Appendix D-1. Deliverable Schedule
TASK NAME |
DESCRIPTION |
DURATION |
START |
FINISH |
Clin 001.1. Updated Data Study Plan |
|
|
Fri 8/30/13 |
Fri 1/3/14 |
|
Draft |
4 wks |
Mon 9/9/13 |
Tue 10/22/13 |
|
4 weeks FNS Review |
4 wks |
Tue 10/22/13 |
Tue 11/19/13 |
|
Revised |
1 wk |
Tue 11/19/13 |
Tue 11/26/13 |
|
4 weeks FNS Review |
4 wks |
Tue 11/26/13 |
Thu 12/26/13 |
|
Final |
1 wk |
Thu 12/26/13 |
Fri 1/3/14 |
Clin 001.2. Draft and Test Data Collection Instruments |
|
|
Mon 9/23/13 |
Wed 2/26/14 |
Data Collection Instruments |
Draft |
5 wks |
Mon 9/23/13 |
Wed 11/13/13 |
|
4 weeks FNS Review |
4 wks |
Wed 11/13/13 |
Fri 12/13/13 |
|
Revised |
3 wks |
Fri 12/13/13 |
Fri 1/3/14 |
|
4 weeks FNS Review |
4 wks |
Fri 1/3/14 |
Mon 2/3/14 |
|
Revised Final |
1.5 wks |
Mon 2/3/14 |
Wed 2/12/14 |
IRB Approval |
Submit for IRB Approval |
8 wks |
Tue 12/10/13 |
Tue 2/4/14 |
|
Revise based on IRB Comments |
2 wks |
Tue 2/4/14 |
Tue 2/18/14 |
Letter and recruitment materials |
Draft |
3.5 wks |
Fri 11/15/13 |
Mon 12/30/13 |
|
4 weeks FNS Review |
4 wks |
Mon 12/30/13 |
Tue 1/28/14 |
|
Final |
1.5 wks |
Tue 1/28/14 |
Fri 2/7/14 |
Pretest |
|
4 wks |
Mon 12/2/13 |
Fri 1/17/14 |
Memo summarizing pretest results |
Draft |
2 wks |
Fri 1/17/14 |
Wed 1/29/14 |
|
4 weeks FNS Review |
3 wks |
Wed 1/29/14 |
Wed 2/19/14 |
|
Final |
1 wk |
Wed 2/19/14 |
Wed 2/26/14 |
Clin 001.3. OMB Clearance Package |
|
|
Tue 1/7/14 |
Fri 2/13/15 |
Prepare OMB packets |
Draft |
3 wks |
Tue 1/7/14 |
Fri 2/28/14 |
|
4 weeks FNS Review |
4 wks |
Fri 2/28/14 |
Fri 3/28/14 |
|
Revised Final – Submit to OMB |
2 wks |
Fri 3/28/14 |
Mon 4/7/14 |
60 Day Notice for Federal Register |
Submit |
|
Tue 10/22/13 |
Wed 11/13/13 |
|
Post/Review |
6 mons |
Wed 11/13/13 |
Fri 5/16/14 |
|
Revise |
2 wks |
Fri 5/16/14 |
Mon 6/2/14 |
Clin 001.4. Data Collector Selection and Training |
|
|
Tue 11/18/14 |
Wed 6/10/15 |
Data collection Training Manual |
Draft |
5 wks |
Tue 11/18/14 |
Fri 12/19/14 |
|
4 weeks FNS Review |
4 wks |
Fri 12/19/14 |
Fri 1/16/15 |
|
Revised |
1.5 wks |
Fri 1/16/15 |
Wed 1/28/15 |
|
4 weeks FNS Review |
4 wks |
Wed 1/28/15 |
Wed 2/25/15 |
|
Final |
1 wk |
Wed 2/25/15 |
Wed 3/4/15 |
Data collection selection |
|
8 wks |
Wed 1/14/15 |
Wed 4/29/15 |
Data collector training |
|
3 wks |
Wed 4/29/15 |
Wed 5/13/15 |
Debriefing memo summarizing training sessions |
|
4 wks |
Wed 5/13/15 |
Wed 6/10/15 |
Clin 001.5. Data Collection |
|
|
Fri 5/1/15 |
Mon 1/25/16 |
Data Collection |
|
7 mons |
Fri 5/1/15 |
Thu 11/12/15 |
Memo summarizing data collection activities |
Draft |
5 wks |
Mon 11/2/15 |
Fri 12/4/15 |
|
4 weeks FNS Review |
4 wks |
Fri 12/4/15 |
Thu 12/31/15 |
|
Final |
3 wks |
Thu 12/31/15 |
Wed 1/20/16 |
Briefing summarizing data collection completion by variable |
|
8 wks |
Tue 12/1/15 |
Mon 1/25/16 |
Bi-Weekly data collection update conference calls |
Bi-weekly |
|
|
|
Clin 001.6. Analyze Data |
|
|
Mon 6/1/15 |
Mon 5/16/16 |
Validate, clean, merge collected data |
Ongoing |
9 mons |
Mon 6/1/15 |
Tue 3/1/16 |
Develop database, raw data files, and analytic files |
Ongoing |
4 mons |
Thu 10/1/15 |
Mon 2/1/16 |
Memo summarizing changes to updated study plan (if needed) |
|
3 wks |
Mon 11/2/15 |
Fri 11/20/15 |
Table and graph shells |
|
4 mons |
Mon 11/30/15 |
Fri 3/18/16 |
Interim Report on Selected Research Questions |
Draft |
6 wks |
Mon 1/11/16 |
Fri 2/19/16 |
|
4 weeks FNS Review |
4 wks |
Fri 2/19/16 |
Thu 3/17/16 |
|
Revised |
3 wks |
Thu 3/17/16 |
Wed 4/6/16 |
|
4 weeks FNS Review |
4 wks |
Wed 4/6/16 |
Tue 5/3/16 |
|
Final |
2 wks |
Tue 5/3/16 |
Mon 5/16/16 |
Clin 001.7. Final Report |
|
|
Fri 2/5/16 |
Tue 8/23/16 |
Report Outline |
|
4 wks |
Fri 2/5/16 |
Thu 3/3/16 |
Design graphics |
|
6 wks |
Wed 5/4/16 |
Tue 6/14/16 |
Final Report |
Draft |
8 wks |
Thu 3/3/16 |
Wed 4/27/16 |
|
6 weeks FNS review |
6 wks |
Wed 4/27/16 |
Tue 6/7/16 |
|
Revised |
3 wks |
Tue 6/7/16 |
Mon 6/27/16 |
|
6 weeks FNS review |
6 wks |
Mon 6/27/16 |
Fri 8/5/16 |
|
Final |
1.5 wks |
Fri 8/5/16 |
Tue 8/16/16 |
FNS Clearance |
|
|
Tue 8/16/16 |
|
Clin 001.8. Prepare and submit analytic files with all documentation to be delivered after each draft of final report and cleared final report |
|
|
Thu 3/10/16 |
Tue 8/23/16 |
Data set and documentation |
Draft (accompanies draft final report) |
8 wks |
Thu 3/10/16 |
Wed 5/4/16 |
|
4 weeks FNS Review |
6 wks |
Wed 5/4/16 |
Tue 6/14/16 |
|
Revised (accompanies revised final report) |
3.5 wks |
Tue 6/14/16 |
Thu 7/7/16 |
|
Final (accompanies final report) |
1 wk |
Wed 8/10/16 |
Tue 8/16/16 |
|
Restricted Use Files (accompanies cleared final report) |
|
|
|
|
Public Use Files (accompanies cleared final report) |
|
|
|
Clin 001.9. Presentation and Briefing at FNS Headquarters |
|
|
Fri 7/1/16 |
Tue 8/30/16 |
Agenda and visual display materials and handouts |
Draft |
4 wks |
Fri 6/17/16 |
Thu 7/14/16 |
|
4 weeks FNS Review |
4 wks |
Thu 7/14/16 |
Wed 8/10/16 |
|
Final |
1 wk |
Wed 8/10/16 |
Tue 8/16/16 |
Memo of outstanding methodological and interpretive issues |
|
5 wks |
Thu 7/7/16 |
Wed 8/10/16 |
Final Briefing at FNS Headquarters |
|
1 day |
Tue 8/23/16 |
Tue 8/23/16 |
Clin 001.10 Progress Reports |
|
|
|
|
Progress Reports |
Monthly |
|
|
|
Clin 001.11 Administrative Tasks |
|
|
|
|
Administrative Tasks |
Ad Hoc |
|
|
|
Kickoff Meeting Agenda |
|
1 wk |
Fri 9/13/13 |
Thu 9/19/13 |
Kickoff Meeting |
|
1 day |
Thu 9/26/13 |
Thu 9/26/13 |
Kickoff Meeting Summary |
|
1 wk |
Thu 9/26/13 |
Wed 10/2/13 |