pdfREPROCESSING PLANTS
CONFIDENTIAL
WHEN COMPLETED
APPROVED BY OMB: NO. 3150-0056
DATE:
EXPIRES: (MM/DD/YYYY)
Estimated burden per response to comply with this mandatory collection request: 360 hours. NRC
is required to collect this information for reporting to IAEA from facility licensees appearing on the
U.S. Eligible List. Send comments regarding burden estimate to the FOIA, Privacy, and
Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC
20555-0001, or by internet e-mail to [email protected], and to the Desk Officer,
Office of Information and Regulatory Affairs, NEOB-10202, (3150-0056), Office of Management
and Budget, Washington, DC 20503. If a means used to impose an information collection does
not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a
person is not required to respond to, the information collection.
INTERNATIONAL ATOMIC ENERGY AGENCY
DEPARTMENT OF SAFEGUARDS AND INSPECTION
DESIGN INFORMATION
QUESTIONNAIRE *
(CONTINUED)
The "Confidential" marking on this form is for IAEA
purposes only. It indicates that the IAEA considers
the information in the completed form to be
'safeguards confidential' and is not to be confused
with any U.S. security classification.
IAEA USE ONLY
* Questions which are not applicable may be left
unanswered.
REPROCESSING PLANTS
OVERALL PROCESS PARAMETERS
13. FACILITY DESCRIPTION
(indicating all process modification stages,
storage areas and feed, product and waste
points as pertaining to the measurement
control and accountancy of nuclear material)
GENERAL FLOW DIAGRAM(S) ATTACHED UNDER REF. NOS.
(The diagram(s) should also indicate equipment, hoods, cells, and those areas
which contain nuclear material, as well as those specific areas where hold-up o f
nuclear material can occur)
14. PROCESS DESCRIPTION
(Also indicating the modification of physical
and chemical forms)
N-74 (MM-YYYY)
CONFIDENTIAL
3
REPROCESSING PLANTS
DATE:
OVERALL PROCESS PARAMETERS
15. DESIGN CAPACITY
(in weight of principle products per annum)
16. ANTICIPATED ANNUAL THROUGHPUT
(in the form of a forward programme (if
applicable), indicating the proportion of various
feeds and products)
17. OTHER IMPORTANT ITEMS OF EQUIPMENT
USING, PRODUCING, OR PROCESSING
NUCLEAR MATERIAL, IF ANY
(such as testing and experimental equipment)
N-74 (MM-YYYY)
CONFIDENTIAL
4
REPROCESSING PLANTS
DATE:
NUCLEAR MATERIAL DESCRIPTION AND FLOW
18.
MAIN MATERIAL DESCRIPTION
i)
FEED
PRODUCT (1)
Main Types of Accountability Units
to Be Handled in the Facility
ii) Chemical and Physical Form
(for feed include types of fuel element/
assemblies, give detailed description
indicating general structure and overall
dimensions of fuel element/assemblies,
including nuclear material content and
enrichment)
Attach drawing(s)
iii) Throughput, Enrichment Ranges and
Pu contents
(for normal flow sheet operation indicating
if blending and/or recycling takes place)
iv) Batch Size/Flow Rate and Campaign
Period, Means of Batch Identification
(1) For example, uranium and plutonium.
N-74 (MM-YYYY)
CONFIDENTIAL
5
REPROCESSING PLANTS
DATE:
NUCLEAR MATERIAL DESCRIPTION AND FLOW
MAIN MATERIAL DESCRIPTION
(Continued)
18.
v)
Storage and Plant Inventory
(indicating any change with throughput)
vi)
Frequency of Receipt or Shipment
(batches/units per month)
FEED
PRODUCT (1)
19. WASTE MATERIAL
(including contaminated equipment,
measured discards, and retained
waste).
Describe for each waste stream:
i) Major Contributions
(sources)
ii)
Type of Waste
iii)
Chemical and Physical Form
(liquid, solid, etc.)
iv)
Estimated Enrichment Ranges, and
Uranium/Plutonium Content
(1) For example, uranium and plutonium.
N-74 (MM-YYYY)
CONFIDENTIAL
6
REPROCESSING PLANTS
DATE:
NUCLEAR MATERIAL DESCRIPTION AND FLOW
19. WASTE MATERIAL (Continued)
v)
Estimated Quantities Per Year,
Period of Storing
vi)
Waste Generated Rates
(as % of input/throughput, quantities
per month)
vii)
Store Inventory Range and
Maximum Capacity
viii) Method and Frequency of
Recovery/Disposal
20. WASTE TREATMENT SYSTEM
N-74 (MM-YYYY)
DIAGRAM(S) ATTACHED UNDER REFERENCE NUMBERS:
CONFIDENTIAL
7
REPROCESSING PLANTS
DATE:
NUCLEAR MATERIAL DESCRIPTION AND FLOW
21. OTHER NUCLEAR MATERIAL IN THE
FACILITY AND ITS LOCATION, IF ANY
DIAGRAM(S) ATTACHED UNDER REFERENCE NUMBERS:
22. SCHEMATIC FLOW SHEET FOR
DIAGRAM(S) ATTACHED UNDER REFERENCE NUMBERS:
NUCLEAR MATERIAL
(identifying sampling points, flow and inventory
measurement points, accountability areas,
inventory locations, etc.)
N-74 (MM-YYYY)
CONFIDENTIAL
8
REPROCESSING PLANTS
DATE:
NUCLEAR MATERIAL DESCRIPTION AND FLOW
23. TYPES, FORM, RANGES OF ENRICHMENT,
PU CONTENT, RANGES OF QUANTITIES OF
NUCLEAR MATERIAL FLOW FOR EACH
NUCLEAR MATERIAL HANDLING AREA,
i.e.:
----
process area
storage area
other locations
(Also indicate maximum quantities of nuclear
material to be handled in accountability areas
at the one time.)
24. RECYCLE PROCESSES
(briefly describe any such processes giving
source and form of material, method of
storage, normal inventory, frequency of
processing, duration of temporary storage,
schedules for any external recycling,
measurement method of fissile content of
recycle material)
N-74 (MM-YYYY)
DIAGRAM(S) ATTACHED UNDER REFERENCE NUMBERS:
CONFIDENTIAL
9
REPROCESSING PLANTS
DATE:
NUCLEAR MATERIAL DESCRIPTION AND FLOW
25. INVENTORY
i)
In-Process
(within plant and equipment during
normal operation; indicate quantity, range
of enrichment, Pu content, form and
principal locations and any significant
change in time or throughput; also
indicate anticipated residual hold-up and
mechanism)
ii)
Feed and Product Storage
iii)
Other Locations
(quantity, range of enrichment, Pu
content, form and location of inventory
not already specified)
NUCLEAR MATERIAL HANDLING
(FOR EACH ACCOUNTABILITY AREA)
26. CONTAINERS, PACKAGING, AND
STORAGE AREA DESCRIPTION
N-74 (MM-YYYY)
DRAWING(S) ATTACHED UNDER REFERENCE NUMBERS:
SEPARATE NOTE TO BE ATTACHED.
Describe for feeds, products, and wastes: the type and size of storage and
shipping containers and packaging used, (including nominal capacity and
capacity for normal operation, and type of material); method of storage or
packing, filling and emptying procedures, shielding; and any special
identification features.
CONFIDENTIAL
10
REPROCESSING PLANTS
DATE:
NUCLEAR MATERIAL HANDLING
(FOR EACH ACCOUNTABILITY AREA)
27. METHODS AND MEANS OF TRANSFER OF
NUCLEAR MATERIAL
(Describe also equipment used for handling of
feed, product, and waste.)
28. TRANSPORTATION ROUTES FOLLOWED
BY NUCLEAR MATERIAL
(with reference to plant layout)
DRAWING(S) ATTACHED UNDER REFERENCE NUMBERS:
30. SHIELDING
(for storage and transfer)
N-74 (MM-YYYY)
CONFIDENTIAL
11
REPROCESSING PLANTS
DATE:
PLANT MAINTENANCE
30. MAINTENANCE, DECONTAMINATION,
CLEAN-OUT
SEPARATE NOTE TO BE ATTACHED
Describing plans and procedures for decontamination and clean-out of
equipment containing nuclear material, defining all sampling and measurement
points associated with:
i) Normal Plant Maintenance;
ii) Plant and Equipment Decontamination and Subsequent Nuclear
Material Recovery;
iii) Plant and Equipment Clean-out Including Means of Ensuring Vessels
Are Empty;
iv) Plant Start-up and Plant Shutdown
(if difference from normal operations)
(In cases where clean-out and/or sampling is not possible, indicate how the
hold-up of nuclear material is measured or calculated.)
PROTECTION AND SAFETY MEASURES
31. BASIC MEASURES FOR PHYSICAL
PROTECTION OF NUCLEAR MATERIAL
N-74 (MM-YYYY)
CONFIDENTIAL
12
REPROCESSING PLANTS
DATE:
PROTECTION AND SAFETY MEASURES
32. SPECIFIC HEALTH AND SAFETY RULES
FOR INSPECTOR COMPLIANCE
(if extensive, attach separately)
NUCLEAR MATERIAL ACCOUNTANCY AND CONTROL
33. SYSTEM DESCRIPTION
SPECIMEN FORMS USED IN ALL PROCEDURES ATTACHED UNDER
Give a description of the nuclear material
REFERENCE NUMBERS:
accountancy system, the method of recording
and reporting accountancy data and
establishing material balances, frequency of
material balances, procedures for account
adjustment after plant inventory, mistakes, etc.,
under the following headings:
i) General
(This section should also state what general
and subsidiary ledgers will be used, their
form (hard copies, tapes, microfilms, etc.), as
well as who has the responsibility and
authority. Source data (e.g., shipping and
receiving forms, the initial recording of
measurements and measurement control
sheets). The procedures for making
adjustments; the source data and records
should be covered as well as how the
adjustments are authorized and
substantiated).
N-74 (MM-YYYY)
CONFIDENTIAL
13
REPROCESSING PLANTS
DATE:
NUCLEAR MATERIAL ACCOUNTANCY AND CONTROL
33. SYSTEM DESCRIPTION (Continued)
i) General (continued)
N-74 (01-2013)
CONFIDENTIAL
14
REPROCESSING PLANTS
DATE:
NUCLEAR MATERIAL ACCOUNTANCY AND CONTROL
33. SYSTEM DESCRIPTION (Continued)
ii)
Receipts
(including method of dealing with shipper/
receiver differences and subsequent
account corrections, the checks and
measurements used to confirm nuclear
material content and the persons
responsible for those determinations
should be defined)
iii)
Shipments
(products, waste, measured discards)
N-74 (MM-YYYY)
CONFIDENTIAL
15
REPROCESSING PLANTS
DATE:
NUCLEAR MATERIAL ACCOUNTANCY AND CONTROL
33. SYSTEM DESCRIPTION (Continued)
iv)
Physical Inventory
Description of procedures, scheduled
frequency, estimated distribution of
nuclear material, methods of operator's
inventory taking (both for item and/or bulk
accountancy, including relevant assay
method), accessability and possible
verification method for irradiated nuclear
material, expected accuracy, and access
to nuclear material.
(In particular, the description of
procedures should also provide the basic
inventory approach to be used, i.e.,
planning, organizing, and conducting the
inventory, pre-listing, use of prior
measurement data; who has primary
responsibility for the inventory; how
process clean-out is accomplished; the
accountancy of process residual hold-up.)
v)
Measured Discards.
(Methods of estimation of quantities per
year/month, method of disposal.
N-74 (MM-YYYY)
LIST OF MAJOR ITEMS OF EQUIPMENT REGARDED AS NUCLEAR
MATERIAL CONTAINERS ATTACHED UNDER REFERENCE NUMBERS:
CONFIDENTIAL
16
REPROCESSING PLANTS
DATE:
NUCLEAR MATERIAL ACCOUNTANCY AND CONTROL
33. SYSTEM DESCRIPTION (Continued)
vi)
Retained Waste
(Method of estimation of quantities per
year, method and envisaged period of
storage; indicate also possible
subsequent uses of retained waste)
vii)
Unmeasured Losses
(Indicate the methods used to estimate
unmeasured losses)
N-74 (01-2013)
CONFIDENTIAL
17
REPROCESSING PLANTS
DATE:
NUCLEAR MATERIAL ACCOUNTANCY AND CONTROL
33. SYSTEM DESCRIPTION (Continued)
viii) Operation Records and Accounts
(Including log books, general ledgers,
internal transfer forms, method of
adjustment or correction and retention
location, and languages; control
measures and responsibility for records)
34. FEATURES RELATED TO CONTAINMENT
AND SURVEILLANCE MEASURES
(General description of applied or possible
measures)
N-74 (MM-YYYY)
CONFIDENTIAL
18
REPROCESSING PLANTS
DATE:
NUCLEAR MATERIAL ACCOUNTANCY AND CONTROL
35. FOR EACH FLOW AND INVENTORY
IF NECESSARY, ATTACH DRAWING(S)
MEASUREMENT POINT, AND SAMPLING
POINTS OF ACCOUNTABILITY AREAS,
IDENTIFIED IN PARTICULAR UNDER QS. 13,
22, 23, GIVE THE FOLLOWING*
i)
Description of Location, Type,
Identification
ii)
Type of Inventory Change Expected at
This Measurement Point
iii)
Possibilities to Use This Measurement
Point for Physical Inventory Taking
iv)
Physical and Chemical Form of
Nuclear Material
(including enrichment range, Pu content,
and cladding materials description)
* For each measurement point, fill in separate sheet.
N-74 (MM-YYYY)
CONFIDENTIAL
19
REPROCESSING PLANTS
DATE:
NUCLEAR MATERIAL ACCOUNTANCY AND CONTROL
35. FOR EACH FLOW AND INVENTORY
MEASUREMENT POINT, AND SAMPLING
POINTS OF ACCOUNTABILITY AREAS,
IDENTIFIED IN PARTICULAR UNDER QS. 13,
22, 23, GIVE THE FOLLOWING* (Continued)
v)
Nuclear Material Containers, Packaging,
and Method of Storage
vi)
Sampling Procedure and Equipment
Used
(including number of samples taken,
frequency and rejection criteria)
vii)
Measurement/Analytical Method(s) and
Equipment Used and Corresponding
Accuracies
* For each measurement point, fill in separate sheet.
N-74 (MM-YYYY)
CONFIDENTIAL
20
REPROCESSING PLANTS
DATE:
NUCLEAR MATERIAL ACCOUNTANCY AND CONTROL
35. FOR EACH FLOW AND INVENTORY
MEASUREMENT POINT, AND SAMPLING
POINTS OF ACCOUNTABILITY AREAS,
IDENTIFIED IN PARTICULAR UNDER QS. 13,
22, 23, GIVE THE FOLLOWING* (Continued)
viii) Source and Level of Random and
Systematic Errors for Feed, Products,
Waste
(weight, volume, sampling, analytical)
ix)
Calculative and Error Propagation
Techniques
x)
Technique and Frequency of Calibration
of Equipment Used, and Standards Used
* For each measurement point, fill in separate sheet.
N-74 (MM-YYYY)
CONFIDENTIAL
21
REPROCESSING PLANTS
DATE:
NUCLEAR MATERIAL ACCOUNTANCY AND CONTROL
35. FOR EACH FLOW AND INVENTORY
MEASUREMENT POINT, AND SAMPLING
POINTS OF ACCOUNTABILITY AREAS,
IDENTIFIED IN PARTICULAR UNDER QS. 13,
22, 23, GIVE THE FOLLOWING* (Continued)
xi)
Programme for the Continuing Appraisal
of the Accuracy of Weight, Volume,
Sampling and Analytical Techniques and
Measurement Methods
xii)
Programme for Statistical Evaluation of
Data from (x) to (xi)
xiii) Method of Converting Source Data to
Batch Data
(standard calculative procedures,
constants and empirical relationships
for feed, products in sub-accounting
areas, and waste)
* For each measurement point, fill in separate sheet.
N-74 (MM-YYYY)
CONFIDENTIAL
22
REPROCESSING PLANTS
DATE:
NUCLEAR MATERIAL ACCOUNTANCY AND CONTROL
35. FOR EACH FLOW AND INVENTORY
MEASUREMENT POINT, AND SAMPLING
POINTS OF ACCOUNTABILITY AREAS,
IDENTIFIED IN PARTICULAR UNDER QS. 13,
22, 23, GIVE THE FOLLOWING* (Continued)
xiv) Means of Batch Identification
xv)
Anticipated Batch Flow Rate Per Year
xvi) Anticipated Number of Inventory Batches
Present at Measurement Point
xvii) Anticipated Number of Items Per Flow
and Inventory Batches
* For each measurement point, fill in separate sheet.
N-74 (MM-YYYY)
CONFIDENTIAL
23
REPROCESSING PLANTS
DATE:
NUCLEAR MATERIAL ACCOUNTANCY AND CONTROL
35. FOR EACH FLOW AND INVENTORY
MEASUREMENT POINT, AND SAMPLING
POINTS OF ACCOUNTABILITY AREAS,
IDENTIFIED IN PARTICULAR UNDER QS. 13,
22, 23, GIVE THE FOLLOWING* (Continued)
xviii)
Type, Composition and Quantity of
Nuclear Material Per Batch
(with indication of batch data, total
weight of each element of nuclear
material and form of nuclear material)
xix)
Features Related to ContainmentSurveillance Measures
36. OVERALL LIMIT OF ERROR
Describe procedures to combine individual
measurement error measurements to obtain
the overall limit of error for:
i)
S/R Differences
ii)
Book Inventory
iii)
Physical Inventory
iv)
MUF
* For each measurement point, fill in separate sheet.
N-74 (MM-YYYY)
CONFIDENTIAL
24
REPROCESSING PLANTS
DATE:
OPTIONAL INFORMATION
37. OPTIONAL INFORMATION
(that the operator considers relevant
to safeguarding the facility)
Signature of Responsible Officer:
Date:
N-74 (MM-YYYY)
CONFIDENTIAL
25
File Type | application/pdf |
File Title | c:\temp\ffdah1.wpf |
Author | dah1 |
File Modified | 2014-02-27 |
File Created | 2014-02-27 |