NESHAP for Secondary Aluminum Production (40 CFR part 63, subpart RRR) (Final Rule)

ICR 201511-2060-002

OMB: 2060-0683

Federal Form Document

Forms and Documents
Document
Name
Status
No forms / supporting documents in this ICR. Check IC Document Collections.
IC Document Collections
ICR Details
2060-0683 201511-2060-002
Historical Inactive 201202-2060-004
EPA/OAR 2453.02
NESHAP for Secondary Aluminum Production (40 CFR part 63, subpart RRR) (Final Rule)
New collection (Request for a new OMB Control Number)   No
Regular
Preapproved 05/02/2016
Retrieve Notice of Action (NOA) 11/15/2015
  Inventory as of this Action Requested Previously Approved
05/31/2019 36 Months From Approved
50 0 0
1,695 0 0
2,316,550 0 0

EPA is proposing amendments to the National Emission Standards for Secondary Aluminum Production. The proposed amendments would correct and clarify various rule requirements and provisions. Specifically, the proposed amendments would require selected affected sources to comply with the emissions limits at all times including periods of startup and shutdown; add a definition of affirmative defense; add a requirement to report performance testing through the Electronic Reporting Tool (ERT); add provisions allowing owners and operators to change furnaces classifications; add requirements to test uncontrolled furnaces; add requirements to test for hydrogen fluoride ; add operating requirements such as monitoring of lime injection rates; and make corrections and clarifications to the applicability, definitions, operating, monitoring, and performance testing requirements. Potential respondents subject to the NESHAP include an estimated 161 existing facilities that process secondary aluminum. There are no additional annual responses attributable to this ICR. The burden estimates are associated with additional performance testing for HF, uncontrolled group 1 furnaces, and changing furance designations. No burden estimates are provided for new sources because no new major source facilities are expected to be affected sources during the next 3 years.

US Code: 42 USC 7401 Name of Law: Section 112
  
None

2060-AQ40 Final or interim final rulemaking

No

1
IC Title Form No. Form Name
NESHAP for Secondary Aluminum Production (40 CFR part 63, subpart RRR)

  Total Request Previously Approved Change Due to New Statute Change Due to Agency Discretion Change Due to Adjustment in Estimate Change Due to Potential Violation of the PRA
Annual Number of Responses 50 0 0 50 0 0
Annual Time Burden (Hours) 1,695 0 0 1,695 0 0
Annual Cost Burden (Dollars) 2,316,550 0 0 2,316,550 0 0
Yes
Changing Regulations
No
The EPA provides an adjustment to this ICR that estimates the costs of the notification, recordkeeping and reporting requirements associated with the final rule amendments that would add provisions allowing owners and operators to change furnaces classifications; add requirements for testing uncontrolled furnaces; add requirements to test for hydrogen fluoride; and add requirements for the monitoring of lime injection rates.

$12,231
No
No
No
No
No
Uncollected
Rochelle boyd 919 541-1390 [email protected]

  No

On behalf of this Federal agency, I certify that the collection of information encompassed by this request complies with 5 CFR 1320.9 and the related provisions of 5 CFR 1320.8(b)(3).
The following is a summary of the topics, regarding the proposed collection of information, that the certification covers:
 
 
 
 
 
 
 
    (i) Why the information is being collected;
    (ii) Use of information;
    (iii) Burden estimate;
    (iv) Nature of response (voluntary, required for a benefit, or mandatory);
    (v) Nature and extent of confidentiality; and
    (vi) Need to display currently valid OMB control number;
 
 
 
If you are unable to certify compliance with any of these provisions, identify the item by leaving the box unchecked and explain the reason in the Supporting Statement.
11/15/2015


© 2024 OMB.report | Privacy Policy