PRC-025-1 Generator Relay Loadability

1 of 22


A. Introduction


1. Title: Generator Relay Loadability


2. Number: PRC-025-1


Purpose: To set load-responsive protective relays associated with generation Facilities at a level to prevent unnecessary tripping of generators during a system disturbance for conditions that do not pose a risk of damage to the associated equipment.


3. Applicability:


3.1. Functional Entities:


3.1.1 Generator Owner that applies load-responsive protective relays at the terminals of the Elements listed in 3.2, Facilities.


3.1.2 Transmission Owner that applies load-responsive protective relays at the terminals of the Elements listed in 3.2, Facilities.


3.1.3 Distribution Provider that applies load-responsive protective relays at the terminals of the Elements listed in 3.2, Facilities.


3.2. Facilities: The following Elements associated with Bulk Electric System (BES) generating units and generating plants, including those generating units and generating plants identified as Blackstart Resources in the Transmission Operator’s system restoration plan:


3.2.1 Generating unit(s).


3.2.2 Generator step-up (i.e., GSU) transformer(s).


3.2.3 Unit auxiliary transformer(s) (UAT) that supply overall auxiliary power necessary to keep generating unit(s) online.1


3.2.4 Elements that connect the GSU transformer(s) to the Transmission system that are used exclusively to export energy directly from a BES generating unit or generating plant. Elements may also supply generating plant loads.


3.2.5 Elements utilized in the aggregation of dispersed power producing resources.


4. Background:


After analysis of many of the major disturbances in the last 25 years on the North American interconnected power system, generators have been found to have tripped for conditions that did not apparently pose a direct risk to those generators and associated equipment within the time period where the tripping occurred. This tripping has often been determined to have expanded the scope and/or extended the duration of that


1 These transformers are variably referred to as station power, unit auxiliary transformer(s) (UAT), or station service transformer(s) used to provide overall auxiliary power to the generator station when the generator is running. Loss

of these transformers will result in removing the generator from service. Refer to the PRC-025-1 Guidelines and

Technical Basis for more detailed information concerning unit auxiliary transformers.


PRC-025-1 Generator Relay Loadability


disturbance. This was noted to be a serious issue in the August 2003 “blackout” in the northeastern North American continent.2


During the recoverable phase of a disturbance, the disturbance may exhibit a “voltage disturbance” behavior pattern, where system voltage may be widely depressed and may fluctuate. In order to support the system during this transient phase of a disturbance,

this standard establishes criteria for setting load-responsive protective relays such that individual generators may provide Reactive Power within their dynamic capability during transient time periods to help the system recover from the voltage disturbance. The premature or unnecessary tripping of generators resulting in the removal of dynamic Reactive Power exacerbates the severity of the voltage disturbance, and as a result changes the character of the system disturbance. In addition, the loss of Real Power could initiate or exacerbate a frequency disturbance.


5. Effective Date: See Implementation Plan


B. Requirements and Measures


R1. Each Generator Owner, Transmission Owner, and Distribution Provider shall apply settings that are in accordance with PRC-025-1 – Attachment 1: Relay Settings, on each load-responsive protective relay while maintaining reliable fault protection. [Violation Risk Factor: High] [Time Horizon: Long-Term Planning]


M1. For each load-responsive protective relay, each Generator Owner, Transmission Owner, and Distribution Provider shall have evidence (e.g., summaries of calculations, spreadsheets, simulation reports, or setting sheets) that settings were applied in accordance with PRC-025-1 – Attachment 1: Relay Settings.


C. Compliance


1. Compliance Monitoring Process


1.1. Compliance Enforcement Authority


As defined in the NERC Rules of Procedure, “Compliance Enforcement Authority” means NERC or the Regional Entity in their respective roles of monitoring and enforcing compliance with the NERC Reliability Standards.


1.2. Evidence Retention


The following evidence retention periods identify the period of time an entity is required to retain specific evidence to demonstrate compliance. For instances where the evidence retention period specified below is shorter than the time since the last audit, the Compliance Enforcement Authority (CEA) may ask an entity to provide other evidence to show that it was compliant for the full time period since the last audit.


2 Interim Report: Causes of the August 14th Blackout in the United States and Canada, U.S.-Canada Power System

Outage Task Force, November 2003 (http://www.nerc.com/docs/docs/blackout/814BlackoutReport.pdf)


2 of 22


PRC-025-1 Generator Relay Loadability


The Generator Owner, Transmission Owner, and Distribution Provider shall keep data or evidence to show compliance as identified below unless directed by its CEA to retain specific evidence for a longer period of time as part of an investigation:


The Generator Owner, Transmission Owner, and Distribution Provider shall retain evidence of Requirement R1 and Measure M1 for the most recent three calendar years.

If a Generator Owner, Transmission Owner, or Distribution Provider is found non-compliant, it shall keep information related to the non- compliance until mitigation is complete and approved or for the time specified above, whichever is longer.


The CEA shall keep the last audit records and all requested and submitted subsequent audit records.


1.3. Compliance Monitoring and Assessment Processes


Compliance Audit Self-Certification Spot Checking

Compliance Investigation


Self-Reporting


Complaint


1.4. Additional Compliance Information


None


3 of 22


PRC-025-1 Generator Relay Loadability


Table of Compliance Elements



R #


Time

Horizon


VRF


Violation Severity Levels


Lower VSL


Moderate VSL


High VSL


Severe VSL


R1


Long-Term

Planning


High


N/A


N/A


N/A


The Generator Owner, Transmission Owner,

and Distribution Provider did not apply settings in accordance with PRC-

025-1 – Attachment 1: Relay Settings, on an applied load-responsive protective relay.


D. Regional Variances


None.


E. Interpretations


None.


F. Associated Documents


NERC System Protection and Control Subcommittee, July 2010, “Power Plant and Transmission System Protection

Coordination.”


IEEE C37.102-2006, “Guide for AC Generator Protection.”


4 of 22


PRC-025-1 Generator Relay Loadability


PRC-025-1 – Attachment 1: Relay Settings


Introduction


This standard does not require the Generator Owner, Transmission Owner, or Distribution Provider to use any of the protective functions listed in Table 1. Each Generator Owner, Transmission Owner, and Distribution Provider that applies load-responsive protective relays on their respective Elements listed in 3.2, Facilities, shall use one of the following Options in Table

1, Relay Loadability Evaluation Criteria (“Table 1”), to set each load-responsive protective relay element according to its application and relay type. The bus voltage is based on the criteria for the various applications listed in Table 1.


Generators


Synchronous generator relay pickup setting criteria values are derived from the unit’s maximum gross Real Power capability, in megawatts (MW), as reported to the Transmission Planner, and the unit’s Reactive Power capability, in megavoltampere-reactive (Mvar), is determined by calculating the MW value based on the unit’s nameplate megavoltampere (MVA) rating at rated power factor. If different seasonal capabilities are reported, the maximum capability shall be used for the purposes of this standard.


Asynchronous generator relay pickup setting criteria values (including inverter-based installations) are derived from the site’s aggregate maximum complex power capability, in MVA, as reported to the Transmission Planner, including the Mvar output of any static or dynamic reactive power devices.


For the application case where synchronous and asynchronous generator types are combined on a generator step-up transformer or on Elements that connect the generator step-up (GSU) transformer(s) to the Transmission system that are used exclusively to export energy directly

from a BES generating unit or generating plant (Elements may also supply generating plant loads.), the pickup setting criteria shall be determined by vector summing the pickup setting criteria of each generator type, and using the bus voltage for the given synchronous generator application and relay type.


Transformers


Calculations using the GSU transformer turns ratio shall use the actual tap that is applied (i.e., in service) for GSU transformers with deenergized tap changers (DETC). If load tap changers (LTC) are used, the calculations shall reflect the tap that results in the lowest generator bus

voltage. When the criterion specifies the use of the GSU transformer’s impedance, the nameplate impedance at the nominal GSU transformer turns ratio shall be used.


Applications that use more complex topology, such as generators connected to a multiple winding transformer, are not directly addressed by the criteria in Table 1. These topologies can result in complex power flows, and may require simulation to avoid overly conservative assumptions to simplify the calculations. Entities with these topologies should set their relays in such a way that they do not operate for the conditions being addressed in this standard.


5 of 22


PRC-025-1 Generator Relay Loadability


Multiple Lines


Applications that use more complex topology, such as multiple lines that connect the generator step-up (GSU) transformer(s) to the Transmission system that are used exclusively to export energy directly from a BES generating unit or generating plant (Elements may also supply generating plant loads) are not directly addressed by the criteria in Table 1. These topologies can result in complex power flows, and it may require simulation to avoid overly conservative assumptions to simplify the calculations. Entities with these topologies should set their relays in such a way that they do not operate for the conditions being addressed in this standard.


Exclusions


The following protection systems are excluded from the requirements of this standard:

1. Any relay elements that are in service only during start up.

2. Load-responsive protective relay elements that are armed only when the generator is disconnected from the system, (e.g., non-directional overcurrent elements used in conjunction with inadvertent energization schemes, and open breaker flashover schemes).

3. Phase fault detector relay elements employed to supervise other load-responsive phase distance elements (e.g., in order to prevent false operation in the event of a loss of potential) provided the distance element is set in accordance with the criteria outlined in the standard.

4. Protective relay elements that are only enabled when other protection elements fail (e.g., overcurrent elements that are only enabled during loss of potential conditions).

5. Protective relay elements used only for Special Protection Systems that are subject to one or more requirements in a NERC or Regional Reliability Standard.

6. Protection systems that detect generator overloads that are designed to coordinate with the generator short time capability by utilizing an extremely inverse characteristic set to operate no faster than 7 seconds at 218% of fullload current (e.g., rated armature current), and prevent operation below 115% of full-load current.3

7. Protection systems that detect transformer overloads and are designed only to respond in time periods which allow an operator 15 minutes or greater to respond to overload conditions.


Table 1


Table 1 beginning on the next page is structured and formatted to aid the reader with identifying an option for a given load-responsive protective relay.


The first column identifies the application (e.g., synchronous or asynchronous generators, generator step-up transformers, unit auxiliary transformers, Elements that connect the GSU transformer(s) to the Transmission system that are used exclusively to export energy directly from a BES generating unit or generating plant. Elements may also supply generating plant


3 IEEE C37.102-2006, “Guide for AC Generator Protection,” Section 4.1.1.2.


6 of 22


PRC-025-1 Generator Relay Loadability


loads). Dark blue horizontal bars, excluding the header which repeats at the top of each page, demarcate the various applications.


The second column identifies the load-responsive protective relay (e.g., 21, 50, 51, 51V-C, 51V- R, or 67) according to the applied application in the first column. A light blue horizontal bar between the relay types is the demarcation between relay types for a given application. These light blue bars will contain no text.


The third column uses numeric and alphabetic options (i.e., index numbering) to identify the available options for setting load-responsive protective relays according to the application and applied relay type. Another, shorter, light blue bar contains the word “OR,” and reveals to the reader that the relay for that application has one or more options (i.e., “ways”) to determine the bus voltage and pickup setting criteria in the fourth and fifth column, respectively. The bus voltage column and pickup setting criteria columns provide the criteria for determining an appropriate setting.


The table is further formatted by shading groups of relays associated with asynchronous generator applications. Synchronous generator applications and the unit auxiliary transformer applications are not shaded. Also, intentional buffers were added to the table such that similar options, as possible, would be paired together on a per page basis. Note that some applications may have an additional pairing that might occur on adjacent pages.


7 of 22


PRC-025-1 Generator Relay Loadability



Table 1. Relay Loadability Evaluation Criteria


Application


Relay Type


Option

Bus Voltage4


Pickup Setting Criteria


Synchronous generating unit(s), or Elements utilized in the aggregation of dispersed power producing resources


Phase distance relay (21) – directional toward the Transmission

system


1a


Generator bus voltage corresponding to 0.95 per unit of the high-side nominal voltage times the turns ratio of the generator step-up transformer

The impedance element shall be set less than the calculated impedance derived from 115% of:

(1) Real Power output – 100% of the gross MW capability reported to the Transmission Planner, and

(2) Reactive Power output – 150% of the MW value, derived from the generator nameplate MVA rating at rated power factor

OR


1b

Calculated generator bus voltage corresponding to 0.85 per unit nominal voltage on the high-side terminals of the generator step-up transformer (including the transformer turns ratio and impedance)


The impedance element shall be set less than the calculated impedance derived from 115% of:

(1) Real Power output – 100% of the gross MW capability reported to the Transmission Planner, and

(2) Reactive Power output – 150% of the MW value, derived from the generator nameplate MVA rating at rated power factor

OR


1c

Simulated generator bus voltage coincident with the highest Reactive Power output achieved during field- forcing in response to a 0.85 per unit nominal voltage on the high-side terminals of the generator step-up transformer prior to field-forcing


The impedance element shall be set less than the calculated impedance derived from 115% of:

(1) Real Power output – 100% of the gross MW capability reported to the Transmission Planner, and

(2) Reactive Power output –100% of the maximum gross Mvar output during field-forcing as determined by simulation


The same application continues on the next page with a different relay type


Shape1

4 Calculations using the generator step-up (GSU) transformer turns ratio shall use the actual tap that is applied (i.e., in service) for GSU transformers with deenergized tap changers (DETC). If load tap changers (LTC) are used, the calculations shall reflect the tap that results in the lowest generator bus voltage. When the criterion specifies the use of the GSU transformer’s impedance, the nameplate impedance at the nominal GSU turns ratio shall be used.


8 of 22


PRC-025-1 Generator Relay Loadability



Table 1. Relay Loadability Evaluation Criteria


Application


Relay Type


Option

Bus Voltage4


Pickup Setting Criteria


Synchronous generating unit(s), or Elements utilized in the aggregation of dispersed power producing resources


Phase time overcurrent relay (51) or (51V-R) – voltage-restrained


2a


Generator bus voltage corresponding to 0.95 per unit of the high-side nominal voltage times the turns ratio of the generator step-up transformer

The overcurrent element shall be set greater than 115% of the calculated current derived from:

(1) Real Power output – 100% of the gross MW capability reported to the Transmission Planner, and

(2) Reactive Power output – 150% of the MW value, derived from the generator nameplate MVA rating at rated power factor

OR


2b

Calculated generator bus voltage corresponding to 0.85 per unit nominal voltage on the high-side terminals of the generator step-up transformer (including the transformer turns ratio and impedance)


The overcurrent element shall be set greater than 115% of the calculated current derived from:

(1) Real Power output – 100% of the gross MW capability reported to the Transmission Planner, and

(2) Reactive Power output – 150% of the MW value, derived from the generator nameplate MVA rating at rated power factor

OR


2c

Simulated generator bus voltage coincident with the highest Reactive Power output achieved during field- forcing in response to a 0.85 per unit nominal voltage on the high-side terminals of the generator step-up transformer prior to field-forcing


The overcurrent element shall be set greater than 115% of the calculated current derived from:

(1) Real Power output – 100% of the gross MW capability reported to the Transmission Planner or, and

(2) Reactive Power output –100% of the maximum gross Mvar output during field-forcing as determined by simulation


The same application continues with a different relay type below

Phase time overcurrent relay (51V-C) – voltage controlled (Enabled to operate as a function of voltage)


3


Generator bus voltage corresponding to 1.0 per unit of the high-side nominal voltage times the turns ratio of the generator step-up transformer


Voltage control setting shall be set less than 75% of the calculated generator bus voltage


A different application starts on the next page


Shape2

9 of 22


PRC-025-1 Generator Relay Loadability


shall be set less than the calculated

130% of the maximum aggregate at rated power factor (including the

c or dynamic reactive power devices)


t shall be set greater than 130% of the ed from the maximum aggregate

at rated power factor (including the

c or dynamic reactive power devices)


hall be set less than 75% of the voltage



Table 1. Relay Loadability Evaluation Criteria


Application


Relay Type


Option

Bus Voltage4



Asynchronous generating unit(s) (including inverter- based installations), or Elements utilized in the aggregation of dispersed power producing resources

Phase distance relay (21) – directional toward the Transmission

system


4


Generator bus voltage corresponding to 1.0 per unit of the high-side nominal voltage times the turns ratio of the generator step-up transformer


The impedance element impedance derived from nameplate MVA output Mvar output of any stati


Phase time overcurrent relay (51) or (51V-R) – voltage-restrained


5

Generator bus voltage corresponding to 1.0 per unit of the high-side nominal voltage times the turns ratio of the generator step-up transformer

The overcurrent elemen calculated current deriv nameplate MVA output Mvar output of any stati


Phase time overcurrent relay (51V-C) – voltage controlled (Enabled to operate as a function of voltage)


6


Generator bus voltage corresponding to 1.0 per unit of the high-side nominal voltage times the turns ratio of the generator step-up transformer


Voltage control setting s calculated generator bus


A different application starts on the next page


10 of 22


PRC-025-1 Generator Relay Loadability



Table 1. Relay Loadability Evaluation Criteria


Application


Relay Type


Option

Bus Voltage4


Pickup Setting Criteria


Generator step-up transformer(s) connected to synchronous generators


Phase distance relay (21) – directional toward the Transmission

system – installed

on generator-side of the GSU

transformer

If the relay is installed on the high-side of the GSU transformer use Option 14


7a


Generator bus voltage corresponding to 0.95 per unit of the high-side nominal voltage times the turns ratio of the generator step-up transformer

The impedance element shall be set less than the calculated impedance derived from 115% of:

(1) Real Power output – 100% of the aggregate generation gross

MW reported to the Transmission Planner, and

(2) Reactive Power output – 150% of the aggregate generation MW value, derived from the generator nameplate MVA rating at rated power factor

OR


7b


Calculated generator bus voltage corresponding to 0.85 per unit nominal voltage on the high-side terminals of the generator step-up transformer (including the transformer turns ratio and impedance)

The impedance element shall be set less than the calculated impedance derived from 115% of:

(1) Real Power output – 100% of the aggregate generation gross

MW reported to the Transmission Planner, and

(2) Reactive Power output – 150% of the aggregate generation MW value, derived from the generator nameplate MVA rating at rated power factor

OR


7c


Simulated generator bus voltage coincident with the highest Reactive Power output achieved during field- forcing in response to a 0.85 per unit nominal voltage on the high-side terminals of the generator step-up transformer prior to field-forcing

The impedance element shall be set less than the calculated impedance derived from 115% of:

(1) Real Power output – 100% of the aggregate generation gross

MW reported to the Transmission Planner, and

(2) Reactive Power output –100% of the aggregate generation maximum gross Mvar output during field-forcing as determined by simulation


The same application continues on the next page with a different relay type


11 of 22


PRC-025-1 Generator Relay Loadability



Table 1. Relay Loadability Evaluation Criteria


Application


Relay Type


Option

Bus Voltage4


Pickup Setting Criteria


Generator step-up transformer(s) connected to synchronous generators


Phase time overcurrent relay (51) – installed on generator-side of the GSU transformer

If the relay is installed on the high-side of the GSU transformer use Option 15


8a


Generator bus voltage corresponding to 0.95 per unit of the high-side nominal voltage times the turns ratio of the generator step-up transformer

The overcurrent element shall be set greater than 115% of the calculated current derived from:

(1) Real Power output – 100% of the aggregate generation gross

MW reported to the Transmission Planner, and

(2) Reactive Power output – 150% of the aggregate generation MW value, derived from the generator nameplate MVA rating at rated power factor

OR


8b


Calculated generator bus voltage corresponding to 0.85 per unit nominal voltage on the high-side terminals of the generator step-up transformer (including the transformer turns ratio and impedance)

The overcurrent element shall be set greater than 115% of the calculated current derived from:

(1) Real Power output – 100% of the aggregate generation gross

MW reported to the Transmission Planner, and

(2) Reactive Power output – 150% of the aggregate generation MW value, derived from the generator nameplate MVA rating at rated power factor

OR


8c


Simulated generator bus voltage coincident with the highest Reactive Power output achieved during field- forcing in response to a 0.85 per unit nominal voltage on the high-side terminals of the generator step-up transformer prior to field-forcing

The overcurrent element shall be set greater than 115% of the calculated current derived from:

(1) Real Power output – 100% of the aggregate generation gross

MW reported to the Transmission Planner, and

(2) Reactive Power output –100% of the aggregate generation maximum gross Mvar output during field-forcing as determined by simulation


The same application continues on the next page with a different relay type


12 of 22


PRC-025-1 Generator Relay Loadability



Table 1. Relay Loadability Evaluation Criteria


Application


Relay Type


Option

Bus Voltage4


Pickup Setting Criteria


Generator step-up transformer(s) connected to synchronous generators


Phase directional time overcurrent relay (67) – directional toward the Transmission system – installed

on generator-side of the GSU

transformer

If the relay is installed on the high-side of the GSU transformer use Option 16


9a


Generator bus voltage corresponding to 0.95 per unit of the high-side nominal voltage times the turns ratio of the generator step-up transformer

The overcurrent element shall be set greater than 115% of the calculated current derived from:

(1) Real Power output – 100% of the aggregate generation gross

MW reported to the Transmission Planner, and

(2) Reactive Power output – 150% of the aggregate generation MW value, derived from the generator nameplate MVA rating at rated power factor

OR


9b


Calculated generator bus voltage corresponding to 0.85 per unit nominal voltage on the high-side terminals of the generator step-up transformer (including the transformer turns ratio and impedance)

The overcurrent element shall be set greater than 115% of the calculated current derived from:

(1) Real Power output – 100% of the aggregate generation gross

MW reported to the Transmission Planner, and

(2) Reactive Power output – 150% of the aggregate generation MW value, derived from the generator nameplate MVA rating at rated power factor

OR


9c


Simulated generator bus voltage coincident with the highest Reactive Power output achieved during field- forcing in response to a 0.85 per unit nominal voltage on the high-side terminals of the generator step-up transformer prior to field-forcing

The overcurrent element shall be set greater than 115% of the calculated current derived from:

(1) Real Power output – 100% of the aggregate generation gross

MW reported to the Transmission Planner, and

(2) Reactive Power output –100% of the aggregate generation maximum gross Mvar output during field-forcing as determined by simulation


A different application starts on the next page


13 of 22


PRC-025-1 Generator Relay Loadability


shall be set less than the calculated

130% of the maximum aggregate at rated power factor (including the

c or dynamic reactive power devices)


t shall be set greater than 130% of the ed from the maximum aggregate

at rated power factor (including the

c or dynamic reactive power devices)


The same application continues on the next page with a different relay type



Table 1. Relay Loadability Evaluation Criteria


Application


Relay Type


Option

Bus Voltage4



Generator step-up transformer(s) connected to asynchronous generators only (including inverter- based installations)

Phase distance relay (21) – directional toward the Transmission

system – installed

on generator-side of the GSU

transformer

If the relay is installed on the high-side of the GSU transformer use Option 17


10


Generator bus voltage corresponding to 1.0 per unit of the high-side nominal voltage times the turns ratio of the generator step-up transformer


The impedance element impedance derived from nameplate MVA output Mvar output of any stati


Phase time overcurrent relay (51) – installed on generator-side of the GSU transformer

If the relay is installed on the high-side of the GSU transformer use Option 18


11


Generator bus voltage corresponding to 1.0 per unit of the high-side nominal voltage times the turns ratio of the generator step-up transformer for overcurrent relays installed on the low-side


The overcurrent elemen calculated current deriv nameplate MVA output Mvar output of any stati



14 of 22


PRC-025-1 Generator Relay Loadability


Table 1. Relay Loadability Evaluation Criteria


Application Relay Type Option Bus Voltage4


Generator step-up transformer(s) connected to asynchronous generators only (including inverter- based installations)


Phase directional time overcurrent relay (67) – directional toward the Transmission system – installed

on generator-side of the GSU

transformer


If the relay is installed on the high-side of the GSU transformer use Option 19


Generator bus voltage corresponding

12 to 1.0 per unit of the high-side nominal voltage times the turns ratio

of the generator step-up transformer


The overcurrent element shall be set greater than 130% of the calculated current derived from the maximum aggregate nameplate MVA output at rated power factor (including the Mvar output of any static or dynamic reactive power devices)


A different application starts below


Unit auxiliary transformer(s) (UAT)


Phase time overcurrent relay (51) applied at the high-side terminals of the UAT, for which operation of the relay will cause the associated generator to trip.


13a


OR


13b


1.0 per unit of the winding nominal voltage of the unit auxiliary transformer


Unit auxiliary transformer bus voltage corresponding to the measured current


The overcurrent element shall be set greater than 150% of the calculated current derived from the unit auxiliary transformer maximum nameplate MVA rating


The overcurrent element shall be set greater than 150% of the unit auxiliary transformer measured current at the generator maximum gross MW capability reported to the Transmission Planner


A different application starts on the next page


15 of 22


PRC-025-1 Generator Relay Loadability



Table 1. Relay Loadability Evaluation Criteria


Application


Relay Type


Option

Bus Voltage4


Pickup Setting Criteria


Elements that connect the GSU transformer(s) to the Transmission system that are used exclusively to export energy directly from

a BES generating unit or generating plant. Elements may also

supply generating

plant loads. – connected to synchronous generators


Phase distance relay (21) – directional toward the Transmission

system – installed on the high-side of the GSU transformer


If the relay is installed on the generator-side of the GSU transformer

use Option 7


14a


0.85 per unit of the line nominal voltage

The impedance element shall be set less than the calculated impedance derived from 115% of:

(1) Real Power output – 100% of the aggregate generation gross

MW reported to the Transmission Planner, and

(2) Reactive Power output – 120% of the aggregate generation MW value, derived from the generator nameplate MVA rating at rated power factor

OR


14b


Simulated line voltage coincident with the highest Reactive Power output achieved during field-forcing in response to a 0.85 per unit nominal voltage on the high-side terminals of the generator step-up transformer prior to field-forcing

The impedance element shall be set less than the calculated impedance derived from 115% of:

(1) Real Power output – 100% of the aggregate generation gross

MW reported to the Transmission Planner, and

(2) Reactive Power output –100% of the aggregate generation maximum gross Mvar output during field-forcing as determined by simulation


The same application continues on the next page with a different relay type


16 of 22


PRC-025-1 Generator Relay Loadability



Table 1. Relay Loadability Evaluation Criteria


Application


Relay Type


Option

Bus Voltage4


Pickup Setting Criteria


Elements that connect the GSU transformer(s) to the Transmission system that are used exclusively to export energy directly from

a BES generating unit or generating plant. Elements may also

supply generating

plant loads. – connected to synchronous generators

Phase overcurrent supervisory element (50) – associated with current-based, communication- assisted schemes where the scheme is capable of tripping for loss of communications installed on the

high-side of the GSU transformer or phase time

overcurrent relay

(51) – installed on the high-side of the GSU transformer


If the relay is installed on the generator-side of the GSU transformer

use Option 8


15a


0.85 per unit of the line nominal voltage

The overcurrent element shall be set greater than 115% of the calculated current derived from:

(1) Real Power output – 100% of the aggregate generation gross

MW reported to the Transmission Planner, and

(2) Reactive Power output – 120% of the aggregate generation MW value, derived from the generator nameplate MVA rating at rated power factor

OR


15b


Simulated line voltage coincident with the highest Reactive Power output achieved during field-forcing in response to a 0.85 per unit nominal voltage on the high-side terminals of the generator step-up transformer prior to field-forcing


The overcurrent element shall be set greater than 115% of the calculated current derived from:

(1) Real Power output – 100% of the aggregate generation gross

MW reported to the Transmission Planner, and

(2) Reactive Power output –100% of the aggregate generation maximum gross Mvar output during field-forcing as determined by simulation


The same application continues on the next page with a different relay type


17 of 22


PRC-025-1 Generator Relay Loadability



Table 1. Relay Loadability Evaluation Criteria


Application


Relay Type


Option

Bus Voltage4


Pickup Setting Criteria


Elements that connect the GSU transformer(s) to the Transmission system that are used exclusively to export energy directly from

a BES generating unit or generating plant. Elements may also

supply generating

plant load. – connected to synchronous generators

Phase directional overcurrent supervisory element (67) – associated with current-based, communication- assisted schemes where the scheme is capable of tripping for loss of communications directional toward the Transmission system installed on the high-side of the GSU transformer or phase directional time overcurrent relay (67) – directional toward the Transmission system installed on the high-side of the GSU transformer


If the relay is installed on the generator-side of the GSU transformer

use Option 9


16a


0.85 per unit of the line nominal voltage

The overcurrent element shall be set greater than 115% of the calculated current derived from:

(1) Real Power output – 100% of the aggregate generation gross

MW reported to the Transmission Planner, and

(2) Reactive Power output – 120% of the aggregate generation MW value, derived from the generator nameplate MVA rating at rated power factor

OR


16b


Simulated line voltage coincident with the highest Reactive Power output achieved during field-forcing in response to a 0.85 per unit nominal voltage on the high-side terminals of the generator step-up transformer prior to field-forcing


The overcurrent element shall be set greater than 115% of the calculated current derived from:

(1) Real Power output – 100% of the aggregate generation gross

MW reported to the Transmission Planner, and

(2) Reactive Power output –100% of the aggregate generation maximum gross Mvar output during field-forcing as determined by simulation


A different application starts on the next page


18 of 22


PRC-025-1 Generator Relay Loadability


shall be set less than the calculated

130% of the maximum aggregate at rated power factor (including the

c or dynamic reactive power devices)


The same application continues on the next page with a different relay type



Table 1. Relay Loadability Evaluation Criteria


Application


Relay Type


Option

Bus Voltage4



Elements that connect the GSU transformer(s) to the Transmission system that are used exclusively to export energy directly from

a BES generating unit or generating plant. Elements may also supply generating plant loads. – connected to asynchronous generators only (including inverter- based installations)

Phase distance relay (21) – directional toward the Transmission system– installed on the high-side of the GSU transformer


If the relay is installed on the generator-side of the GSU transformer

use Option 10


17


1.0 per unit of the line nominal voltage


The impedance element impedance derived from nameplate MVA output Mvar output of any stati



19 of 22


PRC-025-1 Generator Relay Loadability


t shall be set greater than 130% of the ed from the maximum aggregate

at rated power factor (including the

c or dynamic reactive power devices)


The same application continues on the next page with a different relay type



Table 1. Relay Loadability Evaluation Criteria


Application


Relay Type


Option

Bus Voltage4



Elements that connect the GSU transformer(s) to the Transmission system that are used exclusively to export energy directly from

a BES generating unit or generating plant. Elements may also supply generating plant loads. – connected to asynchronous generators only (including inverter- based installations)

Phase overcurrent supervisory element (50) – associated with current-based, communication- assisted schemes where the scheme is capable of tripping for loss of communications installed on the

high-side of the GSU transformer or Phase time

overcurrent relay

(51) – installed on the high-side of the GSU transformer


If the relay is installed on the generator-side of the GSU transformer

use Option 11


18


1.0 per unit of the line nominal voltage


The overcurrent elemen calculated current deriv nameplate MVA output Mvar output of any stati



20 of 22


PRC-025-1 Generator Relay Loadability


t shall be set greater than 130% of the ed from the maximum aggregate

at rated power factor (including the

c or dynamic reactive power devices)



Table 1. Relay Loadability Evaluation Criteria


Application


Relay Type


Option

Bus Voltage4



Elements that connect the GSU transformer(s) to the Transmission system that are used exclusively to export energy directly from

a BES generating unit or generating plant. Elements may also supply generating plant loads. – connected to asynchronous generators only (including inverter- based installations)

Phase directional overcurrent supervisory element (67) – associated with current-based, communication- assisted schemes where the scheme is capable of tripping for loss of communications directional toward the Transmission system installed on the high-side of the GSU transformer or Phase directional time overcurrent relay (67) installed on the high-side of the GSU

transformer


If the relay is installed on the generator-side of the GSU transformer

use Option 12


19


1.0 per unit of the line nominal voltage


The overcurrent elemen calculated current deriv nameplate MVA output Mvar output of any stati


End of Table 1


21 of 22


PRC-025-1 Generator Relay Loadability


Rationale:


During development of this standard, text boxes were embedded within the standard to explain the rationale for various parts of the standard. Upon BOT approval, the text from the rationale text boxes was moved to this section.


Rationale for R1:


Requirement R1 is a risk-based requirement that requires the responsible entity to be aware of each protective relay subject to the standard and applies an appropriate setting based on its calculations or simulation for the conditions established in Attachment 1.


The criteria established in Attachment 1 represent short-duration conditions during which generation Facilities are capable of providing system reactive resources, and for which generation Facilities have been historically recorded to disconnect, causing events to become more severe.


The term, “while maintaining reliable fault protection” in Requirement R1 describes that the responsible entity is to comply with this standard while achieving their desired protection goals. Refer to the Guidelines and Technical Basis, Introduction, for more information.


Version History



Version


Date


Action


Change

Tracking


1


August 15,

2013


Adopted by NERC Board of Trustees


New


22 of 22