Attachment A - 23 U.S.C. 125(a)
Sec. 125(a). Emergency relief
(a) General Eligibility.--Subject to this section and section 120, an emergency fund is authorized for expenditure by the Secretary for the repair or reconstruction of highways, roads, and trails, in any part of the United States, including Indian reservations, that the Secretary finds have suffered serious damage as a result of --
(1) natural disaster over a wide area, such as by a flood, hurricane, tidal wave, earthquake, severe storm, or landslide; or
(2) catastrophic failure from any external cause.
Attachment B - 23 U.S.C. 315
Sec. 315. Rules, regulations, and recommendations
Except as provided in sections 204(f) and 205(a) of this title, the Secretary is authorized to prescribe and promulgate all needful rules and regulations for the carrying out of the provisions of this title. The Secretary may make such recommendations to the Congress and State transportation departments as he deems necessary for preserving and protecting the highways and insuring the safety of traffic thereon.
Attachment C - 23 C.F.R. 668.111(b)
Sec. 668.111(b) Application procedures.
(b) Damage survey. As soon as practical after occurrence, the State will make a preliminary field survey, working cooperatively with the FHWA Division Administrator and other governmental agencies with jurisdiction over eligible highways. The preliminary field survey should be coordinated with the Federal Emergency Management Agency work, if applicable, to eliminate duplication of effort. The purpose of this survey is to determine the general nature and extent of damage to eligible highways.
(1) A damage survey summary report is to be prepared by the State. The purpose of the damage survey summary report is to provide a factual basis for the FHWA Division Administrator's finding that serious damage to Federal-aid highways has been caused by a natural disaster over a wide area or a catastrophe. The damage survey summary report should include by political subdivision or other generally recognized administrative or geographic boundaries, a description of the types and extent of damage to highways and a preliminary estimate of cost of restoration or reconstruction for damaged Federal-aid highways in each jurisdiction. Pictures showing the kinds and extent of damage and sketch maps detailing the damaged areas should be included, as appropriate, in the damage survey summary report.
(2) Unless very unusual circumstances prevail, the damage survey summary report should be prepared within 6 weeks following the applicant's notification.
(3) For large disasters where extensive damage to Federal-aid highways is readily evident, the FHWA Division Administrator may approve an application under Sec. 668.111(d) prior to submission of the damage survey summary report. In these cases, an abbreviated damage survey summary report, summarizing eligible repair costs by jurisdiction, is to be prepared and submitted to the FHWA Division Administrator after the damage inspections have been completed.