in before CY14 0 1 0 6,000 0 $0

52.17(a)(2) – Burden covered under 10 CFR 51.50, approved by OMB under Clearance No. 3150-0021 JLD4: applies to ESP applicants (anticipate none)-assume application for Blue Castle comes in before CY14 0 1 0 JLD4: made this # upbased on relative burden to 52.17(b)(1) 60 0 $0

52.17(b)(1) 0 1 0 20 0 $0

52.17(b)(2)(i) and 52.17(b)(3) without ITAAC 0 0 0 1,000 0 $0

52.17(b)(2)(i) and 52.17(b)(3) with ITAAC 0 0 0 2,667 0 $0

52.17(b)(2)(ii) and 52.17(b)(3) 0 1 0 2,000 0 $0

52.17(b)(4) 0 1 0 40 0 $0

52.17(c) – Burden covered under 10 CFR 50.10(d)(3), approved by OMB under Clearance No. 3150-0011 n/a n/a n/a n/a n/a n/a

52.29(a) 0 0 0 6,000 0 $0

52.35 0 0 0 40 0 $0

52.39(b) – Burden covered under 10 CFR 52.79(b) n/a n/a n/a n/a n/a n/a

52.39(d) 0 1 0 120 0 $0

52.39(e) – Burden covered under 10 CFR 50.90, approved by OMB Clearance No. 3150-0011 n/a n/a n/a n/a n/a n/a

Subtotal: Subpart A 0
0
0 $0





2010 8,180






Delta -8,180




















SUBPART B: STANDARD DESIGN CERTIFICATIONS (DCs)

NRC expects 4 DC applications over the next 3 years. (mPower, NuScale, Westinghouse SMR, APR1400 (4/3=1.3333)










Section Number of Respondents Annually Responses per Respondent Annually Total Responses Annually Burden per Response Total Annual Burden Hours Estimate Annual Cost @ $274/hr

52.45 – Burden covered under 10 CFR 52.46 and 52.47 n/a n/a n/a n/a n/a n/a

52.46 – Burden covered under 10 CFR 50.33 (a) – (c) and 50.33 (j), approved by OMB under Clearance No. 3150-0011 n/a n/a n/a n/a n/a n/a

52.47 (a), except (a)(6) & (a)(27) 1.333 1 1.333 35,300 47,055 $12,893,043

52.47(a)(6) – Burden covered under 10 CFR 20.1406, approved by OMB under Clearance No. 3150-0014 n/a n/a n/a n/a n/a n/a

52.47(a)(27) 1.333 1 1.333 45,400 60,518 $16,581,987

52.47(b)(1) 1.333 1 1.333 25,300 33,725 $9,240,623

52.47(b)(2) – Burden covered under 10 CFR 51.55, approved by OMB under Clearance No. 3150-0021 n/a n/a n/a n/a n/a n/a

52.47(c)(1) – Burden covered under 10 CFR 52.47(a) and 52.47(b) n/a n/a n/a n/a n/a n/a

52.47(c)(2) – Burden covered under 10 CFR 52.47(a) and 52.47(b) n/a n/a n/a n/a n/a n/a

52.51 – Burden covered under 10 CFR 52.47(a) n/a n/a n/a n/a n/a n/a

52.57(a) JLD4: only applies to applications for renewals of DCs. ABWR applications already submitted 0 0 0 10,000 0 $0

52.63(b)(1) – Burden covered under 10 CFR 52.7 n/a n/a n/a n/a n/a n/a

Subtotal: Subpart B 1.3333
3.999
141,298 $38,715,652





2010 141,298


[1] Due to rounding, the total burden cost may not equal the sum of the costs of the individual requirements.


delta 0




















SUBPART C: COMBINED LICENSES (COLs)

NRC expects 0 COL applications over the next 3 years

1 COLs referencing DC applications (0.333 responses/year) and 0 referencing ESP applications (0 responses per year)

4 COLs under construction; 0 COLs in operation (refer to table 3, list of applicants)

NRC expects one uncompleted ITAAC notification and one all ITAAC complete notification over the next 3 years (1/3=0.3333)

Section Number of Respondents Annually Responses per Respondent Annually Total Responses Annually Burden per Response Total Annual Burden Hours Estimate Annual Cost @ $274/hr

52.75 – Burden covered under 10 CFR 50.30, approved by OMB under Clearance No. 3150-0011 n/a n/a n/a n/a n/a n/a

52.77 – Burden covered under 10 CFR 50.33, approved by OMB under Clearance No. 3150-0011 n/a n/a n/a n/a n/a n/a

52.79(a), except (a)(45) & (a)(46) – COL that doesn’t reference any other Part 52 product 0 0 0 58,420 0 $0

52.79(a)(45) – Burden covered under 10 CFR 20.1406, approved by OMB under Clearance No. 3150-0014 n/a n/a n/a n/a n/a n/a

52.79(a)(46) 0 0 0 54,000 0 $0

52.79(b) – COL that references an ESP 0 0 0 102,368 0 $0

52.79(c) – COL that references a design approval 0 0 0 46,460 0 $0

52.79(d) – COL that references a DC 0.3333 1 0.3333 31,460 10,486 $2,873,059

52.79(e) – COL that references a manufactured reactor 0 0 0 36,460 0 $0

52.79(b) & (d) – COL that references both an ESP and a DC 0 1 0 26,560 0 $0

52.80(a) – 40,000 hours for applications which do not reference a DC 0 0 0 40,000 0 $0

10,000 hours for applications that do not reference a certified design 0 0 0 10,000 0 $0

52.80(b) – Burden covered under 10 CFR 51.50, approved by OMB under Clearance No. 3150-0021 n/a n/a n/a n/a n/a n/a

52.80(c) – Burden covered under 10 CFR 50.10(d)(3), approved by OMB under Clearance No. 3150-0011 n/a n/a n/a n/a n/a n/a

52.93(a) – Burden covered under 10 CFR 52.7 n/a n/a n/a n/a n/a n/a

52.93(b) – Burden covered under 10 CFR 52.39 n/a n/a n/a n/a n/a n/a

52.93(c) – Burden covered under 10 CFR 52.171 n/a n/a n/a n/a n/a n/a

52.99(a) - See Table 3 JLD4: 4 plants with an update once every 6 months on ITAAC status 4 2 8 20 160 $43,840

52.99(c)(1)- ITAAC Closure Notification JLD4: 4 plants closing out ~150 ITAAC per year 4 250 1000 40 40,000 $10,960,000

52.99(c)(2)- ITAAC Post-closure Notifications 4 6 24 20 480 $131,520

52.99(c)(3)- Uncompleted ITAAC Notifications 0.33 1 0.33 40 13 $3,617

52.99(c)(4)- All ITAAC Complete Notifications 0.33 1 0.33 8 3 $723

52.99(d)(1) & 52.99(d)(2) – Burden covered under 10 CFR 52.39 (variances) and 52.7 (exemptions) n/a n/a n/a n/a n/a n/a

52.103(a) JLD4: Vogtle Unit 3 ~ Q3 CY2016 0.33 1 0.33 10 3 $904

52.110(a) 0 0 0 20 0 $0

52.110(d) 0 0 0 3,000 0 $0

52.110(g) 0 0 0 20 0 $0

52.110(h)(3) 0 0 0 20 0 $0

52.110(h)(4) 0 0 0 20 0 $0

Subtotal: Subpart C 13.3233
1033.3233
51,145 $14,013,664





2010 41,396






delta 9,749




















SUBPART E: STANDARD DESIGN APPROVALS

NRC expects 0 design approval applications over the next 3 years.










Section Number of Respondents Annually Responses per Respondent Annually Total Responses Annually Burden per Response Total Annual Burden Hours Estimate Annual Cost @ $274/hr

52.135 – Burden covered under 10 CFR 50.30, approved by OMB under Clearance No. 3150-0011 n/a n/a n/a n/a n/a n/a

52.136 – Burden covered under 10 CFR 50.33(a) – (d) and 50.33 (j), approved by OMB under Clearance No. 3150-0011 n/a n/a n/a n/a n/a n/a

52.137(a), except (a)(6) & (a)(25) JLD4: this is for SDAs. Checked RIS responses to FY2012 RIS on SMRs and saw no intention for submission of SDA by any vendors 0 0 0 42,000 0 $0

52.137(a)(6) – Burden covered under 10 CFR 20.1406, approved by OMB under Clearance No. 3150-0014 n/a n/a n/a n/a n/a n/a

52.137(a)(25) JLD4: this is for SDAs. Checked RIS responses to FY2012 RIS on SMRs and saw no intention for submission of SDA by any vendors 0 0 0 54,000 0 $0

Subtotal: Subpart E 0
0
0 0





2010 0






delta 0


SUBPART F: MANUFACTURING LICENSES

NRC expects 0 manufacturing license applications over the next 3 years.










Section Number of Respondents Annually Responses per Respondent Annually Total Responses Annually Burden per Response Total Annual Burden Hours Estimate Annual Cost @ $274/hr

52.155 – Burden covered under 10 CFR 50.30, approved by OMB under Clearance No. 3150-0011 n/a n/a n/a n/a n/a n/a

52.156 – Burden covered under 10 CFR 50.33(a) – (d) and 50.33(j), approved by OMB under Clearance No. 3150-0011 n/a n/a n/a n/a n/a n/a

52.157, except 52.157(f)(9) & (f)(31) 0 0 0 50,000 0 $0

52.157(f)(9) – Burden covered under 10 CFR 20.1406, approved by OMB under Clearance No. 3150-0014 n/a n/a n/a n/a n/a n/a

52.157(f)(31) 0 0 0 54,000 0 $0

52.158(a) 0 0 0 30,000 0 $0

52.158(b) – Burden covered under 10 CFR 51.54, approved by OMB under Clearance No. 3150-0021 n/a n/a n/a n/a n/a n/a

52.171(b) – Burden covered under 10 CFR 50.90 & 50.91, approved by OMB under Clearance No 3150-0011 n/a n/a n/a n/a n/a n/a

52.177 0 0 0 10,000 0 $0

Subtotal: Subpart F 0
0
0 0





2010 0






delta 0




















NRC expects to promulgate 3 DCRs over the next 3 years- US-APWR, EPR, ESBWR

APPENDIX A: ABWR DESIGN CERTIFICATION RULE

NRC expects 0 applicants to reference the ABWR Design Certification Rule over the next 3 years.

NRC expects 0 COLs referencing Appendix A under construction over the next 3 years

Section Number of Respondents Annually Responses per Respondent Annually Total Responses Annually Burden per Response Total Annual Burden Hours Estimate Annual Cost @ $274/hr

JLD4: where is this covered in 52.99? IX.A.2 – Burden covered under 10 CFR 52.99 n/a n/a n/a n/a n/a n/a

X.B.1 - COL departures from DC 0 1 0 8 0 $0

X.B.2 - COL DCD updates 0 1 0 500 0 $0

X.B.3.c – Burden covered under X.B.1 and X.B.2 n/a n/a n/a n/a n/a n/a





































APPENDIX B: SYSTEM 80+ DESIGN CERTIFICATION RULE

NRC expects 0 applicants to reference the System 80+ Design Certification Rule over the next 3 years.

NRC expects 0 COLs referencing Appendix B under construction over the next 3 years

Section Number of Respondents Annually Responses per Respondent Annually Total Responses Annually Burden per Response Total Annual Burden Hours Estimate Annual Cost @ $274/hr

JLD4: where is this covered in 52.99? IX.A.2 – Burden covered under 10 CFR 52.99 n/a n/a n/a n/a n/a n/a

X.B.1 0 1 0 8 0 $0

X.B.2 0 1 0 500 0 $0

X.B.3.c – Burden covered under X.B.1 and X.B.2 n/a n/a n/a n/a n/a n/a



















APPENDIX C: AP600 DESIGN CERTIFICATION RULE

NRC expects 0 applicants to reference the AP600 Design Certification Rule over the next 3 years.

NRC expects 0 COLs referencing Appendix C under construction over the next 3 years

Section Number of Respondents Annually Responses per Respondent Annually Total Responses Annually Burden per Response Total Annual Burden Hours Estimate Annual Cost @ $274/hr

JLD4: where is this covered in 52.99? IX.A.2 – Burden covered under 10 CFR 52.99 n/a n/a n/a n/a n/a n/a

X.B.1 0 1 0 8 0 $0

X.B.2 0 1 0 500 0 $0

X.B.3.c – Burden covered under X.B.1 and X.B.2 n/a n/a n/a n/a n/a n/a



















APPENDIX D: AP1000 DESIGN CERTIFICATION RULE

NRC expects 0 applicants to reference the AP1000 Design Certification Rule over the next 3 years.

NRC expects 4 COLs referencing Appendix D under construction over the next 3 years

Section Number of Respondents Annually Responses per Respondent Annually Total Responses Annually Burden per Response Total Annual Burden Hours Estimate Annual Cost @ $274/hr

JLD4: where is this covered in 52.99? IX.A.2 – Burden covered under 10 CFR 52.99 n/a n/a n/a n/a n/a n/a

X.B.1 4 2 8 8 64 $17,536

X.B.2 4 1 4 500 2,000 $548,000

X.B.3.c – Burden covered under X.B.1 and X.B.2 n/a n/a n/a n/a n/a n/a










Subtotal: Appendices 4
12
2,064 $565,536





2010 0






delta 2,064











[1] Due to rounding, the total burden cost may not equal the sum of the costs of the individual requirements.

























APPENDIX N: STANDARDIZATION OF NUCLEAR POWER PLANT DESIGNS:

COMBINED LICENSES TO CONSTRUCT AND OPERATE NUCLEAR POWER REACTORS OF IDENTICAL DESIGN AT MULTIPLE SITES

NRC expects 0 combined license applicants to use Appendix N over the next 3 years.










Section Number of Respondents Annually Responses per Respondent Annually Total Responses Annually Burden per Response Total Annual Burden Hours Estimate Annual Cost @ $274/hr

Paragraph 2 0 0 0 10 0 $0

Paragraph 3 0 0 0 40 0 $0

Paragraph 4 – Burden covered under 10 CFR 52.80(c)







Subtotal: Appendix N 0
0
0 $0










Total Part 52 Reporting Burden 19.6566
1,050
194,867 $53,393,492





2010 191,774






delta 3,093














































































































TABLE 2



ANNUAL RECORDKEEPING BURDEN



10 CFR PART 52



recordkeepers under 52.63(b)(2) and 52.63(b) are noted as the same record keeper and are only counted once



Section Number of Record keepers Burden Hrs. per Record keeper Total Annual Burden Hours Estimate Annual Cost @ $274/hr



7/3=2.333



0/3=0



(4/3=1.333)
Section 2010 annual burden delta
52.47 2.333 500 1,167 $319,621
52.47 666.5 500
52.57(a)-renewals 0 500 0 $0
52.57(a)-renewals 166.5 -167
52.63(b)(2) 1.333 1,500 2,000 $547,863
52.63(b)(2) 8499 -6,500
52.63(c) & 52.73(b) 1.333 500 667 $182,621
52.63(c) & 52.73(b) 2833 -2,167









APPENDIX A: ABWR DESIGN CERTIFICATION RULE



NRC expects 1 applicant to maintain records for the ABWR Design Certification Rule over the next 3 years.



Section Number of Record keepers Burden Hrs. per Record keeper Total Annual Burden Hours Estimate Annual Cost @ $274/hr



X.A.1 1 34 34 $9,316



X.A.2 – Burden covered under 10 CFR 50.71(e)







X.A.3 – Burden covered under 10 CFR 50.59(d)







X.A.4.a - Burden approved under 3150-0210 * 1 1 3 $822



X.A.4.b - Burden approved under 3150-0210 * 1 1 3 $822












[1] Due to rounding, the total burden cost may not equal the sum of the costs of the individual requirements.







* Burden covered under, U.S Advanced Boiling Water Reactor Aircraft Impact Design Certification Amendment (3150-0210). Following the approval of this renewal, this clearance 3150-0210 will be discontinued.
















APPENDIX B: SYSTEM 80+ DESIGN CERTIFICATION RULE



NRC expects 1 applicant to maintain records for the System 80+ Design Certification Rule over the next 3 years.



Section Number of Record keepers Burden Hrs. per Record keeper Total Annual Burden Hours Estimate Annual Cost @ $274/hr



X.A.1 1 34 34 $9,316



X.A.2 – Burden covered under 10 CFR 50.71(e)







X.A.3 – Burden covered under 10 CFR 50.59(d)
















APPENDIX C: AP600 DESIGN CERTIFICATION RULE



NRC expects 1 applicant to maintain records for the AP600 Design Certification Rule over the next 3 years.



Section Number of Record keepers Burden Hrs. per Record keeper Total Annual Burden Hours Estimate Annual Cost @ $274/hr



X.A.1 1 34 34 $9,316



X.A.2 – Burden covered under 10 CFR 50.71(e)







X.A.3 – Burden covered under 10 CFR 50.59(d)







APPENDIX D: AP1000 DESIGN CERTIFICATION RULE



NRC expects 1 applicant to maintain records for the AP1000 Design Certification Rule over the next 3 years.



Section Number of Record keepers Burden Hrs. per Record keeper Total Annual Burden Hours Estimate Annual Cost @ $274/hr



X.A.1 1 34 34 $9,316



X.A.2 – Burden covered under 10 CFR 50.71(e)







X.A.3 – Burden covered under 10 CFR 50.59(d)
















Total Part 52 Recordkeeping Burden 9.666
3,975 $1,089,013



Total Storage Cost


$435.61





















10 CFR Part 52 Burden








Current 2010 Delta




Total Number of Respondents: 20 20 0




Total Number of Responses: 1,050 67 983.3223




Total Number of Recordkeepers: 10 11 -1




Total Reporting Burden Hours: 194,867 192,830 2036.758




Total Recordkeeping Burden Hours: 3,975 12,325 -8350.5




Total Burden Hours: 198,842 205,155 (6,313)




Total Cost: $54,482,940 $52,447,321 $2,035,619













[1] Due to rounding, the total burden cost may not equal the sum of the costs of the individual requirements.

























TABLE 3

ANNUAL REPORTING BURDEN UNDER 10 CFR 52.99(a)

10 CFR PART 52

NOTE: BELLEFONTE, CALLAWAY, NINE MILE, GRAND GULF, RIVER BEND reviews suspended and removed







Licensee 2014 2015 2016




South Texas (2 units) N N N




Vogtle (2 units) A A Z




Lee (2 units) N N N




Harris (2 units) N N N




Summer (2 units) A A A




Levy County (2 units) N N N




Turkey Point (2 units) N N N




Calvert Cliffs (1 unit) N N N




Bell Bend (1 unit) N N N




North Anna (1 unit) N N N




Fermi (1 unit) N N N




Comanche Peak (2 units) N N N













Total Submittals 0 0 0













Model Year A Year A+1 Year A+2 Year Z-1 Year Z Year Z+1

Number of submittals per year per unit 1 2 2 12 12 12










Note: N = license not yet issued, A = license issued, Z = initial fuel load







Note: Continue ITAAC complete notifications 12 per year until notification of all ITAAC met







Note: Assumes that each unit will submit a separate report








Sheet 2: Sheet2

Reviews






CY 2014 2015 2016



COLA JLD4: STP(1) + Turkey Point (0.5) + Harris (0.5) + Calvert (1) + Bell Bend (1) + Fermi (1) + North Anna (1) + Comanche Peak (1) 6 JLD4: STP(0.5) + Calvert (0.5) + Bell Bend (0.5) + Comanche Peak (1) 2.5 0



ESP JLD4: Blue Castle (1) + PSEG (1) 2 JLD4: Blue Castle (1) 1 0



DCA JLD4: West SMR (1) + mPower (0.5) + APR (1) + APWR(1) + EPR (1) 4.5 JLD4: EPR (0.5) + USAPWR (1) + APR (1) + mPower (1) + NuScale (0.5) + West SMR (1) 5 JLD4: APR(1) + mPower(1) + NuScale (1) + West SMR (1) + APWR (0.5) 4.5



DCR 2 2 0.25











COLs under construction
assumed 4 year construction end





Start Date





Vogtle 3/30/2012 3/30/2016




Summer 3/30/2012 3/30/2016












52.99[c][1] V1 V2 S3 S4


2014 50 100 100 100


2015 250 200 200 200


2016 600 400 400 400
reports/yr 1000
2017 fuel load 200 200 200
4 respondents 250 per year
2018
fuel load fuel load fuel load










Total 900 900 900 900










AP1000 ~900 ITAAC





















52.99[c][2] V1 V2 S3 S4


2014 6 6 6 6


2015 6 6 6 6
reports/yr 24
2016 6 6 6 6
4 respondents 6 per year
2017






2018






NRC ESTIMATES SIX REPORTS PER LICENSEE PER YEAR OF CONSTRUCTION


















52.99 [c][3] Vogtle 3 only potential schedule lag to miss fuel load



1/3=0.333








52.99 [c][4] Vogtle 3 only plant scheduled for 103(g)



1/3=0.333
File Typeapplication/vnd.openxmlformats-officedocument.spreadsheetml.sheet
File Modified0000-00-00
File Created0000-00-00

© 2024 OMB.report | Privacy Policy