Download:
docx |
pdf
Construction
Progress Schedule
U.S.
Department of Housing
OMB
Approval No. 2577-0157 (Exp. 1/31/2017)
and
Urban Development
Office
of Public and Indian Housing
Public
reporting burden for this collection of information is estimated to
average 1 hour per response, including the time for reviewing
instructions, searching existing data sources, gathering and
maintaining the data needed, and completing and reviewing the
collection of information. This agency may not conduct or sponsor,
and a person is not required to respond to, a collection of
information unless that collecton displays a valid OMB control
number.
Construction
practices and HUD administrative requirements establish the need
that HAs maintain certain records or submit certain documents in
conjunction with the oversight of the award of construction
contracts for the construction of new low-income housing
developments or modernization of existing developments. These forms
are used by HAs to provide information on the construction progress
schedule and schedule of amounts for contract payments. Responses to
the collection of information are required to obtain a benefit or to
retain a benefit. The information requested does not lend itself
to
confidentiality.
1.
Name of Public Housing Agency/Indian Housing Authority (PHA/IHA)
2.
City
3.
State
5.
Project Name
11.
Number of Buildings
12.
Number of Dwelling Units
13.
Number of Rooms
(Submit
as many
Year
pages
as necessary
(yyyy)
to
cover the
construction
period.) Month
Actual
Monthly Value, Work in Place
($)
Contractor's
Name
Title
Signature
Date
(mm/dd/yyyy)
PHA/IHA
Title
Date
(mm/dd/yyyy)
Approved
by
Architect
Date
(mm/dd/yyyy)
Previous
edition is obsolete
Page
1 of 2
form
HUD-5372
(1/2014)
4.
Location
6.
Project Number
7.
Contract For
8.
Contract Time (Days)
To
(mm/dd/yyyy)
9.
From (mm/dd/yyyy)
10.
Contract Price $
Submitted
by
Approved
by
Actual
Accumulated
(%)
Progress
|
|
|
|
|
|
|
|
Anticipated
Monthly
($)
Value
|
|
|
|
|
|
|
|
Accumulated
(%)
Scheduled
Progress
|
|
|
|
|
|
|
|
Instructions
for Preparation of Construction Progress Schedule Form HUD-5372
General.
The
information required for items 1 through 6 can be obtained from the
contract documents. (7.) Enter the type of work awarded by the
PHA/IHA. This may be "general construction," "plumbing,"
"heating," "electrical," etc., depending upon
prime
Charting
Actual Progress. The
horizontal space extending through the monthly columns is divided
into "Actual Monthly
Value
of Work in Place – $" and Actual Accumulated Progress –
%.
progress
and the actual value of work in place for that month, as the work
progresses. An anticipated complete shutdown at some stage in the
work because of adverse seasonal weather or otherwise, as may
occur in road work, excavation (grading), etc., is readily shown by
a gap.
"
In each monthly column show the actual accumulated % of
contract
awards. (8.) Enter the contract time in calendar days (unless
otherwise stated). (9.) Enter the starting and completion dates as
established by the Notice to Proceed.
Year
and Month. At
the top of the Schedule, space is provided for inserting the "Year"
and "Month" to identify the times during which the work is
to be performed.
Year.
Enter
the year when the Notice to Proceed was issued. If the starting date
of the contract is such that the time assigned for completion will
be carried into a succeeding year, two yearly designations will be
shown, each centered over the applicable spread of time for each
year.
The
Contractor's name shall be placed in the lower left-hand corner of
the form, together with the signature and title of the employee who
prepared the Schedule and the date. The form then shall be sent to
the Architect for review. If the Architect considers that changes
are necessary to make the Schedule more realistic, it will withhold
approval and so advise the Contractor. When the form is acceptable
and approved by the Architect, and the PHA/ IHA, it will be returned
to the Contractor, who shall reproduce and submit the number and
style of prints required by the PHA/ IHA.
Month.
The
body of the Schedule is divided into Columns, each representing a
period of one month. Starting in the Column with the month stated in
the Notice to Proceed, enter at the top of each column the
successive months corresponding to the entire spread of the total
contract time. The Schedule must contain monthly columns to cover
the entire active period of contract, with extra columns for
possible overruns in contract time.
Normal
building construction experience has proved that the rate of overall
progress (as measured by work in place) accelerates slowly at the
start, reaches its peak in the middle third of the construction
period, and tapers down at the close. The data following illustrate
the general average expectancy of a well-balanced operation and may
be used as a guide. If the proposed progress lies within reasonable
range of these check points, the Schedule may be considered
satisfactory insofar as the time-performance feature is involved.
Computation
of Anticipated Monthly Value of Work in Place
Before
presenting the form for approval, enter in each monthly column the
dollar value (omit cents) of the increment of work anticipated to be
put in place during that interval of time. This shall be the
Contractor's best estimate of the rate of progress for each month.
This section contains a suggested guide for the elapsed contract
time vs. progress percentages.
%
of
%
of
Contract
Accumulated
The
horizontal total of the monthly dollars shown for "Antici-pated
Monthly Value" must equal the contract price shown in the
heading.
Time
Progress
0
208
10
20
Accumulated
Scheduled Progress – %
30
20
Entries
on this line shall show in percentage of total completion the
cumulative stage of progress that is scheduled to be reached at the
end of each monthly interval. It is generally sufficient to state
this anticipated progress to the nearest tenth of one percent, but
for very large contracts it may be advisable to extend compu-tations
to the nearest hundredth.
40
37
50
57
60
75
70
89
80
96
90
99
100
100
The
entry for the first month's column should be the % obtained by the
anticipated monthly dollar value of work in place at the close of
the first month being divided by the contract price.
The
foregoing percentages must be tempered by consideration of seasonal
weather conditions and other known conditions which may affect the
progress of the work. These percentages are offered for information
only.
The
entry for the second month's column is obtained by the sum of the
anticipated monthly dollar values of work in place for Columns 1 and
2 being divided by the contract price.
Enter
in the third month's column the percentage computed similarly, using
the sum of dollar values of work in place for Columns 1, 2, and 3.
Continue in this manner for the succeeding monthly columns until
"100" is reached in the final column.
Previous
edition is obsolete
Page
2 of 2
form
HUD-5372
(1/2014)
File Type | application/vnd.openxmlformats-officedocument.wordprocessingml.document |
File Modified | 0000-00-00 |
File Created | 2021-01-24 |