TASK NAME

DESCRIPTION

DURATION

START

FINISH

Clin 001.1. Updated Data Study Plan



Fri 8/30/13

Fri 1/3/14


Draft

4 wks

Mon 9/9/13

Tue 10/22/13


4 weeks FNS Review

4 wks

Tue 10/22/13

Tue 11/19/13


Revised

1 wk

Tue 11/19/13

Tue 11/26/13


4 weeks FNS Review

4 wks

Tue 11/26/13

Thu 12/26/13


Final

1 wk

Thu 12/26/13

Fri 1/3/14

Clin 001.2. Draft and Test Data Collection Instruments



Mon 9/23/13

Wed 2/26/14

Data Collection Instruments

Draft

5 wks

Mon 9/23/13

Wed 11/13/13


4 weeks FNS Review

4 wks

Wed 11/13/13

Fri 12/13/13


Revised

3 wks

Fri 12/13/13

Fri 1/3/14


4 weeks FNS Review

4 wks

Fri 1/3/14

Mon 2/3/14


Revised Final

1.5 wks

Mon 2/3/14

Wed 2/12/14

IRB Approval

Submit for IRB Approval

8 wks

Tue 12/10/13

Tue 2/4/14


Revise based on IRB Comments

2 wks

Tue 2/4/14

Tue 2/18/14

Letter and recruitment materials

Draft

3.5 wks

Fri 11/15/13

Mon 12/30/13


4 weeks FNS Review

4 wks

Mon 12/30/13

Tue 1/28/14


Final

1.5 wks

Tue 1/28/14

Fri 2/7/14

Pretest


4 wks

Mon 12/2/13

Fri 1/17/14

Memo summarizing pretest results

Draft

2 wks

Fri 1/17/14

Wed 1/29/14


4 weeks FNS Review

3 wks

Wed 1/29/14

Wed 2/19/14


Final

1 wk

Wed 2/19/14

Wed 2/26/14

Clin 001.3. OMB Clearance Package



Tue 1/7/14

Fri 2/13/15

Prepare OMB packets

Draft

3 wks

Tue 1/7/14

Fri 2/28/14


4 weeks FNS Review

4 wks

Fri 2/28/14

Fri 3/28/14


Revised Final – Submit to OMB

2 wks

Fri 3/28/14

Mon 4/7/14

60 Day Notice for Federal Register

Submit


Tue 10/22/13

Wed 11/13/13


Post/Review

6 mons

Wed 11/13/13

Fri 5/16/14


Revise

2 wks

Fri 5/16/14

Mon 6/2/14

Clin 001.4. Data Collector Selection and Training



Tue 11/18/14

Wed 6/10/15

Data collection Training Manual

Draft

5 wks

Tue 11/18/14

Fri 12/19/14


4 weeks FNS Review

4 wks

Fri 12/19/14

Fri 1/16/15


Revised

1.5 wks

Fri 1/16/15

Wed 1/28/15


4 weeks FNS Review

4 wks

Wed 1/28/15

Wed 2/25/15


Final

1 wk

Wed 2/25/15

Wed 3/4/15

Data collection selection


8 wks

Wed 1/14/15

Wed 4/29/15

Data collector training


3 wks

Wed 4/29/15

Wed 5/13/15

Debriefing memo summarizing training sessions


4 wks

Wed 5/13/15

Wed 6/10/15

Clin 001.5. Data Collection



Fri 5/1/15

Mon 1/25/16

Data Collection


7 mons

Fri 5/1/15

Thu 11/12/15

Memo summarizing data collection activities

Draft

5 wks

Mon 11/2/15

Fri 12/4/15


4 weeks FNS Review

4 wks

Fri 12/4/15

Thu 12/31/15


Final

3 wks

Thu 12/31/15

Wed 1/20/16

Briefing summarizing data collection completion by variable


8 wks

Tue 12/1/15

Mon 1/25/16

Bi-Weekly data collection update conference calls

Bi-weekly




Clin 001.6. Analyze Data



Mon 6/1/15

Mon 5/16/16

Validate, clean, merge collected data

Ongoing

9 mons

Mon 6/1/15

Tue 3/1/16

Develop database, raw data files, and analytic files

Ongoing

4 mons

Thu 10/1/15

Mon 2/1/16

Memo summarizing changes to updated study plan (if needed)


3 wks

Mon 11/2/15

Fri 11/20/15

Table and graph shells


4 mons

Mon 11/30/15

Fri 3/18/16

Interim Report on Selected Research Questions

Draft

6 wks

Mon 1/11/16

Fri 2/19/16


4 weeks FNS Review

4 wks

Fri 2/19/16

Thu 3/17/16


Revised

3 wks

Thu 3/17/16

Wed 4/6/16


4 weeks FNS Review

4 wks

Wed 4/6/16

Tue 5/3/16


Final

2 wks

Tue 5/3/16

Mon 5/16/16

Clin 001.7. Final Report



Fri 2/5/16

Tue 8/23/16

Report Outline


4 wks

Fri 2/5/16

Thu 3/3/16

Design graphics


6 wks

Wed 5/4/16

Tue 6/14/16

Final Report

Draft

8 wks

Thu 3/3/16

Wed 4/27/16


6 weeks FNS review

6 wks

Wed 4/27/16

Tue 6/7/16


Revised

3 wks

Tue 6/7/16

Mon 6/27/16


6 weeks FNS review

6 wks

Mon 6/27/16

Fri 8/5/16


Final

1.5 wks

Fri 8/5/16

Tue 8/16/16

FNS Clearance



Tue 8/16/16


Clin 001.8. Prepare and submit analytic files with all documentation to be delivered after each draft of final report and cleared final report



Thu 3/10/16

Tue 8/23/16

Data set and documentation

Draft (accompanies draft final report)

8 wks

Thu 3/10/16

Wed 5/4/16


4 weeks FNS Review

6 wks

Wed 5/4/16

Tue 6/14/16


Revised (accompanies revised final report)

3.5 wks

Tue 6/14/16

Thu 7/7/16


Final (accompanies final report)

1 wk

Wed 8/10/16

Tue 8/16/16


Restricted Use Files (accompanies cleared final report)





Public Use Files (accompanies cleared final report)




Clin 001.9. Presentation and Briefing at FNS Headquarters



Fri 7/1/16

Tue 8/30/16

Agenda and visual display materials and handouts

Draft

4 wks

Fri 6/17/16

Thu 7/14/16


4 weeks FNS Review

4 wks

Thu 7/14/16

Wed 8/10/16


Final

1 wk

Wed 8/10/16

Tue 8/16/16

Memo of outstanding methodological and interpretive issues


5 wks

Thu 7/7/16

Wed 8/10/16

Final Briefing at FNS Headquarters


1 day

Tue 8/23/16

Tue 8/23/16

Clin 001.10 Progress Reports





Progress Reports

Monthly




Clin 001.11 Administrative Tasks





Administrative Tasks

Ad Hoc




Kickoff Meeting Agenda


1 wk

Fri 9/13/13

Thu 9/19/13

Kickoff Meeting


1 day

Thu 9/26/13

Thu 9/26/13

Kickoff Meeting Summary


1 wk

Thu 9/26/13

Wed 10/2/13


File Typeapplication/vnd.openxmlformats-officedocument.wordprocessingml.document
AuthorAndrey Vinokurov
File Modified0000-00-00
File Created2021-01-27

© 2024 OMB.report | Privacy Policy