2060-0505 201509-2060-016
Historical Active 201207-2060-001
EPA/OAR 1938.06
NESHAP for Municipal Solid Waste Landfills (40 CFR Part 63, Subpart AAAA)(Renewal)
Extension without change of a currently approved collection   No
Regular
Approved without change 03/02/2016
Retrieve Notice of Action (NOA) 09/21/2015
In accordance with 5 CFR 1320, the information collection is approved for three years.
  Inventory as of this Action Requested Previously Approved
03/31/2019 36 Months From Approved 03/31/2016
3,381 0 3,372
20,900 0 18,283
16,900 0 16,860

The affected entities are subject to the General Provisions of the NESHAP at 40 CFR part 63, subpart A, and any changes, or additions to the Provisions specified at 40 CFR part 63, subpart AAAA. Owners or operators of the affected facilities must submit initial notification, performance tests, and periodic reports and results. Owners or operators are also required to maintain records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of an affected facility, or any period during which the monitoring system is inoperative. Reports, at a minimum, are required semiannually.

US Code: 44 USC 3501 et seq Name of Law: Clean Air Act
  
None

Not associated with rulemaking

  79 FR 30117 05/27/2014
80 FR 56982 09/21/2015
No

1
IC Title Form No. Form Name
NESHAP for Municipal Solid Waste Landfills (40 CFR Part 63, Subpart AAAA)(Renewal)

  Total Approved Previously Approved Change Due to New Statute Change Due to Agency Discretion Change Due to Adjustment in Estimate Change Due to Potential Violation of the PRA
Annual Number of Responses 3,381 3,372 0 0 9 0
Annual Time Burden (Hours) 20,900 18,283 0 0 2,617 0
Annual Cost Burden (Dollars) 16,900 16,860 0 0 40 0
No
No
There is an increase in the total estimated burden as currently identified in the OMB Inventory of Approved Burdens. This increase is due to an increase in the number of new sources due to industry growth; it is not due to any program changes. In addition, we have adjusted the respondent burden calculation to assume all respondents will re-familiarize themselves with the regulatory requirements each year. There is also an increase in the total O&M cost associated with this ICR. Similar to the total estimated burden, EPA has adjusted the total O&M cost to account for industry growth that has occurred since the previous ICR.

$873,000
No
No
No
No
No
Uncollected
Patrick Yellin 202 564-2970 [email protected]

  No

On behalf of this Federal agency, I certify that the collection of information encompassed by this request complies with 5 CFR 1320.9 and the related provisions of 5 CFR 1320.8(b)(3).
The following is a summary of the topics, regarding the proposed collection of information, that the certification covers:
 
 
 
 
 
 
 
    (i) Why the information is being collected;
    (ii) Use of information;
    (iii) Burden estimate;
    (iv) Nature of response (voluntary, required for a benefit, or mandatory);
    (v) Nature and extent of confidentiality; and
    (vi) Need to display currently valid OMB control number;
 
 
 
If you are unable to certify compliance with any of these provisions, identify the item by leaving the box unchecked and explain the reason in the Supporting Statement.
09/21/2015


© 2024 OMB.report | Privacy Policy