Summary
of Materials Stored U.S.
Department of Housing
and
Urban Development
Office
of Public and Indian Housing
OMB
Approval No. 2577-0157
(exp.
1/31/2017)
form
HUD-51004
(01/201)) Previous
editions are obsolete
This information is collected under the authority of Section 6(c) of the U.S Housing Act of l937 and HUD regulations. HAs are responsible for contract administration to ensure that the work for project development is done in accordance with State laws and HUD requirements. The contractor/subcontractor reports provide details and summaries on payments, change orders, and schedule of materials stored for the project The information will be used to ensure that the total development costs, identified in the ACC, are kept as low as possible and consistent with HUD construction requirements. Responses to the collection are necessary to obtain a benefit. The information requested does not lend itself to confidentiality.
Instructions: This form is for the Contractor to summarize the value of materials stored at the site (as shown on the schedule, form HUD-51003). Use a separate line for the contractor and each of his/her subcontractors. Prepare an original and one copy, attach form HUD-51003, and send to the Public Housing Agency with the Periodic Estimate for Partial Payment, form HUD-51001. Payment Value. No more than 90 percent of the estimated value of the stored materials will be allowed, and only the net amount will be carried to line 13 on the back of the Periodic Estimate for Partial Payment, form HUD-51001. Signatures. This form must be signed by those employees of the contractor and of the Public Housing Agency who prepare and check the Schedule of Materials Stored, form HUD-51003.
Name of Public Housing Agency |
Supporting Periodic Estimate for Partial Payment Number |
Period From (mm/dd/yyyy) To (mm/dd/yyyy) |
|||
Location of Project |
Project Number |
||||
Name of General Contractor |
Contract Number |
||||
Name of General Contractor or Subcontractor |
Amounts |
||||
General Contractor |
$ |
||||
$ |
|||||
|
Total |
$ |
|||
Less 10% |
$ |
||||
Net |
$ |
||||
Prepared by |
Date (mm/dd/yyyy) |
Checked by |
Date (mm/dd/yyyy) |
I certify that I or my authorized representatives have examined and checked in detail the invoices representing the cost of materials set forth
in appended "Schedule of Materials Stored", form HUD-51003, dated (mm/dd/yyyy) __
submitted by __ _____ consisting of _________ sheets with an indicated cost
of $ ______________________ , and find that the net unit prices set forth in the schedule are the same or less than the invoices examined, and that such materials were suitably stored at the site of the development as of (date)(mm/dd/yyyy) _____________________ .
Name of Owner |
By (Authorized Representative) |
Title |
Date (mm/dd/yyyy) |
|
|
|
|
Warning: HUD will prosecute false claims and statements. Conviction may result in criminal and/or civil penalties. (18 U.S.C. 1001, 1010, 1012; 31 U.S.C. 3729, 3802)