10 CFR Part 50, Domestic Licensing of Production and Utilization Facilities

ICR 201408-3150-004

OMB: 3150-0011

Federal Form Document

Forms and Documents
Document
Name
Status
Supporting Statement A
2014-08-21
Supplementary Document
2014-08-21
Supplementary Document
2014-08-21
Supplementary Document
2014-08-21
Supplementary Document
2014-08-21
IC Document Collections
ICR Details
3150-0011 201408-3150-004
Historical Active 201208-3150-003
NRC
10 CFR Part 50, Domestic Licensing of Production and Utilization Facilities
Revision of a currently approved collection   No
Regular
Approved without change 10/09/2014
Retrieve Notice of Action (NOA) 08/25/2014
In accordance with 5 CFR 1320, the information collection request is approved for three years.OMB requests that when the agency submits the package for renewal that it conduct consultations with up to 9 outside entities and incorporate those findings into the ICR package.
  Inventory as of this Action Requested Previously Approved
10/31/2017 10/31/2014 10/31/2014
45,997 0 46,176
4,474,282 0 4,488,602
1,810,380 0 1,810,380

FINAL RULE, APPROVAL OF AMERICAN SOCIETY OF MECHNICAL ENGINEERS' CODE CASES The final rule is the latest in a series of rulemakings that incorporate by reference the latest versions of several Regulatory Guides identifying new and revised unconditionally or conditionally acceptable American Society of Mechanical Engineers (ASME) Code Cases that are approved for use. The incorporation by reference of these Code Cases will reduce the number of alternative requests submitted by licensees under proposed 10 CFR 50.55a(z) by an estimated 179 requests annually. The proposed rule would apply to power reactor licensees and power reactors under construction.

PL: Pub.L. 109 - 58 119 Stat 594 Name of Law: Energy Policy Act of 2005
   PL: Pub.L. 83 - 703 68 Stat. 919 Name of Law: Atomic Energy Act of 1954
  
None

3150-AI72 Final or interim final rulemaking 78 FR 37886 06/24/2013

No

1
IC Title Form No. Form Name
10 CFR Part 50, Domestic Licensing of Production and Utilization Facilities

  Total Approved Previously Approved Change Due to New Statute Change Due to Agency Discretion Change Due to Adjustment in Estimate Change Due to Potential Violation of the PRA
Annual Number of Responses 45,997 46,176 0 -179 0 0
Annual Time Burden (Hours) 4,474,282 4,488,602 0 -14,320 0 0
Annual Cost Burden (Dollars) 1,810,380 1,810,380 0 0 0 0
No
Yes
Changing Regulations
The final rule would decrease the burden for Part 50 from 4,488,602 hours and 46,176 responses to 4,474,282 hours and 45,997 responses, a decrease of 14,320 hours and 179 responses. The final rule reduces burden by incorporating by reference recent ASME Code Cases. As a result of this incorporation by reference, burden on licensees to submit requests for alternatives under 50.55a(z) will be reduced. Licensees would no longer need to submit alternative requests in order to use these Code Cases, once they are included in NRC's Regulatory Guides.

$87,721,512
No
No
No
No
No
Uncollected
Jennifer Tobin 301 415-2328

  No

On behalf of this Federal agency, I certify that the collection of information encompassed by this request complies with 5 CFR 1320.9 and the related provisions of 5 CFR 1320.8(b)(3).
The following is a summary of the topics, regarding the proposed collection of information, that the certification covers:
 
 
 
 
 
 
 
    (i) Why the information is being collected;
    (ii) Use of information;
    (iii) Burden estimate;
    (iv) Nature of response (voluntary, required for a benefit, or mandatory);
    (v) Nature and extent of confidentiality; and
    (vi) Need to display currently valid OMB control number;
 
 
 
If you are unable to certify compliance with any of these provisions, identify the item by leaving the box unchecked and explain the reason in the Supporting Statement.
08/25/2014


© 2024 OMB.report | Privacy Policy